CN102086630A - 一种连续u形梁施工方法 - Google Patents

一种连续u形梁施工方法 Download PDF

Info

Publication number
CN102086630A
CN102086630A CN 201010506982 CN201010506982A CN102086630A CN 102086630 A CN102086630 A CN 102086630A CN 201010506982 CN201010506982 CN 201010506982 CN 201010506982 A CN201010506982 A CN 201010506982A CN 102086630 A CN102086630 A CN 102086630A
Authority
CN
China
Prior art keywords
supported
simply
beams
continuous
shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010506982
Other languages
English (en)
Inventor
张继文
宋守坛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jinling Construction Engineering Group Co Ltd
Southeast University
Original Assignee
Jiangsu Jinling Construction Engineering Group Co Ltd
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jinling Construction Engineering Group Co Ltd, Southeast University filed Critical Jiangsu Jinling Construction Engineering Group Co Ltd
Priority to CN 201010506982 priority Critical patent/CN102086630A/zh
Publication of CN102086630A publication Critical patent/CN102086630A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种连续U形梁施工方法,其施工步骤如下:浇注养护所需简支U形梁,在简支梁端预留普通钢筋及预应力筋管道,满足梁体简支期间以及吊装过程的受力要求,到达安装要求后运至施工现场,采用临时支座整体吊装到位,并在U形梁与U形梁之间预留工缝;在简支的U形梁与U形梁之间的工缝内张拉墩顶负弯矩预应力筋,并湿接缝连接工缝;湿接缝达到强度后拆除临时支座并设置永久支座,使原有简支梁变成连续梁受力。与现有技术相比,本发明先简支后连续U梁桥相比同等跨度的简支梁桥可以减小跨中弯矩,从而节省钢材和混凝土的用量,在技术难度不高、而且在施工周期较短的情况下获得了连续梁桥相同的使用性能,其经济效益和社会效益将会十分可观。

Description

一种连续U形梁施工方法
技术领域
本发明适用于交通领域桥梁建设用U形梁的施工。
背景技术
目前在桥梁工程领域特别是城市轨道交通领域,桥梁的建筑高度往往受到各种因素的制约,U形梁用连接两侧腹板的底板承受荷载作用,可以大大减小梁体的建筑高度,可以解决桥梁净空不足和建筑高度受限等一系列问题。
现有U形梁主要采用简支梁的方案,其具有施工速度快、梁体质量高等优点,可以模数化施工,不足之处在于跨中弯矩大,对梁体截面利用率不高。后来在一些地段采用了连续梁的方案,用现场浇注的施工方法,可以解决简支梁方案的不足,随之而来的是施工周期长,现场浇注混凝土质量保证不足等问题。
发明内容
本发明所要解决的技术问题是为克服简支梁跨中弯矩大,现场浇注连续梁施工周期长的不足,而提供一种采用了先简支后连续的施工方法,既简便快捷,又使得跨中弯矩比简支梁小。
本发明的技术方案是: 一种连续U形梁施工方法,其施工步骤如下:第一步、浇注养护所需简支U形梁,在简支梁端预留普通钢筋及预应力筋管道,满足梁体简支期间以及吊装过程的受力要求,到达安装要求后运至施工现场,采用临时支座整体吊装到位,并在U形梁与U形梁之间预留工缝;第二步、在第一步简支的U形梁与U形梁之间的工缝内张拉墩顶负弯矩预应力筋,并湿接缝连接工缝;第三步、湿接缝达到强度后拆除临时支座并设置永久支座,使原有简支梁变成连续梁受力。
与现有技术相比,本发明先简支后连续U梁桥相比同等跨度的简支梁桥可以减小跨中弯矩,从而节省钢材和混凝土的用量,在技术难度不高、而且在施工周期较短的情况下获得了连续梁桥相同的使用性能, 特别是对于孔数较多的相同跨径的桥梁, 其经济效益和社会效益将会十分可观。
  附图说明
图1、简支变连续施工过程。
图2、湿接缝浇筑前大样图。
图3、湿接缝浇筑后大样图。
具体实施方式
下面结合附图,对本发明连续梁施工方法做详细说明,本发明施工方法步骤大致以下3步:
1、先在制梁厂浇注养护所需简支U形梁1、2和3,张拉一期钢束9,满足梁体简支期间以及吊装过程的受力要求,到达安装要求后运至施工现场整体吊装到位(临时支座),预制梁段预先按简支梁安装到临时支座4形成简支梁段(图1以三跨为例分别形成简支梁1、2、3),并在U形梁与U形梁之间预留工缝,工缝的宽度为1-2m,中间简支梁端预留普通钢筋及预应力筋管道,参见图1a。预留的普通钢筋采用预应力锚具紧固,普通钢筋采用400MPa或500MPa细晶钢筋,见图2。
2、简支的梁与梁之间预留施工缝进行湿接缝连接并张拉墩顶负弯矩预应力筋(二期),安放永久支座8并连接预留普通钢筋后浇注湿接缝段(图1所示湿接缝段5、6),达到一定强度后张拉后期负弯矩预应力短束,见图1b以及图3。
3、湿接缝达到一定强度后设置永久支座并拆除临时支座使原有简支梁变成连续梁7受力。

Claims (3)

1.一种连续U形梁施工方法,其施工步骤如下:第一步、浇注养护所需简支U形梁,在简支梁端预留普通钢筋及预应力筋管道,满足梁体简支期间以及吊装过程的受力要求,到达安装要求后运至施工现场,采用临时支座整体吊装到位,并在U形梁与U形梁之间预留工缝;第二步、在第一步简支的U形梁与U形梁之间的工缝内张拉墩顶负弯矩预应力筋,并湿接缝连接工缝;第三步、湿接缝达到强度后拆除临时支座并设置永久支座,使原有简支梁变成连续梁受力。
2.根据权利要求1所述的连续U形梁施工方法,其特征在于:所述的普通钢筋采用400MPa或500MPa细晶钢筋。
3.根据权利要求1所述的连续U形梁施工方法,其特征在于:所述的工缝的宽度为1-2m。
CN 201010506982 2010-10-14 2010-10-14 一种连续u形梁施工方法 Pending CN102086630A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010506982 CN102086630A (zh) 2010-10-14 2010-10-14 一种连续u形梁施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010506982 CN102086630A (zh) 2010-10-14 2010-10-14 一种连续u形梁施工方法

Publications (1)

Publication Number Publication Date
CN102086630A true CN102086630A (zh) 2011-06-08

Family

ID=44098617

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010506982 Pending CN102086630A (zh) 2010-10-14 2010-10-14 一种连续u形梁施工方法

Country Status (1)

Country Link
CN (1) CN102086630A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103194960B (zh) * 2013-04-12 2016-05-04 北京交通大学 无墩刚构桥体系实现方法
CN108625281A (zh) * 2018-04-12 2018-10-09 中国十七冶集团有限公司 一种先简支后连续桥梁湿接缝连接方法
CN114016423A (zh) * 2021-11-25 2022-02-08 上海市政工程设计研究总院(集团)有限公司 一种隐盖梁先简支后连续小箱梁的施工方法
CN114263121A (zh) * 2022-01-13 2022-04-01 中工武大设计集团有限公司 混凝土箱梁结构体系转化中预应力钢束张拉结构及施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1327108A (zh) * 2001-07-19 2001-12-19 大连理工大学 后穿长束先简支后连续张拉预应力筋技术
CN2477701Y (zh) * 2001-05-24 2002-02-20 周志祥 桥梁由简支变连续的连结构造
CN2575148Y (zh) * 2002-09-26 2003-09-24 上海市隧道工程轨道交通设计研究院 槽型梁
CN101225639A (zh) * 2008-01-28 2008-07-23 上海市城市建设设计研究院 简支变连续箱梁结构施工工艺及其简支变连续箱梁结构

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2477701Y (zh) * 2001-05-24 2002-02-20 周志祥 桥梁由简支变连续的连结构造
CN1327108A (zh) * 2001-07-19 2001-12-19 大连理工大学 后穿长束先简支后连续张拉预应力筋技术
CN2575148Y (zh) * 2002-09-26 2003-09-24 上海市隧道工程轨道交通设计研究院 槽型梁
CN101225639A (zh) * 2008-01-28 2008-07-23 上海市城市建设设计研究院 简支变连续箱梁结构施工工艺及其简支变连续箱梁结构

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
《山东交通科技》 20050818 徐吉存等 先简支后连续预应力砼连续板桥的设计与施工控制 , 第03期 2 *
《山西建筑》 20070220 卞龙等 先简支后连续梁桥施工技术简介 第33卷, 第06期 2 *
《甘肃水利水电技术》 20060630 姜洪军等 预应力预制箱梁简支变连续结构桥梁工程施工与研究 第42卷, 第02期 2 *
《石家庄铁道学院学报》 20020831 高发征等 先简支后连续公路箱梁施工技术 第15卷, 第增刊期 2 *
《赤峰学院学报(自然科学版)》 20080425 孙昊 预应力连续箱梁施工工艺措施 第24卷, 第04期 2 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103194960B (zh) * 2013-04-12 2016-05-04 北京交通大学 无墩刚构桥体系实现方法
CN108625281A (zh) * 2018-04-12 2018-10-09 中国十七冶集团有限公司 一种先简支后连续桥梁湿接缝连接方法
CN114016423A (zh) * 2021-11-25 2022-02-08 上海市政工程设计研究总院(集团)有限公司 一种隐盖梁先简支后连续小箱梁的施工方法
CN114263121A (zh) * 2022-01-13 2022-04-01 中工武大设计集团有限公司 混凝土箱梁结构体系转化中预应力钢束张拉结构及施工方法
CN114263121B (zh) * 2022-01-13 2023-07-04 中工武大设计集团有限公司 混凝土箱梁结构体系转化中预应力钢束张拉结构及施工方法

Similar Documents

Publication Publication Date Title
CN109972517B (zh) 一种钢混结合梁斜拉桥主梁的施工方法
CN102154992B (zh) 波形钢腹板错位安装方法
CN108677685B (zh) 一种超高性能混凝土-部分钢梁组合盖梁及其施工方法
CN108978434B (zh) 一种钢-混组合连续箱梁桥的无支架工业化施工方法
CN107938504A (zh) 一种采用t头钢筋的桥面板湿接缝结构及其施工方法
CN102713071A (zh) 利用了架设索的无张力斜拉索状态的斜拉桥施工方法及用于其的架设索
KR100991262B1 (ko) 교량보강 및 경관 증진 방법
CN102704406B (zh) 基于组合槽型梁的道床板无拉应力施工方法
CN110700103B (zh) 一种连续性组合梁施工方法
CN105484151A (zh) 一种增强预制混凝土节段间连接的构造及其施工方法
CN110924287A (zh) 一种半装配式大跨度组合箱梁及其施工方法
CN202543788U (zh) 一种节段预制拼装桥墩结构
CN108951399A (zh) 一种单箱多室箱梁桥及其施工方法
CN110512530A (zh) 一种组合梁双节段悬臂施工方法
CN102086630A (zh) 一种连续u形梁施工方法
CN109797659A (zh) 一种波形钢腹板连续梁桥移动支架异步施工方法
CN202324606U (zh) 一种u型承力座
CN206769200U (zh) 先穿式后张法竖向预应力现浇混凝土柱结构
CN115652812B (zh) 一种pk型断面组合梁斜拉桥的异步施工方法
CN107100322A (zh) 后张法竖向预应力现浇混凝土柱结构及施工方法
CN209114299U (zh) 一种单箱多室箱梁桥
JP2004324164A (ja) 波形鋼板ウエブpc橋閉合部の施工方法
CN204059178U (zh) 一种预制t型梁
CN206769199U (zh) 后穿式后张法竖向预应力现浇混凝土柱结构
CN102182320B (zh) 大型冶金工业厂房钢骨混凝土钢骨架的安装方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110608