CN101864948A CN201010191836A CN201010191836A CN101864948A CN 101864948 A CN101864948 A CN 101864948A CN 201010191836 A CN201010191836 A CN 201010191836A CN 201010191836 A CN201010191836 A CN 201010191836A CN 101864948 A CN101864948 A CN 101864948A
Authority
CN
China
Prior art keywords
pump
working solution
links
control system
dynamic filtration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201010191836A
Other languages
English (en)
Inventor
金雪松
金玉松
王永明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAI'AN COUNTY PETROLEUM SCIENTIFIC RESEARCH INSTRUMENT Co Ltd
Original Assignee
HAI'AN COUNTY PETROLEUM SCIENTIFIC RESEARCH INSTRUMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HAI'AN COUNTY PETROLEUM SCIENTIFIC RESEARCH INSTRUMENT Co Ltd filed Critical HAI'AN COUNTY PETROLEUM SCIENTIFIC RESEARCH INSTRUMENT Co Ltd
Priority to CN201010191836A priority Critical patent/CN101864948A/zh
Publication of CN101864948A publication Critical patent/CN101864948A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

压裂酸化工作液动态滤失仪,它涉及石油工业领域。它由注入系统(1)、岩心夹持器(2)、环压跟踪泵(3)、回压控制系统(4)和计量系统(5)组成,注入系统(1)与岩心夹持器(2)相连,岩心夹持器(2)与环压跟踪泵(3)相连,环压跟踪泵(3)与回压控制系统(4)相连,回压控制系统(4)与计量系统(5)相连。它能准确地对液体渗透率、渗透率梯度进行测定,以及很好地对地层敏感性评价、采油工艺及提高采收率进行研究,且结构合理、外形美观大方、操作方便,经久耐用。

Description

压裂酸化工作液动态滤失仪
技术领域:
本发明涉及石油工业领域,尤其涉及压裂酸化工作液动态滤失仪。
背景技术:
自进入21世纪以来,世界能源出现危机,国际油价居高不下。在该严峻形势下,要确保最大限度地开发油气资源,就必须保护好油气藏,避免在开发过程中造成不应有的损害。而一些先进的石油仪器也是必不可少的,例如滤失仪,但是现在很多的滤失仪在模拟地层压力,地层温度的条件不能够很好地对液体渗透率、渗透率梯度进行准确地测定,对于地层敏感性评价不够透彻,而且对于采油工艺研究的一些试验不能准确地测量到数据,进行分析。
发明内容:
本发明的目的是提供压裂酸化工作液动态滤失仪,它能准确地对液体渗透率、渗透率梯度进行测定,以及很好地对地层敏感性评价、采油工艺及提高采收率进行研究。
为了解决背景技术所存在的问题,本发明是采用以下技术方案:它由注入系统、岩心夹持器、环压跟踪泵、回压控制系统和计量系统组成,注入系统与岩心夹持器相连,岩心夹持器与环压跟踪泵相连,环压跟踪泵与回压控制系统相连,回压控制系统与计量系统相连。
所述的注入系统由注入泵、中间容器和管阀件组成。
所述的岩心夹持器的轴向设置有测压孔,以便测试测试液侵入深度和岩心端面堵塞程度。
所述的环压跟踪泵由加压泵、气动阀和电磁阀组成,加压泵通过截止阀、单向阀与气动阀相连,气动阀与电磁阀相连。
所述的回压控制系统由回压阀、缓冲容器和回压泵组成,回压阀下端与计量系统相连,上端与缓冲容器相连,缓冲容器与回压泵相连。
本发明是用来在模拟地层压力、地层温度的条件下并通过数据采集系统及自动控制系统等对对液体渗透率、渗透率梯度进行测定;研究钻井、完井、注水、增产措施和修井作业中,外来物质对地层的伤害及避免或减轻伤害的方法,可以进行正反向渗透率测试和酸液滤失测试,可从任意一端注入不同流体,以确定最优的油藏处理方案。
本发明的优点是结构合理、外形美观大方、操作方便,经久耐用。
附图说明:
图1为本发明的结构示意图。
具体实施方式:
参照图1,本具体实施方式采用以下技术方案:它由注入系统1、岩心夹持器2、环压跟踪泵3、回压控制系统4和计量系统5组成,注入系统1与岩心夹持器2相连,岩心夹持器2与环压跟踪泵3相连,环压跟踪泵3与回压控制系统4相连,回压控制系统4与计量系统5相连。
所述的注入系统1由注入泵、中间容器和管阀件组成。
所述的岩心夹持器2的轴向设置有测压孔2-1,以便测试测试液侵入深度和岩心端面堵塞程度。
所述的环压跟踪泵3由加压泵3-1、气动阀3-2和电磁阀3-3组成,加压泵3-1通过截止阀、单向阀与气动阀3-2相连,气动阀3-1与电磁阀3-3相连。
所述的回压控制系统4由回压阀4-1、缓冲容器4-2和回压泵4-3组成,回压阀4-1下端与计量系统5相连,上端与缓冲容器4-2相连,缓冲容器4-2与回压泵4-3相连。
本具体实施方式是用来在模拟地层压力、地层温度的条件下对对液体渗透率、渗透率梯度进行测定;研究钻井、完井、注水、增产措施和修井作业中,外来物质对地层的伤害及避免或减轻伤害的方法,可以进行正反向渗透率测试和酸液滤失测试,可从任意一端注入不同流体,以确定最优的油藏处理方案。
本具体实施方式的优点是结构合理、外形美观大方、操作方便,经久耐用。

Claims (4)

1.压裂酸化工作液动态滤失仪,其特征在于它由注入系统(1)、岩心夹持器(2)、环压跟踪泵(3)、回压控制系统(4)和计量系统(5)组成,注入系统(1)与岩心夹持器(2)相连,岩心夹持器(2)与环压跟踪泵(3)相连,环压跟踪泵(3)与回压控制系统(4)相连,回压控制系统(4)与计量系统(5)相连。
2.根据权利要求1所述的压裂酸化工作液动态滤失仪,其特征在于所述的岩心夹持器(2)的轴向设置有测压孔(2-1)。
3.根据权利要求1所述的压裂酸化工作液动态滤失仪,其特征在于所述的环压跟踪泵(3)由加压泵(3-1)、气动阀(3-2)和电磁阀(3-3)组成,加压泵(3-1)通过截止阀、单向阀与气动阀(3-2)相连,气动阀(3-1)与电磁阀(3-3)相连。
4.根据权利要求1所述的压裂酸化工作液动态滤失仪,其特征在于所述的回压控制系统(4)由回压阀(4-1)、缓冲容器(4-2)和回压泵(4-3)组成,回压阀(4-1)下端与计量系统(5)相连,上端与缓冲容器(4-2)相连,缓冲容器(4-2)与回压泵(4-3)相连。
CN201010191836A 2010-06-04 2010-06-04 压裂酸化工作液动态滤失仪 Pending CN101864948A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010191836A CN101864948A (zh) 2010-06-04 2010-06-04 压裂酸化工作液动态滤失仪

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010191836A CN101864948A (zh) 2010-06-04 2010-06-04 压裂酸化工作液动态滤失仪

Publications (1)

Publication Number Publication Date
CN101864948A true CN101864948A (zh) 2010-10-20

Family

ID=42956854

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010191836A Pending CN101864948A (zh) 2010-06-04 2010-06-04 压裂酸化工作液动态滤失仪

Country Status (1)

Country Link
CN (1) CN101864948A (zh)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102237005A (zh) * 2011-05-10 2011-11-09 中国石油化工股份有限公司 回压自动控制装置
CN102411044A (zh) * 2011-12-05 2012-04-11 中国石油大学(华东) 成岩作用模拟实验装置及方法
CN103015997A (zh) * 2013-01-16 2013-04-03 西南石油大学 一种冰晶暂堵压裂工艺的滤失封堵测试装置及模拟方法
CN103412111A (zh) * 2013-07-25 2013-11-27 中国石油天然气股份有限公司 岩心测量系统和方法
CN103510944A (zh) * 2012-06-28 2014-01-15 中国石油化工股份有限公司 一种高温高压封堵/防吐模拟评价装置及其评价方法
CN103592213A (zh) * 2013-11-25 2014-02-19 中国石油化工集团公司 一种适应多渗透率级差分流酸化实验装置及评价方法
CN103790580A (zh) * 2014-01-11 2014-05-14 南通华兴石油仪器有限公司 一种干热岩压裂原位换热实验室模拟系统装置
CN103790564A (zh) * 2014-01-11 2014-05-14 南通华兴石油仪器有限公司 一种干热岩压裂高压提采实验室模拟装置
CN103868841A (zh) * 2014-03-28 2014-06-18 海安县石油科研仪器有限公司 测定极低泥页岩渗透率和膜效率的实验装置
CN104453871A (zh) * 2014-10-16 2015-03-25 中国海洋石油总公司 油气井工作液储层保护效果静态测试法
CN105388249A (zh) * 2014-09-03 2016-03-09 中国石油天然气股份有限公司 一种测试酸蚀裂缝导流能力的装置及方法
CN110410061A (zh) * 2019-07-10 2019-11-05 中国地质大学(武汉) 一种煤层气渗透滤失测试装置
CN110685680A (zh) * 2019-11-12 2020-01-14 西南石油大学 一种大尺寸多角度酸蚀裂缝酸液评价装置及方法
CN110987764A (zh) * 2019-12-25 2020-04-10 重庆大学 长煤岩样气液渗流测试系统

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102237005A (zh) * 2011-05-10 2011-11-09 中国石油化工股份有限公司 回压自动控制装置
CN102411044A (zh) * 2011-12-05 2012-04-11 中国石油大学(华东) 成岩作用模拟实验装置及方法
CN102411044B (zh) * 2011-12-05 2014-04-30 中国石油大学(华东) 成岩作用模拟实验装置
CN103510944B (zh) * 2012-06-28 2017-03-29 中国石油化工股份有限公司 一种高温高压封堵/防吐模拟评价装置及其评价方法
CN103510944A (zh) * 2012-06-28 2014-01-15 中国石油化工股份有限公司 一种高温高压封堵/防吐模拟评价装置及其评价方法
CN103015997B (zh) * 2013-01-16 2015-05-27 西南石油大学 一种冰晶暂堵压裂工艺的滤失封堵测试装置及模拟方法
CN103015997A (zh) * 2013-01-16 2013-04-03 西南石油大学 一种冰晶暂堵压裂工艺的滤失封堵测试装置及模拟方法
CN103412111B (zh) * 2013-07-25 2015-08-05 中国石油天然气股份有限公司 岩心测量系统和方法
CN103412111A (zh) * 2013-07-25 2013-11-27 中国石油天然气股份有限公司 岩心测量系统和方法
CN103592213A (zh) * 2013-11-25 2014-02-19 中国石油化工集团公司 一种适应多渗透率级差分流酸化实验装置及评价方法
CN103592213B (zh) * 2013-11-25 2015-10-28 中国石油化工集团公司 一种适应多渗透率级差分流酸化实验装置及评价方法
CN103790564B (zh) * 2014-01-11 2017-04-12 吉林大学 一种干热岩压裂高压提高采收率实验室模拟装置
CN103790580A (zh) * 2014-01-11 2014-05-14 南通华兴石油仪器有限公司 一种干热岩压裂原位换热实验室模拟系统装置
CN103790564A (zh) * 2014-01-11 2014-05-14 南通华兴石油仪器有限公司 一种干热岩压裂高压提采实验室模拟装置
CN103868841B (zh) * 2014-03-28 2016-03-02 海安县石油科研仪器有限公司 测定极低泥页岩渗透率和膜效率的实验装置
CN103868841A (zh) * 2014-03-28 2014-06-18 海安县石油科研仪器有限公司 测定极低泥页岩渗透率和膜效率的实验装置
CN105388249B (zh) * 2014-09-03 2017-10-17 中国石油天然气股份有限公司 一种测试酸蚀裂缝导流能力的装置及方法
CN105388249A (zh) * 2014-09-03 2016-03-09 中国石油天然气股份有限公司 一种测试酸蚀裂缝导流能力的装置及方法
CN104453871B (zh) * 2014-10-16 2017-04-05 中国海洋石油总公司 油气井工作液储层保护效果静态测试法
CN104453871A (zh) * 2014-10-16 2015-03-25 中国海洋石油总公司 油气井工作液储层保护效果静态测试法
CN110410061A (zh) * 2019-07-10 2019-11-05 中国地质大学(武汉) 一种煤层气渗透滤失测试装置
CN110685680A (zh) * 2019-11-12 2020-01-14 西南石油大学 一种大尺寸多角度酸蚀裂缝酸液评价装置及方法
CN110685680B (zh) * 2019-11-12 2020-07-28 西南石油大学 一种大尺寸多角度酸蚀裂缝酸液评价装置及方法
CN110987764A (zh) * 2019-12-25 2020-04-10 重庆大学 长煤岩样气液渗流测试系统

Similar Documents

Publication Publication Date Title
CN101864948A (zh) 压裂酸化工作液动态滤失仪
CN201687470U (zh) 压裂酸化工作液动态滤失仪
CN102230375B (zh) 煤层瓦斯参数实时监测方法
CN205277410U (zh) 一种支撑剂铺置及导流能力一体化评价实验装置
GB2445846B (en) Methods and apparatus to sample heavy oil in a subterranean formation
CN103244103B (zh) 基于纳米磁流体的水力压裂裂缝实时监测系统及监测方法
CN105114061B (zh) 一种水平井不动管柱多参数组合测试快速找水管柱及方法
CN204402469U (zh) 水压致裂法地应力测量印模系统
CN103048431A (zh) 水力压裂支撑剂沉降及渗透率测试装置
CN105003236A (zh) 基于纳米磁流体的水驱前缘监测系统及监测方法
EP2700785A3 (en) Natural fracture injection test
CN209485873U (zh) 固态颗粒暂堵剂封堵强度模拟评价装置
CN209586344U (zh) 一种致密油藏注天然气驱效果评价装置
CN104453865A (zh) 单回路水压致裂原地应力测量系统
CN106703768B (zh) 一种模拟高低浓度聚合物驱交替注入时机的确定方法
GB2506569A (en) An apparatus, system and method for injecting a fluid into a formation downhole
CN104564049B (zh) 聚合物驱聚窜通道的检测方法
CN102352747B (zh) 煤层气井控压注入增产的方法
CN104747149B (zh) 二元复合驱剂窜通道的检测方法
CN104564000A (zh) 煤层气井活性水-氮气泡沫复合压裂增产方法
CN202166583U (zh) 聚合物溶液在地层孔隙中渗流距离变化模拟实验装置
CN204008536U (zh) 一种多相流对岩石声电特性影响的实验测试装置
CN107725038B (zh) 一种测试封堵性化学调剖剂在油藏中运移深度的方法
CN113062717B (zh) 压裂水平井同井缝间异步注采实验装置
CN205025412U (zh) 一种水平井不动管柱多参数组合测试快速找水管柱

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20101020