CN102097825A - 一种双馈风电变流器IGBT型Crowbar切出方法 - Google Patents
一种双馈风电变流器IGBT型Crowbar切出方法 Download PDFInfo
- Publication number
- CN102097825A CN102097825A CN2011100209738A CN201110020973A CN102097825A CN 102097825 A CN102097825 A CN 102097825A CN 2011100209738 A CN2011100209738 A CN 2011100209738A CN 201110020973 A CN201110020973 A CN 201110020973A CN 102097825 A CN102097825 A CN 102097825A
- Authority
- CN
- China
- Prior art keywords
- crowbar
- current
- circuit
- controller
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 18
- 230000005611 electricity Effects 0.000 description 5
- 230000008569 process Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 230000003139 buffering effect Effects 0.000 description 2
- 238000010248 power generation Methods 0.000 description 2
- 238000005070 sampling Methods 0.000 description 2
- 230000001052 transient effect Effects 0.000 description 2
- 238000004804 winding Methods 0.000 description 2
- 230000008033 biological extinction Effects 0.000 description 1
- 238000005352 clarification Methods 0.000 description 1
- 230000009514 concussion Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 230000003534 oscillatory effect Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/76—Power conversion electric or electronic aspects
Landscapes
- Control Of Eletrric Generators (AREA)
Abstract
一种双馈风电变流器IGBT型Crowbar切出方法,其特征在于,所述的切出方法是根据电流互感器采集到的定子三相电流,由Crowbar控制器构造出与Crowbar电流相关的虚拟直流电流,并根据所述的虚拟直流电流估算Crowbar电流的波谷时刻;在Crowbar控制器中同时设置Crowbar电路应该投入的最小时间和最大时间,在该时间段内的Crowbar电流的估算波谷时刻切出Crowbar电路,以减小IGBT关断时的开关应力,进而可以简化IGBT缓冲吸收电路的设计。
Description
技术领域
本发明涉及一种双馈式风电机组变流器低电压穿越时的切出方法。
背景技术
风力发电技术迅猛发展,装机容量快速上升,风力发电在电网供电中所占比例不断提高。在风力发电占电网比例越来越大的情况下,新的并网导则要求风电机组在电网故障出现电压跌落时能够保持不脱网,并在故障切除后能尽快帮助电力系统恢复稳定运行,也就是要求风电机组具备低电压穿越能力。
双馈式风力发电机组是当前大型风电机组中获得广泛应用的主流机型,但由于双馈式发电机的定子直接连接电网,在电网电压瞬间跌落的情况下,定子磁链作为电网电压的积分项,不能跟随定子电压突变,会产生直流分量,而转子继续旋转,会产生较大的滑差,引起发电机绕组的过压、过流。一般采用投入Crowbar短路发电机转子绕组,旁路转子变流器的方式来实现低电压穿越。Crowbar转子短路技术主要有两种拓扑结构,一种是晶闸管二极管混合桥型Crowbar电路,一种是IGBT型Crowbar电路。其中,IGBT型Crowbar电路结构如图1所示,当电网电压波动激起双馈发电机电磁暂态导致转子变流器过流时,控制G1导通,通过D1-D6组成的整流桥、IGBT G1和Crowbar电阻Rcb将发电机转子短路。电磁暂态结束后,关断G1,即切出Crowbar电路,同时恢复转子变流器运行。
考虑到Crowbar电路只在电网故障时投入以保护转子变流器,工作时间很短,故Crowbar电路电气元器件选型时裕量都很小,其中的IGBT器件也是如此。当Crowbar电路投入以后,流过IGBT(图1的G1)的电流呈振荡衰减趋势,对于1.5MW双馈机组,震荡电流的波峰和波谷差值可以达到1.5kA以上。如果在电流最小时关断IGBT,可以明显减小IGBT的开关应力,进而可以减小吸收电容的容值,简化IGBT缓冲吸收电路的设计。
判断流过IGBT电流波谷时刻的最简单方法是用传感器直接检测该电流,这势必需要改变原有系统的设计,并增加硬件成本。
目前的文献仅说明在转子电流下降到一定程度时切出Crowbar,但是对Crowbar切出的具体时刻尚未有过明确说明。
发明内容
本发明的目的是克服现有技术的缺点,在没有Crowbar电流检测的条件下,提供一种根据三相定子电流估计Crowbar电流波谷时刻的方法,利用该方法可以在Crowbar电流波谷附近切出Crowbar电路。
本发明切出方法是由电流互感器采集定子三相电流,送到Crowbar控制器,由Crowbar控制器根据所述的定子三相电流构造出与Crowbar电流相关的虚拟直流电流,并根据所述的虚拟直流电流估算Crowbar电流的波谷时刻;同时在Crowbar控制器中设置Crowbar电路应该投入的最小时间和最大时间,在该时间段内的Crowbar电流的估算波谷时刻切换Crowbar电路,以减小IGBT关断时的开关应力。
本发明中的Crowbar电路切出方法包括以下步骤:
(2)Crowbar控制器判断构造出的直流电流Isdc的波谷时刻。判断出波谷时刻后,在之后的一段时间内Crowbar控制器进行反复判断,以确保判断出的是基波电流的波谷。
(3)Crowbar控制器找出基波波谷后,判断Crowbar电路已经投入的时间是否大于Crowbar电路应该投入的最小时间TCBMin,如果大于Crowbar电路应该投入的最小时间TCBMin,切出Crowbar电路。
(4)Crowbar控制器判断Crowbar电路已经投入的时间是否大于Crowbar电路应该投入的最大时间TCBMax,如果大于Crowbar电路应该投入的最大时间TCBMax,切出Crowbar电路。
本发明中的切出方法只在Crowbar电路投入后调用,每个采样周期Ts执行一次。
步骤(1)中的虚拟直流电流Isdc等同于三相定子电流Isa、Isb、Isc经三相全桥整流电路整流出的直流电流。
步骤(3)中的Crowbar应该投入的最小时间TCBMin的设置,是为了确保Crowbar电路投入需要的时间后才允许切出,以使Crowbar电路的投入能发挥到有效作用。
步骤(4)中的Crowbar应该投入的最大时间TCBMax的设置,是为了确保定子电流采集出现问题导致估算方法失效时,Crowbar电路也能够切出,以保护Crowbar电路不被烧毁。
步骤(3)中的TCBMin与步骤(4)中的TCBMax赋值应该保证这个时间段内有一个Crowbar电流的波谷,如果两个变量赋值相同,等同于投入Crowbar后固定时间间隔定时切出。
附图说明
图1为常用的IGBT型双馈风电变流器Crowbar电路;
图2为双馈式风力发电系统结构图;
图3为Crowbar切出算法流程图。
具体实施方式
下面结合附图和具体实施方式进一步说明本发明。
图2所示为本发明的应用对象双馈式风电机组。如图2所示,转子变流器200通过控制双馈异步发电机100的转子有功电流和无功电流,实现发电机100的输出有功功率和无功功率解耦控制,网侧变流器300通过控制与电网交换有功功率的大小来控制直流母线电压的稳定,网侧变流器300也可以通过无功功率控制参与调节机组的功率因数。
当出现电网故障导致定子电压跌落时,Crowbar控制器500控制IGBT型Crowbar电路400动作,通过Crowbar电路400将发电机转子通过Crowbar电阻短接,旁路掉转子变流器200,进而达到保护转子变流器的目的。
当Crowbar电路400动作后,开始触发本发明中的Crowbar切出算法,算法流程图如图3所示。Crowbar控制器500基于TI公司DSP设计,具有高速运算功能。
步骤1:Crowbar控制器500以周期Ts采样双馈异步发电机100的定子三相电流Isa、Isb、Isc,经Crowbar控制器500中的软件模拟整流单元计算得到当前虚拟直流电流根据Isdc(n)和上一拍的Isdc(n-1)计算出电流增量ΔIsdc(n)=Isdc(n)-Isdc(n-1),如图3中10所示。其中,n取值为1、2、3……的正整数。
步骤2:Crowbar控制器根据ΔIsdc(n)的符号寻找波谷时刻,如图3中20所示。
步骤3:Crowbar控制器找到波谷后,在之后的程序周期中持续一段时间进行反复判断,确认找到的是基波电流的波谷,如图3中30所示。
步骤4:Crowbar控制器找到基波电流波谷后,开始判断Crowbar电路已经投入的时间是否大于Crowbar应该投入的最小时间TCBMin,如果大于,切出Crowbar电路,如图3中的流程40、50、70。
步骤5:如果条件不满足步骤4,Crowbar控制器判断Crowbar电路已经投入的时间是否大于Crowbar应该投入的最大时间TCBMax,如果大于,无条件切出Crowbar电路,如图3中的流程41或51、60、70。
步骤6:如果当前是基波电流波谷,但是Crowbar电路投入的时间小于Crowbar应该投入的最小时间TCBMin,如图3中40、51、61流程,或者当前不是基波电流波谷而且电路投入的时间小于Crowbar应该投入的最大时间TCBMax,如图3中的41、61流程,Crowbar电路保持原状态,返回,继续判断基波电流波谷时刻。
在低电压穿越投入Crowbar电路后,Crowbar控制器通过本发明可以确保在Crowbar电流的波谷时刻切出Crowbar,减小IGBT的开关应力,进而减小对Crowbar电路直流过压冲击,并可以简化IGBT的缓冲吸收电路,在一定程度上可以优化IGBT型Crowbar硬件电路的设计。
Claims (2)
1.一种双馈风电变流器IGBT型Crowbar切出方法,其特征在于,所述的切出方法是根据电流互感器采集到的定子三相电流,由Crowbar控制器构造出与Crowbar电流相关的虚拟直流电流,并根据所述的虚拟直流电流估算Crowbar电流的波谷时刻;在Crowbar控制器中同时设置Crowbar电路应该投入的最小时间和最大时间,在该时间段内的Crowbar电流的估算波谷时刻切换Crowbar电路,以减小IGBT关断时的开关应力。
2.按照权利要求1所述的双馈风电变流器IGBT型Crowbar切出方法,其特征在于,所述的切出方法包括以下步骤:
(1)电流互感器采集发电机定子三相电流Isa、Isb、Isc,并将所述的三相电流送入Crowbar控制器,由Crowbar控制器中的软件模拟整流单元根据所述的三相电流构造出定子电流虚拟直流电流Crowbar控制器判断所述的的虚拟直流电流Isdc的波谷时刻,并在之后的一段时间内Crowbar控制器进行反复判断,以确保判断出的是基波电流的波谷时刻;
(2)找出基波波谷时刻后,Crowbar控制器判断Crowbar电路已经投入的时间是否大于Crowbar电路应该投入的最小时间TCBMin,如果大于Crowbar电路应该投入的最小时间TCBMin,切出Crowbar电路;
(3)Crowbar控制器判断Crowbar电路已经投入的时间是否大于Crowbar电路应该投入的最大时间TCBMax,如果大于Crowbar电路应该投入的最大时间TCBMax,切出Crowbar电路。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100209738A CN102097825B (zh) | 2011-01-19 | 2011-01-19 | 一种双馈风电变流器IGBT型Crowbar切出方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100209738A CN102097825B (zh) | 2011-01-19 | 2011-01-19 | 一种双馈风电变流器IGBT型Crowbar切出方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102097825A true CN102097825A (zh) | 2011-06-15 |
CN102097825B CN102097825B (zh) | 2013-04-17 |
Family
ID=44130743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011100209738A Expired - Fee Related CN102097825B (zh) | 2011-01-19 | 2011-01-19 | 一种双馈风电变流器IGBT型Crowbar切出方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102097825B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102223125A (zh) * | 2011-06-29 | 2011-10-19 | 南车株洲电力机车研究所有限公司 | 一种电网电压故障时风电机组不间断运行控制方法及装置 |
CN102255299A (zh) * | 2011-07-21 | 2011-11-23 | 南车株洲电力机车研究所有限公司 | 一种双馈风力发电机变流器主动式保护方法及装置 |
CN102545267A (zh) * | 2012-02-09 | 2012-07-04 | 上海交通大学 | 双馈风电机组低电压穿越方法 |
WO2013041974A3 (en) * | 2011-09-01 | 2014-01-23 | Sergio Aurtenetxea | Method and apparatus for controlling a converter |
CN118157524A (zh) * | 2024-03-14 | 2024-06-07 | 广州擎天实业有限公司 | 一种交流励磁装置逆变桥过流检测方法及装置 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006345649A (ja) * | 2005-06-09 | 2006-12-21 | Hitachi Zosen Corp | 風力発電を利用した水電解水素発生装置およびその運転方法 |
EP1921738A2 (de) * | 2006-11-10 | 2008-05-14 | REpower Systems AG | Verfahren und Vorrichtung zum Betrieb eines Umrichters, insbesondere für Windenergieanlagen |
CN101621204A (zh) * | 2009-08-14 | 2010-01-06 | 清华大学 | 用于双馈式风力发电系统低电压穿越的撬棒电阻设计方法 |
CN101630850A (zh) * | 2009-08-07 | 2010-01-20 | 深圳市禾望电气有限公司 | 一种双馈型感应发电机穿越电网故障的装置及方法 |
-
2011
- 2011-01-19 CN CN2011100209738A patent/CN102097825B/zh not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006345649A (ja) * | 2005-06-09 | 2006-12-21 | Hitachi Zosen Corp | 風力発電を利用した水電解水素発生装置およびその運転方法 |
EP1921738A2 (de) * | 2006-11-10 | 2008-05-14 | REpower Systems AG | Verfahren und Vorrichtung zum Betrieb eines Umrichters, insbesondere für Windenergieanlagen |
CN101630850A (zh) * | 2009-08-07 | 2010-01-20 | 深圳市禾望电气有限公司 | 一种双馈型感应发电机穿越电网故障的装置及方法 |
CN101621204A (zh) * | 2009-08-14 | 2010-01-06 | 清华大学 | 用于双馈式风力发电系统低电压穿越的撬棒电阻设计方法 |
Non-Patent Citations (1)
Title |
---|
苏平,张靠社: "基于主动式IGBT型Crowbar的双馈风力发电系统LVRT仿真研究", 《电力系统保护与控制》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102223125A (zh) * | 2011-06-29 | 2011-10-19 | 南车株洲电力机车研究所有限公司 | 一种电网电压故障时风电机组不间断运行控制方法及装置 |
CN102223125B (zh) * | 2011-06-29 | 2013-06-19 | 南车株洲电力机车研究所有限公司 | 一种电网电压故障时风电机组不间断运行控制方法及装置 |
CN102255299A (zh) * | 2011-07-21 | 2011-11-23 | 南车株洲电力机车研究所有限公司 | 一种双馈风力发电机变流器主动式保护方法及装置 |
CN102255299B (zh) * | 2011-07-21 | 2014-04-09 | 南车株洲电力机车研究所有限公司 | 一种双馈风力发电机变流器主动式保护方法及装置 |
WO2013041974A3 (en) * | 2011-09-01 | 2014-01-23 | Sergio Aurtenetxea | Method and apparatus for controlling a converter |
CN102545267A (zh) * | 2012-02-09 | 2012-07-04 | 上海交通大学 | 双馈风电机组低电压穿越方法 |
CN102545267B (zh) * | 2012-02-09 | 2016-04-13 | 上海交通大学 | 双馈风电机组低电压穿越方法 |
CN118157524A (zh) * | 2024-03-14 | 2024-06-07 | 广州擎天实业有限公司 | 一种交流励磁装置逆变桥过流检测方法及装置 |
Also Published As
Publication number | Publication date |
---|---|
CN102097825B (zh) | 2013-04-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Bernal-Perez et al. | Efficiency and fault ride-through performance of a diode-rectifier-and VSC-inverter-based HVDC link for offshore wind farms | |
Yang et al. | A series-dynamic-resistor-based converter protection scheme for doubly-fed induction generator during various fault conditions | |
Muyeen et al. | Variable speed wind turbine generator system with current controlled voltage source inverter | |
CN102055207B (zh) | 低电压穿越智能功率控制单元及其应用 | |
CN102223125B (zh) | 一种电网电压故障时风电机组不间断运行控制方法及装置 | |
Jin et al. | Enhancement of low voltage ride-through capability for wind turbine driven DFIG with active crowbar and battery energy storage system | |
CN101895126B (zh) | 双馈变速恒频风力发电机组的低电压穿越控制电路 | |
CN102097825B (zh) | 一种双馈风电变流器IGBT型Crowbar切出方法 | |
CN101741100A (zh) | 低电压穿越控制方案 | |
CN103078344B (zh) | 一种提高双馈式变流器低电压穿越性能的方法 | |
CN102646991B (zh) | 用于双馈式风力发电机组低电压穿越的开关和动态电阻 | |
CN203967764U (zh) | 一种风力发电机组双模式变流器 | |
MacDowell et al. | Validation of GE wind plant models for system planning simulations | |
Jiang et al. | A novel DC fault ride-through method for wind farms connected to the grid through bipolar MMC-HVDC transmission | |
CN104967377B (zh) | 双馈风力发电机转子磁链定频模型预测控制方法 | |
VAN et al. | ADVANCED CONTROL, STRATEGY OF BACK-TO-HACK PWM CONVERTERS IN PMSG VVIND POWER SYSTEM | |
Rajvikram et al. | Fault ride-through capability of permanent magnet synchronous generator based wind energy conversion system | |
CN103337871B (zh) | 一种风力发电机组低电压穿越电路及相应的控制方法 | |
Carrasco et al. | Power electronic systems for the grid integration of wind turbines | |
CN102412597A (zh) | 一种双馈风力发电系统低电压穿越控制方法和装置 | |
CN104242346B (zh) | 一种风电机组低电压穿越控制方法 | |
CN102790406A (zh) | 具备可靠低电压穿越能力的双馈变流器 | |
Sartika et al. | Stabilization of PMSG based wind turbine under network disturbance by using new buck controller system for DC-link protection | |
Sarkar et al. | Distance relay performance in future converter dominated power systems | |
CN106300415A (zh) | 一种无刷双馈风力发电机组组合的低电压穿越方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130417 |