CN101839141A - Emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels - Google Patents

Emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels Download PDF

Info

Publication number
CN101839141A
CN101839141A CN 201010141835 CN201010141835A CN101839141A CN 101839141 A CN101839141 A CN 101839141A CN 201010141835 CN201010141835 CN 201010141835 CN 201010141835 A CN201010141835 A CN 201010141835A CN 101839141 A CN101839141 A CN 101839141A
Authority
CN
China
Prior art keywords
tunnel
subaqueous
portal
steel plate
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010141835
Other languages
Chinese (zh)
Other versions
CN101839141B (en
Inventor
彭子晖
李新星
傅华
宋振华
申伟强
曹文宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Original Assignee
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering and Rail Transit Design and Research Institute filed Critical Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority to CN 201010141835 priority Critical patent/CN101839141B/en
Publication of CN101839141A publication Critical patent/CN101839141A/en
Application granted granted Critical
Publication of CN101839141B publication Critical patent/CN101839141B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Revetment (AREA)

Abstract

The invention belongs to the field of tunneling, and particularly relates to an emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels. The method comprises the following steps: respectively burying steel plates on the driveway at the portal at the open section on both ends of the tunnel, and firmly connecting the steel plates with the pavement structure; welding channel-section steel plates above the buried steel plates to form a gate slot structure; arranging the gate steel plate in the gate slot to block the tunnel portal; and pouring slag earth into the tunnel portal from the ground outside the portal to form a mound, which abuts against the gate steel plate and resists the hydraulic pressure impact outside the portals at both ends of the tunnel. The construction method arranges the steel plate mound at the portal at the open section of the tunnel as the temporary flood-prevention measure, and can effectively prevent river water from injecting into the tunnel in an emergency. The construction method adjusts measures according to local conditions, and has the advantages of easy implementation, convenient construction and high speed.

Description

The emergent flood-prevention construction method of subaqueous tunnel
Technical field
The invention belongs to the construction of tunnel field, the concrete emergent flood-prevention construction method that is meant a kind of subaqueous tunnel.
Background technology
Build when getting over the river roads and tunnels problem that rivers water pours in down a chimney in the time of must considering emergency takes place.Lower such as the Urban Area of Shanghai City physical features, elevation generally is in 3.0~3.5m, is lower than long-term mean high water tidal level.As above at the bottom of the seawater tunnel rupture running into burst accident (as blast, earthquake, war or other), when destroying, river pours in the tunnel, and overflows rapidly thus to the city, will be life and the property that jeopardizes the people.
For preventing trouble before it happens, eliminate the risk that the tunnel causes the city to be flooded as intake tunnel under this special operation condition, must take certain temporary anti-flood measure as emergency preplan, with the tunnel closed at both ends, preventing that the tunnel from being flooded jeopardizes the city under case of emergency.Up to the present in the tunnel, all do not consider this situation.
Summary of the invention
The objective of the invention is according to above-mentioned the deficiencies in the prior art part, a kind of emergent flood-prevention construction method of subaqueous tunnel is proposed, secretly the section of burying hole is provided with the steel plate mound used as temporary anti-flood measure in the tunnel, and with the tunnel closed at both ends, anti-blocking river that can be instant pours into the tunnel under case of emergency.
Purpose of the present invention realizes being finished by following technical scheme:
A kind of emergent flood-prevention construction method of subaqueous tunnel, this job practices implementation step is as follows:
1) the handing-over openings position of the section of burying secretly in tunnel open section and tunnel is fixed in a troughing plate on the tunnel road surface structure that described hole is in tunnel open section one side;
2) the door steel plate is placed in the described troughing plate, forms the gate slot structure, block tunnel portal;
3) toward the interior impouring dregs of tunnel open section, form mound, against described door steel plate, the hydraulic pressure of resisting outside the hole, two ends, tunnel impacts.
Above-mentioned steps 1) be embedded with the track pre-embedded steel slab described on the tunnel road surface structure, described track pre-embedded steel slab is connected with described tunnel road surface sound construction, and described troughing plate is fixedly welded on the pre-embedded steel slab of described track; The plate face of described track pre-embedded steel slab keeps concordant with tunnel road surface;
The height and the width of the steel plate of door step 2) are all greater than the tunnel portal diameter;
Above-mentioned door steel plate is spliced by some precast plates.
Advantage of the present invention is, job practices of the present invention adopts in the tunnel secretly that the section of burying hole is provided with the steel plate mound as the temporary anti-flood measure, can prevent effectively that immediately in emergency circumstances rivers water pours into the tunnel, and applicability is stronger, job practices is suited measures to local conditions, and implements easy construction, quick easily.
Description of drawings
Fig. 1 is an embodiment of the invention structural representation.
The specific embodiment
Feature of the present invention and other correlated characteristic are described in further detail by embodiment below in conjunction with accompanying drawing, so that technician's of the same trade understanding:
Label 1-9 representative is tunnel open section 1, tunnel road surface (track) 2, track pre-embedded steel slab 3, road structure 4, troughing plate 5, door steel plate 6, mound 7, unlimited opening 8 in the accompanying drawing, and the tunnel is the section of burying 9 secretly.
For solving in emergency circumstances, river is poured into the subaqueous tunnel, an and difficult problem of invading the city rapidly, the inventive method secretly is provided with the steel plate mound used as temporary anti-flood measure in place, the section of burying handing-over hole in tunnel open section and tunnel, can be with the tunnel closed at both ends under case of emergency, preventing that the tunnel from being flooded jeopardizes the city, can be used as emergency preplan.
In the present embodiment, be example with the cross-river tunnel.At first, buried track pre-embedded steel slab 3 underground in the road structure of the open section 1 at two ends, tunnel and the section of burying 9 junctions secretly, pre-embedded steel slab 3 firmly is connected with road structure 4, and these step need be reconstructed the tunnel in advance, in a single day so that when burst accident taking place, can continue subsequent step.For ease of being open to traffic at ordinary times, the steel plate face of track pre-embedded steel slab 3 should should keep concordant with carriageway surfacing.
In case the generation accident is welded in the top of pre-embedded steel slab 3 with troughing plate 5, forms the gate slot structure; Again door steel plate 6 is placed in the described gate slot afterwards, blocks tunnel portal; At last, on the ground in the hole outside in the tunnel portal impouring dregs, form mound 7, against described door steel plate, resist the hydraulic pressure impact outside the hole, two ends, tunnel.
Stressing practical results property of whole construction method, emergency hangs in door steel plate 6 usefulness cranes in the gate slot when taking place as early as possible.Open section 1 upper position in tunnel is equipped with and opens wide opening 8, the dregs that vehicle is shipped on the ground in the outside, hole via the impouring in the tunnel open section of described unlimited opening 8.
In the present embodiment, will highly be about 7m with the automobile hanging device, some precast plates of width 1m, secretly the splicing of the section of burying hole arranges in the tunnel, is spliced into a steel plate.The height and the width of guaranteeing a steel plate cover tunnel portal fully all greater than the tunnel portal diameter.
In addition,, compress the single aperture of the required earth volume of water pressure (two tracks) and be about 350m3, need to consider the source problem that comes of soil amount because the required interim soil amount of sheetpile earthwork case is bigger.Proterties for mound does not have special requirement, oozes out as long as can satisfy the mound partition river of formation.

Claims (5)

1. the emergent flood-prevention construction method of a subaqueous tunnel is characterized in that this job practices implementation step is as follows:
(1) the handing-over openings position of the section of burying secretly in tunnel open section and tunnel is fixed in a troughing plate on the tunnel road surface structure that described hole is in tunnel open section one side;
(2) the door steel plate is placed in the described troughing plate, forms the gate slot structure, block tunnel portal;
(3) toward the interior impouring dregs of tunnel open section, form mound, against described door steel plate, the hydraulic pressure of resisting outside the hole, two ends, tunnel impacts.
2. meeting an urgent need of a kind of subaqueous tunnel as claimed in claim 1 prevents flooding method, it is characterized in that being embedded with the track pre-embedded steel slab on the tunnel road surface structure described in the step (1), described track pre-embedded steel slab is connected with described tunnel road surface sound construction, and described troughing plate is fixedly welded on the pre-embedded steel slab of described track.
3. the emergent anti-of a kind of subaqueous tunnel as claimed in claim 2 flooded method, it is characterized in that the plate face of described track pre-embedded steel slab keeps concordant with tunnel road surface.
4. the emergent anti-of a kind of subaqueous tunnel as claimed in claim 1 flooded method, and the height and the width that it is characterized in that the steel plate of door described in the step (2) are all greater than described tunnel portal diameter.
5. the emergent anti-of a kind of subaqueous tunnel as claimed in claim 1 flooded method, it is characterized in that described door steel plate is spliced by some precast plates.
CN 201010141835 2010-04-08 2010-04-08 Emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels Active CN101839141B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010141835 CN101839141B (en) 2010-04-08 2010-04-08 Emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010141835 CN101839141B (en) 2010-04-08 2010-04-08 Emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels

Publications (2)

Publication Number Publication Date
CN101839141A true CN101839141A (en) 2010-09-22
CN101839141B CN101839141B (en) 2012-06-06

Family

ID=42742775

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010141835 Active CN101839141B (en) 2010-04-08 2010-04-08 Emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels

Country Status (1)

Country Link
CN (1) CN101839141B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102330568A (en) * 2011-06-21 2012-01-25 上海隧道工程股份有限公司 Shield arrival gate plate type emergency safety device
CN102808653A (en) * 2012-01-22 2012-12-05 张庆东 Full-automatic disaster prevention device of mine flexible belt transportation lane

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000179320A (en) * 1998-12-11 2000-06-27 Ishikawajima Shibaura Mach Co Ltd Diesel engine
CN101012727A (en) * 2006-12-30 2007-08-08 同济大学 Flooding-proof closing partition device of underground structural engineering
CN101100944A (en) * 2006-07-07 2008-01-09 同济大学 Segment deformation control and flood-proof device and operation method for tunnel opening construction
CN101666242A (en) * 2009-09-24 2010-03-10 中国人民解放军总参谋部工程兵第四设计研究院 Hydraulic vertically rotary airtight flood and preventive partition door in metro running

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000179320A (en) * 1998-12-11 2000-06-27 Ishikawajima Shibaura Mach Co Ltd Diesel engine
CN101100944A (en) * 2006-07-07 2008-01-09 同济大学 Segment deformation control and flood-proof device and operation method for tunnel opening construction
CN101012727A (en) * 2006-12-30 2007-08-08 同济大学 Flooding-proof closing partition device of underground structural engineering
CN101666242A (en) * 2009-09-24 2010-03-10 中国人民解放军总参谋部工程兵第四设计研究院 Hydraulic vertically rotary airtight flood and preventive partition door in metro running

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《地下工程与隧道》 20080229 傅华等 轨道交通隧道防淹门系统及门窗受力分析计算 第58-59,62页 , 第2期 2 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102330568A (en) * 2011-06-21 2012-01-25 上海隧道工程股份有限公司 Shield arrival gate plate type emergency safety device
CN102330568B (en) * 2011-06-21 2015-07-08 上海隧道工程股份有限公司 Shield arrival gate plate type emergency safety device
CN102808653A (en) * 2012-01-22 2012-12-05 张庆东 Full-automatic disaster prevention device of mine flexible belt transportation lane
CN102808653B (en) * 2012-01-22 2015-06-24 张庆东 Full-automatic disaster prevention device of mine flexible belt transportation lane

Also Published As

Publication number Publication date
CN101839141B (en) 2012-06-06

Similar Documents

Publication Publication Date Title
CN1837506B (en) Construction method for excavating box-shape structure over an operating tunnel
CN103334452B (en) A kind of underground construction mixed construction method
CN108316354A (en) With waterproof, the underground pipe gallery structure of drain function and its construction method
CN100473791C (en) Installing method for rail beam structure of magnetic suspension tunnel shoreside section
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN111139721A (en) Frame bridge penetrating existing railway bridge downwards and construction method thereof
CN112064751A (en) Deep groove construction method for drainage pipeline
CN106320352B (en) Construction method of multifunctional steel sheet pile cofferdam
CN210216254U (en) Concrete guardrail structure
CN105625446B (en) A kind of construction method of tunnel undercrossing tunnel
CN107938680A (en) A kind of excavation of foundation pit safe construction method
CN101839141B (en) Emergency subaqueous tunnel flood-prevention construction method for subaqueous tunnels
CN107190630A (en) Road changes the new cap excavation method of stealthy bridge type
CN210946536U (en) Protective structure of small dangerous rock falling stone
CN209891207U (en) Retaining structure of water-rich deep foundation pit next to operating high-iron sand pebble bed
CN207538090U (en) A kind of externally reinforced structure of Urban underground Tunnel
CN101845823B (en) Steel plate mound used as temporary anti-flood structure for subaqueous tunnel
CN202954367U (en) System for controlling deformation of deep and big foundation pit by utilizing divisional unloading
KR100402437B1 (en) The construction method of cassion basis using a coagulant
CN105986830A (en) Underground-excavation building method for roadside strip-shaped underground garage
CN211922684U (en) Bury formula cable pit protection architecture
CN209508922U (en) It is a kind of to control flood baffle convenient for current slope formula
CN207260185U (en) A kind of road changes stealthy lid and digs bridge type structure
CN109797637A (en) Geological mapping construction method and structure
Nowak Earthworks design principles

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant