CN101962945A - Method for invertedly machining gate flap panel of steel arch-gate - Google Patents
Method for invertedly machining gate flap panel of steel arch-gate Download PDFInfo
- Publication number
- CN101962945A CN101962945A CN 201010283314 CN201010283314A CN101962945A CN 101962945 A CN101962945 A CN 101962945A CN 201010283314 CN201010283314 CN 201010283314 CN 201010283314 A CN201010283314 A CN 201010283314A CN 101962945 A CN101962945 A CN 101962945A
- Authority
- CN
- China
- Prior art keywords
- gate
- gate flap
- steel arch
- processing
- hinge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Barrages (AREA)
Abstract
The invention relates to a method for invertedly machining a gate flap panel of a steel arch-gate. The method comprises the following steps of: firstly excavating a gate holding base pit according to the appearance characteristics of a structure member, supporting a beam seat on a concrete base by fixed support hinges and connecting the fixed support hinges, wherein the two fixed support hinges are required to be concentric, a movable support hinge is connected with the fixed support hinge by a support hinge shaft, the movable support hinge is connected with a support arm, and the support arm is connected with a gate flap; placing a plain miller at the outer side of the gate flap panel of the steel arch-gate; machining a waterstop surface of the gate flap panel of the steel arch-gate by the milling of the plain miller; and after a station is machined, enabling the gate flap to synchronously and rotatably lift along a support hinge shaft, and then machining the next station.
Description
Technical field
The present invention is applicable to the whole processing of Hydraulic Metal steel arch-gate gate flap panel, also is applicable to large-scale nonstandard steel work cambered surface processing simultaneously.
Background technology
The down-the-hole steel arch-gate radius of Hydraulic Metal is mostly more than 10m, and the area of gate panel is also at width * highly=more than 5m * 7m.
End water seal water, both sides side sealing water shutoff and top sealing water shutoff are adopted in the down-the-hole steel arch-gate gate flap of Hydraulic Metal and the water shutoff of gate hole respectively, form the airtight water-stopping system of " " shape.
End water watertight rubber is installed on the root edge of gate flap, and the weight compression end water rubber by gate flap makes that the end water seal water is tight.Side sealing watertight rubber is installed in the lateral edges outside of steel arch-gate gate flap, and the stainless steel (stainless steel sealing face carries out finished) of watertight rubber and gate hole side sealing embedded part has the 5mm decrement, makes that the pressing of water shutoff bonding surface is tight, and water shutoff is tight.
Top sealing watertight rubber is installed on the lintel of gate hole embedded part, the panel of watertight rubber and steel arch-gate gate flap (down having approximately from the gate top in the sealing zone of 2m to 3m) has the 5mm decrement, because the Segment gate gate flap belongs to welded construction, welding contraction distortion appears in metal construction in welding process, cause the cylindricity of arc surface to occur than mistake, make the panel decrement of watertight rubber and steel arch-gate gate flap produce inhomogeneous, under the effect of high water head, cause water shutoff not tight, infiltration, drainage occur, tend to surpass the requirement of standard.
Along with the instructions for use of modern Hydraulic Metal gate is more and more higher, the cambered surface sealing of its steel arch-gate gate flap part must be processed the required precision that just can meet the requirements of cylindricity, roughness.Guarantee that by this gate water shutoff is tight, stable working.
From processing market, there is not large-scale steel arch-gate load-bearing to exceed hundred tons cylindrical process equipment as yet.Rely on single pure cylindrical process equipment can't finish the processing of steel arch-gate panel sealing part.
Summary of the invention
This construction technology is inverted (the top panel sealing part of gate flap below, root edge is inverted up) with steel arch-gate by the gate flap duty, in gate is placed working pit, make gate flap along a hinge rotation and lifting, finish cambered surface processing by the milling of unit head.
Adopt the method for Milling Process, Milling Process can only be the plane, forms broken line with a plurality of facets, is similar to arc surface, and the facet polygon is more little many more, gets over and becomes to approaching circular arc.More than 10m, if each processing plane height has 80mm, the radius error of its circularity only below 0.008mm, is far superior to the requirement of Hydraulic Metal water shutoff to large-scale Segment gate radius mostly.
This technology is inverted assembling by the gate duty and is connected: at first lay foundation ditch according to structural member resemblance excavation gate, and will fix a hinged bearing beam seat on concrete foundation and be connected and fixed a hinge, two fixing hinges require with one heart, movable hinge is hinged with fixing by a hinge, and movable hinge is connected with support arm; Support arm is connected with the gate flap panel again; Then plain mille is placed steel arch-gate gate flap panels outside, finish the processing of steel arch-gate gate flap panel by the milling of plain mille; After processing a station, buttress that the bottom of the openend by the both sides support arm is provided with and fine setting jack are adjusted the gate flap lifting position, and gate flap is risen along a hinge rotation, carry out the processing of next station; After the fine setting jack reaches the limit of stroke, with steel work gate flap is supported temporarily, adjust the fine setting jack to the limit inferior travel position, extract the conciliation location axle pin on the buttress, reconciling location axle pin makes up with the next locating hole of reconciling, the elevation of buttress is raise, descend the processing of several stations then; Repeat gate flap to be supported temporarily, adjust and reconcile location axle pin and the combination of reconciling locating hole, the elevation of buttress is raise gradually, until the processing of finishing gate flap panel sealing face with steel work.
Use this technical operation to have the following advantages: 1. personnel work on the ground, easy operating, and safety is guaranteed; 2. lathe bed is constant, and Working position is constant; Prop up hinge and fix, the measurement hierarchy of control more easily is set, be easy to control and check crudy; 3. investment cost is low, only excavates working pit, the firm concrete foundation that a fixing hinge place is provided with.
Description of drawings
Fig. 1 is a steel arch-gate gate flap panel sealing face processing schematic diagram;
1. 5. movable hinges of fixing hinged bolsters 4. hinges of 3. fixing hinges of concrete foundation 2., 6. support arms, 7. gate flaves, 8. plain milles, 9. milling machines are installed basic shaped steel 10. buttresses 11. and are reconciled locating holes 12. and reconcile location axle pin 13. fine setting jack.
The specific embodiment
As shown in Figure 1, excavate gate according to the structural member resemblance and lay foundation ditch.Concrete foundation (1) is set, and a fixing hinged bolster (2) (steel work) is located on the concrete foundation, and fixing hinge (3) is installed on the fixing hinged bolster, and the position of adjusting two fixing hinges makes it concentric.Movable hinge (5) is hinged with fixing by a hinge (4).Movable hinge is connected with support arm (6), and support arm is connected with gate flap (7) again, and buttress (10) is set in the bottom of the openend of support arm and fine setting jack (13) is used to adjust the gate flap lifting position.
Plain mille places steel arch-gate gate flap panels outside.Plain mille (8) is loaded on milling machine and basic shaped steel (9) is installed upward with B face installation centering level, and makes the A face be parallel to two hinge centers, and milling cutterhead center is consistent with a hinge center elevation.
Finish the processing of steel arch-gate gate flap panel sealing face by the milling of plain mille, whenever process a station after, synchronization of jacking up both sides fine setting jack (13), the jacking amount is the working height of a last station, continues processing then.After the fine setting jack reaches the limit of stroke, with steel work gate flap is supported temporarily, adjust the fine setting jack to the limit inferior travel position, extract the conciliation location axle pin (12) on the buttress, reconciling location axle pin makes up with the next locating hole (11) of reconciling, the elevation of buttress is raise, descend the processing of several stations then.Repeat gate flap to be supported temporarily, adjust and reconcile location axle pin and the combination of reconciling locating hole, the elevation of buttress is raise gradually, until the processing of finishing gate flap panel sealing face with steel work.
Claims (1)
1. steel arch-gate gate flap faceplate inverted formula processing method, it is characterized in that, at first lay foundation ditch according to structural member resemblance excavation gate, and will fix a hinged bearing beam seat on concrete foundation and be connected and fixed a hinge, two fixing hinges require with one heart, movable hinge is hinged with fixing by a hinge, and movable hinge is connected with support arm; Support arm is connected with the gate flap panel again; Then plain mille is placed steel arch-gate gate flap panels outside, finish the processing of steel arch-gate gate flap panel by the milling of plain mille; After processing a station, buttress that the bottom of the openend by the both sides support arm is provided with and fine setting jack are adjusted the gate flap lifting position, and gate flap is risen along a hinge rotation, carry out the processing of next station; After the fine setting jack reaches the limit of stroke, with steel work gate flap is supported temporarily, adjust the fine setting jack to the limit inferior travel position, extract the conciliation location axle pin on the buttress, reconciling location axle pin makes up with the next locating hole of reconciling, the elevation of buttress is raise, descend the processing of several stations then; Repeat gate flap to be supported temporarily, adjust and reconcile location axle pin and the combination of reconciling locating hole, the elevation of buttress is raise gradually, until the processing of finishing gate flap panel sealing face with steel work.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102833149A CN101962945B (en) | 2010-09-15 | 2010-09-15 | Method for invertedly machining gate flap panel of steel arch-gate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102833149A CN101962945B (en) | 2010-09-15 | 2010-09-15 | Method for invertedly machining gate flap panel of steel arch-gate |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101962945A true CN101962945A (en) | 2011-02-02 |
CN101962945B CN101962945B (en) | 2011-08-17 |
Family
ID=43515985
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010102833149A Active CN101962945B (en) | 2010-09-15 | 2010-09-15 | Method for invertedly machining gate flap panel of steel arch-gate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101962945B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102418329A (en) * | 2011-08-24 | 2012-04-18 | 中国水利水电第五工程局有限公司 | Rapid installation method for large-scale hydraulic radial gate |
CN104695387A (en) * | 2013-12-10 | 2015-06-10 | 南京乐奥威电气有限公司 | Sectional connecting structure of gate and support arm for flood prevention |
CN104929083A (en) * | 2015-06-23 | 2015-09-23 | 中国水利水电第五工程局有限公司 | Hoisting method used for hydraulic-opening-closing down-hole-type double-hoisting-point arc-shaped gate |
CN105369782A (en) * | 2015-12-09 | 2016-03-02 | 葛洲坝机械工业有限公司 | Auxiliary installation device and installation method for radial gate trunnions |
CN106906801A (en) * | 2017-04-24 | 2017-06-30 | 中国水利水电夹江水工机械有限公司 | A kind of big assembly of adjustable arc gate flap is put and assembling method |
CN111015132A (en) * | 2019-12-31 | 2020-04-17 | 中国水利电力对外有限公司 | Method for machining radial gate by using large-scale numerical control gantry boring and milling machine |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1006583A1 (en) * | 1981-08-07 | 1983-03-23 | Ленинградское Отделение Всесоюзного Ордена Ленина Проектно-Изыскательного И Научно-Исследовательского Института "Гидропроект" Им.С.Я.Жука | Method for increasing height of span structure of gate at operating water engineering structures |
CN1037561A (en) * | 1988-05-12 | 1989-11-29 | 王士贤 | New method for building water gate |
CN201205608Y (en) * | 2008-04-30 | 2009-03-11 | 中国水利水电第七工程局机电安装分局 | Arc door panel milling and processing tool |
CN201389777Y (en) * | 2009-05-04 | 2010-01-27 | 中国水利水电建设集团公司 | Integral profiling tooling device for ultra-large arcuate doors |
-
2010
- 2010-09-15 CN CN2010102833149A patent/CN101962945B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1006583A1 (en) * | 1981-08-07 | 1983-03-23 | Ленинградское Отделение Всесоюзного Ордена Ленина Проектно-Изыскательного И Научно-Исследовательского Института "Гидропроект" Им.С.Я.Жука | Method for increasing height of span structure of gate at operating water engineering structures |
CN1037561A (en) * | 1988-05-12 | 1989-11-29 | 王士贤 | New method for building water gate |
CN201205608Y (en) * | 2008-04-30 | 2009-03-11 | 中国水利水电第七工程局机电安装分局 | Arc door panel milling and processing tool |
CN201389777Y (en) * | 2009-05-04 | 2010-01-27 | 中国水利水电建设集团公司 | Integral profiling tooling device for ultra-large arcuate doors |
Non-Patent Citations (1)
Title |
---|
《四川水利发电》 20071031 刘光华,殷永忠 超大型深孔弧门制造加工技术 87-90 1 第26卷, 第5期 2 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102418329A (en) * | 2011-08-24 | 2012-04-18 | 中国水利水电第五工程局有限公司 | Rapid installation method for large-scale hydraulic radial gate |
CN102418329B (en) * | 2011-08-24 | 2013-12-25 | 中国水利水电第五工程局有限公司 | Rapid installation method for large-scale hydraulic radial gate |
CN104695387A (en) * | 2013-12-10 | 2015-06-10 | 南京乐奥威电气有限公司 | Sectional connecting structure of gate and support arm for flood prevention |
CN104695387B (en) * | 2013-12-10 | 2016-06-29 | 南京乐奥威电气有限公司 | A kind of flood control gate arm stagewise attachment structure |
CN104929083A (en) * | 2015-06-23 | 2015-09-23 | 中国水利水电第五工程局有限公司 | Hoisting method used for hydraulic-opening-closing down-hole-type double-hoisting-point arc-shaped gate |
CN104929083B (en) * | 2015-06-23 | 2016-11-09 | 中国水利水电第五工程局有限公司 | A kind of hanging method of the double hanging-point arc shape gate of the down-the-hole type for hydraulic switch |
CN105369782A (en) * | 2015-12-09 | 2016-03-02 | 葛洲坝机械工业有限公司 | Auxiliary installation device and installation method for radial gate trunnions |
CN105369782B (en) * | 2015-12-09 | 2017-05-24 | 中国葛洲坝集团机械船舶有限公司 | Auxiliary installation device and installation method for radial gate trunnions |
CN106906801A (en) * | 2017-04-24 | 2017-06-30 | 中国水利水电夹江水工机械有限公司 | A kind of big assembly of adjustable arc gate flap is put and assembling method |
CN111015132A (en) * | 2019-12-31 | 2020-04-17 | 中国水利电力对外有限公司 | Method for machining radial gate by using large-scale numerical control gantry boring and milling machine |
Also Published As
Publication number | Publication date |
---|---|
CN101962945B (en) | 2011-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101962945B (en) | Method for invertedly machining gate flap panel of steel arch-gate | |
CN108547626B (en) | Shield machine with spiral conveyor floating supporting device | |
CN104234723A (en) | Self-propelled mobile template support trolley for open trench tunnel with rectangular cross section | |
CN106042169B (en) | A kind of bottom die of box-beam system | |
CN112660010B (en) | Tunnel disease quick repair engineering vehicle | |
CN108691277A (en) | The three-dimensional adjustment tooling positioned in erection process for precast segment spliced girder | |
CN207003748U (en) | A kind of upper connecting node of precast concrete out-hung panel | |
CN110205946B (en) | Swivel spherical hinge steel skeleton for bridge swivel construction | |
CN208632979U (en) | The three-dimensional adjustment tooling positioned in erection process for precast segment spliced girder | |
CN109778883B (en) | Novel steel cofferdam structure and installation method | |
CN204455855U (en) | A kind of pressure rackwork of sections pier shaft docking | |
CN210713003U (en) | Underwater soil body positioning excavation device suitable for non-water-cut-off repair of large-scale water delivery channel | |
CN202164810U (en) | Hydraulic lifting type construction platform | |
CN112854200A (en) | Deviation correcting device of double-wheel milling stirrer | |
CN219806029U (en) | Municipal administration drain pipe connection structure | |
CN218716567U (en) | Dual-purpose raise boring machine chassis | |
CN111706343A (en) | Front shield construction site assembling system and method in super-large-diameter shield tunneling machine | |
CN219487979U (en) | Novel section roof beam transportation support frame | |
CN212671202U (en) | Device for horizontally correcting large-span top steel formwork | |
CN214464229U (en) | Two linings in tunnel, escape canal integral type construction steel mould platform trucks | |
CN112474811B (en) | Quick replacing device for finish rolling bending cylinder | |
CN219527668U (en) | Building foundation pit supporting device | |
CN218669366U (en) | Positioning bracket for starting of shield tunneling machine | |
CN204308531U (en) | A kind of power station stator apparatus for examination and repair | |
CN219653524U (en) | Temporary support is assembled to steel case roof beam cable-stayed bridge single-column internal inclination steel tower bridge position |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |