CN101839074A - Steel frame reinforcing column and reinforcing method thereof - Google Patents
Steel frame reinforcing column and reinforcing method thereof Download PDFInfo
- Publication number
- CN101839074A CN101839074A CN 201010205793 CN201010205793A CN101839074A CN 101839074 A CN101839074 A CN 101839074A CN 201010205793 CN201010205793 CN 201010205793 CN 201010205793 A CN201010205793 A CN 201010205793A CN 101839074 A CN101839074 A CN 101839074A
- Authority
- CN
- China
- Prior art keywords
- steel
- steel frame
- reinforced
- frame post
- strengthening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 148
- 239000010959 steel Substances 0.000 title claims abstract description 148
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 17
- 238000000034 method Methods 0.000 title abstract description 4
- 238000010276 construction Methods 0.000 claims abstract description 24
- 238000007789 sealing Methods 0.000 claims abstract description 12
- 229910000746 Structural steel Inorganic materials 0.000 claims description 84
- 238000005728 strengthening Methods 0.000 claims description 82
- 238000003466 welding Methods 0.000 claims description 43
- 230000002787 reinforcement Effects 0.000 claims description 7
- 239000000725 suspension Substances 0.000 claims description 7
- 230000035515 penetration Effects 0.000 claims description 6
- 229910000679 solder Inorganic materials 0.000 claims description 6
- 239000003973 paint Substances 0.000 claims description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract 3
- 238000010586 diagram Methods 0.000 description 8
- 235000008331 Pinus X rigitaeda Nutrition 0.000 description 1
- 235000011613 Pinus brutia Nutrition 0.000 description 1
- 241000018646 Pinus brutia Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
A steel frame reinforced column and a reinforcing method thereof are characterized in that a sealing reinforcing steel plate is welded between two wing plates on two sides of an H-shaped steel frame column along the whole length of the column, the sealing reinforcing steel plate is arranged at openings on two sides of the H-shaped steel frame column in an assembling mode and is welded with the two wing plates at the openings of the H-shaped steel frame column, and two sealing reinforcing steel plates which are adjacent up and down are welded with each other. According to the invention, the reinforced steel plate is prefabricated into parts, is directly hoisted in place during construction, and penetrates through the steel column in the direction of the weak axis of the H-shaped steel frame column to be welded in the full-length assembly mode, so that the structural stress of the steel reinforced column is more reasonable, the structural bearing capacity of an original building is increased, and the structural bearing stress requirement is met. By adopting the construction method, the original structure can be reinforced without unloading, and the normal office work of the original building is not influenced. All the reinforced steel plates can be prefabricated in factories, so that the construction period can be shortened, the construction cost can be reduced, the engineering quality can be ensured, and the requirement of building extension can be met.
Description
Technical field
The present invention relates to a kind of ruggedized construction and reinforced construction method of construction steel frame post.
Background technology
Along with the fast development of large-span space structure building, the designed structural span of architect is also increasing, and moulding is more and more novel, unique, and structure connects and becomes increasingly complex.Original steel structure member is because historical reasons and the passing of time cause local damage, corrosion easily, or because member section is little, bearing capacity is low, can't satisfy the requirement of workmanship.Existing reinforcing mode can't be in the existing building normal office work, and under the situation about not unloading the original structure Steel Frame Column is transformed, reinforced.Existing structural strengthening mode complex procedures, circulation material have high input, long construction period, can not adapt to the requirement of modern architecture construction.
Summary of the invention
The purpose of this invention is to provide a kind of steel frame reinforced column and reinforcement means thereof, solve existing steel work reinforcement means and need unload construction, working procedure complexity, long technical problem of cycle.
For achieving the above object, the present invention adopts following technical scheme: this steel frame reinforced column, comprise H structural steel frame post, be welded with along the post total length between two wing plates of described H structural steel frame post both sides and seal strengthening steel slab, seal strengthening steel slab in the both sides of H structural steel frame post open-mouth group to being provided with, and with the welding of two wing plates of H structural steel frame post open-mouth, neighbouring two seal strengthening steel slab is welded to each other.
The described strengthening steel slab that seals is slotted in the intersection with steel-frame beam, and steel-frame beam embeds in the above-mentioned groove.
The welding of strengthening steel slab base and steel column base plate is sealed at the suspension column place of described H structural steel frame post, and each vertical welding of web two sides of H structural steel frame post is connected to a web and reinforces the strength plate, and web is reinforced the base and the welding of steel column base plate of strength plate; Seal strengthening steel slab and reinforce the welding of strength plate with web simultaneously, each vertical welding of two wing plates middle part of H structural steel frame post is connected to a wing plate and reinforces the strength plate, and wing plate is reinforced the base and the welding of steel column base plate of strength plate.
The variable cross-section place of described H structural steel frame post also is welded with one deck steel liner plate sealing between strengthening steel slab and the H structural steel frame post.
The described weld seam that seals between strengthening steel slab and the steel column base plate is butt weld; The weld seam that web is reinforced between strength plate, wing plate reinforcing strength plate and the steel column base plate is a penetration T type weld seam; The weld seam that seals between strengthening steel slab, web reinforcing strength plate, wing plate reinforcing strength plate and the H structural steel frame post is the fillet weld seam.
The reinforced construction method of this steel frame reinforced column, construction sequence is as follows: step 1, the fireproof paint of H structural steel frame post is removed and cleaned out.
B, between two wing plates of H structural steel frame post both sides the solder up strengthening steel slab, and will seal strengthening steel slab and web and reinforce the welding of strength plate, will seal strengthening steel slab and steel column base plate and weld.
C, in the middle of two wing plates of H structural steel frame post, respectively weld a wing plate and reinforce the strength plate, and wing plate is reinforced the strength plate weld with the steel column base plate.
In H structural steel frame post and steel-frame beam intersection, will seal the web thickness fluting of strengthening steel slab in advance according to steel-frame beam, steel-frame beam is embedded in the above-mentioned groove, will seal the two wing plates welding of strengthening steel slab and H structural steel frame post open-mouth again.
The variable cross-section place of described H structural steel frame post also is welded with one deck steel liner plate sealing between strengthening steel slab and the H structural steel frame post.
When the typical construction of described H structural steel frame post was reinforced, the longitudinal angle weld seam between solder up strengthening steel slab and the H structural steel frame post was waited to be reduced to after the environment temperature in the neighbouring horizontal butt weld of sealing strengthening steel slab of welding earlier again.
Described web reinforces the strength plate, seal strengthening steel slab and wing plate is reinforced the strength plate when weld with H structural steel frame post, welds longitudinal weld longitudinal seam after all welding transverse weld earlier.
Beneficial effect of the present invention is as follows: the present invention is according to easy construction, rational principle, the strengthening steel slab that the steel framework reinforced column is used is prefabricated into part earlier, directly lift during construction and put in place, direction of principal axis connects the welding of steel column total length a little less than H structural steel frame post, can make the structure stress of steel reinforced column more reasonable, the structural bearing capacity of original building is strengthened, satisfy the structural bearing force request.Adopt job practices of the present invention, original structure need not to unload and can carry out strengthening construction to the framework steel column of former steel work, does not influence the normal office work of existing building.All strengthening steel slabs all can adopt prefabrication, not only can the reductions of erection time, reduce construction cost, and also guarantee workmanship, and can satisfy the needs of building enlarging.
Description of drawings
The present invention is further detailed explanation below in conjunction with accompanying drawing.
Fig. 1 is the schematic diagram that H structural steel frame post suspension column is reinforced.
Fig. 2 is the schematic diagram that H structural steel frame post typical construction is reinforced.
Fig. 3 is the schematic diagram that H structural steel frame post and steel-frame beam node place reinforce.
Fig. 4 is the schematic diagram that H structural steel frame post variable cross-section place reinforces.
Fig. 5 is the neighbouring schematic diagram that seals butt weld place between the strengthening steel slab.
Fig. 6 is the schematic diagram that web is reinforced penetration T type commissure between strength plate, wing plate reinforcing strength plate and the steel column base plate.
Fig. 7 is the schematic diagram that seals penetration T type commissure between strengthening steel slab and the steel column base plate.
Fig. 8 is the schematic diagram that seals strengthening steel slab and H structural steel frame post longitudinal seam place.
Reference numeral: 1-H structural steel frame post, 1.1-web, 1.2-wing plate, 2-seal strengthening steel slab, 3-steel-frame beam, 4-steel liner plate, 5-web reinforcing strength plate, 6-wing plate reinforcing strength plate, 7-steel column base plate.
The specific embodiment
Embodiment is referring to shown in Figure 2, this steel frame reinforced column, comprise H structural steel frame post 1, be welded with along the post total length between two wing plates 1.2 of described H structural steel frame post 1 both sides and seal strengthening steel slab 2, seal strengthening steel slab in the both sides of H structural steel frame post open-mouth group to being provided with, and with two wing plates 1.2 welding of H structural steel frame post open-mouth, neighbouring two seal strengthening steel slab 2 is welded to each other.
Referring to shown in Figure 3, the described strengthening steel slab 2 that seals is slotted in the intersection with steel-frame beam 3, and steel-frame beam embeds in the above-mentioned groove.
Referring to shown in Figure 1, strengthening steel slab 2 bases and 7 welding of steel column base plate are sealed by the suspension column place of described H structural steel frame post 1, and each vertical welding of web 1.1 two sides of H structural steel frame post is connected to a web and reinforces strength plate 5, and web is reinforced the base and 7 welding of steel column base plate of strength plate; Seal strengthening steel slab 2 and reinforce 5 welding of strength plate with web simultaneously, each vertical welding of two wing plates, 1.2 middle parts of H structural steel frame post is connected to a wing plate and reinforces strength plate 6, and wing plate is reinforced the base and 7 welding of steel column base plate of strength plate.
Referring to shown in Figure 4, the variable cross-section place of described H structural steel frame post 1 also is welded with one deck steel liner plate 4 sealing between strengthening steel slab 2 and the H structural steel frame post 1.
Referring to shown in Figure 5, the two adjacent weld seams that seal between the strengthening steel slab 2 are butt weld up and down.
Referring to shown in Figure 6, the weld seam that web is reinforced between strength plate 5, wing plate reinforcing strength plate 6 and the steel column base plate 7 is a penetration T type weld seam.
Referring to shown in Figure 7, the weld seam that seals between strengthening steel slab 2 and the steel column base plate 7 is a penetration T type weld seam.
Referring to shown in Figure 8, the weld seam that seals between strengthening steel slab 2, web reinforcing strength plate 5, wing plate reinforcing strength plate 6 and the H structural steel frame post 1 is the fillet weld seam.
The reinforced construction method of this steel frame reinforced column, step is as follows: step 1, the fireproof paint of H structural steel frame post 1 is removed and cleaned out.
B, between two wing plates of H structural steel frame post both sides solder up strengthening steel slab 2, and will seal strengthening steel slab 2 and reinforce 5 welding of strength plate with web, will seal strengthening steel slab and weld with steel column base plate 7.
C, in the middle of two wing plates 1.2 of H structural steel frame post, respectively weld a wing plate and reinforce strength plate 6, and wing plate is reinforced the strength plate weld with the steel column base plate.
Described web reinforces strength plate 5, seal strengthening steel slab 2 and wing plate is reinforced strength plate 6 when weld with H structural steel frame post, welds longitudinal weld longitudinal seam after all welding transverse weld earlier.
In H structural steel frame post 1 and steel-frame beam 3 intersections, will seal the web thickness fluting of strengthening steel slab 2 in advance according to steel-frame beam, steel-frame beam is embedded in the above-mentioned groove, will seal two wing plates, 1.2 welding of strengthening steel slab and H structural steel frame post open-mouth again.
At the variable cross-section place of H structural steel frame post 1, also be welded with one deck steel liner plate 4 sealing between strengthening steel slab 2 and the H structural steel frame post 1.
Claims (7)
1. steel frame reinforced column, comprise H structural steel frame post (1), it is characterized in that: be welded with along the post total length between two wing plates (1.2) of described H structural steel frame post (1) both sides and seal strengthening steel slab (2), seal strengthening steel slab in the both sides of H structural steel frame post open-mouth group to being provided with, and with the welding of two wing plates (1.2) of H structural steel frame post open-mouth, neighbouring two seal strengthening steel slab (2) is welded to each other;
The described strengthening steel slab (2) that seals is slotted in the intersection with steel-frame beam (3), and steel-frame beam embeds in the above-mentioned groove;
The suspension column place of described H structural steel frame post (1), seal the welding of strengthening steel slab (2) base and steel column base plate (7), each vertical welding of web (1.1) two sides of H structural steel frame post is connected to a web and reinforces strength plate (5), and web is reinforced the base and steel column base plate (7) welding of strength plate; Seal strengthening steel slab (2) and reinforce strength plate (5) welding with web simultaneously, each vertical welding of two wing plates (1.2) middle part of H structural steel frame post is connected to a wing plate and reinforces strength plate (6), and wing plate is reinforced the base and steel column base plate (7) welding of strength plate.
2. steel frame reinforced column according to claim 1 is characterized in that: the variable cross-section place of described H structural steel frame post (1) also is welded with one deck steel liner plate (4) sealing between strengthening steel slab (2) and the H structural steel frame post (1).
3. steel frame reinforced column according to claim 1 is characterized in that: described neighbouring two weld seams that seal between the strengthening steel slab (2) are butt weld; The weld seam that seals between strengthening steel slab (2), web reinforcing strength plate (5), wing plate reinforcing strength plate (6) and the steel column base plate (7) is a penetration T type weld seam; The weld seam that seals between strengthening steel slab (2), web reinforcing strength plate (5), wing plate reinforcing strength plate (6) and the H structural steel frame post (1) is the fillet weld seam.
4. reinforcement means as any described steel frame reinforced column of claim 1-3 is characterized in that construction sequence is as follows:
Step 1 is removed the fireproof paint of H structural steel frame post (1) and clean out;
Step 2 is set up non-bearing operation scaffold on every side being reinforced H structural steel frame post (1);
Step 3 puts prefabricated strengthening steel slab lifting in place;
Step 4 is reinforced H structural steel frame post suspension column, and concrete steps are as follows:
A, web of each vertical welding is reinforced strength plate (5) on web (1.1) two sides of H structural steel frame post, and web is reinforced strength plate (6) and steel column base plate (7) welding;
B, between two wing plates of H structural steel frame post both sides solder up strengthening steel slab (2), and will seal strengthening steel slab (2) and web and reinforce strength plate (5) welding, will seal strengthening steel slab and steel column base plate (7) and weld;
C, in the middle of two wing plates (1.2) of H structural steel frame post, respectively weld a wing plate and reinforce strength plate (6), and wing plate is reinforced the strength plate weld with the steel column base plate;
Step 5, reinforce H structural steel frame post typical construction, weak direction of principal axis at H structural steel frame post (1) seals strengthening steel slab (2) along the welding of steel column total length, organizes the right strengthening steel slab that seals and is symmetrically welded in the both sides open-mouth of H structural steel frame post, and the neighbouring strengthening steel slab that seals is welded to each other;
In H structural steel frame post (1) and steel-frame beam (3) intersection, to seal the web thickness fluting of strengthening steel slab (2) in advance according to steel-frame beam, steel-frame beam is embedded in the above-mentioned groove, will seal two wing plates (1.2) welding of strengthening steel slab and H structural steel frame post open-mouth again.
5. the reinforcement means of steel frame reinforced column according to claim 4 is characterized in that: the variable cross-section place of described H structural steel frame post (1) also is welded with one deck steel liner plate (4) sealing between strengthening steel slab (2) and the H structural steel frame post (1).
6. the reinforcement means of steel frame reinforced column according to claim 4, it is characterized in that: when the typical construction of described H structural steel frame post (1) is reinforced, the longitudinal angle weld seam between solder up strengthening steel slab (2) and the H structural steel frame post (1) is waited to be reduced to after the environment temperature in the neighbouring horizontal butt weld of sealing strengthening steel slab (2) of welding earlier again.
7. the reinforcement means of steel frame reinforced column according to claim 4, it is characterized in that: described web reinforces strength plate (5), seal strengthening steel slab (2) and wing plate is reinforced strength plate (6) when weld with H structural steel frame post, welds longitudinal weld longitudinal seam after welding transverse weld all earlier.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102057932A CN101839074B (en) | 2010-06-22 | 2010-06-22 | Steel frame reinforcing column and reinforcing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102057932A CN101839074B (en) | 2010-06-22 | 2010-06-22 | Steel frame reinforcing column and reinforcing method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101839074A true CN101839074A (en) | 2010-09-22 |
CN101839074B CN101839074B (en) | 2011-07-27 |
Family
ID=42742714
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010102057932A Expired - Fee Related CN101839074B (en) | 2010-06-22 | 2010-06-22 | Steel frame reinforcing column and reinforcing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101839074B (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102155067A (en) * | 2011-04-18 | 2011-08-17 | 江苏沪宁钢机股份有限公司 | Round cross-shaped column base and manufacturing method thereof |
CN102352694A (en) * | 2011-09-13 | 2012-02-15 | 浙江大学 | Reinforcing method for steel structural column |
CN103352568A (en) * | 2013-07-08 | 2013-10-16 | 陕西煤业化工建设(集团)有限公司 | Method for building constructional column on foundation pad |
CN103485475A (en) * | 2013-09-22 | 2014-01-01 | 重庆一建建设集团有限公司 | Trough beam |
CN104153599A (en) * | 2014-08-26 | 2014-11-19 | 中铁八局集团建筑工程有限公司 | System of section steel concrete beam structure without section steel column support and bracket for construction of section steel concrete beam |
CN104722986A (en) * | 2013-12-18 | 2015-06-24 | 五冶集团上海有限公司 | Welding deformation control method for non-oriented silicon steel process steel structure door-shaped framework |
CN105672687A (en) * | 2016-02-03 | 2016-06-15 | 河南省文博加固工程有限公司 | Reinforcement method for concrete poles of transformer substation structural support |
CN106003543A (en) * | 2015-03-31 | 2016-10-12 | 住友重机械工业株式会社 | Injection molding machine |
CN106545176A (en) * | 2016-10-21 | 2017-03-29 | 钟立朋 | A kind of building wall corbeling |
CN108425461A (en) * | 2018-03-10 | 2018-08-21 | 中南林业科技大学 | A kind of novel steel and wood composite structural column and its manufacturing method |
CN108532828A (en) * | 2018-03-10 | 2018-09-14 | 中南林业科技大学 | A kind of steel and wood composite structural beams |
CN109991311A (en) * | 2019-04-09 | 2019-07-09 | 中国十七冶集团有限公司 | A kind of workshop column reinforcing method and its detection device |
CN110388088A (en) * | 2019-07-26 | 2019-10-29 | 江苏省建筑工程集团有限公司 | A kind of increasing of steel-structure factory building is across remodeling method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1953093A1 (en) * | 1968-11-04 | 1970-06-04 | Hermann Mueller | Support column |
FR2034220A7 (en) * | 1969-02-26 | 1970-12-11 | Valon Freres Et Cie | |
CN2583229Y (en) * | 2002-11-22 | 2003-10-29 | 上海市第二建筑有限公司 | Steel holding hoop fastening structure of added storey new and old point pitch of high rise building |
JP2004156773A (en) * | 2002-09-12 | 2004-06-03 | Nippon Steel Corp | High-strength bolted connection structure with no fire resistant coating |
CN1554839A (en) * | 2003-12-28 | 2004-12-15 | 昆明理工大学 | Steel-steel concrete fully prefabricated assembling structure |
US20070209314A1 (en) * | 2006-03-10 | 2007-09-13 | Vaughn William B | Moment-resistant building column insert system and method |
CN201050139Y (en) * | 2007-06-06 | 2008-04-23 | 广州大学 | Rectangular steel pipe column steel frame beam column joint |
CN201695705U (en) * | 2010-06-22 | 2011-01-05 | 中国建筑第二工程局有限公司 | Steel frame reinforced column |
-
2010
- 2010-06-22 CN CN2010102057932A patent/CN101839074B/en not_active Expired - Fee Related
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1953093A1 (en) * | 1968-11-04 | 1970-06-04 | Hermann Mueller | Support column |
FR2034220A7 (en) * | 1969-02-26 | 1970-12-11 | Valon Freres Et Cie | |
JP2004156773A (en) * | 2002-09-12 | 2004-06-03 | Nippon Steel Corp | High-strength bolted connection structure with no fire resistant coating |
CN2583229Y (en) * | 2002-11-22 | 2003-10-29 | 上海市第二建筑有限公司 | Steel holding hoop fastening structure of added storey new and old point pitch of high rise building |
CN1554839A (en) * | 2003-12-28 | 2004-12-15 | 昆明理工大学 | Steel-steel concrete fully prefabricated assembling structure |
US20070209314A1 (en) * | 2006-03-10 | 2007-09-13 | Vaughn William B | Moment-resistant building column insert system and method |
CN201050139Y (en) * | 2007-06-06 | 2008-04-23 | 广州大学 | Rectangular steel pipe column steel frame beam column joint |
CN201695705U (en) * | 2010-06-22 | 2011-01-05 | 中国建筑第二工程局有限公司 | Steel frame reinforced column |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102155067A (en) * | 2011-04-18 | 2011-08-17 | 江苏沪宁钢机股份有限公司 | Round cross-shaped column base and manufacturing method thereof |
CN102352694A (en) * | 2011-09-13 | 2012-02-15 | 浙江大学 | Reinforcing method for steel structural column |
CN102352694B (en) * | 2011-09-13 | 2013-09-04 | 浙江大学 | Reinforcing method for steel structural column |
CN103352568A (en) * | 2013-07-08 | 2013-10-16 | 陕西煤业化工建设(集团)有限公司 | Method for building constructional column on foundation pad |
CN103485475A (en) * | 2013-09-22 | 2014-01-01 | 重庆一建建设集团有限公司 | Trough beam |
CN103485475B (en) * | 2013-09-22 | 2016-03-02 | 重庆一建建设集团有限公司 | Trough girder |
CN104722986B (en) * | 2013-12-18 | 2016-06-01 | 五冶集团上海有限公司 | A kind of non orientating silicon steel technique steel construction gate frame welding deformation control method |
CN104722986A (en) * | 2013-12-18 | 2015-06-24 | 五冶集团上海有限公司 | Welding deformation control method for non-oriented silicon steel process steel structure door-shaped framework |
CN104153599B (en) * | 2014-08-26 | 2016-04-20 | 中铁八局集团建筑工程有限公司 | Without steel column bearing steel and concrete girder construction system and construction rest thereof |
CN104153599A (en) * | 2014-08-26 | 2014-11-19 | 中铁八局集团建筑工程有限公司 | System of section steel concrete beam structure without section steel column support and bracket for construction of section steel concrete beam |
CN106003543A (en) * | 2015-03-31 | 2016-10-12 | 住友重机械工业株式会社 | Injection molding machine |
CN105672687A (en) * | 2016-02-03 | 2016-06-15 | 河南省文博加固工程有限公司 | Reinforcement method for concrete poles of transformer substation structural support |
CN105672687B (en) * | 2016-02-03 | 2017-08-29 | 河南文博建设工程有限公司 | A kind of substation truss concrete frame reinforcement means |
CN106545176A (en) * | 2016-10-21 | 2017-03-29 | 钟立朋 | A kind of building wall corbeling |
CN108425461A (en) * | 2018-03-10 | 2018-08-21 | 中南林业科技大学 | A kind of novel steel and wood composite structural column and its manufacturing method |
CN108532828A (en) * | 2018-03-10 | 2018-09-14 | 中南林业科技大学 | A kind of steel and wood composite structural beams |
CN109991311A (en) * | 2019-04-09 | 2019-07-09 | 中国十七冶集团有限公司 | A kind of workshop column reinforcing method and its detection device |
CN109991311B (en) * | 2019-04-09 | 2021-06-11 | 中国十七冶集团有限公司 | Factory building column reinforcing method and weld joint detection device thereof |
CN110388088A (en) * | 2019-07-26 | 2019-10-29 | 江苏省建筑工程集团有限公司 | A kind of increasing of steel-structure factory building is across remodeling method |
Also Published As
Publication number | Publication date |
---|---|
CN101839074B (en) | 2011-07-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101839074B (en) | Steel frame reinforcing column and reinforcing method thereof | |
CN109339229B (en) | Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor | |
CN108193782A (en) | Prefabricated modular frame node and assembling method thereof | |
CN105133791A (en) | Construction method for prefabricated thick plate steel rib concrete column variable cross-section transformation node structure | |
CN104775516A (en) | Field connecting method among prefabricated reinforced concrete columns | |
CN209907608U (en) | Assembled shear force wall connected node | |
CN104532953A (en) | 3D printing based assembly type special-shaped column framework structure and construction method thereof | |
CN105332449A (en) | Connecting piece between fabricated precast concrete shear wall and steel beam | |
CN108179818A (en) | Stiffened column and steel beam connecting joint with closing steel plate hoop | |
CN208870183U (en) | A kind of adjustable beam-to-column joint structure of rigidity for steel construction and Housing Structure System | |
CN112502714B (en) | Assembled shaft barrel structure and design and construction method | |
CN207846685U (en) | Stiffened column and steel beam connecting joint with closing steel plate hoop | |
CN201695705U (en) | Steel frame reinforced column | |
CN112240055B (en) | Fully assembled reinforced concrete structure system | |
CN214784707U (en) | Full-fabricated reinforced concrete structure system | |
CN110359580B (en) | Prefabricated rigid concrete column member node connecting structure and supporting method | |
CN106592821B (en) | Side-standing type integral forming structure and method of shear steel plate and one side reinforcing mesh | |
CN210767266U (en) | Prefabricated assembled type stiffening concrete column member node connecting structure | |
CN211621953U (en) | Prefabricated beam column connected node structure | |
CN108457374A (en) | A kind of box beam and column are linked and packed formula node preparation process and its node | |
CN210066817U (en) | Assembly integral vault is striden no post underground structure greatly | |
CN104314105A (en) | Connecting vertical seaming structure for basement external wall boards and cast-in-situ buttress column and construction method of connecting vertical seaming structure | |
CN111663566A (en) | Underground cylindrical reinforced concrete combined outer wall structure and construction method | |
CN210066818U (en) | Assembled flat top has post underground structure | |
CN210658451U (en) | Open cut method composite assembly formula underground structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110727 Termination date: 20150622 |
|
EXPY | Termination of patent right or utility model |