CN101956403A - Construction method of rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall - Google Patents

Construction method of rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall Download PDF

Info

Publication number
CN101956403A
CN101956403A CN 201010252506 CN201010252506A CN101956403A CN 101956403 A CN101956403 A CN 101956403A CN 201010252506 CN201010252506 CN 201010252506 CN 201010252506 A CN201010252506 A CN 201010252506A CN 101956403 A CN101956403 A CN 101956403A
Authority
CN
China
Prior art keywords
ater
casting
wall
concrete
masterplate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010252506
Other languages
Chinese (zh)
Other versions
CN101956403B (en
Inventor
王喆
王静波
周文静
致栓明
韩永利
刘瑞权
丁继军
郭曙光
马宝青
郭太平
陈致炳
马政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xingtai Construction Group Co., Ltd
Original Assignee
INNER MONGOLIA XINGTAI CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INNER MONGOLIA XINGTAI CONSTRUCTION CO Ltd filed Critical INNER MONGOLIA XINGTAI CONSTRUCTION CO Ltd
Priority to CN2010102525063A priority Critical patent/CN101956403B/en
Publication of CN101956403A publication Critical patent/CN101956403A/en
Application granted granted Critical
Publication of CN101956403B publication Critical patent/CN101956403B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a construction method of a rear pouring band with a prefabricated concrete edge sealing plate for a basement outer shear wall. The method comprises the following steps of: (1) binding reinforcing steel bars; (2) laying a wall body template and reserving a rear pouring band; (3) pouring wall body concrete; (4) preparing the prefabricated concrete edge sealing plate; (5) after the wall body concrete is condensed, fabricating a rear pouring band template; and (6) pouring the rear pouring band concrete. In the invention, the prefabricated concrete edge sealing plate and structural entities at two sides of the rear pouring band have no mutual restraining effect, and the effect of the rear pouring band is sufficiently guaranteed, thus the edge sealing quality is effectively guaranteed. The invention has the advantages of simple structure, easy construction, short construction time, good effect, low cost, and the like.

Description

The job practices that has the post-poured strip of outer shear wall of basement of precast concrete banded plate
Technical field
The present invention relates to a kind of job practices of post-poured strip of outer shear wall of basement, particularly a kind of job practices that has the post-poured strip of outer shear wall of basement of precast concrete banded plate.
Background technology
In building engineering construction, the waterproof construction of basement and peripheral backfill generally need be built in the ater-casting and just can be carried out after sealing is finished, and to build the ater-casting, generally by designing requirement all after the concreting of outer wall of basement body 60 days or top out after just can carry out the closure construction of ater-casting, just can carry out the work of the waterproof construction and the backfilling of earthwork of the external side of outer wall of basement after finishing Deng the ater-casting closure construction, so just influence the building operations progress greatly.For addressing this problem, the method that generally adopts brick retaining wall in the prior art is with after the brick work barricade is done sealing outside the outer wall of basement body indentation, there at place, ater-casting, carry out the backfilling of earthwork work of the external side of outer wall of basement again, this job practices is not only complicated, but also influence the construction of follow-up basement waterproofing, and the pouring construction of later stage ater-casting is very inconvenient, and its waterproof effect is poor, occurs drainage easily.In addition, also there is the edge sealing that adopts precast concrete plank to carry out the ater-casting to handle, four jiaos of pre-embedded steel slabs of precast concrete plank and shear force wall reinforcing steel bar welding, and be close to shear wall and install, this method easy construction, waterproof effect makes moderate progress, but the rigid connection method that welds with shear force wall reinforcing steel bar has been adopted in its installation, can't make the structural solid of precast concrete banded plate and both sides, ater-casting realize three-dimensional moving, therefore also have mass defect.
Summary of the invention
The object of the present invention is to provide a kind of job practices that has the post-poured strip of outer shear wall of basement of precast concrete banded plate.
Purpose of the present invention is implemented by following technical scheme: a kind of job practices that has the post-poured strip of outer shear wall of basement of precast concrete banded plate, it comprises the steps:
(1) ties up reinforcing bar, reinforcing bar by horizontal and vertical binding or be welded into latticedly, is distributed in the body of wall;
(2) shop body of wall masterplate is reserved the ater-casting, in the body of wall masterplate that lays, inserts the ater-casting inner formword along body of wall masterplate cross section, and every ater-casting is separated out by two ater-casting inner formwords, and reserving the ater-casting width is 80-120 centimetre;
(3) cast wall concrete;
(4) prepare precast concrete banded plate, it comprises steel bar concrete body, suspension member, and suspension member one end is preset in the steel bar concrete body, the other end is protruding, the end of external part has two oval fixing holes, and one is along horizontal oval fixing hole, and another is an oval fixing hole longitudinally;
(5) treat that walls concrete condenses after, do the ater-casting masterplate, precast concrete banded plate places the side of ater-casting near back fill course, the suspension member external part bends to the U type around transverse reinforcement or longitudinal reinforcement, make two oval fixing holes lay respectively at the both sides of transverse reinforcement or longitudinal reinforcement, pass two oval fixing holes respectively with fixture, make precast concrete banded plate be close to condense the body of wall side to be fixed; The ater-casting exterior sheathing is close to the body of wall that condenses and is fixed in the side of ater-casting away from back fill course, takes out two ater-casting inner formwords, and precast concrete banded plate, ater-casting exterior sheathing and the both sides body of wall that condenses is formed the ater-casting masterplate jointly;
(6) cast ater-casting concrete.
The invention has the advantages that, the U-shaped hook of shear force wall reinforcing steel bar and suspension member realizes that three-dimensional relatively moves, meanwhile, precast concrete banded plate and condense and also obtained three-dimensional mobile space between the body of wall, the U-shaped hook has been adjusted the asynchronous displacement that produces of both sides, ater-casting distortion.Precast concrete banded plate and ater-casting structure on two sides entity do not have mutual effect of contraction, and the effect of ater-casting has obtained abundant guarantee, and sealing edge quality is effectively guaranteed.The present invention has simple in structure, and construction is easy, and the engineering time is short, and is effective, low cost and other advantages.
Description of drawings:
Fig. 1 is the precast concrete banded plate front view;
Fig. 2 is the precast concrete banded plate vertical view;
Fig. 3 is for reserving ater-casting masterplate schematic diagram;
Fig. 4 is a post-poured strip of outer shear wall of basement masterplate schematic diagram.
Ater-casting inner formword 1, steel bar concrete body 2, suspension member 3, along horizontal oval fixing hole 4, oval fixing hole 5 longitudinally, precast concrete banded plate 6, back fill course 7, transverse reinforcement 8, longitudinal reinforcement 9, U type hook 10, bolt 11, nut 12, the body of wall 13 that condenses, ater-casting exterior sheathing 14.
The specific embodiment: a kind of job practices that has the post-poured strip of outer shear wall of basement of precast concrete banded plate, it comprises the steps:
(1) ties up reinforcing bar, reinforcing bar by horizontal and vertical binding or be welded into latticedly, is distributed in the body of wall;
(2) shop body of wall masterplate is reserved the ater-casting, in the body of wall masterplate that lays, inserts ater-casting inner formword 1 along body of wall masterplate cross section, and every ater-casting is separated out by two ater-casting inner formwords 1, and reserving the ater-casting width is 100 centimetres;
(3) cast wall concrete;
(4) prepare precast concrete banded plate, it comprises steel bar concrete body 2, suspension member 3, suspension member 3 one ends are preset in the steel bar concrete body 2, the other end is protruding, the end of external part has two oval fixing holes, one is along horizontal oval fixing hole 4, and another is an oval fixing hole 5 longitudinally;
(5) treat that walls concrete condenses after, do the ater-casting masterplate, precast concrete banded plate 6 places the side of ater-casting near back fill course 7, suspension member 3 external parts bend to U type hook 10 around longitudinal reinforcement 9, make two oval fixing holes 4,5 lay respectively at the both sides of longitudinal reinforcement 9, pass two oval fixing holes 4,5 respectively with bolt 11, and tighten fixingly with nut 12, make precast concrete banded plate 6 be close to condense body of wall 13 sides to be fixed; Ater-casting exterior sheathing 14 is close to the body of wall 13 that condenses and is fixed in the side of ater-casting away from back fill course 7, takes out two ater-casting inner formwords 1, precast concrete banded plate 6, ater-casting exterior sheathing 14 and the both sides body of wall 13 common ater-casting masterplates of forming that condense;
(6) cast ater-casting concrete.

Claims (1)

1. a job practices that has the post-poured strip of outer shear wall of basement of precast concrete banded plate is characterized in that it comprises the steps:
(1) ties up reinforcing bar, reinforcing bar by horizontal and vertical binding or be welded into latticedly, is distributed in the body of wall;
(2) shop body of wall masterplate is reserved the ater-casting, in the body of wall masterplate that lays, inserts the ater-casting inner formword along body of wall masterplate cross section, and every ater-casting is separated out by two ater-casting inner formwords, and reserving the ater-casting width is 80-120 centimetre;
(3) cast wall concrete;
(4) prepare precast concrete banded plate, it comprises steel bar concrete body, suspension member, and suspension member one end is preset in the steel bar concrete body, the other end is protruding, the end of external part has two oval fixing holes, and one is along horizontal oval fixing hole, and another is an oval fixing hole longitudinally;
(5) treat that walls concrete condenses after, do the ater-casting masterplate, precast concrete banded plate places the side of ater-casting near back fill course, the suspension member external part bends to the U type around transverse reinforcement or longitudinal reinforcement, make two oval fixing holes lay respectively at the both sides of transverse reinforcement or longitudinal reinforcement, pass two oval fixing holes respectively with fixture, make precast concrete banded plate be close to condense the body of wall side to be fixed; The ater-casting exterior sheathing is close to the body of wall that condenses and is fixed in the side of ater-casting away from back fill course, takes out two ater-casting inner formwords, and precast concrete banded plate, ater-casting exterior sheathing and the both sides body of wall that condenses is formed the ater-casting masterplate jointly;
(6) cast ater-casting concrete.
CN2010102525063A 2010-08-13 2010-08-13 Construction method of rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall Active CN101956403B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102525063A CN101956403B (en) 2010-08-13 2010-08-13 Construction method of rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102525063A CN101956403B (en) 2010-08-13 2010-08-13 Construction method of rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall

Publications (2)

Publication Number Publication Date
CN101956403A true CN101956403A (en) 2011-01-26
CN101956403B CN101956403B (en) 2012-06-20

Family

ID=43483975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102525063A Active CN101956403B (en) 2010-08-13 2010-08-13 Construction method of rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall

Country Status (1)

Country Link
CN (1) CN101956403B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206088A (en) * 2013-04-18 2013-07-17 成军 Shear wall structural wall and slab integral pouring construction method
CN103410173A (en) * 2013-08-21 2013-11-27 天津二十冶建设有限公司 Construction method for vertical post pouring belt plugging of underground structural outer wall
CN105780924A (en) * 2016-03-31 2016-07-20 初明进 I-shaped steel and concrete combined structural member
CN113550572A (en) * 2021-07-09 2021-10-26 南京坤佳防水防腐保温工程有限公司 Basement outer wall post-cast strip structure and construction method thereof
CN114718310A (en) * 2022-03-08 2022-07-08 中国建筑第二工程局有限公司 Building construction structure and building construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030046782A (en) * 2001-12-06 2003-06-18 김해영 Elastic Joint of Retaining Wall
JP2006348523A (en) * 2005-06-14 2006-12-28 Ohbayashi Corp Wall panel joining structure, construction method for continuous underground wall, and continuous underground wall
CN201241343Y (en) * 2008-07-15 2009-05-20 北京建工集团有限责任公司 Rear pouring belt precast concrete suspending board
CN201280725Y (en) * 2008-09-27 2009-07-29 中国建筑第五工程局有限公司 Post-casting construction precast slab for basement of buildings
CN101666125A (en) * 2009-09-15 2010-03-10 中建四局第三建筑工程有限公司 Sealing method and structure of late poured band of basement
CN101696580A (en) * 2009-10-23 2010-04-21 中冶京唐建设有限公司 Outboard template construction method of post-pouring belt of outer wall of underground structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030046782A (en) * 2001-12-06 2003-06-18 김해영 Elastic Joint of Retaining Wall
JP2006348523A (en) * 2005-06-14 2006-12-28 Ohbayashi Corp Wall panel joining structure, construction method for continuous underground wall, and continuous underground wall
CN201241343Y (en) * 2008-07-15 2009-05-20 北京建工集团有限责任公司 Rear pouring belt precast concrete suspending board
CN201280725Y (en) * 2008-09-27 2009-07-29 中国建筑第五工程局有限公司 Post-casting construction precast slab for basement of buildings
CN101666125A (en) * 2009-09-15 2010-03-10 中建四局第三建筑工程有限公司 Sealing method and structure of late poured band of basement
CN101696580A (en) * 2009-10-23 2010-04-21 中冶京唐建设有限公司 Outboard template construction method of post-pouring belt of outer wall of underground structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《工程质量》 20071231 任道远,王旭峰 地下室外墙后浇带超前止水施工工法 第58-59页 1 , 第6期 2 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103206088A (en) * 2013-04-18 2013-07-17 成军 Shear wall structural wall and slab integral pouring construction method
CN103206088B (en) * 2013-04-18 2015-10-28 南通卓强建设集团有限公司 Parts of shear wall structure wall, slab integral pouring construction method
CN103410173A (en) * 2013-08-21 2013-11-27 天津二十冶建设有限公司 Construction method for vertical post pouring belt plugging of underground structural outer wall
CN105780924A (en) * 2016-03-31 2016-07-20 初明进 I-shaped steel and concrete combined structural member
CN113550572A (en) * 2021-07-09 2021-10-26 南京坤佳防水防腐保温工程有限公司 Basement outer wall post-cast strip structure and construction method thereof
CN113550572B (en) * 2021-07-09 2022-06-24 南京坤佳防水防腐保温工程有限公司 Basement outer wall post-cast strip structure and construction method thereof
CN114718310A (en) * 2022-03-08 2022-07-08 中国建筑第二工程局有限公司 Building construction structure and building construction method

Also Published As

Publication number Publication date
CN101956403B (en) 2012-06-20

Similar Documents

Publication Publication Date Title
CN104652654B (en) Assembled shear wall structure
CN107326940B (en) basement advanced water stop post-cast strip structure and construction method thereof
KR101379305B1 (en) Wall structure manufacturing method using precast front wall panel and precast back wall panel
CN101956403B (en) Construction method of rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall
CN104120647A (en) Segmental assembling concrete frame bridge pier system suitable for rapid construction and construction method
CN205024731U (en) A prefabricated plate component for basement outer wall post -cast strip
CN205296388U (en) Apron is sealed to garage wall post -cast strip
CN109024989A (en) Precast shear wall body and precast shear wall body production method
CN104790684A (en) Wall hole opening construction method adopting encased angle iron method
CN204199330U (en) The overall steel plate for sealing water in a kind of ater-casting
CN205712204U (en) A kind of multiple waterstop and waterproof construction thereof
CN101956402B (en) Rear pouring band with prefabricated concrete edge sealing plate for basement outer shear wall
CN105821908A (en) Multiple water stop belt, waterproof structure and construction method of waterproof structure
CN114164977A (en) Method for combining construction of aluminum template and laminated slab
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
KR101098998B1 (en) Recyclable hybrid type connecting device for steel beam to concrete wall and method thereof
CN205444504U (en) Building structure post -cast strip
CN107237448A (en) A kind of prefabricated interior fill concrete wallboard and its manufacture method
KR100735681B1 (en) Thick wall using truss decks as permanent concrete form
CN204703191U (en) A kind of double preformed pile and top board node connecting structure doing structure outer
CN204780859U (en) Prefabrication - cast -in -place mixed underground continuous wall
CN113062236A (en) Wall protection integrated pipe culvert and construction method thereof
KR100717390B1 (en) Assembly precasted panel for excavation tunnel
CN110409669A (en) Using vertical reinforcement reinforcement without constructional column rammed earth wall and its method of construction
KR20100072510A (en) Steel-concrete composite sheet pile and method of construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20161010

Address after: 017010 the Inner Mongolia Autonomous Region Ordos Ulan New District of Kangbashi City, the South Bank of the Mulun River Xingtai Business Plaza (CBD) T4 tower room 2207

Patentee after: INNER MONGOLIA XINGTAI CONSTRUCTION GROUP CO., LTD.

Address before: The Inner Mongolia Autonomous Region city Dongsheng District 017000 Erdos ejinhuro Street No. 7 Room 308

Patentee before: Inner Mongolia Xingtai Construction Co., Ltd.

CP03 Change of name, title or address

Address after: The Inner Mongolia Autonomous Region city Dongsheng District 017000 Ordos ejinhuro Street No. 7

Patentee after: Xingtai Construction Group Co., Ltd

Address before: 017010 the Inner Mongolia Autonomous Region Ordos Ulan New District of Kangbashi City, the South Bank of the Mulun River Xingtai Business Plaza (CBD) T4 tower room 2207

Patentee before: INNER MONGOLIA XINGTAI CONSTRUCTION GROUP Co.,Ltd.

CP03 Change of name, title or address