CN101851896B - Replaceable concrete road bed device of steel trussed bridge and construction method - Google Patents

Replaceable concrete road bed device of steel trussed bridge and construction method Download PDF

Info

Publication number
CN101851896B
CN101851896B CN2010101697429A CN201010169742A CN101851896B CN 101851896 B CN101851896 B CN 101851896B CN 2010101697429 A CN2010101697429 A CN 2010101697429A CN 201010169742 A CN201010169742 A CN 201010169742A CN 101851896 B CN101851896 B CN 101851896B
Authority
CN
China
Prior art keywords
concrete road
road bed
bridge
replaceable
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2010101697429A
Other languages
Chinese (zh)
Other versions
CN101851896A (en
Inventor
赵兴亚
段雪炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Original Assignee
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Reconnaissance and Design Institute Co Ltd filed Critical China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority to CN2010101697429A priority Critical patent/CN101851896B/en
Publication of CN101851896A publication Critical patent/CN101851896A/en
Application granted granted Critical
Publication of CN101851896B publication Critical patent/CN101851896B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a replaceable concrete road bed device of a steel trussed bridge and a construction method. The device comprises a concrete road bed plate, a rail bearing table, a steel sole plate, shear nails and a rubber cushion block, and the device is fixed to the bridge floor through connecting parts. The construction method comprises the steps of: manufacturing a load transfer component and a main bridge at the same time; installing the main bridge; installing a replaceable concrete road bed formed by the steel sole plate, the shear nails and the concrete road bed plate; casting the rail bearing table; and connecting the replaceable concrete road bed with the load transfer component by the connecting parts. By using the replaceable concrete road bed device, in the process of using a bridge, the replaceable concrete road bed of a steel trussed bridge can be completely separated from the main bridge structure. When the bridge floor structure has a problem, the device can be replaced at any time. The use of the replaceable concrete road bed device of a steel trussed bridge can not affect the structures of a girder of the main bridge, and can not affect the maintenance of the main bridge structure. The rubber cushion block ensures that passengers can feel comfortable when a train runs on a bridge, and can decrease noise effect of the train during running on ambient environment.

Description

The job practices of replaceable concrete road bed device of steel trussed bridge
Technical field
The present invention relates to a kind of replaceable concrete road bed device of steel trussed bridge and job practices.
Background technology
The railway concrete ballast bed structure of large span steel truss bridge directly links to each other with the bridge deck of structure of main bridge on the Line for Passenger Transportation now, the working condition of railway concrete ballast bed structure directly influences the safety of structure of main bridge, causes the bridge deck maintenance difficulty of structure of main bridge after directly linking to each other simultaneously.The railway concrete ballast bed structure of large span steel truss bridge often adopts the ballast aggregate bridge floor in addition, and the structure dead load of itself is bigger.In order to improve the deficiency of above-mentioned bridge floor form, special invention steel bridge replaceable concrete road bed device.
Summary of the invention
The objective of the invention is at above-mentioned present situation, aim to provide a kind of structure of main bridge that do not influence, when bridge deck structure goes wrong, can be convenient for changing, and can guarantee train the time during comfortable, the train driving of passenger to little replaceable concrete road bed device of steel trussed bridge and the job practices of ambient noise influence.
The implementation of the object of the invention is, replaceable concrete road bed device of steel trussed bridge, by concrete road bed board and top support rail platform thereof, following steel sole plate constitutes, steel sole plate and concrete road bed board are affixed by WELDING STUDS, affixed by the Force transmission parts on connector and the bridge floor, under the steel sole plate rubber cushion blocks is arranged, rubber cushion blocks is on bridge floor.
The job practices of replaceable concrete road bed device of steel trussed bridge, concrete construction sequence is: when making main bridge, make Force transmission parts simultaneously, the main bridge of mounting strap Force transmission parts again, replaceable concrete road bed and the rubber cushion blocks of being made up of steel sole plate, WELDING STUDS, concrete road bed board is installed again, cast support rail platform links together with Force transmission parts replaceable concrete road bed with connector, and construction is finished.
Adopt the present invention, in the bridge use, replaceable concrete road bed device of steel trussed bridge can separate fully with structure of main bridge, and bridge deck structure can be changed when going wrong as required at any time.The use of replaceable concrete road bed device of steel trussed bridge does not influence each structure of main bridge girder steel, does not influence the maintenance of structure of main bridge yet.The passenger was comfortable when rubber cushion blocks guaranteed train operation, in the time of can reducing train driving to the influence of noise of surrounding environment.Adopt this device can reduce the engineering quantity of structure of main bridge.
Description of drawings
Fig. 1 is the replaceable concrete road bed device structural representation on the close crossbeam steel bridge deck bridge floor,
Fig. 2 is the replaceable concrete road bed device structural representation on the longitudinal and transverse beam system bridge floor.
The specific embodiment
Replaceable concrete road bed device of the present invention is by concrete road bed board 3 and top support rail platform 4 thereof, following steel sole plate 1 constitutes, steel sole plate 1 is affixed by WELDING STUDS 2 with concrete road bed board 3, affixed by connector 6 with the Force transmission parts on the bridge floor, rubber cushion blocks 5 is arranged under the steel sole plate, and rubber cushion blocks is on bridge floor.
Steel sole plate 1, WELDING STUDS 2 and concrete road bed board 3 are mainly as the load-carrying construction of railway loading, support rail platform 4 is as rail leveling and support rail parts, the effect of rubber cushion blocks 5 mainly is damping and noise reduction, the effect of connector 6 is that the Force transmission parts 7 that will increase newly in replaceable concrete road bed and the main structure is connected and fixed, the connector 6 main high-strength bolts that adopt, and can unclamp high-strength bolt when needs are changed the road bed board, removing needs the concrete road bed of replacing.
The concrete construction sequence of job practices of the present invention is: when making main bridge, make Force transmission parts 7 simultaneously, the main bridge of mounting strap Force transmission parts 7 again, replaceable concrete road bed and the rubber cushion blocks of being made up of steel sole plate 1, WELDING STUDS 2, concrete road bed board 35 is installed again, cast-in-site support rail platform 4, link together with Force transmission parts 7 replaceable concrete road bed with connector 6, construction is finished.
By replaceable concrete road bedly making at the construction field (site) that steel sole plate 1, WELDING STUDS 2, concrete road bed board 3 are formed, or factory makes.
The present invention adopts different forms according to the form of structure difference of main bridge bridge floor, to satisfy the needs of different bridge floors.
As the bridge floor of present close crossbeam steel bridge deck is adopted as shown in Figure 1 be form of structure.On the basis of former close crossbeam steel bridge bridge floor, increase Force transmission parts 7, corresponding member welding in Force transmission parts 7 and the close crossbeam steel bridge bridge deck.Force transmission parts 7 is with replaceable concrete road bed affixed by connector 6.
As the bridge floor of present longitudinal and transverse beam system is adopted as shown in Figure 2 be form of structure.The longeron upper body of the bridge of longitudinal and transverse beam system increases Force transmission parts 7, and Force transmission parts 7 is with replaceable concrete road bed affixed by connector 6.

Claims (2)

1. the job practices of replaceable concrete road bed device of steel trussed bridge, it is characterized in that replaceable concrete road bed device of steel trussed bridge is by concrete road bed board and top support rail platform thereof, following steel sole plate constitutes, steel sole plate and concrete road bed board are affixed by WELDING STUDS, affixed by the Force transmission parts on connector and the bridge floor, under the steel sole plate rubber cushion blocks is arranged, rubber cushion blocks is on bridge floor; Construction sequence is: when making main bridge, make Force transmission parts simultaneously, the main bridge of mounting strap Force transmission parts again, replaceable concrete road bed and the rubber cushion blocks of being made up of steel sole plate, WELDING STUDS, concrete road bed board is installed again, cast support rail platform, link together with Force transmission parts replaceable concrete road bed with connector, construction is finished.
2. the job practices of replaceable concrete road bed device of steel trussed bridge according to claim 1 is characterized in that replaceable concrete road bedly being made at the construction field (site) or making in factory by what steel sole plate (1), WELDING STUDS (2), concrete road bed board (3) were formed.
CN2010101697429A 2010-05-11 2010-05-11 Replaceable concrete road bed device of steel trussed bridge and construction method Active CN101851896B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101697429A CN101851896B (en) 2010-05-11 2010-05-11 Replaceable concrete road bed device of steel trussed bridge and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101697429A CN101851896B (en) 2010-05-11 2010-05-11 Replaceable concrete road bed device of steel trussed bridge and construction method

Publications (2)

Publication Number Publication Date
CN101851896A CN101851896A (en) 2010-10-06
CN101851896B true CN101851896B (en) 2011-09-07

Family

ID=42803566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101697429A Active CN101851896B (en) 2010-05-11 2010-05-11 Replaceable concrete road bed device of steel trussed bridge and construction method

Country Status (1)

Country Link
CN (1) CN101851896B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064210A (en) * 2015-08-25 2015-11-18 中铁大桥勘测设计院集团有限公司 Steel-concrete combined structure having corrosion resistant performance and construction method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004156284A (en) * 2002-11-06 2004-06-03 Railway Technical Res Inst Tie and method for adjusting height of tie

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3520294B2 (en) * 1994-11-17 2004-04-19 独立行政法人鉄道建設・運輸施設整備支援機構 How to build a sleeper track

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004156284A (en) * 2002-11-06 2004-06-03 Railway Technical Res Inst Tie and method for adjusting height of tie

Also Published As

Publication number Publication date
CN101851896A (en) 2010-10-06

Similar Documents

Publication Publication Date Title
CN201512345U (en) Multifunctional integrated lifting frame
CN101550769B (en) Movable trestle
CN101613990B (en) Construction method of railway steel truss girder T-shaped stiffening rib orthotropic slab bridge deck
CN107401113B (en) Stiff skeleton straining beam structure and construction method built in a kind of high pier
CN204750295U (en) Prevent spouting and repair special transport vechicle subframe of well equipment
CN101851896B (en) Replaceable concrete road bed device of steel trussed bridge and construction method
CN103343507A (en) Composite structure of three main trusses, longitudinal beams, transverse beams and concrete slabs
CN102433837B (en) Orthogonal anisotropic plate integrated steel bridge deck of side box girder and longitudinal and transverse beam railway and construction method
CN101695986A (en) Assembly-type large-span heavy-load gantry crane
CN109853377B (en) Bridge deck continuous connection structure adopting ultra-high performance concrete and construction method thereof
CN103938508A (en) Complete machine long-distance transport, loading and unloading device and method of track laying machine
CN103835232A (en) Bridge deck structure with longitudinal beams and transverse beam combined
CN203834340U (en) Open type bond beam truss bridge
CN207452684U (en) Stiff skeleton straining beam structure built in high pier
CN202416173U (en) Wide girder bridge floor system structure with horizontal K support
CN201099836Y (en) Bridge site cast-in-situ flange plate construction equipment
CN214831983U (en) Novel asynchronous basket construction structures of hanging
CN102225580A (en) Method for longitudinally moving box girder internal mold
CN104404975A (en) Universal five-point support loading type tower crane foundation and construction method
CN101457515B (en) In situ cast-in-situ steel girder railway bridge deck pre-stress concrete channel beam construction method
CN105421253B (en) Prestress concrete simply supported beam reinforcing method and reinforcing structure thereof
CN211972931U (en) Guide rail beam
CN204488812U (en) For the lightweight truck frame of subway engineering car
CN204401646U (en) Universal 5 support ballast formula foundation for tower crane
CN202766936U (en) Multifunctional transporting device for ballastless track base plate construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant