CN101899832A - 一种适用于岩溶区的桩基施工方法及其桩基结构 - Google Patents

一种适用于岩溶区的桩基施工方法及其桩基结构 Download PDF

Info

Publication number
CN101899832A
CN101899832A CN2010101261886A CN201010126188A CN101899832A CN 101899832 A CN101899832 A CN 101899832A CN 2010101261886 A CN2010101261886 A CN 2010101261886A CN 201010126188 A CN201010126188 A CN 201010126188A CN 101899832 A CN101899832 A CN 101899832A
Authority
CN
China
Prior art keywords
pile
pile foundation
holes
karst
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010101261886A
Other languages
English (en)
Inventor
付宏渊
楼晓昱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN2010101261886A priority Critical patent/CN101899832A/zh
Publication of CN101899832A publication Critical patent/CN101899832A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种适用于岩溶区的桩基施工方法及其桩基结构,在岩溶地基中施工桩基时,先挖孔形成桩孔(4),遇到桩端附近水平岩溶极为发育情况时,在地基上部岩体力学性质较好的位置进行扩孔形成扩大孔(5)并形成中部支承面(6),然后在该支承面(6)上设置一垫层(7),该垫层(7)的厚度和刚度应保证扩大孔(5)以下桩段的侧阻力可以先行发挥,往桩孔(4)放置钢筋笼(8)后,于扩大孔(5)处现场绑扎扩大孔钢筋笼(9),其搭接长度需满足抗剪和抗弯刚度要求,最后往桩孔(4)内浇灌混凝土形成桩基本体(10),桩基本体(10)在扩大孔(5)处形成承载体(13)。本发明能适应桩端水平岩溶较发育的岩溶区安装桩基且能保证工程安全。

Description

一种适用于岩溶区的桩基施工方法及其桩基结构
技术领域
本发明专利涉及一种适用于岩溶区的桩基施工方法及其桩基结构,特指在岩溶区开挖桩基的过程中,遇到桩端水平岩溶十分发育而地基上部岩石相对完整的情况时,在性质较好的地基中施工一个扩大孔,对其进行配筋并在扩大孔下设置具有一定厚度和刚度条件的垫层,扩大孔处承载体形成,使桩基中部承载体按设计意图发挥承载力,以保证工程安全。
背景技术
在岩溶区修建桥梁桩基时,由于溶洞发育情况十分复杂,钻孔难以完全反映实际状态,给工程修建带来许多困难。较为典型的情况是虽钻孔未揭露溶洞,但施工却发现桩端一定范围内有夹泥和溶洞存在,由于缺乏好的技术方案,目前普遍采取将桩基加长,直至将桩设置在完整基岩上的办法处治。但采用这种方法处理尚有如下问题:①桩基加长后虽承载能力增大,但桩顶刚度减小,实际承载性状为摩擦桩,桩顶位移难以控制;②桩基加长时,越往深部开挖越为困难,施工不安全且使造价显著增高;③如遇地基深部水平向岩溶极为发育的情况时,要在经济合理的范围内找到合适的持力层将十分困难;④即使将桩嵌入完整基岩,桩端地基以下及周围的含溶洞情况仍难以预测,无法完全保证桩端承载力能够按设计值发挥。事实上,地基中垂直发育的岩溶具有明显的由地表向深部减弱的特征,而水平发育的岩溶则受可溶岩位置及地下水的影响而有一定的埋藏深度,工程中常遇地基上部一定范围内岩体工程性状尚好,而往深部较长范围内地基条件均较差的复杂情况。如能将让性状较好的岩层多提供一些支承力,即可不必一味加长桩基,减少不必要的浪费,亦能更好的保证工程安全。
发明内容
本发明所要解决的第一技术问题是提供一种能适应桩端水平岩溶较发育的岩溶区安装桩基且能保证工程安全的适用于岩溶区的桩基施工方法。
本发明所要解决的第二个技术问题是提供一种能适应桩端水平岩溶较发育的岩溶区安装且能保证工程安全的适用于岩溶区的桩基结构。
为了解决上述第一个技术问题,本发明提供的适用于岩溶区的桩基施工方法是:在岩溶地基中施工桩基时,先挖孔形成桩孔,遇到桩端附近水平岩溶极为发育的情况时,在地基上部岩体力学性质较好的位置进行扩孔形成扩大孔,并形成中部支承面,然后在该支承面上设置一垫层,该垫层的厚度和刚度应保证扩大孔以下桩段的侧阻力可以先行发挥,往桩孔放置钢筋笼后,于扩大孔处现场绑扎扩大孔钢筋笼,其搭接长度需满足抗剪和抗弯刚度要求,最后往桩孔内浇灌混凝土形成桩基本体,桩基本体在扩大孔处形成承载体。
为了解决上述第二个技术问题,本发明提供的适用于岩溶区的桩基结构,包括桩基本体,在所述的桩基本体中部设有承载体,在所述的承载体的下部设有垫层。
采用上述技术方案的适用于岩溶区的桩基施工方法及其桩基结构,通过对桩基进行改型,利用桩身中部工程性质较好的岩体提供一定的支承力,在桩身中部岩体较好部位进行扩孔处理,形成中部支承面,然后在该支承面面上设置具有一定厚度和刚度要求的垫层,形成桩基后,中部支承面可提供一定的支承力,即可达到不必一味加长桩基,亦可较好保证工程安全的目的。桩基承受竖向荷载作用时,由于扩孔处垫层的初始刚度较小,桩基的侧摩阻力先发挥,随着荷载的增大,扩孔处垫层刚度增大,中部支承力逐渐完全发挥,桩基承载力达到极限值。
综上所述,本发明是一种能适应桩端水平岩溶较发育的岩溶区安装桩基且能保证工程安全的适用于岩溶区的桩基施工方法及其桩基结构。
附图说明
图1是桩基改型处理方案流程图;
图2是中部扩孔桩基承载示意图;
图3是图2中A处放大图。
具体实施方式
下面结合附图和具体实施方式对本发明作进一步说明。
参见图1、图2和图3,在桩基本体10中部设有承载体13,在承载体13的下部设有垫层7。
参见图1、图2和图3,岩溶地基由上覆土层1、岩石2及地基中的溶洞3组成,采用人工挖孔方式形成桩孔4,由于桩端以下岩溶极为发育,此时在上部的岩石2中对桩孔4进行扩径处理,形成扩大孔5并形成承载面6,然后在承载面6上施工一层垫层7,往桩孔4内吊放钢筋笼8后,再于扩大孔5处人工绑扎扩大孔钢筋笼9,最后往桩孔4内浇灌混凝土形成桩基本体10,桩基本体10在扩大孔5处形成承载体13。
参见图1、图2和图3,当桩基本体10受到桩顶荷载11作用时,由于垫层7初始刚度较小,桩基本体10的各桩段摩阻力12首先发挥,当桩顶荷载11逐渐增大时,垫层7的刚度逐渐增大,扩大孔5处的承载体13的承载面6的承载力11逐渐完全发挥,该桩基本体10达到承载力极限值,以保证工程安全。

Claims (2)

1.一种适用于岩溶区的桩基施工方法,其特征是:在岩溶地基中施工桩基时,先挖孔形成桩孔(4),遇到桩端附近水平岩溶极为发育的情况时,在地基上部岩体力学性质较好的位置进行扩孔形成扩大孔(5)并形成中部支承面(6),然后在该支承面(6)上设置一垫层(7),该垫层(7)的厚度和刚度应保证扩大孔(5)以下桩段的侧阻力可以先行发挥,往桩孔(4)放置钢筋笼(8)后,于扩大孔(5)处现场绑扎扩大孔钢筋笼(9),其搭接长度需满足抗剪和抗弯刚度要求,最后往桩孔(4)内浇灌混凝土形成桩基本体(10),桩基本体(10)在扩大孔(5)处形成承载体(13)。
2.一种适用于岩溶区的桩基结构,包括桩基本体(10),其特征是:在所述的桩基本体(10)中部设有承载体(13),在所述的承载体(13)的下部设有垫层(7)。
CN2010101261886A 2010-03-17 2010-03-17 一种适用于岩溶区的桩基施工方法及其桩基结构 Pending CN101899832A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101261886A CN101899832A (zh) 2010-03-17 2010-03-17 一种适用于岩溶区的桩基施工方法及其桩基结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101261886A CN101899832A (zh) 2010-03-17 2010-03-17 一种适用于岩溶区的桩基施工方法及其桩基结构

Publications (1)

Publication Number Publication Date
CN101899832A true CN101899832A (zh) 2010-12-01

Family

ID=43225719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101261886A Pending CN101899832A (zh) 2010-03-17 2010-03-17 一种适用于岩溶区的桩基施工方法及其桩基结构

Country Status (1)

Country Link
CN (1) CN101899832A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635114A (zh) * 2012-05-07 2012-08-15 北京市三一重机有限公司 扩底灌注桩和扩底灌注桩的成桩方法
CN103195113A (zh) * 2013-04-19 2013-07-10 山东大学 咸水区水泥土桩全寿命周期内承载力预测方法
CN103469789A (zh) * 2013-09-30 2013-12-25 中铁二十局集团有限公司 一种岩溶地区桥梁水中墩钻孔桩施工方法
CN103526748A (zh) * 2013-09-30 2014-01-22 中铁二十局集团有限公司 串珠式岩溶地区深水桥梁水中墩大口径钻孔桩施工工艺

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6383314A (ja) * 1986-09-24 1988-04-14 Takenaka Komuten Co Ltd 場所打ち杭工法
CN2247195Y (zh) * 1996-01-12 1997-02-12 刘瑞祺 葫芦桩
JP2003176532A (ja) * 2001-12-11 2003-06-24 Marugo Foundation Corp 場所打ちコンクリート杭構造
CN1730839A (zh) * 2004-08-07 2006-02-08 曾毅学 水泥土加芯扩径桩
US20070065233A1 (en) * 2003-09-24 2007-03-22 Vincenzo Collina Method of constructing a pile foundation
CN1936195A (zh) * 2006-10-26 2007-03-28 郭祥山 爆炸形成扩大头灌注桩的结构部件及施工方法
CN201095760Y (zh) * 2007-08-07 2008-08-06 王国奋 建筑基础桩
CN201713810U (zh) * 2010-03-17 2011-01-19 长沙理工大学 一种适用于岩溶区的桩基结构

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6383314A (ja) * 1986-09-24 1988-04-14 Takenaka Komuten Co Ltd 場所打ち杭工法
CN2247195Y (zh) * 1996-01-12 1997-02-12 刘瑞祺 葫芦桩
JP2003176532A (ja) * 2001-12-11 2003-06-24 Marugo Foundation Corp 場所打ちコンクリート杭構造
US20070065233A1 (en) * 2003-09-24 2007-03-22 Vincenzo Collina Method of constructing a pile foundation
CN1730839A (zh) * 2004-08-07 2006-02-08 曾毅学 水泥土加芯扩径桩
CN1936195A (zh) * 2006-10-26 2007-03-28 郭祥山 爆炸形成扩大头灌注桩的结构部件及施工方法
CN201095760Y (zh) * 2007-08-07 2008-08-06 王国奋 建筑基础桩
CN201713810U (zh) * 2010-03-17 2011-01-19 长沙理工大学 一种适用于岩溶区的桩基结构

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635114A (zh) * 2012-05-07 2012-08-15 北京市三一重机有限公司 扩底灌注桩和扩底灌注桩的成桩方法
CN103195113A (zh) * 2013-04-19 2013-07-10 山东大学 咸水区水泥土桩全寿命周期内承载力预测方法
CN103195113B (zh) * 2013-04-19 2014-10-22 山东大学 咸水区水泥土桩全寿命周期内承载力预测方法
CN103469789A (zh) * 2013-09-30 2013-12-25 中铁二十局集团有限公司 一种岩溶地区桥梁水中墩钻孔桩施工方法
CN103526748A (zh) * 2013-09-30 2014-01-22 中铁二十局集团有限公司 串珠式岩溶地区深水桥梁水中墩大口径钻孔桩施工工艺
CN103526748B (zh) * 2013-09-30 2016-05-11 中铁二十局集团有限公司 串珠式岩溶地区深水桥梁水中墩大口径钻孔桩施工工艺

Similar Documents

Publication Publication Date Title
JP5520347B2 (ja) 杭の中掘工法
CN103321244B (zh) 砂土地基既有建筑增设地下室的施工方法
CN102653945B (zh) 基础托换结构及其施工方法
KR100894988B1 (ko) 직천공 그라우팅용 나선형 강관파일을 이용한 구조물보강방법
CN102644275A (zh) 复杂地质条件下旋挖组合成桩施工方法
CN101899832A (zh) 一种适用于岩溶区的桩基施工方法及其桩基结构
KR20110072814A (ko) 지표 부근의 상단부 직경이 확대된 변단면 기초 말뚝의 시공방법
CN202865855U (zh) 稳定板式锚固桩支挡结构
CN102635110B (zh) 混凝土桩的施工方法
CN109667273A (zh) 一种深基坑支护结构的施工方法
CN105464105A (zh) 一种无摩擦桩成桩结构及成桩方法
CN107100160A (zh) 一种用于下水库拦沙坝振冲碎石桩的施工工艺
CN205399503U (zh) 一种地下室抗浮底板锚板式机械锚固高强锚杆
CN201713810U (zh) 一种适用于岩溶区的桩基结构
CN205399410U (zh) 一种旋挖钻孔先注浆扩底桩
CN102493436A (zh) 矩形抗滑桩人工掘进新工法
CN102220760B (zh) 深度倒t型桩的浇铸方法
KR100687496B1 (ko) 건축단지 천공 층간에 확대공간을 갖는 착정공의 파일시공방법
CN104294817B (zh) 混凝土桩的施工方法
CN209324377U (zh) 拱盖法暗挖地铁车站拱脚加固结构
CN103195053B (zh) 一种带桩肩的桩基结构的施工方法
CN204626443U (zh) 一种输电线路斜柱直挖扩底大板基础
KR101334393B1 (ko) 소구경 기초파일의 프리보링 시공방법
JP5140515B2 (ja) 地下階柱の設置方法および地中構造物の構築方法
CN201713811U (zh) 一种适用于岩溶区的阶梯锥形桩基

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20101201