CN101831921A - 一种补偿收缩混凝土的施工方法 - Google Patents

一种补偿收缩混凝土的施工方法 Download PDF

Info

Publication number
CN101831921A
CN101831921A CN 201010175331 CN201010175331A CN101831921A CN 101831921 A CN101831921 A CN 101831921A CN 201010175331 CN201010175331 CN 201010175331 CN 201010175331 A CN201010175331 A CN 201010175331A CN 101831921 A CN101831921 A CN 101831921A
Authority
CN
China
Prior art keywords
expansive concrete
expansive
construction
concrete
reinforcing band
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010175331
Other languages
English (en)
Inventor
赵卫政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd
Original Assignee
JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd filed Critical JIANGSU XINGXIA BUILDING INSTALLATION CO Ltd
Priority to CN 201010175331 priority Critical patent/CN101831921A/zh
Publication of CN101831921A publication Critical patent/CN101831921A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

一种补偿收缩混凝土的施工方法,涉及建筑技术领域,特别是工程长度超过强制性规范要求,设计一般会以设置后浇带形式处理的结构技术领域。本发明的补偿收缩混凝土的施工方法是:在两段补偿收缩混凝土之间设置加强带膨胀混凝土。本发明在施工中采用膨胀加强带代替后浇带,不但防水效果得到大大提高,还进一步简化了施工工艺,缩短施工工期、工效高,使经济效率能得到有效提高。

Description

一种补偿收缩混凝土的施工方法
技术领域
本发明涉及建筑技术领域,特别是工程长度超过强制性规范要求,设计一般会以设置后浇带形式处理的结构技术领域。
背景技术
随着我国建设事业的迅速发展,越来越多的工程长度己超过强制性规范要求,设计一般会以设置后浇带形式处理。设置后浇带、施工缝为地下工程防水的最大隐患。同时,后浇带施工比较麻烦,最关键的是后浇带须在结构完成后42天才能封闭,许多工程工期根本不允许等如此长时间。
发明内容
本发明的目的是提出一种工期短、防水效果好的补偿收缩混凝土的施工方法。
本发明的补偿收缩混凝土的施工方法是:在两段补偿收缩混凝土之间设置加强带膨胀混凝土。
本发明在施工中采用膨胀加强带代替后浇带,不但防水效果得到大大提高,还进一步简化了施工工艺,缩短施工工期、工效高,使经济效率能得到有效提高。
另外,本发明所述加强带膨胀混凝土的至少一个端部叠加在位于该端的补偿收缩混凝土之上。
膨胀加强带是一种旨在提高混凝土结构抗裂性能的技术措施。施工中采用膨胀加强的目的是代替后浇带,进一步简化施工工艺,所以一般设置在后浇带的位置。为了有效发挥膨胀效果,增加长度方向的膨胀绝对量,所以其宽度应该比后浇带更宽一些。增加加强带是一种“抗”的措施,所以在连续施工的混凝土结构中,为提高其抵御收缩应力的能力,增设一些附加钢筋。膨胀加强带的构造与后浇带基本相同,但是在较厚的板中,一般不用设止水带。
附图说明
图1为本发明的连续式膨胀加强带示意图。
图2为本发明的间歇式膨胀加强带示意图。
图3为本发明的后浇式膨胀加强带示意图。
图4为本发明的墙体后浇式膨胀加强带示意图。
具体实施方式
图1至4是工程实践过程中应用效果比较好的部分节点构造示意,工程技术人员应该根据工程特点选择更合理的构造形式。
其中图1至3是厚底板结构中三种膨胀加强带构造示意图。
图1是连续浇筑混凝土时的膨胀加强带构造示意图。施工时,先浇筑一段两段补偿收缩混凝土1,再浇筑一段加强带膨胀混凝土2,最后再浇筑一段补偿收缩混凝土3。
图2是与先浇筑混凝土相接时采用的膨胀加强带构造示意图。施工时,先在两侧分别浇筑一段补偿收缩混凝土1、3,再在两段补偿收缩混凝土之间浇筑一段加强带膨胀混凝土2,并将加强带膨胀混凝土2左侧的上部叠加在左侧段的补偿收缩混凝土1的右端之上。
图3是一种类似于后浇带的后浇筑方式,除大体积混凝土考虑温度收缩应力外,一般可以在浇筑完两侧膨胀混凝土的任何时候回填浇筑。施工时,先在两侧分别浇筑一段补偿收缩混凝土1、3,再在两段补偿收缩混凝土之间浇筑一段加强带膨胀混凝土2,并将加强带膨胀混凝土2左侧的上部叠加在左侧段的补偿收缩混凝土1的右端之上,将加强带膨胀混凝土2右侧的上部叠加在右侧段的补偿收缩混凝土3的左端之上。
图4是用于墙体的膨胀加强带构造图。施工时,先浇筑一段两段补偿收缩混凝土1,再浇筑一段加强带膨胀混凝土2,最后再浇筑一段两段补偿收缩混凝土3。并将钢板止水带4、5分别置于补偿收缩混凝土1、3和加强带膨胀混凝土2的交界处。
另,补偿收缩混凝土的浇筑结构长度可按表1确定。
表1补偿收缩混凝土连续浇筑结构长度
Figure GSA00000104758300031
Figure GSA00000104758300041

Claims (2)

1.一种补偿收缩混凝土的施工方法,其特征在于:在两段补偿收缩混凝土之间设置加强带膨胀混凝土。
2.根据权利要求1所述补偿收缩混凝土的施工方法,其特征在于:所述加强带膨胀混凝土的至少一个端部叠加在位于该端的补偿收缩混凝土之上。
CN 201010175331 2010-05-12 2010-05-12 一种补偿收缩混凝土的施工方法 Pending CN101831921A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010175331 CN101831921A (zh) 2010-05-12 2010-05-12 一种补偿收缩混凝土的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010175331 CN101831921A (zh) 2010-05-12 2010-05-12 一种补偿收缩混凝土的施工方法

Publications (1)

Publication Number Publication Date
CN101831921A true CN101831921A (zh) 2010-09-15

Family

ID=42716120

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010175331 Pending CN101831921A (zh) 2010-05-12 2010-05-12 一种补偿收缩混凝土的施工方法

Country Status (1)

Country Link
CN (1) CN101831921A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276752A (zh) * 2013-06-20 2013-09-04 江苏城市职业学院 一种地下连续墙膨胀混凝土接头的施工方法
CN103485370A (zh) * 2013-09-24 2014-01-01 国网上海市电力公司 一种防止墙板有害裂缝的混凝土施工控制方法
CN104250976A (zh) * 2013-06-27 2014-12-31 上海三益建筑设计有限公司 地下室
CN109252553A (zh) * 2018-09-07 2019-01-22 江苏兴厦建设工程集团有限公司 一种无抗拔桩地库抗浮结构及施工方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1312233A (zh) * 2000-03-06 2001-09-12 李志刚 一种膨胀混凝土及其低碱高效混凝土膨胀剂
CN101353930A (zh) * 2007-07-24 2009-01-28 中国石油化工集团公司 超长混凝土水池结构无缝设计方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1312233A (zh) * 2000-03-06 2001-09-12 李志刚 一种膨胀混凝土及其低碱高效混凝土膨胀剂
CN101353930A (zh) * 2007-07-24 2009-01-28 中国石油化工集团公司 超长混凝土水池结构无缝设计方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《中国高新技术企业》 20080201 司红东 结构自防水混凝土渗漏原因分析及预防措施 , 第03期 *
《中国高新技术企业》 20080201 王邦国等 超长地下室钢筋混凝土结构加强带的设置与施工 , 第03期 *
《山西建筑》 20090120 叶平洋 超长混凝土结构无缝施工中膨胀加强带的设置 , 第03期 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276752A (zh) * 2013-06-20 2013-09-04 江苏城市职业学院 一种地下连续墙膨胀混凝土接头的施工方法
CN104250976A (zh) * 2013-06-27 2014-12-31 上海三益建筑设计有限公司 地下室
CN103485370A (zh) * 2013-09-24 2014-01-01 国网上海市电力公司 一种防止墙板有害裂缝的混凝土施工控制方法
CN103485370B (zh) * 2013-09-24 2016-01-06 国网上海市电力公司 一种防止墙板有害裂缝的混凝土施工控制方法
CN109252553A (zh) * 2018-09-07 2019-01-22 江苏兴厦建设工程集团有限公司 一种无抗拔桩地库抗浮结构及施工方法

Similar Documents

Publication Publication Date Title
CA2603559A1 (en) Segments for building spliced prestressed concrete girder and method of manufacturing the segments
CN101831921A (zh) 一种补偿收缩混凝土的施工方法
CN203684458U (zh) 柔性连接的混凝土预制墙板结构
CN202265926U (zh) 砌块拱式楼板
CN202658765U (zh) 龙骨构架混凝土抗裂填充墙体
CN206201157U (zh) 一种预制模板
CN201485965U (zh) 一种新型节能建筑结构
CN202000562U (zh) 一种剪力墙用多功能限位装置
CN109440992B (zh) 一种全干式预制装配混凝土板柱结构体系
JP2008144459A (ja) スラブ型枠、および合成床版の構築方法
CN108412080A (zh) 提高砖砌体整体性的加强连接结构、其施工方法及砖砌体
CN201671116U (zh) 补偿收缩混凝土的后浇带
CN102051929A (zh) 配置钢骨的砌块砌体墙及制造方法
CN201485994U (zh) 一种新型节能复合承重墙体
CN209669686U (zh) 一种箱梁头部装配式封堵结构
CN213390813U (zh) 一种组合式预制板
CN201224951Y (zh) 构造柱钢筋固定卡子
CN207934246U (zh) 提高砖砌体整体性的加强连接结构及砖砌体结构
CN103526877B (zh) 一种预制混凝土构件
CN202755532U (zh) 一种拉砌组合建筑装配式墙板
CN206752755U (zh) 一种构造柱浇筑免支模预制构件
CN205444666U (zh) 一种预制保温墙体构件
CN211523255U (zh) 一种基础承台模板制造工具
CN103541492A (zh) 一种预制混凝土构件
CN201635397U (zh) 混凝土模板支撑件

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20100915