CN101914668A CN 201010264764 CN201010264764A CN101914668A CN 101914668 A CN101914668 A CN 101914668A CN 201010264764 CN201010264764 CN 201010264764 CN 201010264764 A CN201010264764 A CN 201010264764A CN 101914668 A CN101914668 A CN 101914668A
Authority
CN
China
Prior art keywords
bracing
strutting arrangement
support unit
base
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010264764
Other languages
Chinese (zh)
Other versions
CN101914668B (en
Inventor
丛轶
葛树涛
曲萍
王永斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China International Marine Containers Group Co Ltd
Original Assignee
China International Marine Containers Group Co Ltd
Dalian CIMC Heavy Chemical Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China International Marine Containers Group Co Ltd, Dalian CIMC Heavy Chemical Equipment Co Ltd filed Critical China International Marine Containers Group Co Ltd
Priority to CN 201010264764 priority Critical patent/CN101914668B/en
Publication of CN101914668A publication Critical patent/CN101914668A/en
Application granted granted Critical
Publication of CN101914668B publication Critical patent/CN101914668B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a supporting device for thermal treatment of a U-shaped pipe. The supporting device comprises a front supporting unit, a rear supporting unit, a movable connecting piece and at least one spacer member, wherein the front supporting unit and the rear supporting unit are arranged at an interval; the front supporting unit comprises a first supporting member; the rear supporting unit comprises a second supporting member; the movable connecting piece is connected between the front supporting unit and the rear supporting unit for adjusting the distance between the front supporting unit and the rear supporting unit; and the at least one spacer member comprises a front spacer member arranged on the front supporting unit and a rear spacer member arranged on the rear supporting unit, and the U-shaped pipe can be placed on the at least one spacer member. Through the supporting device of the invention, the U-shaped pipes with different bending radiuses and different lengths can be treated and the U-shaped pipes can be supported for various kinds of thermal treatment.

Description

The bracing or strutting arrangement that is used for thermal treatment of U-shaped pipe
Technical field
The present invention relates to pressurized vessel, relate in particular to a kind of bracing or strutting arrangement that is used for thermal treatment of U-shaped pipe.
Background technology
At petrochemical industry, the U-shaped pipe of interchanger needs to heat-treat behind bend pipe, to improve the mechanical property of U-shaped pipe.Yet, different according to Application Areas and unit type, the U-shaped pipe may adopt different materials, has different elbow radius, perhaps has different length.In addition, the type of heat treatment that is carried out also is not quite similar, for example stainless steel solid solution, the normalizing of low alloy steel and carbon steel and tempering etc.
At present, there is not general, effective support device so far in the thermal treatment field of U-shaped pipe bend loss, to satisfy the different elbow radius of U-shaped pipe, different length, different heat treatment kind and the needs of handling many U-shaped pipes simultaneously.For instance, the solution heat treatment of the bend loss of stainless steel heat transfer tube generally uses welding machine and soldering turret to fix its bend loss two ends, heat-treats after the energising, and this kind method can only be by root operation, many, the inefficiency of process, cost consumption height.Normally adopt for the thermal treatment of the bend loss of the U-shaped pipe of other material the U-shaped pipe is tiled on the chassis, bend loss is stretched in the High Temperature Furnaces Heating Apparatus heat-treat.Yet it is limited that this kind method is handled number of tubes, inefficiency, thermal treatment cost height.
Therefore, need provide a kind of bracing or strutting arrangement of thermal treatment of U-shaped pipe that is used for to address the above problem.
Summary of the invention
Introduced the notion of a series of reduced forms in the summary of the invention part, this will further describe in the embodiment part.Summary of the invention part of the present invention does not also mean that key feature and the essential features that will attempt to limit technical scheme required for protection, does not more mean that the protection domain of attempting to determine technical scheme required for protection.
In order to address the above problem, the invention discloses a kind of bracing or strutting arrangement that is used for thermal treatment of U-shaped pipe, comprising: the preceding support unit of each interval and back support unit, described preceding support unit comprises first strut member, and described back support unit comprises second strut member; Active connection, described active connection are connected between described preceding support unit and the described back support unit, are used to regulate the distance between described preceding support unit and the described back support unit; And one deck compartment part at least, the described compartment part of one deck at least comprise be arranged on described before on the support unit preceding compartment part and be arranged on back compartment part on the support unit of described back, on the described compartment part of one deck at least, to place described U-shaped pipe.
Preferably, described preceding support unit also comprises skeleton construction, and described skeleton construction is connected to described first strut member, and compartment part is arranged on the described skeleton construction before described.
Preferably, described skeleton construction is an annular.
Preferably, described first strut member comprises column, crossbeam and base, and described column is perpendicular to described crossbeam and be connected to described crossbeam one end, and described base is connected to the other end of described crossbeam.
Preferably, described column and described crossbeam are made more than or equal to 300 ℃ material by fusing point.
Preferably, described column and described crossbeam are made by stainless steel.
Preferably, described second strut member comprises column and base, and described column is connected to described base vertically.
Preferably, the base of the base of described first strut member and described second strut member comprises base column, base protection sleeve and roller respectively, wherein, described roller rollably is connected the bottom of described base column, described base protection sleeve is tapered, and be arranged on the lower end of described base column and can move up and down along described base column, to expose described roller at upper position and to surround described roller at lower position.
Preferably, the bottom of described base column is provided with outside screw, the top of described base protection sleeve is provided with the internal thread that the outside screw with described base column is complementary, by rotating described base protection sleeve described base protection sleeve is moved up and down between described upper position and described lower position along described base column.
Preferably, described base column is provided with upper limit spare and lower limit part, be provided with card-bit part in the described base protection sleeve, engage with described upper limit spare or described lower limit part by described card-bit part and make described base protection sleeve be positioned at described upper position or described lower position.
Preferably, described active connection comprises first part and second section, described first part with described before support unit link to each other, described second section links to each other with described support unit afterwards, is connected to flexible connection between described first part and the described second section.
Preferably, described first part and described second section are connected to described preceding support unit and described back support unit by bolt respectively.
Preferably, be connected to the connection that to pivot between described first part and the described second section.
Preferably, described first part can pivot each other by movable latch with described second section and be connected.
Preferably, the described first part of described active connection and the angle between the described second section can be regulated in 30 ° of-180 ° of scopes.
Preferably, described active connection comprises superposed first active connection and is positioned at second active connection of bottom, wherein, be positioned at described first active connection of described bracing or strutting arrangement homonymy and the both sides that described second active connection lays respectively at described first strut member and described second strut member.
Preferably, be connected to socket connection between described first part and the described second section.
Preferably, described first part and described second section are provided with corresponding positioning hole, and described first part is connected with the corresponding positioning hole of described second section by positioning element being inserted described first part with described second section.
Preferably, described bracing or strutting arrangement also comprises at least one intermediate strut unit, described intermediate strut unit is support unit and described afterwards between the support unit before described, and by described active connection with described before support unit be connected with described support unit afterwards, described intermediate strut unit is provided with intermediate interlayer spare.
By bracing or strutting arrangement of the present invention, can handle different elbow radius, the U-shaped pipe of different lengths, and can adopt according to bracing or strutting arrangement of the present invention for the various thermal treatments that will carry out.In addition, according to bracing or strutting arrangement of the present invention, first part and second section by the dismounting active connection are detachable bracing or strutting arrangement, manually just can carry mobilely, do not need mechanical transportation, therefore save resource, and are easy to deposit.And this support device structure is simple, low cost of manufacture, and simple operation is efficient.
Description of drawings
Fig. 1 is the side perspective view of bracing or strutting arrangement according to an embodiment of the invention;
Fig. 2 A and Fig. 2 B are respectively first strut member of bracing or strutting arrangement according to an embodiment of the invention and the synoptic diagram of second strut member;
Fig. 3 is the synoptic diagram of the active connection of bracing or strutting arrangement according to an embodiment of the invention;
Fig. 4 is that bracing or strutting arrangement is in the synoptic diagram of folded state according to an embodiment of the invention;
Fig. 5 is the front perspective view of bracing or strutting arrangement according to an embodiment of the invention;
Fig. 6 is the rear perspective view of bracing or strutting arrangement according to an embodiment of the invention;
Fig. 7 A and Fig. 7 B are the synoptic diagram of the base of bracing or strutting arrangement according to an embodiment of the invention;
Fig. 8 is the side perspective view of bracing or strutting arrangement in accordance with another embodiment of the present invention;
Fig. 9 is the user mode reference drawing of bracing or strutting arrangement in accordance with another embodiment of the present invention.
Embodiment
In the following description, a large amount of concrete details have been provided so that more thorough understanding of the invention is provided.Yet, it will be apparent to one skilled in the art that the present invention can need not one or more these details and implemented.In other example,, be not described for technical characterictics more well known in the art for fear of obscuring with the present invention.
In order thoroughly to understand the present invention, detailed structure will be proposed in following description.Obviously, execution of the present invention is not limited to the specific details that those skilled in the art has the knack of.Preferred embodiment of the present invention is described in detail as follows, yet except these were described in detail, the present invention can also have other embodiments.
With reference to figure 1, be the side perspective view of bracing or strutting arrangement according to an embodiment of the invention.Shown in Fig. 1 is state after the bracing or strutting arrangement assembling.Bracing or strutting arrangement comprises preceding support unit 110, back support unit 120, active connection 130 and one deck compartment part 150 at least.
Preceding support unit 110 and back support unit 120 each intervals, active connection 130 are connected between preceding support unit 110 and the back support unit 120.Preceding support unit 110 can comprise a plurality of first strut members, and back support unit 120 can comprise a plurality of second strut members.According to one embodiment of the present invention, bracing or strutting arrangement comprises two first strut members and two second strut members that are positioned at four jiaos in rectangle, to support other parts and U-shaped pipe.Because view, first strut member, second strut member and the active connection that wherein are positioned at the bracing or strutting arrangement opposite side are not shown.Two active connections 130 shown in the figure between support unit 110 and the back support unit 120, are used to regulate the distance between preceding support unit 110 and the back support unit 120 before it is connected to approximate horizontal respectively.Active connection 130 is connected by bolt, screw with back support unit 120 with preceding support unit 110, and perhaps alternate manner removably connects.
Compartment part 150 comprise be arranged on before on the support unit 110 preceding compartment part 151 and be arranged on back compartment part 152 on the support unit 120 of back.Before on the support unit 110 preceding compartment part 151 and afterwards the quantity of the back compartment part 152 on the support unit 120 is identical corresponding with the position.In the use pending U-shaped pipe is placed on one deck compartment part 150, can horizontal stacking places a plurality of U-shaped pipes like this,, thereby improve heat treatment efficiency and thermal treatment quality so that the bend loss of a plurality of U-shaped pipes is by even heating.Be understandable that the diameter of the size of quantity and the bracing or strutting arrangement of preceding compartment part 151 and back compartment part 152 and pending U-shaped pipe is relevant, so is not limited to the quantity shown in the present embodiment.Fig. 1 only shows the side of one deck compartment part 150 at least, and the back will be described in detail preceding compartment part 151 and back compartment part 152 respectively in conjunction with the front perspective view (Fig. 5) and the rear perspective view (Fig. 6) of bracing or strutting arrangement.
Be to be understood that, above-mentioned description to first strut member, second strut member and active connection 130 quantity does not constitute the restriction to bracing or strutting arrangement of the present invention, it will be apparent to those skilled in the art that, can be provided with more than two first strut members and second strut member, for example three first strut members and three second strut members, and a plurality of active connections, for example, six.As long as the agent structure that above-mentioned three kinds of parts are built can support other parts and pending U-shaped pipe, be included in the scope of the present invention.
In addition, also comprise skeleton construction 140 according to support unit 110 before of the present invention.Here former support unit 110 comprises two first strut members respectively with back support unit 120 and two second strut members are example, and the position of skeleton construction 140 is described.Skeleton construction 140 is positioned at the front end of first strut member, and is connected to two first strut members.Preferably, skeleton construction 140 removably is connected to two first strut members.In heat treatment process, skeleton construction 140 will near or stretch in the High Temperature Furnaces Heating Apparatus, therefore use repeatedly under hot environment when skeleton construction 140 distortion to occur, described removably connect can guarantee to change convenient.Preferably, preceding compartment part 151 is arranged on the skeleton construction 140, so that change with skeleton construction 140.The shape of skeleton construction 140 can be preferably annular for annular, Polygons etc.Skeleton construction 140 is made into annular not only can saves material, and be complementary with the structure of pending interchanger.Interchanger is formed by a plurality of U-shaped pipe coupling, and interchanger is up and down multilayer, inside and outside multiwalled structure, the bending radius of U-shaped pipe from the middle layer up and down layer reduce successively, and also surround the U-shaped pipe that a plurality of bending radius reduce successively in the U-shaped pipe in middle layer.Therefore, the skeleton construction 140 of annular can be complementary with interchanger.
Below each parts of bracing or strutting arrangement are described in detail.
With reference to figure 2A and Fig. 2 B, be respectively first strut member 210 of bracing or strutting arrangement and the synoptic diagram of second strut member 220 according to an embodiment of the invention.As mentioned above, preceding support unit comprises a plurality of same or analogous first strut members 210, and back support unit comprises a plurality of same or analogous second strut members 220, therefore only one of them first strut member and one second strut member is described in detail here.
First strut member 210 comprises column 211, crossbeam 212 and base 213, and wherein, column 211 is perpendicular to crossbeam 212 and be connected to an end of crossbeam 212, and base 213 is connected to the other end of crossbeam 212.Preferably, column 211 and crossbeam 212 are structure as a whole.When first strut member 210 was connected by screw or bolt with active connection, first strut member 210 also comprised screw 214a and 214b.The warp architecture of first strut member 210 can make the front end of bracing or strutting arrangement stretch in the High Temperature Furnaces Heating Apparatus, to improve heating efficiency.
Second strut member 220 comprises column 221 and base 222, and column 221 is connected to base 222 vertically.When second strut member 220 was connected by screw or bolt with active connection, second strut member 220 also comprised screw 223a and 223b.
Be understandable that first strut member 210 also can not adopt above-mentioned warp architecture, but adopt and second strut member, 220 same or analogous structures, and other equivalent structure.In addition, adopt alternate manner to be connected with first strut member 210 with second strut member 220, then do not comprise screw on first strut member 210 and second strut member 220 as active connection.
In addition and since first strut member 210 near or stretch in the High Temperature Furnaces Heating Apparatus, therefore the column 211 and the crossbeam 212 of first strut member 210 should select for use fusing point more than or equal to 300 ℃ of materials, for example stainless steel etc.And the base 213 and second strut member 220 can be selected the bigger material of carbon steel equal strength for use.
Then with reference to figure 3, be the synoptic diagram of the active connection of bracing or strutting arrangement according to an embodiment of the invention.Bracing or strutting arrangement according to the present invention comprises a plurality of same or analogous active connections, only one of them active connection is described in detail here.
Active connection 300 comprises first part 301 and second section 302, is connected to flexible connection between first part 301 and the second section 302.According to one embodiment of the present invention, be connected to the connection that can pivot between first part 301 and the second section 302, for example, by movable latch 303 connection that can pivot each other.Fig. 3 is in the synoptic diagram of folded state for active connection 300.The other end of first part 301 links to each other with preceding support unit (not shown), and the other end of second section 302 links to each other with back support unit (not shown), and its mode of connection can adopt bolt to connect.In such cases, active connection 300 also comprises screw 304, so that by unclamping the pivot and the location of realizing first part 301 and second section 302 with fastening this bolt.
Distance (as shown in Figure 4) before pivoted mode of connection between first part 301 and the second section 302 can change between support unit and the back support unit, use with the U-shaped pipe that cooperates all lengths, and can also deposit the time save space by folding bracing or strutting arrangement.Particularly, can in 30 ° of-180 ° of scopes, regulate angle between first part 301 and the second section 302 according to bracing or strutting arrangement of the present invention, in use, by the distance between support unit before adjusting angle between first part 301 and the second section 302 and changing and the back support unit.In addition, connect first part 301 and second section 302 by movable latch 303, can also be when not using this equipment for a long time, dismantle bracing or strutting arrangement by dismounting movable latch 303, but so just a dead lift moves, and does not need mechanical transportation, therefore save resource, and be easy to deposit.
Replacedly, be connected to the socket connection (not shown) between first part and the second section.First part and second section adopt the mode of pegging graft, and promptly first part can insert second section inside, and perhaps second section can insert first part inside, to realize the flexible of active connection.Further, can also on first part and second section, corresponding positioning hole be set, and positioning element be inserted in the corresponding positioning hole of first part and second section, so that first part and second section are fixed.
With reference to Fig. 4, be that bracing or strutting arrangement is in the synoptic diagram of folded state according to an embodiment of the invention.Active connection comprises first active connection 431 that is positioned at the top and second active connection 432 that is positioned at the bottom.In order to make first active connection 431 that is arranged in the bracing or strutting arrangement homonymy and second active connection 432 in pivot process non-interference, preferably, first active connection 431 and second active connection 432 lay respectively at the both sides of first strut member and second strut member, and are connected with second strut member with first strut member.That is to say, be arranged in first active connection 431 of bracing or strutting arrangement homonymy and an inboard at bracing or strutting arrangement of second active connection 432 and be connected to first strut member and second strut member, another outside at bracing or strutting arrangement is connected to first strut member and second strut member.Fig. 4 shows first active connection 431 and is positioned at the outside, and second active connection 432 is positioned at inboard situation.
When bracing or strutting arrangement bigger, when being used for the more U-shaped pipe for the treatment of number simultaneously, in order firmly to connect, each side of bracing or strutting arrangement can comprise more than two active connections, and the active connection that is positioned at the bracing or strutting arrangement homonymy can alternately be arranged in the both sides of first strut member and second strut member.
With reference to Fig. 5, be the front perspective view of bracing or strutting arrangement according to an embodiment of the invention.Skeleton view is positioned at first active connection 531 of bracing or strutting arrangement homonymy and the both sides that second active connection 532 lays respectively at first strut member 510 as can be seen from behind.Skeleton construction 540 is positioned at the front of bracing or strutting arrangement, and is connected on first strut member 510.According to embodiments of the invention, skeleton construction 540 is an annular, and is connected on first strut member 510 by bolt.Preceding compartment part 551 flatly, equally spaced is connected on the skeleton construction 540.Skeleton construction 540 and preceding compartment part 551 can be structure as a whole, or the structure that is fixed together by modes such as welding.Skeleton construction 540 and the compartment part 551 on it can select for use fusing point more than or equal to 300 ℃ material, for example, and stainless steel.In addition, also comprise the hanger 541 that is arranged on skeleton construction 540 tops on the skeleton construction 540, so that the replacing of skeleton construction 540.
With reference to Fig. 6, be the rear perspective view of bracing or strutting arrangement according to an embodiment of the invention.Skeleton view is positioned at first active connection 631 of bracing or strutting arrangement homonymy and the both sides that second active connection 632 lays respectively at second strut member 620 as can be seen from behind.Back compartment part 652 flatly, equally spaced is connected between second strut member 620, and back compartment part 652 can be fixed on second strut member 620 by modes such as welding, riveted joints.
Fig. 7 A and Fig. 7 B are the synoptic diagram of the base of bracing or strutting arrangement according to an embodiment of the invention.Many people haulage equipment in the installation and removal process, one embodiment of the present of invention are improved the structure of base.Fig. 7 A shows the synoptic diagram of base state of living in the equipment handling process, and shown in Fig. 7 A, base 700 mainly is made up of base column 701, base protection sleeve 702 and roller 703.Roller 703 can roll and hang down the bottom that is connected to base column 701.Base protection sleeve 702 can be tapered, and be arranged on the lower end of base column 701 and can move up and down along base column 701, to expose roller 703 at upper position and to surround roller 703 at lower position.When the needs conveying and supporting device, base protection sleeve 702 is moved to upper position, to expose roller 703, so only need simple the promotion just can move this Equipment for Heating Processing.When this bracing or strutting arrangement is moved to the predetermined position, in the time of need being fixed, base protection sleeve 702 is moved to lower position (shown in Fig. 7 B) along base column 701.At this moment, the lower-most point of the lower surface of base protection sleeve 702 and roller 703 is neat mutually or a little less than the lower-most point of roller, and this bracing or strutting arrangement is fixed on the predetermined position.
Particularly, can outside screw be set, the internal thread that the outside screw with base column 701 is complementary is set at the top of base protection sleeve 702 in the bottom of base column 701.By rotating base sheath 702, base protection sleeve 702 is being moved up and down between upper position and lower position along base column 701.
Replacedly, upper limit spare and lower limit part can also be set on base column 701, also be provided with card-bit part in the base protection sleeve 702.When needing mobile or device for positioning and supporting, engage with upper limit spare or lower limit part respectively, make base protection sleeve 702 be positioned at upper position or lower position by the card-bit parts in the base protection sleeve 702.
Should be understood that moving up and down and locating of base protection sleeve 702 can be not limited to mode above-mentioned, can also adopt alternate manner to realize.
Usually can have large heat exchanger at petrochemical industry, U-shaped pipe wherein is longer, therefore can also comprise at least one intermediate strut unit according to bracing or strutting arrangement of the present invention, so that satisfy the long needs of straight length of U-shaped pipe.The intermediate strut unit and is connected with back support unit by active connection and preceding support unit between preceding support unit and back support unit.Be example only below, explain principle of the present invention to comprise an intermediate strut unit.
Fig. 8 is the side perspective view of bracing or strutting arrangement in accordance with another embodiment of the present invention.As shown in Figure 8, on bracing or strutting arrangement shown in Figure 1, increase an intermediate strut unit 800, to prolong bracing or strutting arrangement.Intermediate strut unit 800 mainly is made up of the 3rd strut member 801 and intermediate interlayer spare 802.Intermediate strut unit 800 is connected with the back support unit with preceding support unit by active connection 803.Intermediate strut unit 800 can comprise a plurality of the 3rd strut members 801, and preferably, each the 3rd strut member 801 may be embodied as with second strut member has same or analogous structure, also can have other structure.Intermediate interlayer spare 802 flatly is arranged on the intermediate strut unit 800, and has and compartment part identical quantity and the corresponding position of preceding support unit with the back support unit, is positioned horizontally on the bracing or strutting arrangement to guarantee a plurality of U-shaped pipes.
Fig. 9 is the user mode reference drawing of bracing or strutting arrangement in accordance with another embodiment of the present invention.The U-shaped pipe 902 of all lengths and bending radius is placed in the bracing or strutting arrangement 901.It is unitary with on one deck compartment part that U-shaped pipe 902 is positioned at each strut member.The front end of bracing or strutting arrangement 901 stretches in the High Temperature Furnaces Heating Apparatus 903, to improve heating efficiency.
By bracing or strutting arrangement of the present invention, can change distance between the support unit by adjusting active connection, handle the U-shaped pipe of different lengths, differently curved radius; Realized that by the number of plies of adjusting compartment part the multilayer of U-shaped pipe stacks, can handle a plurality of U-shaped pipes simultaneously, therefore had higher working efficiency.According to bracing or strutting arrangement of the present invention, first part and second section by the dismounting active connection are detachable bracing or strutting arrangement, manually just can carry mobilely, do not need mechanical transportation, therefore save resource, and are easy to deposit.Further, also comprise at least one intermediate strut unit, therefore can handle the U-shaped pipe of large heat exchanger according to bracing or strutting arrangement of the present invention.And this support device structure is simple, low cost of manufacture, and simple operation is efficient.
The present invention is illustrated by the foregoing description, but should be understood that, the foregoing description just is used for for example and illustrative purposes, but not is intended to the present invention is limited in the described scope of embodiments.It will be appreciated by persons skilled in the art that in addition the present invention is not limited to the foregoing description, can also make more kinds of variants and modifications according to instruction of the present invention, these variants and modifications all drop in the present invention's scope required for protection.Protection scope of the present invention is defined by the appended claims and equivalent scope thereof.

Claims (19)

1. a bracing or strutting arrangement that is used for thermal treatment of U-shaped pipe is characterized in that, comprising:
The preceding support unit of each interval and back support unit, described preceding support unit comprises first strut member, and described back support unit comprises second strut member;
Active connection, described active connection are connected between described preceding support unit and the described back support unit, are used to regulate the distance between described preceding support unit and the described back support unit; And
At least one deck compartment part, the described compartment part of one deck at least comprise be arranged on described before on the support unit preceding compartment part and be arranged on back compartment part on the support unit of described back, on the described compartment part of one deck at least, to place described U-shaped pipe.
2. according to the described bracing or strutting arrangement of claim 1, it is characterized in that described preceding support unit also comprises skeleton construction, described skeleton construction is connected to described first strut member, and compartment part is arranged on the described skeleton construction before described.
3. according to the described bracing or strutting arrangement of claim 2, it is characterized in that described skeleton construction is an annular.
4. according to the described bracing or strutting arrangement of claim 1, it is characterized in that described first strut member comprises column, crossbeam and base, described column is perpendicular to described crossbeam and be connected to described crossbeam one end, and described base is connected to the other end of described crossbeam.
5. according to the described bracing or strutting arrangement of claim 4, it is characterized in that described column and described crossbeam are made more than or equal to 300 ℃ material by fusing point.
6. according to the described bracing or strutting arrangement of claim 5, it is characterized in that described column and described crossbeam are made by stainless steel.
7. according to the described bracing or strutting arrangement of claim 1, it is characterized in that described second strut member comprises column and base, described column is connected to described base vertically.
8. according to claim 4 or 7 described bracing or strutting arrangements, it is characterized in that, the base of the base of described first strut member and described second strut member comprises base column, base protection sleeve and roller respectively, wherein, described roller rollably is connected the bottom of described base column, described base protection sleeve is tapered, and is arranged on the lower end of described base column and can moves up and down along described base column, to expose described roller at upper position and to surround described roller at lower position.
9. according to the described bracing or strutting arrangement of claim 8, it is characterized in that, the bottom of described base column is provided with outside screw, the top of described base protection sleeve is provided with the internal thread that the outside screw with described base column is complementary, by rotating described base protection sleeve described base protection sleeve is moved up and down between described upper position and described lower position along described base column.
10. according to the described bracing or strutting arrangement of claim 8, it is characterized in that, described base column is provided with upper limit spare and lower limit part, be provided with card-bit part in the described base protection sleeve, engage with described upper limit spare or described lower limit part by described card-bit part and make described base protection sleeve be positioned at described upper position or described lower position.
11. according to the described bracing or strutting arrangement of claim 1, it is characterized in that, described active connection comprises first part and second section, described first part links to each other with described preceding support unit, described second section links to each other with described back support unit, is connected to flexible connection between described first part and the described second section.
12., it is characterized in that described first part and described second section are connected to described preceding support unit and described back support unit by bolt respectively according to the described bracing or strutting arrangement of claim 11.
13. according to the described bracing or strutting arrangement of claim 11, it is characterized in that, be connected to the connection that to pivot between described first part and the described second section.
14., it is characterized in that described first part can pivot each other by movable latch with described second section and be connected according to the described bracing or strutting arrangement of claim 13.
15., it is characterized in that the described first part of described active connection and the angle between the described second section can be regulated according to the described bracing or strutting arrangement of claim 13 in 30 ° of-180 ° of scopes.
16. according to the described bracing or strutting arrangement of claim 13, it is characterized in that, described active connection comprises superposed first active connection and is positioned at second active connection of bottom, wherein, be positioned at described first active connection of described bracing or strutting arrangement homonymy and the both sides that described second active connection lays respectively at described first strut member and described second strut member.
17. according to the described bracing or strutting arrangement of claim 11, it is characterized in that, be connected to socket connection between described first part and the described second section.
18. according to the described bracing or strutting arrangement of claim 17, it is characterized in that, described first part and described second section are provided with corresponding positioning hole, and described first part is connected with the corresponding positioning hole of described second section by positioning element being inserted described first part with described second section.
19. according to the described bracing or strutting arrangement of claim 1, it is characterized in that, described bracing or strutting arrangement also comprises at least one intermediate strut unit, described intermediate strut unit is support unit and described afterwards between the support unit before described, and by described active connection with described before support unit be connected with described support unit afterwards, described intermediate strut unit is provided with intermediate interlayer spare.
CN 201010264764 2010-08-27 2010-08-27 Supporting device for thermal treatment of U-shaped pipe Expired - Fee Related CN101914668B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010264764 CN101914668B (en) 2010-08-27 2010-08-27 Supporting device for thermal treatment of U-shaped pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010264764 CN101914668B (en) 2010-08-27 2010-08-27 Supporting device for thermal treatment of U-shaped pipe

Publications (2)

Publication Number Publication Date
CN101914668A true CN101914668A (en) 2010-12-15
CN101914668B CN101914668B (en) 2013-04-17

Family

ID=43322304

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010264764 Expired - Fee Related CN101914668B (en) 2010-08-27 2010-08-27 Supporting device for thermal treatment of U-shaped pipe

Country Status (1)

Country Link
CN (1) CN101914668B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106282516A (en) * 2016-08-29 2017-01-04 苏州倍声声学技术有限公司 The device of U-shaped armature is placed in heat-treatment furnace
CN106331976A (en) * 2016-08-29 2017-01-11 苏州倍声声学技术有限公司 Method for inhibiting opening sizes of U-shaped armatures

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54116306A (en) * 1978-03-02 1979-09-10 Sumitomo Metal Ind Ltd Heating method for steel pipe u-bend by applying electric current directly
KR20030036411A (en) * 2003-03-31 2003-05-09 조호봉 Heat Treatment system for U Bending pipe
CN2882450Y (en) * 2006-01-20 2007-03-28 吴国忠 Clothes hanger
CN201793655U (en) * 2010-08-27 2011-04-13 中国国际海运集装箱(集团)股份有限公司 Support device for heat treatment of U-shaped tube

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54116306A (en) * 1978-03-02 1979-09-10 Sumitomo Metal Ind Ltd Heating method for steel pipe u-bend by applying electric current directly
KR20030036411A (en) * 2003-03-31 2003-05-09 조호봉 Heat Treatment system for U Bending pipe
CN2882450Y (en) * 2006-01-20 2007-03-28 吴国忠 Clothes hanger
CN201793655U (en) * 2010-08-27 2011-04-13 中国国际海运集装箱(集团)股份有限公司 Support device for heat treatment of U-shaped tube

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106282516A (en) * 2016-08-29 2017-01-04 苏州倍声声学技术有限公司 The device of U-shaped armature is placed in heat-treatment furnace
CN106331976A (en) * 2016-08-29 2017-01-11 苏州倍声声学技术有限公司 Method for inhibiting opening sizes of U-shaped armatures
CN106282516B (en) * 2016-08-29 2018-04-24 苏州倍声声学技术有限公司 For placing the device of U-shaped armature in heat-treatment furnace

Also Published As

Publication number Publication date
CN101914668B (en) 2013-04-17

Similar Documents

Publication Publication Date Title
CN201793655U (en) Support device for heat treatment of U-shaped tube
CN105928394A (en) Laminated finned tube heat exchanger
CN101914668B (en) Supporting device for thermal treatment of U-shaped pipe
CN202692789U (en) Solar medium-temperature energy storage device
CN202877293U (en) Multiple-heat-exchange-tube forming device
CN205528443U (en) Chemical toughening glass inserts frame
EP2951521B1 (en) A tubular heat treatment apparatus with improved energy efficiency
CN102312069B (en) Thermal treatment furnace
CN206186345U (en) PVC pipeline swan neck system
CN212451549U (en) Semi-axis class work piece thermal treatment harness
CN207221894U (en) A kind of movable type reaction kettle heating furnace body
CN210759194U (en) Straightening device for carbon fiber tube
CN107283096A (en) Movable welding is picked up
CN207741629U (en) A kind of tight bar of expansion of cooling tower filler installation
CN218280584U (en) Waste heat recovery recycles device in sodium methoxide production process
CN205278599U (en) Marine gas double -wall pipe structure
CN218836407U (en) Fishbone type brazing furnace mesh belt supporting piece
CN215893381U (en) Exhaust device for heat exchanger
CN214398044U (en) Outdoor buffer memory frame mechanism of insulating tube finished product pipe
CN203949536U (en) Stacked heat exchanger device
CN207797817U (en) U-tube heat exchanger tail support structure
CN109202426A (en) A kind of large-scale vertical fixed tube-sheet exchanger scene process equipment for pipe penetration device and technique
CN207730026U (en) Big flat tube ties up component into stove
CN202209878U (en) Square box heating furnace with radiation coil pipes mounted at top of radiation chamber
CN201755725U (en) Header welding deformation prevention device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20151026

Address after: Harbour Road Shekou Industrial District of Shenzhen City, Guangdong province 518067 No. 2 CIMC Research Center Building

Patentee after: Chinese International Marine Container (Group) Co., Ltd.

Address before: Harbour Road Shekou Industrial District of Shenzhen City, Guangdong province 518067 No. 2 CIMC Research Center Building

Patentee before: Chinese International Marine Container (Group) Co., Ltd.

Patentee before: Dalian CIMC Heavy Chemical Equipment Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130417

Termination date: 20160827