CN101862699A CN201010191141A CN201010191141A CN101862699A CN 101862699 A CN101862699 A CN 101862699A CN 201010191141 A CN201010191141 A CN 201010191141A CN 201010191141 A CN201010191141 A CN 201010191141A CN 101862699 A CN101862699 A CN 101862699A
Authority
CN
China
Prior art keywords
grinding
semi
machine
vertical
finished
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201010191141A
Other languages
Chinese (zh)
Other versions
CN101862699B (en
Inventor
王志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING XUANLI HEAVY MACHINERY CO Ltd
Original Assignee
NANJING XUANLI HEAVY MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING XUANLI HEAVY MACHINERY CO Ltd filed Critical NANJING XUANLI HEAVY MACHINERY CO Ltd
Priority to CN2010101911418A priority Critical patent/CN101862699B/en
Publication of CN101862699A publication Critical patent/CN101862699A/en
Application granted granted Critical
Publication of CN101862699B publication Critical patent/CN101862699B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/10Production of cement, e.g. improving or optimising the production methods; Cement grinding

Landscapes

  • Crushing And Grinding (AREA)
  • Disintegrating Or Milling (AREA)

Abstract

The invention belongs to the technical field of cement grinding, in particular to a semi-finished pre-grinding vertical-milling and ball-milling combined grinding device which comprises a semi-finished pre-grinding vertical-milling machine and a ball milling machine, wherein the feeding end of the semi-finished pre-grinding vertical-milling machine is connected with the discharging end of a proportioning belt scale, a gas outlet is connected with a dust remover, and the discharging hole of the dust remover is connected with a finished product conveying machine; the discharging hole of the semi-finished pre-grinding vertical-milling machine is connected with a lifting machine through a vertical milling discharging belt, and the discharging hole of the lifting machine is connected with the feeding hole of the ball milling machine; the gas outlet of the ball milling machine is connected with the dust remover, the discharging hole of the dust remover is connected with the finished product conveying machine; and the discharging hole of the ball milling machine is connected with a powder concentrating machine through the lifting machine, the finished product fine powder discharging hole of the powder concentrating machine is connected with a third finished product conveying machine, and the crude powder discharging hole of the powder concentrating machine is connected with the feeding hole of the ball milling machine through a feed back conveying machine. The invention combines high yield and energy saving of the vertical milling machine with cement grading advantages of the ball milling machine, and has lower investment, lower electricity consumption, more reasonable grading of cement particles, very convenient maintenance and remarkable economic benefit.

Description

Semi-finished pre-grinding vertical and ball milling combination grinding device
Technical field
The invention belongs to the cement grinding technical field, a kind of specifically semi-finished pre-grinding vertical and ball milling combination grinding device.
Background technology
Tradition cement grinding ball mill grinding, the cement granules pattern is good, the concrete good operation performance, the building good endurance, but the ball mill grinding adopts the steel ball fragmentation, and mill efficiency is low, the power consumption height.
At present, more advanced cement grinding process is that roll squeezer adds the ball mill combination grinding device, two kinds of forms are specifically arranged: a kind of is that roll squeezer is made pre-grinding: adopt roll squeezer to add the scattering and grading machine, back road mill adopts open-circuit grinding, can improve mill output 40%~50%, this device enters road, back mill and causes the road, back to grind grinding easily, road, influence back abrasive dust mill power consumption and grog utilization rate because the material that roll squeezer comes out has the fine powder of a great deal of; Another kind is that roll squeezer is made half whole grinding device: adopt roll squeezer to add the V-type powder concentrator, realize half whole grinding, dispose according to different process, can improve mill output 50%~80%, but because the material fine powder content height that the V-type powder concentrator comes out, back road mill must be gone up high-efficient powder concentrator, form two closed-circuit systems, this device is too complicated, and construction investment is very big, and preceding road circulating load is very big, power consumption is very big, the main air blower serious wear must be changed, in addition in 3 months, the common fault of roll squeezer is can not change after the roll wear, can only built-up welding safeguard, maintain extremely difficultly, have a strong impact on system's running rate.
At present, domestic Vertical Mill mainly is used on the new type dry kiln raw grinding, Tianjin Design Inst. of Cement Industry and Chengdu cement industry design and research institute have begun the whole grinding test of Vertical Mill, but because the problem of Vertical Mill cement granules appearance, and thing followed concrete operational problem and endurance issues, present stage is difficult to extensive popularization.
Summary of the invention
Technical problem to be solved by this invention is: at the shortcoming of above prior art existence, a kind of semi-finished pre-grinding vertical and ball milling combination grinding device are proposed, the high yield and saving energy of Vertical Mill and the cement grating advantage of ball mill are combined, invest low, power consumption is lower, and the cement granules grating is more reasonable.
The technical scheme that the present invention solves above technical problem is:
Semi-finished pre-grinding vertical and ball milling combination grinding device, comprise semi-finished pre-grinding vertical machine and ball mill, the semi-finished pre-grinding vertical machine comprises powder concentrator, feeding mouth, mill, top scraper plate, reductor, main motor, air outlet, grinding roller, rocking arm, bottom scraper plate and semi-finished product discharging opening, and the feed end of semi-finished pre-grinding vertical machine connects the blanking end that proportioning belt claims by belt feeder; The gas outlet of semi-finished pre-grinding vertical machine connects first deduster, and the discharging opening of first deduster connects first finished product conveyer, and first deduster links to each other with first dedusting fan; The discharging opening of semi-finished pre-grinding vertical machine connects first elevator by the Vertical Mill outfeed belt, the receive charging aperture of grinding machine of the discharging opening of first elevator; The gas outlet of ball mill connects second deduster, and the discharging opening of second deduster connects second finished product conveyer, and second deduster links to each other with second dedusting fan; The discharging opening of ball mill connects powder concentrator by second elevator, and the finished product fine powder discharging opening of powder concentrator connects the 3rd finished product conveyer, and the meal discharging opening of powder concentrator is by the receive charging aperture of grinding machine of feed back conveyer.
Like this, grinding material is delivered to the semi-finished pre-grinding vertical machine by belt, grinding in the semi-finished pre-grinding vertical machine, the light matter material rises with air-flow, than heavy material whereabouts semi-finished pre-grinding vertical motor spindle, the rising dust-contained airflow is fine graded by dynamic powder concentrator, what meet the finished product requirement is transported to the deduster collection with air-flow, do not meet the synthetic closely knit material bed of the thin returning charge of finished product requirement and charging and continue to mill, collect discharging opening, enter ball mill, the material in small, broken bits that the semi-finished pre-grinding vertical machine comes out enters ball mill and carries out fine-grinding, select powder by elevator to powder concentrator, meal is got back to ball mill bistrique grinding again, and the finished product fine powder is directly put in storage.
This shows, science of the present invention semi-finished pre-grinding vertical machine and ball mill are combined, material are at first carried out half whole grinding by the semi-finished pre-grinding vertical system, and the closed-circuit ball mill system by the band powder concentrator carries out whole grinding then, thereby make the grinding granule-morphology good, the mill efficiency height.
Technical scheme as the further qualification of the present invention:
The outer rim of mill is provided with the barrier circle, and the barrier circle is that a cross section is L shaped annulus, opens the backgauge hole at inner ring, opens fixing hole on the bottom sides, and the barrier circle is fixed by bolts to the edge on mill top by the fixing hole on the bottom sides.The aperture in backgauge hole is 3mm.Material is all extracted out by wind-force in traditional vertical mill, wind-force consumption is big, the blower fan wearing and tearing are big, and after the present invention is provided with the barrier circle, through the material after rolling, constantly move to the mill outer rim down ordering about continuously of centrifugal force, tiny qualified material is outwards dished out from the barrier circle, the coarse granule material is returned mill by barrier circle obstruction to be continued to roll, and guarantees to have only particle diameter to pass through from special barrier circle less than the material of 3mm, can realize many thickness grading once.
The semi-finished pre-grinding vertical machine is supplied hot blast from the bottom, is 30% of traditional Vertical Mill with wind.Pulling moves upward tradition Vertical Mill material 100% by wind-force, after roughly selecting, process Vertical Mill powder concentrator goes out machine, and the most of material of the present invention's half whole Vertical Mill is dished out through barrier, through discharging from half whole Vertical Mill bottom after the air classification, the qualified material of selecting through more than half whole Vertical Mill powder concentrators accounts for about 20% of half whole Vertical Mill charging total amount, and the material material-gas ratio of certain granules is certain, all half whole Vertical Mill actual consumption air quantity are 20% of traditional Vertical Mills, consider certain affluence amount, design air flow is determined 30%.
That end that belt feeder is connected with the feed end of semi-finished pre-grinding vertical machine is provided with a tramp iron separator, can the iron in the cement grinding material can be removed before semi-finished pre-grinding vertical.
The feed end of semi-finished pre-grinding vertical machine is provided with a lattice wheel, can play the effect of lock wind.
First deduster goes out the machine specific surface area of finished products and is controlled at 350m 2/ kg~360m 2/ kg, 0.08mm tail over and are controlled at below 3%.The machine material specific surface area that goes out that the semi-finished pre-grinding vertical machine enters ball mill is controlled at 180m 2/ kg~200m 2/ kg, 0.08mm tail over and are controlled at 40%~50%.The machine specific surface area of finished products that goes out of ball mill is controlled at 460m 2/ kg~480m 2/ kg, 0.08mm tail over and are controlled at below 1%.The machine specific surface area of finished products that goes out of second deduster is controlled at 400m 2/ kg~420m 2/ kg, 0.08mm tail over and are controlled at below 2%.Control out machine material specific surface area and 0.08mm and tail over and to make the cement granules grating more reasonable, help the thickness grading of abrasive material, make grinding effect better.
Advantage of the present invention is: the present invention combines the cement grating advantage of the high yield and saving energy of Vertical Mill and ball mill, invests lowlyer, and power consumption is lower, and the cement granules grating is more reasonable, and Maintenance and Repair are very convenient, and economic benefit is very remarkable.
Description of drawings
Fig. 1 is a structural representation of the present invention.
Fig. 2 is the structural representation of semi-finished pre-grinding vertical machine.
Fig. 3 is the connection diagram of mill and barrier circle.
Fig. 4 is the structural representation of barrier circle.
The specific embodiment
Embodiment one
Present embodiment is a kind of semi-finished pre-grinding vertical and ball milling combination grinding device, and structure comprises semi-finished pre-grinding vertical machine 5 and ball mill 11 as shown in Figure 1.The structure of semi-finished pre-grinding vertical machine 5 as shown in Figure 2, comprise powder concentrator 20, feeding mouth 21, mill 22, top scraper plate 23, reductor 24, main motor 25, air outlet 26, grinding roller 27, rocking arm 28, bottom scraper plate 30 and semi-finished product discharging opening 31, mill 22 is installed on the transmission device of being made up of main motor 25 and braking maneuver 4, and grinding roller 27 is installed on the rocking arm 28.Material enters the semi-finished pre-grinding vertical machine by feeding mouth 21.The outer rim of mill 22 is provided with barrier circle 29, mill is connected as shown in Figure 3 with the barrier circle, and barrier circle 29 is that a cross section is L shaped annulus, opens the backgauge hole at inner ring, open fixing hole on the bottom sides, barrier circle 29 is fixed on the edge on mill 22 tops with bolt 32 by the fixing hole on the bottom sides.The structure of barrier circle 29 as shown in Figure 4, the aperture in backgauge hole 33 is 3mm.Semi-finished pre-grinding vertical machine 5 is from bottom supply hot blast, the semi-finished pre-grinding vertical mill is interior to be 30% of traditional Vertical Mill with wind, pulling moves upward tradition Vertical Mill material 100% by wind-force, after roughly selecting, process Vertical Mill powder concentrator goes out machine, and the most of material of the present invention's half whole Vertical Mill is dished out through barrier, through discharging from half whole Vertical Mill bottom after the air classification, the qualified material of selecting through more than half whole Vertical Mill powder concentrators accounts for about 20% of half whole Vertical Mill charging total amount, and the material material-gas ratio of certain granules is certain, all half whole Vertical Mill actual consumption air quantity are 20% of traditional Vertical Mills, consider certain affluence amount, design air flow is determined 30%.Be provided with top material scraping plate 23 on the top of barrier circle 29.Semi-finished pre-grinding vertical machine 5 bottoms are provided with bottom material scraping plate 30 and semi-finished product discharging opening 31, and material enters from feeding mouth 21, and the hot blast of semi-finished pre-grinding vertical machine 5 enters from bottom sides, from the air-out of powder concentrator air outlet.
The feed end of semi-finished pre-grinding vertical machine 5 connects proportioning belt by belt feeder 2 and claims 1 blanking end, that end that belt feeder 2 is connected with the feed end of semi-finished pre-grinding vertical machine 5 is provided with a tramp iron separator 3, and the feed end of semi-finished pre-grinding vertical machine 5 is provided with a lattice wheel 4.The discharging opening that the gas outlet of semi-finished pre-grinding vertical machine 5 connects first deduster, 6, the first dedusters 6 connects first finished product conveyer, 7, the first dedusters 6 and links to each other with first dedusting fan 8.The receive charging aperture of grinding machine 11 of the discharging opening that the discharging opening of semi-finished pre-grinding vertical machine 5 connects first elevator, 10, the first elevators 10 by Vertical Mill outfeed belt 9.The discharging opening that the gas outlet of ball mill 11 connects second deduster, 17, the second dedusters 17 connects second finished product conveyer, 18, the second dedusters 17 and links to each other with second dedusting fan 19.The discharging opening of ball mill 11 connects powder concentrator 13 by second elevator 12, and the finished product fine powder discharging opening of powder concentrator 13 connects the 3rd finished product conveyer 16, and the meal discharging opening of powder concentrator 13 is by the receive charging aperture of grinding machine 11 of feed back conveyer 15.Semi-finished pre-grinding vertical machine 5 goes out the whole grinding of closed-circuit ball mill 11 realizations that the machine fine powder enters the band powder concentrator, the powder concentrator blower fan adopts inner loop mode, after material enters powder concentrator, utilize air to separate, coarse granule returns ball mill 11 bistriques grinding again, qualified material enters the whirlwind tube and collects as finished product usefulness, the ad hoc deduster of ball mill 11 mill inner ventilations, and the fine powder of collection is directly used as finished product.
The present invention after cement grinding materials such as clinker, slag, gypsum process proportioning belt claims batching, delivers to semi-finished pre-grinding vertical by belt in the specific implementation, process tramp iron separator deironing before semi-finished pre-grinding vertical.Material is taken turns charging by lattice before entering semi-finished pre-grinding vertical, mainly has been the effect of lock wind, and hot blast enters from the semi-finished pre-grinding vertical bottom.
Material is fallen mill central authorities by feeding mouth, and mill is being done at the uniform velocity gyration by main motor, reductor under driving, and mill outwards evenly disperses material, spreads out by action of centrifugal force, makes it form certain thickness material bed.Under the effect of pressure, grinding roller and mill roll material by relative motion.In this process, material is subjected to rolling of a plurality of grinding rollers on the mill simultaneously, and is pulverized under the effect of pressure.Material is all extracted out by wind-force in the tradition vertical mill, and wind-force consumption is big, and the blower fan wearing and tearing are big.Key of the present invention be in the mill edge designs barrier circle.Special barrier circle will guarantee that through accurate Calculation the bed depth in the semi-finished pre-grinding vertical running is suitable.Through the material after rolling, constantly move ordering about continuously down of centrifugal force to the mill outer rim, tiny qualified material is outwards dished out from the barrier circle, the coarse granule material is returned mill by barrier circle obstruction to be continued to roll, assurance has only particle diameter to pass through from special barrier circle less than the material of 3mm, realizes one time thickness grading.From the bottom supply hot blast of semi-finished pre-grinding vertical, the semi-finished pre-grinding vertical mill is interior to be 30% of traditional Vertical Mill with wind.From the material classification under the effect of ascending air of dishing out of barrier circle, the light matter material rises with air-flow, than heavy material whereabouts semi-finished pre-grinding vertical bottom, realizes the classification of secondary selection by winnowing.The rising dust-contained airflow is fine graded by dynamic powder concentrator three times, meets being transported to deduster with air-flow and collecting of finished product requirement, and the finished product fine powder accounts for material charging total amount 20%, realizes half whole grinding, requires the product specific area to be controlled at 350m 2/ kg~360m 2/ kg, 0.08mm tail over below 3%.The semi-finished pre-grinding vertical gas circuit is an open circuit, the deduster exhaust gas evacuation.Not meeting the synthetic closely knit material bed of the thin returning charge of finished product requirement and charging continues to mill.Fall into the material that accounts for charging total amount 80% of semi-finished pre-grinding vertical bottom, collect discharging opening, enter down the road mill, require to control out the machine material specific surface area at 180m by the bottom scraper plate 2/ kg~200m 2/ kg, 0.08mm tails over 40%~50%.
The material in small, broken bits that semi-finished pre-grinding vertical comes out enters ball mill and carries out fine-grinding, selects powder by elevator to powder concentrator, and meal is got back to ball mill bistrique grinding again, and the finished product fine powder is directly put in storage, requires specific area at 460m 2/ kg~480m 2/ kg, 0.08mm tail over below 1%.Mill tail deduster is collected fine powder in the mill, requires the control ratio surface area at 400m 2/ kg~420m 2/ kg, 0.08mm tail over below 2%.
The present invention can also have other embodiment, and the technical scheme that equal replacement of all employings or equivalent transformation form all drops within the scope of protection of present invention.

Claims (10)

1. semi-finished pre-grinding vertical and ball milling combination grinding device, comprise semi-finished pre-grinding vertical machine (5) and ball mill (11), described semi-finished pre-grinding vertical machine (5) comprises powder concentrator (20), feeding mouth (21), mill (22), top scraper plate (23), reductor (24), main motor (25), air outlet (26), grinding roller (27), rocking arm (28), bottom scraper plate (30) and semi-finished product discharging opening (31), it is characterized in that: the feed end of described semi-finished pre-grinding vertical machine (5) connects the blanking end that proportioning belt claims (1) by belt feeder (2); The gas outlet of described semi-finished pre-grinding vertical machine (5) connects first deduster (6), and the discharging opening of described first deduster (6) connects first finished product conveyer (7), and described first deduster (6) links to each other with first dedusting fan (8); The discharging opening of described semi-finished pre-grinding vertical machine (5) connects first elevator (10) by Vertical Mill outfeed belt (9), and the discharging opening of described first elevator (10) connects the charging aperture of described ball mill (11); The gas outlet of described ball mill (11) connects second deduster (17), and the discharging opening of described second deduster (17) connects second finished product conveyer (18), and described second deduster (17) links to each other with second dedusting fan (19); The discharging opening of described ball mill (11) connects powder concentrator (13) by second elevator (12), the finished product fine powder discharging opening of described powder concentrator (13) connects the 3rd finished product conveyer (16), and the meal discharging opening of described powder concentrator (13) connects the charging aperture of described ball mill (11) by feed back conveyer (15).
2. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device, it is characterized in that: the outer rim of described mill (22) is provided with barrier circle (29), described barrier circle (29) is that a cross section is L shaped annulus, open backgauge hole (33) at inner ring, open fixing hole (34) on the bottom sides, described barrier circle (29) is fixed on the edge on mill (22) top with bolt (32) by the fixing hole on the bottom sides (34).
3. semi-finished pre-grinding vertical as claimed in claim 2 and ball milling combination grinding device is characterized in that: the aperture in described backgauge hole (33) is 3mm.
4. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device is characterized in that: described semi-finished pre-grinding vertical machine (5) is from bottom supply hot blast, and mill is interior to be 30% of traditional Vertical Mill with wind.
5. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device is characterized in that: described belt feeder (2) is provided with a tramp iron separator (3) with that end that the feed end of described semi-finished pre-grinding vertical machine (5) is connected.
6. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device is characterized in that: the feed end of described semi-finished pre-grinding vertical machine (5) is provided with a lattice wheel (4).
7. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device is characterized in that: described first deduster (6) goes out the machine specific surface area of finished products and is controlled at 350m 2/ kg~360m 2/ kg, 0.08mm tail over and are controlled at below 3%.
8. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device is characterized in that: the machine material specific surface area that goes out that described semi-finished pre-grinding vertical machine (5) enters ball mill (11) is controlled at 180m 2/ kg~200m 2/ kg, 0.08mm tail over and are controlled at 40%~50%.
9. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device is characterized in that: the machine specific surface area of finished products that goes out of described ball mill (11) is controlled at 460m 2/ kg~480m 2/ kg, 0.08mm tail over and are controlled at below 1%.
10. semi-finished pre-grinding vertical as claimed in claim 1 and ball milling combination grinding device is characterized in that: the machine specific surface area of finished products that goes out of described second deduster (17) is controlled at 400m 2/ kg~420m 2/ kg, 0.08mm tail over and are controlled at below 2%.
CN2010101911418A 2010-06-03 2010-06-03 Semi-finished pre-grinding vertical-milling and ball-milling combined grinding device Expired - Fee Related CN101862699B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101911418A CN101862699B (en) 2010-06-03 2010-06-03 Semi-finished pre-grinding vertical-milling and ball-milling combined grinding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101911418A CN101862699B (en) 2010-06-03 2010-06-03 Semi-finished pre-grinding vertical-milling and ball-milling combined grinding device

Publications (2)

Publication Number Publication Date
CN101862699A true CN101862699A (en) 2010-10-20
CN101862699B CN101862699B (en) 2012-01-04

Family

ID=42954736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101911418A Expired - Fee Related CN101862699B (en) 2010-06-03 2010-06-03 Semi-finished pre-grinding vertical-milling and ball-milling combined grinding device

Country Status (1)

Country Link
CN (1) CN101862699B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102179285A (en) * 2011-03-02 2011-09-14 江苏羚羊水泥工程技术有限公司 Single-compartment ball mill type cement vertical mill grinding device
CN103567046A (en) * 2013-10-31 2014-02-12 河南技兴机械有限公司 Carbon fiber smashing equipment
CN104003635A (en) * 2013-02-21 2014-08-27 高县天顺建材有限责任公司 Waste heat grinding process and device
CN104415844A (en) * 2013-09-06 2015-03-18 浙江力普粉碎设备有限公司 Complete production line for refined cotton smashing
CN105498927A (en) * 2015-12-15 2016-04-20 莱歇研磨机械制造(上海)有限公司 Semi-finished milling system
CN105750064A (en) * 2016-03-21 2016-07-13 南通弘亚机械制造有限公司 Grinding equipment for dry type cement production line
CN106040405A (en) * 2016-07-26 2016-10-26 新乡市长城机械有限公司 Pre-grinding vertical mill united semi-finish grinding system with built-in powder concentrator
CN107737642A (en) * 2017-11-20 2018-02-27 重庆嘉韵实业有限公司 The production line and its technique of a kind of flyash
CN108126811A (en) * 2017-11-13 2018-06-08 盐城吉达环保设备有限公司 A kind of iron ore by dry method fine grinding system
CN112108255A (en) * 2020-10-13 2020-12-22 南京凯盛国际工程有限公司 Vertical grinding sand making system with shaping function

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004188368A (en) * 2002-12-13 2004-07-08 Ube Machinery Corporation Ltd Grinding method
CN101596483A (en) * 2009-06-26 2009-12-09 南京凯盛水泥技术工程有限公司 A kind of material grinding system
CN101671134A (en) * 2009-09-22 2010-03-17 南京旋立重型机械有限公司 Semi-finished grinding process of cement wind selection pre-grinding and device thereof
CN201768603U (en) * 2010-06-03 2011-03-23 南京旋立重型机械有限公司 Semi-finished pre-grinding vertical mill and ball mill combined grinding device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004188368A (en) * 2002-12-13 2004-07-08 Ube Machinery Corporation Ltd Grinding method
CN101596483A (en) * 2009-06-26 2009-12-09 南京凯盛水泥技术工程有限公司 A kind of material grinding system
CN101671134A (en) * 2009-09-22 2010-03-17 南京旋立重型机械有限公司 Semi-finished grinding process of cement wind selection pre-grinding and device thereof
CN201768603U (en) * 2010-06-03 2011-03-23 南京旋立重型机械有限公司 Semi-finished pre-grinding vertical mill and ball mill combined grinding device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《四川水泥》 20090831 王志强 FM风选磨是对球破机在预粉磨工艺上的升级创新 19-21 1-10 , 第4期 2 *
《昆明冶金高等专科学校学报》 20060131 王英 粒化高炉矿渣立式磨预粉磨技术应用研究 8-11 1-10 第22卷, 第1期 2 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102179285A (en) * 2011-03-02 2011-09-14 江苏羚羊水泥工程技术有限公司 Single-compartment ball mill type cement vertical mill grinding device
CN104003635A (en) * 2013-02-21 2014-08-27 高县天顺建材有限责任公司 Waste heat grinding process and device
CN104415844A (en) * 2013-09-06 2015-03-18 浙江力普粉碎设备有限公司 Complete production line for refined cotton smashing
CN103567046A (en) * 2013-10-31 2014-02-12 河南技兴机械有限公司 Carbon fiber smashing equipment
CN105498927A (en) * 2015-12-15 2016-04-20 莱歇研磨机械制造(上海)有限公司 Semi-finished milling system
CN105498927B (en) * 2015-12-15 2019-05-21 莱歇研磨机械制造(上海)有限公司 A kind of half whole formula grinding system
CN105750064A (en) * 2016-03-21 2016-07-13 南通弘亚机械制造有限公司 Grinding equipment for dry type cement production line
CN106040405A (en) * 2016-07-26 2016-10-26 新乡市长城机械有限公司 Pre-grinding vertical mill united semi-finish grinding system with built-in powder concentrator
CN108126811A (en) * 2017-11-13 2018-06-08 盐城吉达环保设备有限公司 A kind of iron ore by dry method fine grinding system
CN107737642A (en) * 2017-11-20 2018-02-27 重庆嘉韵实业有限公司 The production line and its technique of a kind of flyash
CN112108255A (en) * 2020-10-13 2020-12-22 南京凯盛国际工程有限公司 Vertical grinding sand making system with shaping function
CN112108255B (en) * 2020-10-13 2024-04-12 中材国际智能科技有限公司 Vertical mill sand making system with shaping function

Also Published As

Publication number Publication date
CN101862699B (en) 2012-01-04

Similar Documents

Publication Publication Date Title
CN101862699B (en) Semi-finished pre-grinding vertical-milling and ball-milling combined grinding device
CN201768603U (en) Semi-finished pre-grinding vertical mill and ball mill combined grinding device
CN102179272B (en) Final grinding system of rolling machine in steel slag and mineral slag micropowder production line
CN101134175B (en) Roller press combination grinding device
CN102389852B (en) Multitime-separation high-efficient cement vertical mill
CN203002448U (en) Cement open-circuit grinding system with powder pre-selecting function
WO2016127869A1 (en) Ore sorting system
CN206746767U (en) A kind of desulfurization agstone preparation system
CN102847587A (en) External-circulation slag vertical roller mill
CN202137014U (en) Outer circulation deironing grinding equipment
CN209302870U (en) A kind of spreading is evenly distributed with the roller type vertical mill of spout ring
CN110732383A (en) Process system for producing fine sand by machine-made sand vertical mill
CN103045777A (en) Dry processing technique for iron-containing steel slag
CN110732382A (en) machine-made sand vertical mill and production process system thereof
CN105709883A (en) Cement semi-final powder milling vertical milling and ball milling combination system
CN102847586A (en) Air-swept efficient vertical roller mill
CN111215220A (en) Production process system for producing multi-product machine-made sand
WO2016127870A1 (en) Ore sorting system
CN201361574Y (en) Discharging iron-removal conveyor controlled by return powder seal in closed grinding circulation system
CN111822129A (en) Iron ore dry grinding and dressing device and process
CN209501830U (en) The coarse grained Vertical Mill of automatic screening in grinding
CN207238206U (en) A kind of environment-friendly type pulverized coal preparation system
CN205550427U (en) Half whole grinding of cement grinds and ball -milling combination system immediately
CN101941074B (en) Milling production line of steel slag micro powder
CN110773298A (en) Staged grinding method for slag micro powder

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120104