CN102061808A CN 201010600660 CN201010600660A CN102061808A CN 102061808 A CN102061808 A CN 102061808A CN 201010600660 CN201010600660 CN 201010600660 CN 201010600660 A CN201010600660 A CN 201010600660A CN 102061808 A CN102061808 A CN 102061808A
Authority
CN
China
Prior art keywords
installation
railings
upright posts
column
safety fence
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010600660
Other languages
English (en)
Inventor
沈献强
安少雄
郑南轩
何宏兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges Corp
Original Assignee
China Three Gorges Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges Corp filed Critical China Three Gorges Corp
Priority to CN 201010600660 priority Critical patent/CN102061808A/zh
Publication of CN102061808A publication Critical patent/CN102061808A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种检修安全围栏的安装方法,包括以下步骤:1)按设计要求打安装孔的步骤;2)以定位靠模定位安装立柱套管的步骤;3)在立柱套管内安装组装成组的立柱和栏杆的步骤;通过上述步骤在现场快速的安装检修安全围栏。本发明方法中的栏杆和立柱在工厂内安装成组,安装精度高、生产效率高,栏杆或立柱上的安装孔可以采用圆孔,连接刚度高,抗冲击能力强。现场施工时,直接插入到立柱套管中紧固,然后连接各个成组的栏杆和立柱即可,节省了现场安装时间,受恶劣环境影响小,整体外形美观规范。

Description

检修安全围栏的安装方法
技术领域
本发明涉及安全防护领域,特别是一种检修安全围栏的安装方法。
背景技术
现有的检修安全围栏有采用移动式底座,存在的问题是运输不便,现场安装费时,而且遇风雨或特殊情况例如外力撞击,会移动位置,无法起到防护作用。也有采用打孔后将围栏立柱埋入的方法,这样在现场的施工时间很长,效率低,容易受恶劣天气的影响。
发明内容
本发明所要解决的技术问题是提供一种检修安全围栏的安装方法,可以在现场快速的安装检修安全围栏,而且检修安全围栏可以承受一定的外力撞击。
为解决上述技术问题,本发明所采用的技术方案是:一种检修安全围栏的安装方法,包括以下步骤:
1)按设计要求打安装孔的步骤;
2)以定位靠模定位安装立柱套管的步骤;
3)在立柱套管内安装组装成组的立柱和栏杆的步骤;
通过上述步骤在现场快速的安装种检修安全围栏。
所述的立柱和栏杆在工厂内安装成组。
在步骤2)中,以定位靠模定位立柱套管后,在安装孔内灌浆。
本发明提供的一种检修安全围栏的安装方法,通过采用定位靠模先期安装立柱套管,然后后期将在工厂内组装成组的立柱和栏杆直接安装到立柱套管内的方法,节省了检修安全围栏的现场安装时间,提高了施工效率,而且采用了定位靠模提高了立柱套管的安装精度,从而减少了后期的调节时间,避免了现有施工方法中,因为立柱的安装误差,常常在安装栏杆时需要浪费很多时间进行现场的调整。
而且现有的施工方法中为了补偿这种误差,需要将栏杆或立柱上的安装孔设置成可以滑动的安装槽,这样降低了连接的刚度。
本发明方法中的栏杆和立柱在工厂内安装成组,安装精度高、生产效率高,栏杆或立柱上的安装孔为圆孔,连接刚度高,抗冲击能力强。现场施工时,直接插入到立柱套管中紧固,然后连接各个成组的栏杆和立柱即可,节省了现场安装时间,受恶劣环境影响小,可以承受一定的外力撞击,整体外形美观规范。
附图说明
下面结合附图和实施例对本发明作进一步说明。
图1是本发明的整体结构示意图。
图2是本发明中定位靠模的俯视图。
具体实施方式
如图1中,一种检修安全围栏的安装方法,包括以下步骤:
1)按设计要求打安装孔5的步骤;
2)以定位靠模3定位安装立柱套管4的步骤;安装时需确保定位靠模3平整,立柱套管4贴紧定位靠模3的定位面,安装多个立柱套管4后需重新校准作为基准的立柱套管4。以定位靠模3定位立柱套管4后,在安装孔5内灌浆。
3)在立柱套管4内安装组装成组的立柱2和栏杆1的步骤;立柱2和栏杆1在工厂内安装成组,在工厂内组装可以获得精度远高于在现场施工组装的组件,而且生产效率也大大提高,将成组的检修安全围栏的立柱2插入到对应的立柱套管4内并紧固,连接各组件即可。
通过上述步骤在现场快速的安装检修安全围栏。

Claims (3)

1.一种检修安全围栏的安装方法,其特征在于包括以下步骤:
1)按设计要求打安装孔(5)的步骤;
2)以定位靠模(3)定位安装立柱套管(4)的步骤;
3)在立柱套管(4)内安装组装成组的立柱(2)和栏杆(1)的步骤;
通过上述步骤实现在现场快速的安装检修安全围栏。
2.根据权利要求1所述的一种检修安全围栏的安装方法,其特征在于:所述的立柱(2)和栏杆(1)在工厂内安装成组。
3.根据权利要求1所述的一种检修安全围栏的安装方法,其特征在于:在步骤2)中,以定位靠模(3)定位立柱套管(4)后,在安装孔(5)内灌浆。
CN 201010600660 2010-12-23 2010-12-23 检修安全围栏的安装方法 Pending CN102061808A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010600660 CN102061808A (zh) 2010-12-23 2010-12-23 检修安全围栏的安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010600660 CN102061808A (zh) 2010-12-23 2010-12-23 检修安全围栏的安装方法

Publications (1)

Publication Number Publication Date
CN102061808A true CN102061808A (zh) 2011-05-18

Family

ID=43997287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010600660 Pending CN102061808A (zh) 2010-12-23 2010-12-23 检修安全围栏的安装方法

Country Status (1)

Country Link
CN (1) CN102061808A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112796450A (zh) * 2021-04-01 2021-05-14 中铁城建集团有限公司 隐框横梁结构及安装方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008175043A (ja) * 2007-01-22 2008-07-31 Kiyoshi Nakamura 誰でもが1人で作業して組立施工出来る竹垣組立法
JP2008223466A (ja) * 2007-02-14 2008-09-25 Yagashiro Zoen:Kk 丸太柵および柵の構成要素
CN101349118A (zh) * 2008-09-11 2009-01-21 南京建工集团有限公司 建设工程插接式临边围护栏杆
US20090293420A1 (en) * 2008-05-30 2009-12-03 Smith Jeffery L Ballistic and Forced Entry Resistant Construction
CN101906899A (zh) * 2010-07-08 2010-12-08 江苏省电力公司徐州供电公司 底座固定式安全围栏
CN101918657A (zh) * 2007-10-26 2010-12-15 约翰·克莱门特·普雷斯顿 安全屏障

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008175043A (ja) * 2007-01-22 2008-07-31 Kiyoshi Nakamura 誰でもが1人で作業して組立施工出来る竹垣組立法
JP2008223466A (ja) * 2007-02-14 2008-09-25 Yagashiro Zoen:Kk 丸太柵および柵の構成要素
CN101918657A (zh) * 2007-10-26 2010-12-15 约翰·克莱门特·普雷斯顿 安全屏障
US20090293420A1 (en) * 2008-05-30 2009-12-03 Smith Jeffery L Ballistic and Forced Entry Resistant Construction
CN101349118A (zh) * 2008-09-11 2009-01-21 南京建工集团有限公司 建设工程插接式临边围护栏杆
CN101906899A (zh) * 2010-07-08 2010-12-08 江苏省电力公司徐州供电公司 底座固定式安全围栏

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112796450A (zh) * 2021-04-01 2021-05-14 中铁城建集团有限公司 隐框横梁结构及安装方法
CN112796450B (zh) * 2021-04-01 2021-06-29 中铁城建集团有限公司 隐框横梁结构及安装方法

Similar Documents

Publication Publication Date Title
EP3538760B1 (en) Electrical unit for a wind turbine
WO2009080035A3 (en) Method for installing an offshore wind turbine and a barge system
EP3130796B1 (en) Wind turbine assembly system and related method
AU2009200700A1 (en) Method and system for assembling components in a tower of a wind energy turbine
WO2005028781A3 (en) Composite tower for a wind turbine and method of assembly
JP3165884U (ja) 太陽電池パネル装置の基礎架台構造
EP3467304A1 (en) Tower section for automatically raising a wind turbine and automatic raising method for same
EP2870302A1 (en) Nodal constructive system of rapid assembly for load bearing structures, buildings and artifacts of multi-purpose use
CN102061808A (zh) 检修安全围栏的安装方法
DK201370038A (en) Building structure
US20140075878A1 (en) Frame support
EP2344755A1 (en) Method and tool for aligning wind turbine tower fasteners
WO2011135172A4 (en) Method for assembling a wind turbine tower on an erection foundation and a device
CN207583079U (zh) 一种可弯曲调节护栏挡板系统
KR101186979B1 (ko) 재사용이 가능한 조립식 건축물의 복도모듈 시공방법
CN102535693B (zh) 幕墙柱安装方法及安装装置
CN102912993A (zh) 保障预制混凝土构件安装精度的方法及其模具
KR20190001638A (ko) 강관주 설치용 하부 베이스 조립체
CN202100057U (zh) 一种组合式防护栅栏
KR200473612Y1 (ko) 찬넬연결체가 구비된 데크플레이트
CN202131672U (zh) 组合式钢结构房屋
CN201407417Y (zh) 一种混凝土厂房柱上的管道支架节点结构
CN204940115U (zh) 一种组装桥梁护栏
CN104775652A (zh) 塔式结构及其加工安装方法
CN218061577U (zh) 一种建筑施工用安全防护装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110518