CN101864834B - Construction method of wall wood formers adopting steel pipes as back edges - Google Patents

Construction method of wall wood formers adopting steel pipes as back edges Download PDF

Info

Publication number
CN101864834B
CN101864834B CN2010101975195A CN201010197519A CN101864834B CN 101864834 B CN101864834 B CN 101864834B CN 2010101975195 A CN2010101975195 A CN 2010101975195A CN 201010197519 A CN201010197519 A CN 201010197519A CN 101864834 B CN101864834 B CN 101864834B
Authority
CN
China
Prior art keywords
steel pipe
wall
wooden model
wood
formers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2010101975195A
Other languages
Chinese (zh)
Other versions
CN101864834A (en
Inventor
苑宗双
李建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN2010101975195A priority Critical patent/CN101864834B/en
Publication of CN101864834A publication Critical patent/CN101864834A/en
Application granted granted Critical
Publication of CN101864834B publication Critical patent/CN101864834B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a construction method of wall wood formers adopting steel pipes as back edges. The method comprises the following steps of: cutting wall wood formers according to the specification of a building component; fixing wood frames at two side edges and the lower edge of the back of a lowest wall wood former; punching holes on the wall wood formers; hoisting and installing the wall wood formers to a specified position; splicing a plurality of manufactured same wall wood formers together; fixedly connecting steel pipe positioning battens at both the upper ends and the lower ends of the wood frames of the wall wood formers; penetrating a longitudinal steel pipe back edge between the wall wood formers and the steel pipe positioning battens; mounting counter bolts and arranging transverse steel pipe back edges at the upper side and the lower side of each counter bolt; and fastening the counter bolts to clamp all the steel pipe back edges. In the method, ordinary steel pipes replace battens to be used as the back edges of the wall wood formers, thereby wood is greatly saved, the workload of wood processing is reduced, and the steel pipe back edges can be frequently used. The construction method has simplicity, easy application, consumption reduction, stable template structure, good construction appearance quality, high working efficiency, sufficient waste timber utilization, cost saving, environmental protection and economy.

Description

Adopt the body of wall wooden model job practices of steel pipe as back cord
Technical field
The present invention relates to the job practices of the body of wall wooden model in the building construction process, particularly a kind of body of wall wooden model job practices that adopts steel pipe as back cord.
Background technology
Along with the raising that further Surface Quality of Concrete is required, the mould material that uses bamboo offset plate, wood glue plate and composite plate conduct and concrete surface directly to contact in the building concrete work progress in large quantities.And because these sheet materials itself are thinner, rigidity is little, and the lateral pressure that produces in the time of can not bearing concreting need be provided with the rigidity that back cord is strengthened sheet material, and existing comparative maturity and the back cord material that generally adopts are: flitch.Adopt flitch its easy processing to be arranged as back cord, the easy advantage that is connected with wood-based planet, but it also has significant disadvantages: with iron nail flitch is fixed on the wooden model back side, needs processing wooden model personnel many, the process-cycle is long; Wooden model and flitch damage easily during dismounting, and waste material increases cost; Increase the timber use amount, the waste resource.These defectives have a strong impact on construction quality and efficient at work progress.
Summary of the invention
The present invention be directed in the prior art with flitch as many defectives that back cord exists, provide that a kind of structure is firm, construction quality good, the employing steel pipe of high efficiency is as the body of wall wooden model job practices of back cord.
Realize that the technical scheme that above-mentioned purpose adopts is: a kind of body of wall wooden model job practices that adopts steel pipe as back cord, this job practices is carried out according to following steps:
1. cut the body of wall wooden model according to the size of building unit;
2. the dual-side and the bottom at the body of wall wooden model back side below fix a wooden frame respectively, and the thickness of this wooden frame equates with outer diameter of steel pipes as back cord;
3. according to the spacing of split bolt to be installed, on the body of wall wooden model, punch;
The body of wall wooden model that 4. will have wooden frame lifts the designated mounting position;
5. a plurality of identical body of wall wooden model that will make is bolted together, and it is fixing that the joint of left and right sides neighboring walls wooden model leads nail with wood board sheet, and the wooden frame of neighbouring body of wall wooden model joint is fixed with short flitch;
6. the wooden frame in body of wall wooden model both sides is connected with horizontally disposed steel pipe positioning bar in two ends up and down;
7. between body of wall wooden model and steel pipe positioning bar, place many vertical steel pipe back cords;
8. split bolt is installed, horizontal steel pipe back cord is set, in the end of each split bolt the clamp that is used for fixing horizontal steel pipe back cord is installed again in the both sides up and down of every split bolt;
9. fastening split bolt clamps each steel pipe back cord.
Compared with prior art, the present invention adopts common steel tube to replace the back cord of flitch as the body of wall wooden model, has saved timber greatly, reduce the workload of Wood Processing, can frequently use, job practices is simple, reduces to consume, formwork structure is firm, the construction presentation quality is good, and high efficiency makes full use of waste and old timber, save cost, environmental protection and economy.
Description of drawings
Fig. 1 is a body of wall wooden model formwork structural representation of the present invention.
Fig. 2 is adjacent wooden model docking structure schematic diagram.
Fig. 3 is that the A-A of Fig. 1 is to structural representation.
Fig. 4 is that the B-B of Fig. 1 is to structural representation.
Fig. 5 is that the C-C of Fig. 1 is to structural representation.
Among the figure: body of wall wooden model 1, vertical steel pipe back cord 2, horizontal steel pipe back cord 3, steel pipe positioning bar 4, clamp 5, split bolt 6, wooden frame 7, wood board sheet 8, short flitch 9.
The specific embodiment
The invention will be described further below in conjunction with drawings and Examples.
Referring to accompanying drawing 1-5, in the present embodiment, this employing steel pipe is as the body of wall wooden model job practices of back cord, and this job practices is carried out according to following steps:
1. the size that makes up according to building is cut body of wall wooden model 1, and this body of wall wooden model 1 is wooden platy structure.
2. the dual-side and the bottom at body of wall wooden model 1 back side below fix a wooden frame 7 respectively, this wooden frame 7 adopts the flitch frame of 48*48 (mm), with the flitch of 48*48 nail wooden frame 7 is fixed on the back side of body of wall wooden model 1, the thickness of this wooden frame 7 is identical with outer diameter of steel pipes as back cord.
3. according to the spacing of split bolt to be installed 6, punching is used to install split bolt on body of wall wooden model 1.
The body of wall wooden model 1 that 4. will have wooden frame 7 lifts the designated mounting position.
5. a plurality of identical body of wall wooden model 1 that will make is bolted together, and wherein: it is fixing that the joint of left and right sides neighboring walls wooden model 1 leads nail with wood board sheet 8; The short flitch 9 of wooden frame 7 usefulness of neighbouring body of wall wooden model 1 joint is fixed, and is generally vertical fixing, and guarantees its stability; , to strengthen the bonding strength of adjacent wooden model.
6. the wooden frame in body of wall wooden model 1 both sides is connected with horizontally disposed steel pipe positioning bar 4 with steel nail respectively in two ends about in the of 7, promptly follow closely respectively together at the two ends up and down of wooden frame 7, this steel pipe positioning bar 4 is horizontally fixed on the surface of wooden frame 7, distance between steel pipe positioning bar 4 and the body of wall wooden model 1 is the thickness of wooden frame 7, be the diameter of steel pipe, the steel pipe back cord adopts the scaffold pipe of ∮ 48*3.5.
7. between body of wall wooden model 1 and steel pipe positioning bar 4, place many vertical steel pipe back cords 2.
8. split bolt 6 is installed, in the both sides up and down of every split bolt 6 horizontal steel pipe back cord 3 is set, in the end of each split bolt 6 clamp 5 that is used for fixing horizontal steel pipe back cord is installed again, this clamp 5 adopts " mountain " type clamping structure, and be sleeved on the screw rod, be close to horizontal steel pipe back cord 2.
9. fastening split bolt 6 clamps each steel pipe back cord by steel pipe positioning bar 4, and wherein the thickness of wooden frame equates with the external diameter of steel pipe back cord.
More than disclosed be one embodiment of the present of invention only, but the present invention is not limited thereto, any those skilled in the art can think variation, all should drop within protection scope of the present invention.

Claims (1)

1. body of wall wooden model job practices that adopts steel pipe as back cord is characterized in that this job practices is carried out according to following steps:
1. cut the body of wall wooden model according to the size of building unit;
2. the dual-side and the bottom at the body of wall wooden model back side below fix a wooden frame respectively, and the thickness of this wooden frame equates with outer diameter of steel pipes as back cord;
3. according to the spacing of split bolt to be installed, on the body of wall wooden model, punch;
The body of wall wooden model that 4. will have wooden frame lifts the designated mounting position;
5. a plurality of identical body of wall wooden model that will make is bolted together, and it is fixing that the joint of left and right sides neighboring walls wooden model leads nail with wood board sheet, and the wooden frame of neighbouring body of wall wooden model joint is fixed with short flitch;
6. the wooden frame in body of wall wooden model both sides is connected with horizontally disposed steel pipe positioning bar in two ends up and down;
7. between body of wall wooden model and steel pipe positioning bar, place many vertical steel pipe back cords;
8. split bolt is installed, in the both sides up and down of every split bolt horizontal steel pipe back cord is set, in the end of each split bolt the clamp that is used for fixing horizontal steel pipe back cord is installed again, this clamp adopts " mountain " type clamping structure, and be sleeved on the screw rod, be close to horizontal steel pipe back cord;
9. fastening split bolt clamps each steel pipe back cord.
CN2010101975195A 2010-06-11 2010-06-11 Construction method of wall wood formers adopting steel pipes as back edges Active CN101864834B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101975195A CN101864834B (en) 2010-06-11 2010-06-11 Construction method of wall wood formers adopting steel pipes as back edges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101975195A CN101864834B (en) 2010-06-11 2010-06-11 Construction method of wall wood formers adopting steel pipes as back edges

Publications (2)

Publication Number Publication Date
CN101864834A CN101864834A (en) 2010-10-20
CN101864834B true CN101864834B (en) 2011-07-20

Family

ID=42956742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101975195A Active CN101864834B (en) 2010-06-11 2010-06-11 Construction method of wall wood formers adopting steel pipes as back edges

Country Status (1)

Country Link
CN (1) CN101864834B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102777031A (en) * 2012-08-06 2012-11-14 中国建筑第六工程局有限公司 Construction method of template with no split bolt hole
CN105822056B (en) * 2016-03-24 2019-03-26 中国五冶集团有限公司 Shear wall formwork supporting

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2052097A5 (en) * 1969-07-18 1971-04-09 Bourgeat Eugene
CN2489023Y (en) * 2001-07-05 2002-05-01 王振功 High precision universal combined big shuttering
CN101654956B (en) * 2008-08-18 2011-05-11 杨小平 Support mould method for cast-in-situ wall bodies
CN201386392Y (en) * 2009-04-21 2010-01-20 中建三局第二建设工程有限责任公司 Concrete hollow supporting body used for wall body construction technique

Also Published As

Publication number Publication date
CN101864834A (en) 2010-10-20

Similar Documents

Publication Publication Date Title
CN102704672A (en) Installation construction method for large all-steel formwork at internal corner of shear wall
CN201232354Y (en) Wooden formwork for shaping metal lining cylinder
CN204040458U (en) A kind of aluminum template system aluminium extruded sections
CN101864834B (en) Construction method of wall wood formers adopting steel pipes as back edges
CN201193401Y (en) Template for coated bamboo plywood with steel frame
CN101089329B (en) Assemblied polyvinyl chloride building engineering shuttering
CN201943501U (en) Steel-wood door frame
CN203213587U (en) Floor early-dismounting template made of aluminum alloy
CN201778486U (en) Quick-detach stereotyped wood plywood wallboard system
CN204715738U (en) A kind of corner for building template
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN204199509U (en) Thin-walled square chest float Structure
CN211447754U (en) Composite building template with multilayer structure
CN211622593U (en) Modular floor formwork device
CN206144136U (en) Construction of steel wood combination formula is with a supporting beam
CN202627485U (en) Aluminum-alloy-framed building formwork
CN204826653U (en) Stupefied fixing clip of vertical back of body of aluminum mould board
CN201334861Y (en) Ascending stair
CN204401851U (en) A kind of composite ceiling structure for building
CN204850424U (en) Aluminum alloy template
CN204826636U (en) Ear design support is chosen to plain type roof beam
CN212562501U (en) Building template support device
CN204850425U (en) Aluminum alloy template
CN202658881U (en) Large simple and easy sizing shear wall bamboo glue template
CN210552010U (en) Building template

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant