CN101881801A - 一种光伏逆变器漏电流检测方法 - Google Patents

一种光伏逆变器漏电流检测方法 Download PDF

Info

Publication number
CN101881801A
CN101881801A CN 201010232636 CN201010232636A CN101881801A CN 101881801 A CN101881801 A CN 101881801A CN 201010232636 CN201010232636 CN 201010232636 CN 201010232636 A CN201010232636 A CN 201010232636A CN 101881801 A CN101881801 A CN 101881801A
Authority
CN
China
Prior art keywords
leakage current
formula
time
limit
variation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010232636
Other languages
English (en)
Other versions
CN101881801B (zh
Inventor
徐锡军
张彦虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Chint Power Systems Co ltd
Original Assignee
SHANGHAI CHINT POWER SYSTEMS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI CHINT POWER SYSTEMS CO Ltd filed Critical SHANGHAI CHINT POWER SYSTEMS CO Ltd
Priority to CN2010102326360A priority Critical patent/CN101881801B/zh
Publication of CN101881801A publication Critical patent/CN101881801A/zh
Application granted granted Critical
Publication of CN101881801B publication Critical patent/CN101881801B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Inverter Devices (AREA)
  • Photovoltaic Devices (AREA)

Abstract

本发明提供了一种基于加权滑动平均预测法的光伏逆变器漏电流检测方法,将漏电流的变化程度量化为漏电流和其作用时间的积分,通过加权滑动平均预测的方法,实现对漏电流的动态保护。仿真和实验结果显示所提方法对动态漏电流变化的保护是有效的,符合安规要求,可以应用于具有时间阶梯特性的动态保护领域。

Description

一种光伏逆变器漏电流检测方法
技术领域
本发明涉及逆变器领域,尤其涉及光伏逆变器漏电流检测领域,具体地说是一种基于加权滑动平均预测算法的光伏逆变器漏电流检测方法,可用于具有阶梯时间保护特性的应用场合。
背景技术
在光伏逆变器产品中,软件保护种类繁多,从保护反应速度来看,有瞬时值保护、有稳态值保护、有均方根值保护及变化率保护等等。在VDE0126-1-1,2006-02标准中,漏电流保护需分成两种:静态保护和动态保护。由于动态保护要求对不同变化率要有不同的反应时间,但其又没有明确指出其变化率的量化指标,因而给实际操作带来很大的难度。
发明内容
本发明要解决的是现有光伏逆变器漏电流检测方法不能对漏电流的变化率和其作用时间的进行综合考虑并量化的问题,旨在提供一种基于加权滑动平均预测法的光伏逆变器漏电流检测方法,通过加权累加方法针对变化率进行监控保护的方法,可以应用于具有时间阶梯特性的动态保护领域。
解决上述问题采用的技术方案是:一种光伏逆变器漏电流检测方法,其特征在于包括以下步骤:
一、采用加权滑动平均预测法确定增量面积和阀值的计算方法
1)基本增量面积的确定
设定对象运动方程为y=f(xk),对象时间从xk变化到xk+n,输出相应从yk变化到yk+n,将这段时间变化的程度用增量面积表示,利用冲量等效原理,增量面积ΔS用公式(1)表示为:
ΔS = ∫ x k x k + n f ( x ) dx - f ( x k ) × ( x k + n - x k ) - - - ( 1 )
≈ y k × ( x k + 1 - x k ) + y k + 1 × ( x k + 2 - x k + 1 ) + . . . + y k + n - 1 × ( x k + n - x k + n ) - y k × ( x k + n - x k )
式中:x表示时间,y表示漏电流,角标k表示经过离散化处理后的结果,n表示时间窗口范围;
设采样时间为固定的Ts,那么
xk+i=xk+i×Ts    (2)
式中,i表示第i个采样点;
把公式(2)代入公式(1),得:
ΔS=(yk+1-yk)×Ts+(yk+2-yk)×Ts+...+(yk+n-1-yk)×Ts    (3)
2)对增量面积加权
若yk+i相对于yk变化范围比较大时,我们期望表示变化程度的ΔS应相应加强,而yk+i相对于yk变化范围比较小时,期望表示变化程度的ΔS相应减弱;用权重系数ηi与(yk+i-yk)的乘积来表示变化程度是否要加强,加权后的增量面积ΔS用公式(4)表示为:
ΔS=[(yk+1-yk)×ηk+(yk+2-yk)×ηk+1+...+(yk+n-1-yk)×ηk+n-2]×Ts    (4)
所述的权重系数ηi采用运动方程y=f(xk)为阶跃曲线时的特殊情况来确定:设ΔS在xk+m时就达到阀值ΔSlimit,其中,m表示阶跃量持续的时间长度,且m≤n,ΔSlimit表示对应于漏电流最大程度变化、最快时间响应要求时的增量面积,如此可得
ΔSlimit=[(yk+1-yk)×ηk+(yk+2-yk)×ηk+1+...+(yk+m-1-yk)×ηk+m-2]×Ts    (5)
yk+1=yk+2=...=yk+m-1=yk+m=...=yk+n    (6)
ηk=ηk+1=...=ηk+m-2=ηk+m-1=...=ηk+n-1    (7)
把公式(6)和公式(7)代入公式(5):
ΔSlimit=[(yk+1-yk)×ηk×(m-1)]×Ts    (8)
所以根据公式(8)可得:
η k = Δ S limit ( y k + 1 - y k ) × ( m - 1 ) × T s - - - ( 9 )
二、实时监控漏电流
1)根据公式(8)计算出需要保护的阀值ΔSlimit
2)根据公式(9)计算出各段漏电流程度变化及其对应时间响应的权重系数ηi,进而实时根据公式(4)计算出ΔS;
3)若ΔS≥ΔSlimit,则报故障;反之,ΔS<ΔSlimit,则无故障,继续滑动窗口,Ts时间后,获取新的yk+n,再重新计算新的ΔS,并与ΔSlimit比较。
本发明的光伏逆变器漏电流检测方法,将漏电流的变化程度量化为漏电流和其作用时间的积分,通过加权滑动平均预测的方法,实现对漏电流的动态保护。仿真和实验结果显示所提方法对动态漏电流变化的保护是有效的,符合安规要求。
对于起点yk的取值方法也是可以多样性的,可取xj(xk前的时刻)到xk时刻的滑动平均值、加权平均值、加权滑动平均、最大值或最小值等,具体采用何种方法计算出的yk根据实际系统要求而定。
另外,n值大小即时间窗口范围的截取原则需根据保护最长时间要求、软件计算和存储量来综合考虑。
附图说明
下面结合附图和实施例对本发明作进一步说明。
图1是运动方程y=f(x)曲线示意图。
图2是运动方程y=f(x)为阶跃曲线时示意图。
图3是漏电流变化30mA时,微处理器响应波形图。
图4是漏电流变化60mA时,微处理器响应波形图。
图5是漏电流变化150mA时,微处理器响应波形图。
具体实施方式
本发明的光伏逆变器漏电流检测方法,包括以下步骤:
一,加权滑动平均预测算法
设定对象运动方程为y=f(x),对象时间从xk变化到xk+n,运动状态相应从yk变化到yk+n,那么这段时间变化的程度可以用增量面积表示(下图1中阴影区域)。利用冲量等效原理,定义增量面积ΔS可用公式(1)表示为:
ΔS = ∫ x k x k + n f ( x ) dx - f ( x k ) × ( x k + n - x k ) - - - ( 1 )
≈ y k × ( x k + 1 - x k ) + y k + 1 × ( x k + 2 - x k + 1 ) + . . . + y k + n - 1 × ( x k + n - x k + n ) - y k × ( x k + n - x k )
若采样时间为固定的Ts,那么
xk+i=xk+i×Ts    (2)
把公式(2)代入公式(1),可得:
ΔS=(yk+1-yk)×Ts+(yk+2-yk)×Ts+...+(yk+n-1-yk)×Ts    (3)
若yk+i相对于yk变化范围比较大时,我们期望表示变化强度的增量面积ΔS应相应加强,而yk+i相对于yk变化范围比较小时,期望表示变化程度的ΔS相应减弱。在这里,我们可以引入权重系数ηi,让ηi与(yk+i-yk)的乘积来表示变化强度是否要加强,即得到加权滑动平均算法
ΔS=[(yk+1-yk)×ηk+(yk+2-yk)×ηk+1+...+(yk+n-1-yk)×ηk+n-2]×Ts    (4)
yk+i可以通过采样得到,权重系数ηi的确定原理:对于运动方程y=f(x)为阶跃曲线(如图2所示)时,我们期望ΔS在xk+m(m≤n)时就达到保护阀值ΔSlimit(ΔSlimit对应于最大程度变化、最快时间响应要求时的增量面积),如此,可得ΔSlimit=[(yk+1-yk)×ηk+(yk+2-yk)×ηk+1+...+(yk+m-1-yk)×ηk+m-2]×Ts    (5)由图2可知:
yk+1=yk+2=...=yk+m-1=yk+m=...=yk+n           (6)
ηk=ηk+1=...=ηk+m-2=ηk+m-1=...=ηk+n-1    (7)
把公式(6)和公式(7)代入公式(5):
ΔSlimit=[(yk+1-yk)×ηk×(m-1)]×Ts              (8)
所以根据公式(8)可得:
η k = Δ S limit ( y k + 1 - y k ) × ( m - 1 ) × T s - - - ( 9 )
对于起点yk的取值方法也是可以多样性的,可取xj(xk前的时刻)到xk时刻的滑动平均值、加权平均值、加权滑动平均、最大值或最小值等,具体采用何种方法计算出的yk根据实际系统要求而定。
另外,n值大小即时间窗口范围的截取原则需根据保护最长时间要求、软件计算和存储量来综合考虑。
二算法应用及设计
例如,在光伏并网逆变器系统中,VDE标准对漏电流动态不同程度变化时,逆变器动作时间有不同要求,具体见表1:
Table 1-Maximum break times
  r.m.s.value of residualcurrent/(mA)   Break time/(s)
  30   0.3
  60   0.15
  150   0.04
因为漏电流基频为50HZ(电网频率),所以软件设计有效值采样间隔时间Ts为20ms。最强的要求是当漏电流变化150mA时,需要在40ms内执行保护动作,让150mA对应的权重系数ηk(150mA)等于单位1,根据式(8)可得到保护阈值
ΔSlimit=[(yk+1-yk)×ηk×(m-1)]×Ts=150mA×1×(2-1)×20ms=0.003A*s。
对于变化30mA漏电流,逆变器需要在0.3s前动作,在这里,设定软件中实际动作时间为0.24s,则m=0.24s/20ms=12,再根据公式(9)就可计算出对应的30mA漏电流变化时权重系数
η k ( 30 mA ) = Δ S limit ( y k + 1 - y k ) × ( m - 1 ) × T s = 0.003 A * s 30 mA × ( 12 - 1 ) × 20 ms ≈ 0.45
同理,对于变化60mA漏电流,逆变器需要在0.15s前动作。在这里,设定软件中实际动作时间为0.12s,则
Figure BDA0000023531740000053
而ΔSlimit为0.003A*s,根据公式(9)算出对应变化60mA的ηk(60mA)=0.5。
类似地,当漏电流在60mA~150mA之间时,为了确定加权系数,可利用线性插值法或其它插值算法,计算出保护响应时间,进而可计算出加权系数。如此,在实际系统中,实时按公式(4)计算瞬时ΔS,然后与ΔSlimit(等于0.003As)比较。若ΔS>ΔSlimit,则报故障;反之,ΔS<ΔSlimit,则无故障,继续滑动窗口,Ts时间后,获取新的yk+n,再重新计算新的ΔS,并与ΔSlimit比较。利用此保护策略,就可用软件实现漏电流动态变化保护。
三算法验证
根据上面设计思想和原理,编写了光伏逆变器漏电流保护代码。利用信号发生器产生交流信号,该信号模拟为漏电流信号(图3、4、5中CH1信号)。当微处理认为需要漏电流保护动作时,微处理器的IO口(图3、4、5中CH2信号)输出高电平信号,否则输出低电平。
1)漏电流有效值从0mA→30mA时,微处理器的动作响应时间约为220ms,微处理器响应波形图参见图3;
2)漏电流有效值从0mA→60mA时,微处理器的动作响应时间约为120ms,微处理器响应波形图参见图4;
3)漏电流有效值从0mA→150mA时,微处理器的动作响应时间约为40ms,微处理器响应波形图参见图5。
从测试效果分析,漏电流保护正确,符合VDE0126-1-1标准要求。另外,在实际调试中,由于采样误差和有效值计算滞后因素影响,需要对权重系数ηk进行微调,这样才有比较好的动态响应效果。
应该理解到的是:上述实施例只是对本发明的说明,而不是对本发明的限制,任何不超出本发明实质精神范围内的发明创造,均落入本发明的保护范围之内。

Claims (3)

1.一种光伏逆变器漏电流检测方法,其特征在于包括以下步骤:
一、采用加权滑动平均预测法确定增量面积和阀值的计算方法
1)基本增量面积的确定
设定对象运动方程为y=f(xk),对象时间从xk变化到xk+n,输出相应从yk变化到yk+n,将这段时间变化的程度用增量面积表示,利用冲量等效原理,增量面积ΔS用公式(1)表示为:
ΔS = ∫ x k x k + n f ( x ) dx - f ( x k ) × ( x k + n - x k ) - - - ( 1 )
≈ y k × ( x k + 1 - x k ) + y k + 1 × ( x k + 2 - x k + 1 ) + . . . + y k + n - 1 × ( x k + n - x k + n ) - y k × ( x k + n - x k )
式中:x表示时间,y表示漏电流,k表示经过离散化处理后的结果,n表示时间窗口范围;
设采样时间为固定的Ts,那么
xk+i=xk+i×Ts    (2)
式中:i表示第i个采样点;
把公式(2)代入公式(1),得:
ΔS=(yk+1-yk)×Ts+(yk+2-yk)×Ts+...+(yk+n-1-yk)×Ts    (3)
2)对增量面积加权
若yk+i相对于yk变化范围比较大时,我们期望表示变化程度的ΔS应相应加强,而yk+i相对于yk变化范围比较小时,期望表示变化程度的ΔS相应减弱;用权重系数ηi与(yk+i-yk)的乘积来表示变化程度是否要加强,加权后的增量面积ΔS用公式(4)表示为:
ΔS=[(yk+1-yk)×ηk+(yk+2-yk)×ηk+1+...+(yk+n-1-yk)×ηk+n-2]×Ts    (4)
所述的权重系数ηi采用运动方程y=f(x)为阶跃曲线时的特殊情况来确定:
设ΔS在xk+m时就达到阀值ΔSlimit,其中,m表示阶跃量持续的时间长度,且m≤n,ΔSlimit表示对应于漏电流最大程度变化、最快时间响应要求时的增量面积,如此可得
ΔSlimit=[(yk+1-yk)×ηk+(yk+2-yk)×ηk+1+...+(yk+m-1-yk)×ηk+m-2]×Ts    (5)
yk+1=yk+2=...=yk+m-1=yk+m=...=yk+n                                   (6)
ηk=ηk+1=...=ηk+m-2=ηk+m-1=...=ηk+n-1                            (7)
把公式(6)和公式(7)代入公式(5):
ΔSlimit=[(yk+1-yk)×ηk×(m-1)]×Ts                                      (8)
所以根据公式(8)可得:
η k = Δ S limit ( y k + 1 - y k ) × ( m - 1 ) × Ts - - - ( 9 )
二、实时监控漏电流
1)根据公式(8)计算出需要保护的阀值ΔSlimit
2)根据公式(9)计算出各段漏电流程度变化及其对应时间响应的权重系数ηi,进而实时根据公式(4)计算出ΔS;
3)若ΔS≥ΔSlimit,则报故障;反之,ΔS<ΔSlimit,则无故障,继续滑动窗口,Ts时间后,获取新的yk+n,再重新计算新的ΔS,并与ΔSlimit比较。
2.如权利要求1所述的光伏逆变器漏电流检测方法,其特征在于起点时刻漏电流yk的取值方法是取xj到xk时刻的滑动平均值、加权平均值、加权滑动平均、最大值或最小值中的任何一种方法,其中xj是xk之前的时刻。
3.如权利要求1或2所述的光伏逆变器漏电流检测方法,其特征在于时间窗口范围n值的截取原则根据保护最长时间要求、软件计算和存储量来综合考虑。
CN2010102326360A 2010-07-21 2010-07-21 一种光伏逆变器漏电流检测方法 Active CN101881801B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102326360A CN101881801B (zh) 2010-07-21 2010-07-21 一种光伏逆变器漏电流检测方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102326360A CN101881801B (zh) 2010-07-21 2010-07-21 一种光伏逆变器漏电流检测方法

Publications (2)

Publication Number Publication Date
CN101881801A true CN101881801A (zh) 2010-11-10
CN101881801B CN101881801B (zh) 2012-07-11

Family

ID=43053862

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102326360A Active CN101881801B (zh) 2010-07-21 2010-07-21 一种光伏逆变器漏电流检测方法

Country Status (1)

Country Link
CN (1) CN101881801B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103543322A (zh) * 2013-10-29 2014-01-29 清源科技(厦门)股份有限公司 一种光伏并网逆变器漏电流检测装置
CN104133099A (zh) * 2014-07-07 2014-11-05 中国电子科技集团公司第四十一研究所 一种光伏阵列残余电流检测装置及方法
CN106372369A (zh) * 2016-10-08 2017-02-01 国家电网公司 用于逆变器输出直流分量、谐波分量检测的瞬时计算方法
CN106374435A (zh) * 2016-11-02 2017-02-01 科博达技术有限公司 逆变器漏电保护方法
CN107968627A (zh) * 2017-11-14 2018-04-27 珠海格力电器股份有限公司 检测装置及方法、以及包含该装置的非隔离型光伏系统
CN109038485A (zh) * 2017-06-12 2018-12-18 孙麓轩 一种漏电流故障的检测方法、装置和系统
CN110073565A (zh) * 2016-11-30 2019-07-30 Abb瑞士股份有限公司 用于控制光伏装置中的漏电流保护设备的方法
CN113421802A (zh) * 2021-06-07 2021-09-21 武汉特试特科技股份有限公司 一种低压智慧断路器保护方法及系统

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1375902A (zh) * 2001-02-26 2002-10-23 佳能株式会社 逆变器、供电系统和减小供电系统中的漏电流的方法
CN1794537A (zh) * 2006-01-06 2006-06-28 清华大学 基于光伏电池的电网功率振荡抑制器
JP3805953B2 (ja) * 2000-07-10 2006-08-09 オムロン株式会社 パワーコンディショナおよびこれを用いた太陽光発電システム
US20090034304A1 (en) * 2007-08-04 2009-02-05 Sma Solar Technology Ag Inverter for grounded direct current source, more specifically for a photovoltaic generator
CN101488662A (zh) * 2008-01-16 2009-07-22 李尔公司 用于故障隔离和漏电流检测的系统和方法
EP2157437A1 (de) * 2008-08-19 2010-02-24 SMA Solar Technology AG Verfahren zur Messung eines Stroms, insbesondere durch eine Erdungsvorrichtung
CN201464592U (zh) * 2009-05-25 2010-05-12 北京天恒华意科技发展有限公司 一种光伏并网逆变器的漏电检测装置
WO2010058536A1 (ja) * 2008-11-18 2010-05-27 三菱電機株式会社 電力変換装置

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3805953B2 (ja) * 2000-07-10 2006-08-09 オムロン株式会社 パワーコンディショナおよびこれを用いた太陽光発電システム
CN1375902A (zh) * 2001-02-26 2002-10-23 佳能株式会社 逆变器、供电系统和减小供电系统中的漏电流的方法
CN1794537A (zh) * 2006-01-06 2006-06-28 清华大学 基于光伏电池的电网功率振荡抑制器
US20090034304A1 (en) * 2007-08-04 2009-02-05 Sma Solar Technology Ag Inverter for grounded direct current source, more specifically for a photovoltaic generator
CN101488662A (zh) * 2008-01-16 2009-07-22 李尔公司 用于故障隔离和漏电流检测的系统和方法
EP2157437A1 (de) * 2008-08-19 2010-02-24 SMA Solar Technology AG Verfahren zur Messung eines Stroms, insbesondere durch eine Erdungsvorrichtung
WO2010058536A1 (ja) * 2008-11-18 2010-05-27 三菱電機株式会社 電力変換装置
CN201464592U (zh) * 2009-05-25 2010-05-12 北京天恒华意科技发展有限公司 一种光伏并网逆变器的漏电检测装置

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
《中国电机工程学报》 20100625 肖华锋等 非隔离型光伏并网逆变器漏电流分析模型研究 第9-14页 1-3 第30卷, 第18期 *
《中国电机工程学报》 20100625 肖华锋等 非隔离型光伏并网逆变器漏电流分析模型研究 第9-14页 1-3 第30卷, 第18期 2 *
《电力电子技术》 20040430 首福俊等 一种新型的光伏逆变器控制方法 第66-68页 1-3 第38卷, 第2期 *
《电力电子技术》 20040430 首福俊等 一种新型的光伏逆变器控制方法 第66-68页 1-3 第38卷, 第2期 2 *
《电力电子技术》 20050630 陈厚岩等 具有零电流关断特性的并网型光伏逆变器研制 第38-39页 1-3 , *
《电力电子技术》 20050630 陈厚岩等 具有零电流关断特性的并网型光伏逆变器研制 第38-39页 1-3 , 2 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103543322A (zh) * 2013-10-29 2014-01-29 清源科技(厦门)股份有限公司 一种光伏并网逆变器漏电流检测装置
CN103543322B (zh) * 2013-10-29 2016-05-04 清源科技(厦门)股份有限公司 一种光伏并网逆变器漏电流检测装置
CN104133099A (zh) * 2014-07-07 2014-11-05 中国电子科技集团公司第四十一研究所 一种光伏阵列残余电流检测装置及方法
CN106372369A (zh) * 2016-10-08 2017-02-01 国家电网公司 用于逆变器输出直流分量、谐波分量检测的瞬时计算方法
CN106372369B (zh) * 2016-10-08 2019-07-19 国家电网公司 用于逆变器输出直流分量、谐波分量检测的瞬时计算方法
CN106374435A (zh) * 2016-11-02 2017-02-01 科博达技术有限公司 逆变器漏电保护方法
CN106374435B (zh) * 2016-11-02 2018-10-02 科博达技术股份有限公司 逆变器漏电保护方法
CN110073565A (zh) * 2016-11-30 2019-07-30 Abb瑞士股份有限公司 用于控制光伏装置中的漏电流保护设备的方法
CN110073565B (zh) * 2016-11-30 2021-08-06 马里奇控股荷兰有限公司 用于控制光伏装置中的漏电流保护设备的方法
CN109038485A (zh) * 2017-06-12 2018-12-18 孙麓轩 一种漏电流故障的检测方法、装置和系统
CN107968627A (zh) * 2017-11-14 2018-04-27 珠海格力电器股份有限公司 检测装置及方法、以及包含该装置的非隔离型光伏系统
CN113421802A (zh) * 2021-06-07 2021-09-21 武汉特试特科技股份有限公司 一种低压智慧断路器保护方法及系统

Also Published As

Publication number Publication date
CN101881801B (zh) 2012-07-11

Similar Documents

Publication Publication Date Title
CN101881801B (zh) 一种光伏逆变器漏电流检测方法
CN102930175B (zh) 基于动态概率潮流的智能配电网脆弱性评估方法
Eidiani Supplementary resource for Using energy function to detect voltage collapse
CN103543403B (zh) 电力系统机组一次调频能力检测方法
Yang et al. Probabilistic short-term wind power forecast using componential sparse Bayesian learning
Khoshkhoo et al. On-line dynamic voltage instability prediction based on decision tree supported by a wide-area measurement system
CN102946253B (zh) 数据采样方法与系统及其在参数辨识中的应用方法与系统
KR20120134052A (ko) 풍력 발전 시스템 및 풍력 발전 시스템에 있어서의 풍력 발전기 증설 방법
CN103150635A (zh) 电力设备运维方法
CN109102132A (zh) 一种基于概率论的微电网脆弱性评估方法及装置
CN103455716A (zh) 一种基于超短期风电功率预测的电力系统电压稳定裕度计算方法
CN114707734A (zh) 一种超短期风功率的预测方法、装置及介质
KR20180093054A (ko) 계통 연계 설비
CN107276105A (zh) 一种基于动态死区的水电机组一次调频方法
Zhicun et al. Evaluating the effect of sample length on forecasting validity of FGM (1, 1)
CN112651560B (zh) 一种超短期风功率预测方法、装置及设备
CN105116959A (zh) 基于最优梯度变步长的最大功率点跟踪控制与预测方法
Petre et al. The use of Markov chains in forecasting wind speed: Matlab source code and applied case study
CN103746383A (zh) 一种基于广域测量系统的节点电压幅值预测方法
CN108959739A (zh) 一种抽水蓄能电站过渡过程压力脉动的分析方法及装置
CN103713688B (zh) 一种自适应变步长mppt控制方法
CN106910010A (zh) 一种主动配电网不确定性潮流分析方法及装置
CN102856884B (zh) 基于热积累的变频器过载方法
CN101650385A (zh) 一种电力网络仪表修改采样频率的方法
CN105587476B (zh) 一种用于风力发电系统的状态监测方法以及装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180308

Address after: 201600 Shanghai city Songjiang District Sixian Road No. 3255 Building No. 4, block B

Co-patentee after: ZHEJIANG ASTRONERGY NEW ENERGY DEVELOPMENT Co.,Ltd.

Patentee after: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

Address before: 201614 Building No. 855, Wen he Lu, Songjiang District, Shanghai

Patentee before: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200417

Address after: 201620 building 4, No. 3255, Sixian Road, Songjiang District, Shanghai

Co-patentee after: ZHEJIANG ASTRONERGY NEW ENERGY DEVELOPMENT Co.,Ltd.

Patentee after: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

Co-patentee after: Zhejiang Zhengtai Power System Co.,Ltd.

Address before: 201600 Shanghai city Songjiang District Sixian Road No. 3255 Building No. 4, block B

Co-patentee before: ZHEJIANG ASTRONERGY NEW ENERGY DEVELOPMENT Co.,Ltd.

Patentee before: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230323

Address after: 201620 building 4, 3255 Sixian Road, Songjiang District, Shanghai

Patentee after: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

Patentee after: Zhejiang Zhengtai Power System Co.,Ltd.

Address before: 201620 building 4, 3255 Sixian Road, Songjiang District, Shanghai

Patentee before: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

Patentee before: ZHEJIANG ASTRONERGY NEW ENERGY DEVELOPMENT Co.,Ltd.

Patentee before: Zhejiang Zhengtai Power System Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240429

Address after: 201600 block B, building 4, 3255 Sixian Road, Songjiang District, Shanghai

Patentee after: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

Country or region after: China

Address before: 201620 building 4, 3255 Sixian Road, Songjiang District, Shanghai

Patentee before: SHANGHAI CHINT POWER SYSTEMS Co.,Ltd.

Country or region before: China

Patentee before: Zhejiang Zhengtai Power System Co.,Ltd.