CN101985880A - Stone mining process - Google Patents
Stone mining process Download PDFInfo
- Publication number
- CN101985880A CN101985880A CN 201010294140 CN201010294140A CN101985880A CN 101985880 A CN101985880 A CN 101985880A CN 201010294140 CN201010294140 CN 201010294140 CN 201010294140 A CN201010294140 A CN 201010294140A CN 101985880 A CN101985880 A CN 101985880A
- Authority
- CN
- China
- Prior art keywords
- stone
- mining technology
- ore body
- splitting
- punching
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Processing Of Stones Or Stones Resemblance Materials (AREA)
Abstract
The invention discloses a stone mining process, which comprises the following steps of: 1, drilling holes for the first time: drilling holes at preset positions of a stone ore body; 2, splitting for the first time: splitting part of the stone ore body from the stone ore body by utilizing the drilled holes to form a large-sized quarry stone; 3, jacking the quarry stone; 4, drilling holes for the second time: drilling holes at preset positions of the quarry stone; 5, splitting for the second time: splitting the large quarry stone into large building stones; 6, chopping: chopping smaller blocks left after the secondary splitting into small-dimension stones; and 7, crushing: crushing much smaller chopped blocks left into gravel and/or stone powder in various specifications. The stone mining process of the technical scheme can greatly improve the yield of high-quality stones, and improve the profits of stone mining enterprises; more importantly, the nonrenewable resources, namely stones can be fully utilized, and the effective utilization rate is near 100 percent.
Description
Technical field
The present invention relates to the stone mining technical field, be specifically related to a kind of stone mining technology.
Background technology
Before the history of the exploitation of stone material can be traced back to thousands of years, just there has been stone material already such as China B.C., but in the historical long river in thousands of years, the technology of stone mining is all more original and backward, how just stone material sparetime university exists in the mode of handicraft workshop, and the historical this workshop-based production model that is handed down continues into the present always.
In the age of greatly developing township enterprise, stone mining is done at the ore body edge that the rules of our country allow township enterprise to enter state-owned enterprise, and this exploitation, has still continued the mining type of our country's small workshop mode in several thousand.Under the driving of interests, much exploit enterprise and be eager mineral resources are transformed into capital, thereby just ignored the mine development management planning and the mining technology of standard, science, cause the unordered exploitation in mine.The indiscriminate mining and serious waste of jumping on the bandwagon of various exploitations, processing enterprise, when destroying forest cover, dust, waste water, plaster and noise etc. that exploitation and processing stone material produce have aggravated Ecological environment worsening.In addition, uncontrolled, destructive, or even rob resource dissolvingly, making is wasted in a large number as the stone material of non-renewable resources.As everyone knows, the large block of certain scale size, price double in undersized waste material, but the exploitation method of domestic enterprise has no idea to exploit out large-scale, the waste material of high-quality, because the volume of the uncontrollable waste material of explosive, massive stone inside also tends to occur crackle.That is to say that we have wasted a large amount of precious resources, but can only struggle, earn very meagre profit, and hanied something on a silver platter in high-end stone material market at the low side of stone material industry.Relevant department's statistics, rock material resource reserves the first in the world of China, the waste of rock material resource also is the first in the world, and the outstanding approaching exhaustion of rock material resource of part.
In sum, the technology of China's stone mining is also comparatively backward, needs to improve, and to improve the effective rate of utilization of stone material mineral reserve, improves the profit of stone mining enterprise simultaneously.
Summary of the invention
Technical problem to be solved by this invention provides a kind of stone mining technology, and it is serious to solve in the present stone mining rock material resource waste, the situation that profit is meagre.
For solving the problems of the technologies described above, the present invention adopts following technical scheme:
A kind of stone mining technology comprises the steps:
S1), once punching: the waste material of presplitting length direction is according to the intensive punching of predeterminated position on the stone material ore body, and ready for follow-up division, described pitch of holes is between 10 to 100 centimetres, and the depth-width ratio of the waste material of described presplitting is greater than 2;
S2), once division: utilize the hole of accomplishing fluently before, the part of stone material ore body is divided from the stone material ore body split, form large-sized waste material;
S3), fall on the top: the famine material that will separate with the stone material ore body turns over;
S4), secondary punching: on the famine material of overturning, punch, for follow-up secondary split is got ready according to predeterminated position;
S5), secondary split: divide oversize rock material from the famine material;
S6), cut: waste material remaining behind the secondary split is cut the stone material product or the semiproduct that become than small-sized;
S7), fragmentation: will cut rubble and/or stone flour that the remaining stone in back is broken into all size.
In the optimized technical scheme, step S 1) described in preferred 10 to 50 centimetres of pitch-row.
In the optimized technical scheme, step S1) punching described in, employing be hydraulic gate or hydraulic drill ring.
In the optimized technical scheme, step S2) division described in is meant and adopts the spalling device to come spalling.
In the optimized technical scheme, step S4) punching described in, employing be hydraulic gate or hydraulic drill ring.
In the optimized technical scheme, step S5) division described in is meant and adopts the spalling device to come spalling.
In the optimized technical scheme, step S5) division described in is meant and adopts the hydraulic pressure splitting machine to come splitting.
In the optimized technical scheme, step S3) backs down described in and adopt hydraulic pressure apex stone device.
What cut employing in the optimized technical scheme, step S6) is to cut the stone machine.
It is in the optimized technical scheme, step S7) broken described in that what adopt is stone breaker.
The invention has the beneficial effects as follows:
Adopt a kind of stone mining technology of technical solution of the present invention, not only can improve the lumber recovery of high-quality stone material greatly, promoted the profit of stone mining enterprise; And key is to make full use of this non-renewable resource of stone material, the approaching a hundred per cent of effective rate of utilization.
Description of drawings
Fig. 1 is the flow chart of specific embodiment of the invention stone mining technology.
Fig. 2 is the schematic diagram that once punches and divide in the specific embodiment of the invention stone mining technology.
Fig. 3 backs down in the specific embodiment of the invention stone mining technology and the schematic diagram of secondary punching.
Fig. 4 is the schematic diagram of secondary split in the specific embodiment of the invention stone mining technology.
The invention will be further described below in conjunction with accompanying drawing.
The specific embodiment
As shown in Figure 1, a kind of stone mining technology that this specific embodiment provides is mainly used in the exploitation of common stone materials such as marble, granite, comprises the steps:
Once punching: as shown in Figure 2, on the stone material ore body 2 in mine 1, stamp a round 4 according to the position of the waste material 3 of default presplitting, for follow-up division is got ready.Presplitting is waste expects 3 as shown in Figure 2, and its length is C, and width is K, highly is G; In general, depth-width ratio G/K should split otherwise be difficult for dividing greater than 2, and is also inconvenient follow-up with its overturning.Spacing between the hole 4 generally should be between 10 to 100 centimetres, and preferred pitch of holes scope is 10 to 50 centimetres.
Once division: as shown in Figure 2, the hole of accomplishing fluently before utilizing 4 becomes large-sized waste material 5 with the part (the waste material 3 of presplitting) of stone material ore body 2 from stone material ore body 2 division open forms.Division can be used quick-fried rope controlled blasting, perhaps expansive agent for cement slurry static blasting, but preferred spalling device comes spalling, and relevant spalling device and method please refer to a kind of rock introduced among the Chinese invention patent ZL200710076924.X or concrete cracking method and device and comes spalling.
There is unsafe factor in quick-fried rope controlled blasting, and explosive force is bigger to stone material destruction, makes that the volume recovery of stone material is very low, has wasted valuable non-renewable resources, has also caused environment pollution, thereby slowly has been eliminated now.Though expansive agent for cement slurry spalling method is safer, need to consume more expansive agent for cement slurry, thereby cost is higher, has compressed limited profit margin, make that a lot of ore deposits are main and be unwilling to use.And expansive agent for cement slurry is very responsive to infusion time and temperature, and early stage is seldom consistent with the expansion rate of expansive agent for cement slurry in hole 4 of later stage perfusion.In addition, expansive agent for cement slurry is influenced by environmental temperature, is lower than 5 degrees centigrade and just can't have used basically; Chemical time is long, needs five or six hours at normal temperatures, is unfavorable for continuous, sharp work.At last, expansive agent for cement slurry pollutes the environment, and is not inconsistent with current environmental protection concept, thereby will be eliminated.
Relevant employing spalling device and spalling method realize the details of division, please refer to Chinese invention patent ZL200710076924.X, and this paper no longer describes in detail.
Need to prove, split the law is that the position, aperture from default hole 4 tears apart rock, and the spalling rule is the even application of force on the whole length in hole 4, the rock spalling is opened, both effects are more or less the same in fact, and when just adopting split the law, too dark hole is nonsensical, and the spalling rule can be applied to darker hole 4, can also adopt the series connection of more piece spalling device in case of necessity.
Back down: as shown in Figure 3, the famine material 5 that separates with stone material ore body 2 is backed down, make its overturning, convenient follow-up secondary split also avoids influencing the exploitation of follow-up waste material.This step can adopt hydraulic pressure apex stone device.Hydraulic pressure apex stone machine is a kind of novel mine special-purpose machinery according to the characteristics design of stone mining, is mainly used in mobile, the overturning operation of oversize rock material, has simplified original operating type greatly, and this part belongs to prior art, and this paper no longer describes in detail.
Secondary punching: as shown in Figure 3, on the famine material 5 under the exploitation, punch 6, for follow-up secondary split is got ready according to predeterminated position.This be because the famine material 5 that separates from stone material ore body 2 has tens cubes, more than 100 cube, even hundreds of cube be inconvenient to transport and following process, so is needed secondary split.The secondary punching is the same with the method and the mode of once punching employing, and this place is no longer described in detail.
Secondary split: as shown in Figure 4, do not have the partial segmentation of defectives such as crackle to open on the famine material 5 with bulk, formation can be transported the directly oversize rock material 7 of processing of back, and described oversize rock material can further be processed into sheet material or other finished product or semiproduct.The remaining part that defectives such as crackle are arranged is a waste material 8, can carry out the processing of subsequent step.
Splitting method and mode can adopt the spalling device and method that adopts when once dividing, and this place is no longer described in detail.But secondary split can also adopt the hydraulic pressure splitting machine.Splitting machine is to be energy source with the hydraulic oil, drive the piston rod assembly motion that is connected with piston by piston, and use the wedge amplification principle dexterously, promote two split blocks and do the action of splitting, its splitting power can reach the hundreds of ton, even go up kiloton, can be in tens seconds on kiloton megalith easily splitting open.Since splitting machine have volume little, in light weight, easy to operate, safe and reliable, use flexibly, friction when high efficiency, work, no impact, noiselessness, no dust, cleavage direction controllability, characteristics such as economical and practical, be extensive use of in extraction industry such as quarrying, mineral products and infrastructure at present, a kind of machinery especially is absolutely necessary in urban construction, river course mediation, disaster relief and rescue, work such as remove obstacles.Certainly, this step can also be adopted modes such as blade saw, string bead saw, rope saw, and with the waste material of bulk further separately, but this class methods efficient is low, energy consumption is high, cost is high, therefore advises that preferred splitting machine comes splitting.
Cut: waste material 8 remaining behind the secondary split is cut the stone material product or the semiproduct that become than small-sized.Behind the secondary split, flawless major part has become bigger building stones 7 in the waste material of bulk, but also has some to exist the part of flaws such as crackle and less stone not to be utilized, and this paper is referred to as waste material 8.The stone machine is cut in the employing of this step, and remaining waste material 8 and less stone behind the secondary split are cut into the stone brick, and the stone brick may also have several different specifications, a little bit smaller more also can cut stone or the stone matter mosaic that becomes littler.Cut Shi Jiye and belong to prior art, this paper no longer describes in detail.
Broken: as will to cut rubble and/or stone flour that the remaining stone in back is broken into all size.Through after cutting, the major part of waste material has all obtained effective utilization, but some littler stone is not utilized, and may cause waste and contaminated environment.This step is used crushing engine, and the stone of remaining smaller szie is carried out fragmentation, can sieve into the rubble of different size after the fragmentation, is used for different purposes.
A kind of stone mining technology that adopts the specific embodiment of the invention to provide not only can improve the lumber recovery of high-quality stone material greatly, promotes the profit of stone mining enterprise; And key is to make full use of this non-renewable resource of stone material, the approaching a hundred per cent of effective rate of utilization.
Above content be in conjunction with concrete preferred implementation to further describing that the present invention did, can not assert that concrete enforcement of the present invention is confined to these explanations.For the general technical staff of the technical field of the invention, without departing from the inventive concept of the premise, can also make some simple deduction or replace, all should be considered as belonging to protection scope of the present invention.
Claims (10)
1. a stone mining technology comprises the steps:
S1), once punching: the waste material of presplitting length direction is according to the intensive punching of predeterminated position on the stone material ore body, and ready for follow-up division, described pitch of holes is between 10 to 100 centimetres, and the depth-width ratio of the waste material of described presplitting is greater than 2;
S2), once division: utilize the hole of accomplishing fluently before, the part of stone material ore body is divided from the stone material ore body split, form large-sized waste material;
S3), fall on the top: the famine material that will separate with the stone material ore body turns over;
S4), secondary punching: on the famine material of overturning, punch, for follow-up secondary split is got ready according to predeterminated position;
S5), secondary split: divide oversize rock material from the famine material;
S6), cut: waste material remaining behind the secondary split is cut the stone material product or the semiproduct that become than small-sized;
S7), fragmentation: will cut rubble and/or stone flour that the remaining stone in back is broken into all size.
2. a kind of stone mining technology as claimed in claim 1 is characterized in that step S 1) described in preferred 10 to 50 centimetres of pitch-row.
3. a kind of stone mining technology as claimed in claim 1 is characterized in that step S 1) described in the punching, employing be hydraulic gate or hydraulic drill ring.
4. a kind of stone mining technology as claimed in claim 1 is characterized in that step S2) described in division, be meant and adopt the spalling device to come spalling.
5. a kind of stone mining technology as claimed in claim 1 is characterized in that step S4) described in the punching, employing be hydraulic gate or hydraulic drill ring.
6. a kind of stone mining technology as claimed in claim 1 is characterized in that step S5) described in division, be meant and adopt the spalling device to come spalling.
7. a kind of stone mining technology as claimed in claim 1 is characterized in that step S5) described in division, be meant and adopt the hydraulic pressure splitting machine to come splitting.
8. as any described a kind of stone mining technology in the claim 1 to 7, it is characterized in that step S3) described in back down and adopt hydraulic pressure apex stone device.
9. as any described a kind of stone mining technology in the claim 1 to 7, it is characterized in that step S6) described in what cut employing is to cut the stone machine.
10. as any described a kind of stone mining technology in the claim 1 to 7, it is characterized in that step S7) described in broken what adopt is stone breaker.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010294140 CN101985880A (en) | 2010-09-27 | 2010-09-27 | Stone mining process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010294140 CN101985880A (en) | 2010-09-27 | 2010-09-27 | Stone mining process |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101985880A true CN101985880A (en) | 2011-03-16 |
Family
ID=43710270
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010294140 Pending CN101985880A (en) | 2010-09-27 | 2010-09-27 | Stone mining process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101985880A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102418529A (en) * | 2011-09-02 | 2012-04-18 | 湖州鹿山坞矿业有限公司 | Mining method |
CN103485788A (en) * | 2012-06-13 | 2014-01-01 | 山东港华石材有限公司 | Method for mining conglomerate |
CN104000443A (en) * | 2014-06-18 | 2014-08-27 | 郑文衡 | Bluestone pillow and preparation method thereof |
CN104695962A (en) * | 2015-02-11 | 2015-06-10 | 泉州市洛江区双阳金刚石工具有限公司 | Combined type stone block exploiting method |
CN105298493A (en) * | 2015-11-23 | 2016-02-03 | 武汉理工大学 | Nondestructive explosion mining method for underground gently-inclined thin-layered jade mine |
CN109653747A (en) * | 2018-11-06 | 2019-04-19 | 能诚集团有限公司 | Ore self-open decomposition method |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101519965A (en) * | 2009-03-09 | 2009-09-02 | 黄晓东 | Method and device for exploiting stone |
-
2010
- 2010-09-27 CN CN 201010294140 patent/CN101985880A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101519965A (en) * | 2009-03-09 | 2009-09-02 | 黄晓东 | Method and device for exploiting stone |
Non-Patent Citations (3)
Title |
---|
《石材》 20070430 方莹 装饰石材荒料开采方法的新探讨 , 第4期 2 * |
《石材》 20080930 游宝坤 无声破碎剂开采石材荒料的方法 , 第9期 2 * |
《矿业快报》 20040228 陆文 含裂隙石材矿床的开采技术研究 , 第2期 2 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102418529A (en) * | 2011-09-02 | 2012-04-18 | 湖州鹿山坞矿业有限公司 | Mining method |
CN103485788A (en) * | 2012-06-13 | 2014-01-01 | 山东港华石材有限公司 | Method for mining conglomerate |
CN103485788B (en) * | 2012-06-13 | 2016-01-20 | 山东港华石材有限公司 | A kind of method of exploiting conglomerate |
CN104000443A (en) * | 2014-06-18 | 2014-08-27 | 郑文衡 | Bluestone pillow and preparation method thereof |
CN104695962A (en) * | 2015-02-11 | 2015-06-10 | 泉州市洛江区双阳金刚石工具有限公司 | Combined type stone block exploiting method |
WO2016127676A1 (en) * | 2015-02-11 | 2016-08-18 | 泉州市洛江区双阳金刚石工具有限公司 | Combined method for excavating quarry stone |
CN104695962B (en) * | 2015-02-11 | 2017-03-01 | 泉州市洛江区双阳金刚石工具有限公司 | A kind of combination type waste material recovery method |
CN105298493A (en) * | 2015-11-23 | 2016-02-03 | 武汉理工大学 | Nondestructive explosion mining method for underground gently-inclined thin-layered jade mine |
CN105298493B (en) * | 2015-11-23 | 2018-05-01 | 武汉理工大学 | Underground low-angle dip lamelliform jade ore deposit nondestructive blasting mining methods |
CN109653747A (en) * | 2018-11-06 | 2019-04-19 | 能诚集团有限公司 | Ore self-open decomposition method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101985880A (en) | Stone mining process | |
RU2645694C2 (en) | Method for separately mining and transporting thick coal seam with gangue, and backfilling goaf with gangue | |
CN202250086U (en) | Machine for cutting through hills | |
EP2370673B1 (en) | Pre-conditioning for cave mining by fracturing | |
CN105134221A (en) | Cannon-free mechanical tunneling technology for hard rock | |
CN101718199B (en) | Method for constructing underground coal mine chamber of large cross section | |
CN104564089A (en) | Rock roadway quick tunneling process of impact crushing rock roadway tunneling machine | |
CN103343688B (en) | Surface mine clear end machine | |
CN203394529U (en) | Foundation clearing machine for opencast mine | |
WO2019109535A1 (en) | Clean and efficient coal mining method | |
CN205700860U (en) | A kind of low-noise efficient coal pulverizer | |
Xu et al. | Numerical simulation of coupled gas flow in failure process of gassy coal-rock. | |
CN106089210A (en) | A kind of hole, environment-friendly type mine mining method | |
Pickering, RGB* & Ebner | Hard rock cutting and the development of a continuous mining machine for narrow platinum reefs | |
CN203756165U (en) | High-frequency vibrating rake device | |
CN204436381U (en) | Radial type telescopic oscillating device is impacted in a kind of underground mine use fragmentation | |
CN203716983U (en) | Telescopic swinging device with crushing, impacting and excavating functions for underground coal mine | |
CN112227435A (en) | Double-roller drilling-explosion-free rapid excavation integrated modular equipment | |
CN204822970U (en) | Removable tongue for elevating conveyor of medium plate and back cover board | |
LIU et al. | Development path and key technology analysis of shaft and tunnel construction in deep stratum with high temperature | |
CN104775821A (en) | Cave mining method for granite used for veneer | |
Valgma et al. | Low depth mining in Estonian oil shale deposit-Abbau von Ölschiefer in Estland | |
CN204728989U (en) | A kind of intelligent hydraulic hammer drill for blast hole drilling | |
CN108204000A (en) | A kind of discarded fixed hydraulic quartering hammer and the utilization method for scrapping hidden hole drilling | |
CN203655296U (en) | Ultrahigh pressure leakproof hydraulic rock splitter |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20110316 |