CN101830388A - Installation method of counter-weight frame of elevator - Google Patents
Installation method of counter-weight frame of elevator Download PDFInfo
- Publication number
- CN101830388A CN101830388A CN 201010186429 CN201010186429A CN101830388A CN 101830388 A CN101830388 A CN 101830388A CN 201010186429 CN201010186429 CN 201010186429 CN 201010186429 A CN201010186429 A CN 201010186429A CN 101830388 A CN101830388 A CN 101830388A
- Authority
- CN
- China
- Prior art keywords
- wire rope
- counterweight
- counter
- counterweight frame
- hoistway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 19
- 238000009434 installation Methods 0.000 title claims abstract description 17
- 230000007246 mechanism Effects 0.000 claims abstract description 17
- 230000005484 gravity Effects 0.000 claims abstract description 6
- 230000009471 action Effects 0.000 claims abstract description 4
- 238000012423 maintenance Methods 0.000 claims description 4
- 238000004873 anchoring Methods 0.000 claims description 3
- GNFTZDOKVXKIBK-UHFFFAOYSA-N 3-(2-methoxyethoxy)benzohydrazide Chemical compound COCCOC1=CC=CC(C(=O)NN)=C1 GNFTZDOKVXKIBK-UHFFFAOYSA-N 0.000 claims description 2
- 229910000831 Steel Inorganic materials 0.000 abstract description 8
- 239000010959 steel Substances 0.000 abstract description 8
- 238000010276 construction Methods 0.000 abstract description 5
- 238000005553 drilling Methods 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 9
- 230000008569 process Effects 0.000 description 2
- 230000008859 change Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Images
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
Description
技术领域technical field
本发明涉及电梯安装工程领域,尤其是涉及电梯对重架的安装方法。The invention relates to the field of elevator installation engineering, in particular to an installation method of an elevator counterweight frame.
背景技术Background technique
电梯的安装方式主要有两种,一种是传统且广泛使用的使用脚手架的安装方法,另一种是逐步开始使用的无脚手架的安装方法。在涉及电梯对重架的安装时,由于需要利用轿架作为作业平台进行导轨等井道部件的安装,而导轨等井道部件必须由下往上逐步安装。因此,轿架作为作业平台需要在首层安装,而对重架需要在顶层进入井道安装,而且对重架通常位于远离轿厢门的井道一侧上。目前的通常做法是在井道内顶部位置搭设一个悬空的临时简易作业平台或两层悬空式脚手架,利用该平台或脚手架协助使对重架进入井道内完成就位,安装就位后又需要拆卸该简易平台或脚手架,这样的方式不仅增加材料成本又会增加工作量,还存在一定的安全隐患。There are two main ways to install elevators, one is the traditional and widely used installation method using scaffolding, and the other is the installation method without scaffolding that has gradually begun to be used. When involving the installation of the elevator counterweight frame, due to the need to utilize the car frame as the work platform to carry out the installation of shaft components such as guide rails, the shaft components such as guide rails must be installed step by step from bottom to top. Therefore, the car frame needs to be installed on the first floor as a working platform, and the counterweight frame needs to be installed on the top floor into the hoistway, and the counterweight frame is usually located on the side of the hoistway away from the car door. The current common practice is to set up a suspended temporary simple work platform or a two-layer suspended scaffold at the top of the hoistway, and use the platform or scaffold to assist the counterweight frame into the hoistway to complete its position. After installation, it needs to be dismantled. Simple platforms or scaffolding, this method not only increases the cost of materials but also increases the workload, and there are certain safety hazards.
发明内容Contents of the invention
本发明的目的是提供一种简单方便、无需在顶层搭建作业平台且安全高效的电梯对重架的安装方法。The object of the present invention is to provide a safe and efficient method for installing an elevator counterweight frame that is simple and convenient, does not require a work platform to be built on the top floor.
本发明的技术解决方案是:一种电梯对重架的安装方法,它包括以下步骤:a、在电梯机房检修吊钩上设置吊装机构,并在井道的顶层楼板上钻通孔,从通孔内放入对重吊装钢丝绳,该对重吊装钢丝绳的一端安装在吊装机构上,另一端穿过通孔进入井道内并放置在顶层层门处,对重架移动至顶层层门处;b、在主机的曳引轮上设置曳引钢丝绳,该曳引钢丝绳的一端穿过机房对重曳引孔连接在对重架上,另一端穿过轿厢曳引孔放下至轿厢顶部;c、将顶层层门处的对重吊装钢丝绳的端部固定在对重架上;d、控制吊装机构使对重吊装钢丝绳将对重架吊起,直至对重架在顶层层门处处于竖立状态且其顶部进入井道内;e、完成轿厢顶部的曳引钢丝绳的连接固定;f、完成对重架上对重块的安装及固定;g、控制吊装机构使对重吊装钢丝绳将对重架吊起并进入井道内后,释放对重吊装钢丝绳,使对重架在重力作用下在井道内移动直至就位;h、待曳引钢丝绳完全受力张紧后,解除对重吊装钢丝绳在吊装机构上的固定,使其自由悬挂在对重架上。The technical solution of the present invention is: a method for installing the counterweight frame of an elevator, which includes the following steps: a. Install a hoisting mechanism on the maintenance hook of the elevator machine room, and drill a through hole on the top floor of the hoistway. Put the counterweight hoisting wire rope inside, one end of the counterweight hoisting wire rope is installed on the hoisting mechanism, the other end enters the hoistway through the through hole and is placed at the top floor door, and the counterweight frame moves to the top floor door; b. A traction wire rope is set on the traction sheave of the main engine, and one end of the traction wire rope is connected to the counterweight frame through the counterweight traction hole of the machine room, and the other end is lowered to the top of the car through the traction hole of the car; c. Fix the end of the counterweight hoisting wire rope at the top floor door on the counterweight frame; d, control the hoisting mechanism so that the counterweight hoisting wire rope lifts the counterweight frame until the counterweight frame is in an upright state at the top floor door and Its top enters the hoistway; e, complete the connection and fixation of the traction wire rope on the top of the car; f, complete the installation and fixing of the counterweight on the counterweight frame; g, control the hoisting mechanism so that the counterweight hoisting wire rope will lift the counterweight frame After lifting and entering the hoistway, release the counterweight hoisting wire rope, so that the counterweight frame moves in the hoistway under the action of gravity until it is in place; Fixed on the top, so that it hangs freely on the counterweight frame.
在井道的顶层楼板上设置通孔,穿设对重吊装钢丝绳在顶层层门处吊起对重架,完成对重块的设置,在曳引钢丝绳分别固定在对重架和轿厢后,通过控制对重吊装钢丝绳将对重架移动至井道内,并依靠其自身重力移动到位。这样的设置方式,可以免去在井道内设置脚手架或作业平台的步骤,施工比较方便,而且施工过程中,对重架始终被对重吊装钢丝绳牵引,到位过程也只需要调整对重吊装钢丝绳,利用重力便可以实现,整个过程安全可靠,高效便捷。Set a through hole on the top floor of the hoistway, pass the counterweight hoisting wire rope to lift the counterweight frame at the top floor door, and complete the setting of the counterweight block. After the traction steel wire rope is respectively fixed on the counterweight frame and the car, pass through Control the counterweight hoisting wire rope to move the counterweight frame into the hoistway, and move it into place by its own gravity. This kind of setting method can save the step of setting up scaffolding or working platform in the hoistway, and the construction is more convenient. In addition, during the construction process, the counterweight frame is always pulled by the counterweight hoisting wire rope, and only need to adjust the counterweight hoisting wire rope when it is in place. It can be realized by gravity, and the whole process is safe, reliable, efficient and convenient.
在步骤b中,还包括将轿厢侧的所述曳引钢丝绳通过钢丝绳夹固定在所述轿厢曳引孔处的步骤。防止轿厢侧曳引钢丝绳完全下坠。In step b, the step of fixing the traction wire rope on the side of the car at the traction hole of the car through a wire rope clamp is also included. Prevent the car side traction wire rope from falling completely.
在步骤b中还包括将轿厢侧的所述曳引钢丝绳挂靠在所述顶层层门侧面的挂靠支架上的步骤。避免轿厢侧的曳引钢丝绳影响其他部件的安装。In step b, it also includes the step of hanging the traction wire rope on the side of the car on the hanging bracket on the side of the top floor door. Avoid the traction wire rope on the car side from affecting the installation of other components.
在步骤g中,还包括在对重架移动至井道深度一半位置时,取下挂靠在挂靠支架上的曳引钢丝绳并脱开钢丝绳夹的固定,设置顶层层门护板的步骤。防止发生人员意外坠落的危险。In step g, it also includes the step of removing the traction wire rope attached to the anchor bracket when the counterweight frame moves to half the depth of the hoistway, disengaging the fixing of the wire rope clip, and setting the top floor door protection plate. Protect against accidental fall hazards.
所述通孔的垂直投影位于电梯厅门中间,且离井道内前壁300-400mm处。通孔靠近井道前壁,对重架的吊装位置靠近层门,方便施工。The vertical projection of the through hole is located in the middle of the elevator hall door, and is 300-400mm away from the inner front wall of the hoistway. The through hole is close to the front wall of the hoistway, and the hoisting position of the counterweight frame is close to the landing door, which is convenient for construction.
所述吊装机构为手动葫芦,工具简便易得,操作方便。The hoisting mechanism is a manual hoist, and the tools are easy to obtain and easy to operate.
本发明的优点是:无需辅助作业平台或脚手架便可以实现顶层安装对重架,施工方便,安全可靠,有效降低了作业成本和避免了安全风险。The invention has the advantages that the counterweight frame can be installed on the top floor without an auxiliary operation platform or scaffolding, the construction is convenient, safe and reliable, and the operation cost is effectively reduced and safety risks are avoided.
附图说明Description of drawings
附图1为本发明实施例中对重吊装钢丝绳设置示意图;
附图2为本发明实施例中曳引钢丝绳设置示意图;Accompanying
附图3为本发明实施例中轿厢侧曳引钢丝绳挂靠示意图;Accompanying
附图4为本发明实施例中对重吊装钢丝绳连接对重架示意图;Accompanying
附图5为本发明实施例中对重架吊起示意图;Accompanying
附图6为本发明实施例中安装轿厢曳引钢丝绳示意图;Accompanying
附图7为本发明实施例中安装对重块示意图;Accompanying drawing 7 is the schematic diagram of installing counterweight in the embodiment of the present invention;
附图8为本发明实施例中对重架进入井道内示意图;Accompanying drawing 8 is a schematic diagram of the counterweight frame entering the hoistway in the embodiment of the present invention;
附图9为本发明实施例中对重架就位示意图;Accompanying drawing 9 is the schematic diagram of counterweight frame in the embodiment of the present invention;
1、对重吊装钢丝绳,2、对重架,3、曳引钢丝绳,4、钢丝绳夹,5、标记,6、挂靠支架,7、对重块,8、对重固定压板,9、对重防撞墙轮,10、层门护板,11、顶层层门,12、顶层楼板,13、通孔,14、检修吊钩,15、主机,16、手动葫芦,17、对重曳引孔,18、轿厢曳引孔,19、轿厢。1. Counterweight hoisting wire rope, 2. Counterweight frame, 3. Traction wire rope, 4. Wire rope clamp, 5. Marking, 6. Anchor bracket, 7. Counterweight block, 8. Counterweight fixing plate, 9. Counterweight Anti-collision wall wheel, 10, landing door guard, 11, top landing door, 12, top floor, 13, through hole, 14, maintenance hook, 15, main engine, 16, manual hoist, 17, counterweight traction hole , 18, car traction hole, 19, car.
具体实施方式Detailed ways
实施例:Example:
一种电梯对重架的安装方法,其步骤如图1-9中所示:A method for installing an elevator counterweight frame, the steps of which are shown in Figures 1-9:
参见图1,将手动葫芦16挂设在电梯机房的检修吊钩14上,在电梯机房地面楼板也就是井道的顶层楼板12上上钻一个φ18mm的通孔13,该通孔13的垂直投影落在电梯厅门口中间,在井道内离井道前壁约300-400mm处。从通孔13放下一条对重吊装钢丝绳1,一头挂在手动葫芦16的吊钩上,另一头穿过顶层楼板12放至顶层层门11外侧。对重架2从顶层外侧搬移至层门11附件位置上;Referring to Fig. 1, the
参见图2,安装曳引钢丝绳3:从机房对重曳引孔17放下一侧已装好锥套的曳引钢丝绳3,从顶层井道内引至顶层层门11外侧,并安装在对重架2的绳头板上,事先还需要根据井道尺寸计算出曳引钢丝绳3位置长度尺寸后用绝缘胶布做好位置标记5。曳引钢丝绳3另一侧从机房轿厢曳引孔18完全放下至轿厢19顶部位置,按正常排布挂设在主机15的曳引轮上,用机房钢丝绳夹4将曳引钢丝绳3临时夹紧固定,防止轿厢侧曳引钢丝绳完全下坠。如此重复,将所有曳引钢丝绳3都挂设完成。Refer to Figure 2, install the traction wire rope 3: put down the
参见图3,每一条曳引钢丝绳3放下挂设完成后,将它临时挂靠在挂靠支架6上,防止阻碍其他钢丝绳的安装,直至所有曳引钢丝绳放设完成。Referring to Fig. 3, after each
参见图4,将机房放下至顶层层门11侧的对重吊装钢丝绳1穿过对重架2并绑扎好在对重架2上,准备起吊对重架2。Referring to Fig. 4, put down the counterweight hoisting
参见图5,通过控制机房钢丝绳夹4逐条放下曳引钢丝绳3,使位置标记5按要求停留在指定的位置。再用手动葫芦16将对重架2吊起使它逐步进入井道内,直至其底部停靠在顶层层门11约400~600mm的位置处。Referring to Fig. 5, by controlling the
参见图6,完成轿厢侧的曳引钢丝绳3与轿厢19的连接。Referring to Fig. 6, the connection of the
参见图7,在顶层层门11外,往对重架2加入适量的对重块7,加入完后用对重固定压板8压紧对重块7,并在对重固定压板8上安装好对重防撞墙轮9。Referring to Fig. 7, outside the
参见图8,使用手动葫芦16将对重架2吊起,待对重架2完全进入井道内后,释放手动葫芦16,对重架2在重力作用下往右侧移动,移动至约井道深度一半的行程时,解除临时挂靠在挂靠支架6上全部曳引钢丝绳3后再解除机房钢丝绳夹4,恢复顶层层门护板10;继续释放手动葫芦16使对重架2往右侧移动,直至对重架2完成就位。Referring to Figure 8, use the manual hoist 16 to lift the
参见图9所示,曳引钢丝绳完全受力后,解除机房手动葫芦吊钩上的对重吊装钢丝绳1,将对重吊装钢丝绳1从机房φ18mm的通孔放下井道,让它自由地悬挂在对重架上。此时完成对重架2的安装。As shown in Figure 9, after the traction wire rope is fully stressed, remove the counterweight hoisting
上列详细说明是针对本发明之一可行实施例的具体说明,该实施例并非用以限制本发明的专利范围,凡未脱离本发明所为的等效实施或变更,均应包含于本案的专利范围中。The above detailed description is a specific description of a feasible embodiment of the present invention. This embodiment is not intended to limit the patent scope of the present invention. Any equivalent implementation or change that does not depart from the present invention should be included in the scope of this case. within the scope of the patent.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010101864296A CN101830388B (en) | 2010-05-21 | 2010-05-21 | Installation method of counter-weight frame of elevator |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010101864296A CN101830388B (en) | 2010-05-21 | 2010-05-21 | Installation method of counter-weight frame of elevator |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101830388A true CN101830388A (en) | 2010-09-15 |
| CN101830388B CN101830388B (en) | 2012-05-30 |
Family
ID=42714636
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2010101864296A Active CN101830388B (en) | 2010-05-21 | 2010-05-21 | Installation method of counter-weight frame of elevator |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101830388B (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104477736A (en) * | 2012-10-12 | 2015-04-01 | 广州广日电梯工程有限公司 | Shaft elevator installation method |
| JP2016132515A (en) * | 2015-01-16 | 2016-07-25 | 三菱電機ビルテクノサービス株式会社 | Elevator balance weight shipping and carrying-in device |
| CN106081797A (en) * | 2016-05-03 | 2016-11-09 | 马海英 | A kind of novel elevator mounting process lifting |
| JP2017007784A (en) * | 2015-06-19 | 2017-01-12 | 三菱電機ビルテクノサービス株式会社 | Elevator balancing weight carrying-out method and elevator balancing weight carrying-out tool |
| CN108087667A (en) * | 2017-12-26 | 2018-05-29 | 浙江西子重工机械有限公司 | A kind of counterweight frame of roller type and the Elevator weight sensor and its installation method using the counterweight frame |
| CN109132820A (en) * | 2017-06-27 | 2019-01-04 | 三菱电机大楼技术服务株式会社 | It adjusts the removing method of counterweight and adjusts the supporting arrangement of counterweight |
| CN112203967A (en) * | 2018-06-13 | 2021-01-08 | 三菱电机大楼技术服务株式会社 | Elevator counterweight frame assembly auxiliary device and elevator counterweight frame assembly method |
| CN115783957A (en) * | 2022-11-30 | 2023-03-14 | 日立电梯(中国)有限公司 | Counterweight guide device and counterweight installation method for scaffoldless elevator installation |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0375208A1 (en) * | 1988-12-22 | 1990-06-27 | Otis Elevator Company | Method of mounting a lift |
| JPH0859132A (en) * | 1994-08-26 | 1996-03-05 | Mitsubishi Denki Bill Techno Service Kk | Lifting of load |
| CN1161678A (en) * | 1994-08-29 | 1997-10-08 | 奥蒂斯电梯公司 | Method and apparatus for mounting and balancing an elevator car |
| JPH11228048A (en) * | 1998-02-19 | 1999-08-24 | Hitachi Building Systems Co Ltd | Elevator counterweight loading device and loading method |
| JP2003155178A (en) * | 2001-11-21 | 2003-05-27 | Hitachi Building Systems Co Ltd | Elevator lifting structure |
| JP2005225627A (en) * | 2004-02-13 | 2005-08-25 | Mitsubishi Electric Corp | Elevator equipment |
| CN1990371A (en) * | 2005-12-27 | 2007-07-04 | 上海三菱电梯有限公司 | Elevator installation method and up-down system used therein |
| CN201334295Y (en) * | 2008-12-31 | 2009-10-28 | 苏州江南嘉捷电梯股份有限公司 | Lifting installation system for installation of machine room-less elevator traction machine |
-
2010
- 2010-05-21 CN CN2010101864296A patent/CN101830388B/en active Active
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP0375208A1 (en) * | 1988-12-22 | 1990-06-27 | Otis Elevator Company | Method of mounting a lift |
| JPH0859132A (en) * | 1994-08-26 | 1996-03-05 | Mitsubishi Denki Bill Techno Service Kk | Lifting of load |
| CN1161678A (en) * | 1994-08-29 | 1997-10-08 | 奥蒂斯电梯公司 | Method and apparatus for mounting and balancing an elevator car |
| JPH11228048A (en) * | 1998-02-19 | 1999-08-24 | Hitachi Building Systems Co Ltd | Elevator counterweight loading device and loading method |
| JP2003155178A (en) * | 2001-11-21 | 2003-05-27 | Hitachi Building Systems Co Ltd | Elevator lifting structure |
| JP2005225627A (en) * | 2004-02-13 | 2005-08-25 | Mitsubishi Electric Corp | Elevator equipment |
| CN1990371A (en) * | 2005-12-27 | 2007-07-04 | 上海三菱电梯有限公司 | Elevator installation method and up-down system used therein |
| CN201334295Y (en) * | 2008-12-31 | 2009-10-28 | 苏州江南嘉捷电梯股份有限公司 | Lifting installation system for installation of machine room-less elevator traction machine |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104477736A (en) * | 2012-10-12 | 2015-04-01 | 广州广日电梯工程有限公司 | Shaft elevator installation method |
| JP2016132515A (en) * | 2015-01-16 | 2016-07-25 | 三菱電機ビルテクノサービス株式会社 | Elevator balance weight shipping and carrying-in device |
| JP2017007784A (en) * | 2015-06-19 | 2017-01-12 | 三菱電機ビルテクノサービス株式会社 | Elevator balancing weight carrying-out method and elevator balancing weight carrying-out tool |
| CN106081797A (en) * | 2016-05-03 | 2016-11-09 | 马海英 | A kind of novel elevator mounting process lifting |
| CN109132820A (en) * | 2017-06-27 | 2019-01-04 | 三菱电机大楼技术服务株式会社 | It adjusts the removing method of counterweight and adjusts the supporting arrangement of counterweight |
| CN109132820B (en) * | 2017-06-27 | 2021-10-26 | 三菱电机大楼技术服务株式会社 | Method for taking out adjustment counter weight and support device for adjustment counter weight |
| CN108087667A (en) * | 2017-12-26 | 2018-05-29 | 浙江西子重工机械有限公司 | A kind of counterweight frame of roller type and the Elevator weight sensor and its installation method using the counterweight frame |
| CN112203967A (en) * | 2018-06-13 | 2021-01-08 | 三菱电机大楼技术服务株式会社 | Elevator counterweight frame assembly auxiliary device and elevator counterweight frame assembly method |
| CN112203967B (en) * | 2018-06-13 | 2022-11-08 | 三菱电机楼宇解决方案株式会社 | Elevator counterweight frame assembling auxiliary device and elevator counterweight frame assembling method |
| CN115783957A (en) * | 2022-11-30 | 2023-03-14 | 日立电梯(中国)有限公司 | Counterweight guide device and counterweight installation method for scaffoldless elevator installation |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101830388B (en) | 2012-05-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101830388A (en) | Installation method of counter-weight frame of elevator | |
| CN113167072B (en) | Building site equipment with climbing form and elevator system | |
| CN102216545B (en) | Mobile cantilever platforms and methods of installation thereof | |
| CN101466630B (en) | Method for installing hoisting ropes of an elevator | |
| CN104340813B (en) | A kind of elevator installation construction method | |
| CN110228743A (en) | Two-to-one suspension is set in elevator traction than building hoist and its operational method | |
| CN103086227B (en) | Lift facility | |
| CN115190862A (en) | Elevator arrangement and method for building an elevator | |
| CN104477736A (en) | Shaft elevator installation method | |
| CN115720568A (en) | Method for constructing a lift installation and lift installation suitable for carrying out the method | |
| JP4929045B2 (en) | Guide rail installation method for machine room-less elevator | |
| CN104030176B (en) | The equalizer bar of hoisting platform truss and hanging method thereof | |
| CN203959697U (en) | The equalizing bar of hoisting platform truss | |
| CN110094101A (en) | The method that tower crane removes standard knot under restricted clearance | |
| JP4841171B2 (en) | Rise-up elevator installation method | |
| CN205575520U (en) | Installation device of super high -rise building elevator | |
| CN205153559U (en) | Cast -in -place roof beam prestressing force tensioning equipment | |
| CN210976551U (en) | External hanging protective frame | |
| JP2014105035A (en) | Method for replacing main rope of elevator | |
| CN106081797A (en) | A kind of novel elevator mounting process lifting | |
| KR101976724B1 (en) | Method for installing elevator guide rails without a machine room | |
| CN119102370B (en) | Construction method of hanging basket without counterweight | |
| JPH082850A (en) | Elevator hoistway construction method | |
| CN202831596U (en) | Top storey installation platform used for well elevator installation | |
| JPH0751432B2 (en) | Main rope replacement method for elevators |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |