CN101884989B - Method for dredging pressure guiding system by using high-pressure nitrogen backblowing - Google Patents

Method for dredging pressure guiding system by using high-pressure nitrogen backblowing Download PDF

Info

Publication number
CN101884989B
CN101884989B CN2010102082949A CN201010208294A CN101884989B CN 101884989 B CN101884989 B CN 101884989B CN 2010102082949 A CN2010102082949 A CN 2010102082949A CN 201010208294 A CN201010208294 A CN 201010208294A CN 101884989 B CN101884989 B CN 101884989B
Authority
CN
China
Prior art keywords
pressure
guiding system
nitrogen
valve
dredging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2010102082949A
Other languages
Chinese (zh)
Other versions
CN101884989A (en
Inventor
王杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wengfu Group Co Ltd
Original Assignee
Wengfu Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wengfu Group Co Ltd filed Critical Wengfu Group Co Ltd
Priority to CN2010102082949A priority Critical patent/CN101884989B/en
Publication of CN101884989A publication Critical patent/CN101884989A/en
Application granted granted Critical
Publication of CN101884989B publication Critical patent/CN101884989B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • Pipeline Systems (AREA)

Abstract

The invention relates to a method for dredging a pressure guiding system by using high-pressure nitrogen backblowing, comprising the following steps: analyzing the current situation of the pressure guiding system to estimate the upper-limit pressure of nitrogen and establish a dredging scheme; preparing a set of device capable of supplying relevant-pressure nitrogen and carefully checking to ensure that each part is perfect and qualified; preparing a set of joint; after preparation, closing an instrument block valve to ensure that a drain valve and a root valve of the pressure guiding system are both opened; connecting a nitrogen outlet guide pipe with a drain guide pipe through the joint; opening an on/off valve and slowly opening a pressure reducer/a regulating valve to observe the change of the indication number of a pressure gage, wherein if the pressure does not change, it indicates that the pressure guiding system is still being dredged, and if the pressure suddenly and rapidly drops, it indicates that the pressure guiding system is dredged successfully; continuously blowing to accomplish the dredging of the pressure guiding system; after finishing dredging, dismantling each part of the air supply device, closing the pressure guiding system and opening the block valve to use the pressure guiding system again. The method can safely and easily remove obstructions and dredge pressure taking/sampling guide pipes without using special equipment and has the advantages of simple operation, economy and application, low cost, safety and reliability.

Description

The method of dredging pressure guiding system by using high-pressure nitrogen backblowing
Technical field
The present invention relates to the parts of instrument, relate in particular to the connecting pipe and the supporting valve of blending agent pressure, specifically, relate to the dredging method after these parts stop up
Background technology
In the Chemical Manufacture, the place that often utilizes conduit that processing medium is caused handled easily is measured or is taken a sample.Owing to multiple reason, the channel part of these pressures (or sampling) conduit, valve, pressure tappings usually can be blocked, and causes measuring undesired or can not take a sample.Run into this situation; Often need the technical staff to remove conduit with starting a section; Search stifled place, and then tamper is removed, in particular cases technical staff's poisonous and hazardous process equipment of entering of also having to take a risk with methods such as striking shake, intensification, flushing; Perhaps have to carry out dangerous operations such as high-altitude, also must carry out the destructiveness maintenance sometimes process equipment, lagging facility.Obviously, this had both wasted resource, had security risk in various degree again.
In the existing patent database, relating to the application part that utilizes the nitrogen dredging pipeline only has No. 200910052098 " COREX fusion reducing furnace dust pelletizing system blocking cleaning process ", No. 200910010470 " method and apparatus of blast furnace two-stage type blowing breeze ", No. 200920066425 " a kind of polymerization production vacuum system dredger ".Above-mentioned patented technology does not all belong to the mediation of instrument piping.Still do not have at present and use the blocked instrument piping of nitrogen mediation and the patent application part of valve.
Summary of the invention
The object of the present invention is to provide a kind of method of dredging pressure guiding system by using high-pressure nitrogen backblowing, to solve the mediation difficult problem of blocked instrument piping and valve.
The method that the inventor provides is: earlier pressure guiding system is carried out As-Is analysis, estimate the upper limit pressure of mediation with nitrogen, and formulate corresponding mediation scheme targetedly; Then, prepare the feeder that a cover can provide relevant pressure nitrogen, comprise the close/open valve of one of nitrogen steel cylinder, the indication of tape input pressure and each one in pressure reducer/control valve, two sections of the mediation air feed connecting pipes of band output pressure indication; Scrutiny guarantees that each parts is intact and qualified; Prepare process joint one cover that a cover can be complementary with conduit to be dredged again; After preparation is accomplished, close the stop valve of instrument, guarantee that blowoff valve and pressure guiding system root valve keep all opening; The dredging system delivery channel of dredging system nitrogen feeder is connected with drain guide pipe through the process joint that is complementary, check and guarantee safety, firmly, reliable; Open close/open valve, slowly open pressure reducer/control valve, and note observing the variation of its upward pressure table indication numerical value, and the authorized pressure will guarantee to indicate the numerical value maximum to be no more than ex ante analysis the time; Observe pressure changing, the variation if pressure does not descend keeps the mediation state, if pressure descends rapidly suddenly from a certain numerical value, shows and dredges successfully, continues to purge again, and accomplishes the pressure guiding system mediation; After mediation finishes, remove each parts of dredging system nitrogen feeder, close pressure guiding system, open stop valve, pressure guiding system comes into operation again.
The nitrogen pressure that above-mentioned nitrogen steel cylinder provides is 0.5MPa~2.5MPa.
The time that above-mentioned mediation state keeps is 3~10 minutes; The time of dredging successful continued purging is 2~5 minutes.
The method of dredging pressure guiding system by using high-pressure nitrogen backblowing of the present invention can be removed stifled thing, mediation pressure/sampling catheter safely, like a cork; Method is simple, need not special equipment, and is easy to operate; Do not need pressure/sampler or process equipment are painstakingly destroyed, economic and practical; Avoided dangerous operations such as high-altitude, made the mediation carrier with nitrogen, cost is low, and is safe and reliable.Be applicable to liquid, gas, the solution of latus rectum, perhaps wherein connecting pipe and the supporting valve of both or the pressure of the three's blending agent mediation after blocked of gas, liquid, solid at DN5.5~DN20.
Description of drawings
Fig. 1 is typical pressure guiding system sketch map, and Fig. 2 stops up the nitrogen feeder sketch map that uses for mediation.1 is process equipment among the figure, and 2 is the pressure guiding system root valve, and 3 is connecting pipe, and 4 is stop valve, and 5 are measurement/sampler, and 6 is blowoff valve, and 7 is the nitrogen steel cylinder; 8 close/open valves for the pressure indication; 9 is wireway; 10 pressure reducer/control valves for the pressure indication, 11 is drain guide pipe, 12 is delivery channel.
The specific embodiment
Embodiment: the pressure guiding system of dredging the connecting pipe obstruction of teletransmission pressure transmitter according to following steps:
1 pair of pressure guiding system is carried out As-Is analysis, estimates mediation and uses the upper limit pressure of nitrogen to be 2.5MPa, and make the mediation scheme targetedly;
2 prepare dredging system nitrogen feeder one cover like accompanying drawing 2; Comprise the close/open valve 8 of 7 one of nitrogen steel cylinders, the indication of tape input pressure and respectively one in pressure reducer/control valve 10,3 two sections of the mediation air feed connecting pipes of band output pressure indication; Confirm that each dribbleware is intact and qualified, guarantee that the air container internal gas pressure meets the requirements;
3 prepare a cover can with wait to dredge the joint that connecting pipe 3 or drain guide pipe 11 are complementary;
4 close stop valve 4, guarantee that blowoff valve 6 and pressure guiding system root valve 2 keep 100% aperture;
The 5 dredging system delivery channels 12 with dredging system nitrogen feeder are connected with drain guide pipe 11 through the process joint that is complementary, check and guarantee safety, firmly, reliable;
6 open close/open valve 8, slowly open pressure reducer/control valve 10, and note observing the variation of its upward pressure table indication numerical value, and will guarantee that the maximum of this indicating value is no more than authorized pressure 2.5MPa;
7 variations if pressure does not descend can keep 3~10 minutes, if pressure descends rapidly, showed and dredged successfully, continued purging again and promptly accomplished the pressure guiding system mediation in 2~5 minutes;
After 8 mediations finish, remove dredging system nitrogen feeder and annex, close pressure guiding system 6, open stop valve 4;
9 pressure guiding system come into operation again.

Claims (3)

1. the method for dredging pressure guiding system by using high-pressure nitrogen backblowing is characterized in that this method is: earlier pressure guiding system is carried out As-Is analysis, estimate the upper limit pressure of mediation with nitrogen, and formulate corresponding mediation scheme targetedly; Then, prepare the feeder that a cover can provide relevant pressure nitrogen, comprise the close/open valve of one of nitrogen steel cylinder, the indication of tape input pressure and each one in pressure reducer/control valve, two sections of the mediation air feed connecting pipes of band output pressure indication; Scrutiny guarantees that each parts is intact and qualified; Prepare process joint one cover that a cover can be complementary with conduit to be dredged again; After preparation is accomplished, close the stop valve of instrument, guarantee that blowoff valve and pressure guiding system root valve keep all opening; The dredging system delivery channel of dredging system nitrogen feeder is connected with drain guide pipe through the process joint that is complementary, check and guarantee safety, firmly, reliable; Open close/open valve, slowly open pressure reducer/control valve, and note observing the variation of its upward pressure table indication numerical value, and the authorized pressure will guarantee to indicate the numerical value maximum to be no more than ex ante analysis the time; Observe pressure changing, the variation if pressure does not descend keeps the mediation state, if pressure descends rapidly suddenly from a certain numerical value, shows and dredges successfully, continues to purge again, and accomplishes the pressure guiding system mediation; After mediation finishes, remove each parts of dredging system nitrogen feeder, close pressure guiding system, open stop valve, pressure guiding system comes into operation again.
2. the method for claim 1 is characterized in that the nitrogen pressure that said nitrogen steel cylinder provides is 0.5MPa~2.5MPa.
3. the method for claim 1 is characterized in that the time that said mediation state keeps is 3~10 minutes; The time of dredging successful continued purging is 2~5 minutes.
CN2010102082949A 2010-06-24 2010-06-24 Method for dredging pressure guiding system by using high-pressure nitrogen backblowing Active CN101884989B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102082949A CN101884989B (en) 2010-06-24 2010-06-24 Method for dredging pressure guiding system by using high-pressure nitrogen backblowing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102082949A CN101884989B (en) 2010-06-24 2010-06-24 Method for dredging pressure guiding system by using high-pressure nitrogen backblowing

Publications (2)

Publication Number Publication Date
CN101884989A CN101884989A (en) 2010-11-17
CN101884989B true CN101884989B (en) 2012-01-25

Family

ID=43071172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102082949A Active CN101884989B (en) 2010-06-24 2010-06-24 Method for dredging pressure guiding system by using high-pressure nitrogen backblowing

Country Status (1)

Country Link
CN (1) CN101884989B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104019361A (en) * 2014-06-10 2014-09-03 中国海洋石油总公司 Online unclogging device for small-size valves
CN104132247B (en) * 2014-07-07 2017-06-13 中国寰球工程公司 The long-range pressure line protection device of pilot operated safety valve
CN106755675A (en) * 2016-11-18 2017-05-31 内蒙古包钢钢联股份有限公司 The method of breeze blowing pipe-line system and quick treatment coal spraying pipeline Severe blockage
CN110014002B (en) * 2019-05-22 2021-09-28 中南大学 Dredging device and method for parallel multi-path small-caliber pressure measurement pressure guide hose
CN112916544B (en) * 2019-12-06 2022-07-05 中国石油天然气股份有限公司 Blockage removing device and blockage removing method for condensate cylinder
CN113048407A (en) * 2021-03-18 2021-06-29 中国商用飞机有限责任公司 System for detecting and dredging blockage point of aircraft waste water pipeline and control method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201102027Y (en) * 2007-11-20 2008-08-20 中国石化集团胜利石油管理局黄河钻井总公司钻前公司 Device for removing obstructions in waste pipe with high pressure gas
CN101480653A (en) * 2009-02-20 2009-07-15 中冶实久建设有限公司南京分公司 Nitrogen purging device of hydraulic line and method for cleaning hydraulic line
CN201427121Y (en) * 2009-03-06 2010-03-24 范经刚 High-pressure air impulse pipeline cleaning device
CN201410485Y (en) * 2009-06-04 2010-02-24 广州创特技术有限公司 Air conveying cleaning device

Also Published As

Publication number Publication date
CN101884989A (en) 2010-11-17

Similar Documents

Publication Publication Date Title
CN101884989B (en) Method for dredging pressure guiding system by using high-pressure nitrogen backblowing
CN102305761A (en) Acid medium transmission pipeline welded joint and parent metal corrosion simulation testing device and method
CN109140249A (en) A kind of submerged structure gas leakage simulator
EP3198178B1 (en) A metal seal fitting for use on a pipeline
CN109357165B (en) Monitoring and alarming device and method for pressure drop rate of main pipeline of gas pipeline
CN205067238U (en) Pipeline tries water and presses with automatic monitoring system
CN205084729U (en) Waste liquid recovery processing device
CN102563201B (en) Device for eliminating leakage risk of gas gate valve online
CN203500858U (en) Device for detecting coal gas pressure and flow and preventing blockage
CN110681520B (en) Quenching tower spray gun dredging device and dredging control method
CN109856187B (en) Online real-time detection method for hydrocarbon dew point of gas pipeline
CN209841751U (en) Online real-time detection device for water dew point of gas pipeline
CN209927761U (en) Online real-time detection device for hydrocarbon dew point of gas pipeline
CN105546257B (en) Do not stop the supple of gas or steam online boring device and method
CN203683155U (en) BSL-3 laboratory active toxic wastewater centralized treatment system
CN211502028U (en) Pollution discharge and exhaust device for instrument
CN202494674U (en) Centralized online sulfur hexafluoride detection system
CN207248572U (en) Fluid sampling device in a kind of vacuum pipe
CN106989276B (en) A kind of on-line automatic method for discharging pollution of gas pipeline yard
CN209086016U (en) A kind of sampler
CN210674555U (en) Purging device of analysis gas sampling device
CN109655349A (en) The high pressure pressure testing device of pipeline for remotely controlling
CN204554362U (en) A kind of Chlorine Buffer Vessel
CN217051630U (en) Automatic safe unloading system for anhydrous hydrogen fluoride
CN204154535U (en) For the solution sampling system of ammonium nitrate tank car

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 550500 Guizhou Province, Qiannan Buyei and Miao Autonomous Prefecture Fuquan Racecourse town Yingbin Road No. 1 Wengfu group

Patentee after: WENGFU GROUP Co.,Ltd.

Address before: 23, 550002 floor, urn Fuk international, No. 57, South City Road, Guizhou, Guiyang

Patentee before: WENGFU GROUP Co.,Ltd.

CP02 Change in the address of a patent holder