CN101812836A - Construction platform of hydraulic plug board on sea - Google Patents
Construction platform of hydraulic plug board on sea Download PDFInfo
- Publication number
- CN101812836A CN101812836A CN200910014451A CN200910014451A CN101812836A CN 101812836 A CN101812836 A CN 101812836A CN 200910014451 A CN200910014451 A CN 200910014451A CN 200910014451 A CN200910014451 A CN 200910014451A CN 101812836 A CN101812836 A CN 101812836A
- Authority
- CN
- China
- Prior art keywords
- hydraulic
- plug board
- steel pipe
- sea
- construction platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Revetment (AREA)
Abstract
The invention relates to a construction platform of a hydraulic plug board on the sea, comprising a prepared hole, a steel tube and a pedal plate which are all on the hydraulic plug board. The steel tube penetrates through the prepared hole on the hydraulic plug board, the pedal plate is mounted on the steel tube to form an integral body with the steel tube. The invention has the characteristics of integral body capable of resisting impact from various wind waves, no damage to an operating table, raw material saving, very convenient assembly and disassembly, high construction speed, low construction cost, and the like, and can be broadly applied to dam construction of the hydraulic plug board on the sea, the lake and the river.
Description
One, technical field
The present invention relates to the marine engineering operating platform, particularly a kind of marine water conservancy plate operation platform.
Two, background technology
In the hydraulic plug board on sea construction project, finish that slip casting is stitched admittedly and work such as top assembling reinforcement, cast-in-place cap, at first mounting platform.Existing marine plate engineering adopts the building scaffold of land use to construct, and thisly landly exists following shortcoming or deficiency with scaffold: 1. owing to be subjected to the impact of marine stormy waves, installation work is very difficult; 2. be easy to again after installing be washed out, 3. be difficult to guarantee safe construction by stormy waves; 3. exist potential safety hazard.
Three, summary of the invention
The technical problem to be solved in the present invention provides a kind of construction platform of hydraulic plug board on sea, adopt with hydraulic sheeting and form integrative-structure, the shortcoming or the deficiency that had both overcome or avoided existing in the above-mentioned prior art, safety is firm again, the slip casting of finishing smoothly the hydraulic plug board on sea engineering fast admittedly seam, assembling reinforcement, supporting template, beat construction task such as concrete cap-beam.
Construction platform of hydraulic plug board on sea of the present invention comprises hydraulic sheeting, steel pipe and foot rest.Described hydraulic sheeting is provided with preformed hole, and steel pipe passes the preformed hole on the hydraulic sheeting, and foot rest is installed on the steel pipe, forms an integral body with hydraulic sheeting.
Wherein, described foot rest is the frame type member, is fixed on the steel pipe that passes hydraulic sheeting preformed hole both sides.Preformed hole on the described hydraulic sheeting is positioned at the top of hydraulic sheeting.Described foot rest is made framework, framework upper berth welding steel expanded metals, steel plate bar or reinforcing bar by steel pipe or angle steel weldering.Described foot rest and steel pipe are fixed together by connector.Described connector is platform buckle, bolt or the member that is easy to fixing and dismounting.
The present invention compared with prior art has following advantage or beneficial effect:
1, the safety and stability performance is good, traditional platform is difficult to keep stable under sea beat, adopts marine plate operation platform because it is to be tightened to an integral body by steel pipe insertion concrete plate holes two ends with connector and foot rest can resist the damage that the impact of various stormy waves can not cause operating desk.
2, saved material consumption, adopt traditional platform from ground to the operating table surface, need use a large amount of steel pipes to form framework, and adopt the steel pipe of marine plate operation platform from ground to the operating table surface all to be cancelled, can save a large amount of steel pipes, also avoid steel pipe support to be washed out the loss that causes by stormy waves.
3, installation and dismounting are all very convenient, and the whole operation platform has only the such three kinds of things of the steel pipe, foot rest and the connector that insert in the preformed hole, and installation and dismounting are all very simple, help improving speed of application, reduce construction cost.
Four, description of drawings
Fig. 1 is a kind of structural representation of the present invention
Fig. 2 is for pressing hydraulic sheeting preformed hole structural representation shown in Figure 1
Fig. 3 is for pressing plan structure schematic diagram shown in Figure 1
Structural representation when Fig. 4 inserts steel pipe for pressing preformed hole shown in Figure 1
Five, the specific embodiment:
Referring to Fig. 1-Fig. 4, a kind of construction platform of hydraulic plug board on sea comprises a kind of construction platform of hydraulic plug board on sea, comprises hydraulic sheeting, steel pipe and foot rest.Hydraulic sheeting 5 is provided with preformed hole 1, and steel pipe 2 passes the preformed hole 1 on the hydraulic sheeting, and foot rest 4 is installed on the steel pipe 2, forms an integral body with hydraulic sheeting 5.
Dismantling connector 3 after construction finishes regains foot rests 4 and inserts steel pipe 2 usefulness cement mortar and block after the preformed hole 1 whole engineering and promptly accuse and finish.
Claims (6)
1. a construction platform of hydraulic plug board on sea comprises hydraulic sheeting, steel pipe and foot rest, it is characterized in that described hydraulic sheeting is provided with preformed hole, and steel pipe passes the preformed hole on the hydraulic sheeting, and foot rest is installed on the steel pipe, forms an integral body with hydraulic sheeting.
2. construction platform of hydraulic plug board on sea according to claim 1 is characterized in that described foot rest is the frame type member, is fixed on the steel pipe that passes hydraulic sheeting preformed hole both sides.
3. construction platform of hydraulic plug board on sea according to claim 1 and 2 is characterized in that the preformed hole on the described hydraulic sheeting is positioned at the top of hydraulic sheeting.
4. construction platform of hydraulic plug board on sea according to claim 1 and 2 is characterized in that described foot rest makes framework, framework upper berth welding steel expanded metals, steel plate bar or reinforcing bar by the weldering of steel pipe or angle steel.
5. construction platform of hydraulic plug board on sea according to claim 1 and 2 is characterized in that described foot rest and steel pipe are fixed together by connector.
6. construction platform of hydraulic plug board on sea according to claim 1 or 5 is characterized in that described connector is platform buckle, bolt or the member that is easy to fixing and dismounting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200910014451A CN101812836A (en) | 2009-02-23 | 2009-02-23 | Construction platform of hydraulic plug board on sea |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200910014451A CN101812836A (en) | 2009-02-23 | 2009-02-23 | Construction platform of hydraulic plug board on sea |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101812836A true CN101812836A (en) | 2010-08-25 |
Family
ID=42620192
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200910014451A Pending CN101812836A (en) | 2009-02-23 | 2009-02-23 | Construction platform of hydraulic plug board on sea |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101812836A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102168418A (en) * | 2011-03-22 | 2011-08-31 | 毕承会 | Construction method of offshore elevated platform |
CN107627079A (en) * | 2017-09-26 | 2018-01-26 | 浙江中南建设集团钢结构有限公司 | Large Diameter Pipeline steel pipe runs through plate processing method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB609428A (en) * | 1946-03-14 | 1948-09-30 | Ernest Goodall Malthouse | Improvements in or relating to scaffolds and gantries |
JPS6250507A (en) * | 1985-08-28 | 1987-03-05 | Taisei Corp | Offshore scaffold |
CN2166178Y (en) * | 1993-08-03 | 1994-05-25 | 张鸿勋 | Gangboard stand of scaffold and its dust-proof life net combined apparatus |
CN2336042Y (en) * | 1998-07-23 | 1999-09-01 | 金美华 | Scaffold board |
CN2683755Y (en) * | 2004-02-25 | 2005-03-09 | 肖冰 | Treadle of false work |
CN2911009Y (en) * | 2006-01-23 | 2007-06-13 | 中国海洋石油总公司 | One-leg three-pile simple platform suitable for developing medium-small oil fields in sea |
CN201377087Y (en) * | 2009-02-23 | 2010-01-06 | 何富荣 | Marine hydropower insert plate construction scaffold |
-
2009
- 2009-02-23 CN CN200910014451A patent/CN101812836A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB609428A (en) * | 1946-03-14 | 1948-09-30 | Ernest Goodall Malthouse | Improvements in or relating to scaffolds and gantries |
JPS6250507A (en) * | 1985-08-28 | 1987-03-05 | Taisei Corp | Offshore scaffold |
CN2166178Y (en) * | 1993-08-03 | 1994-05-25 | 张鸿勋 | Gangboard stand of scaffold and its dust-proof life net combined apparatus |
CN2336042Y (en) * | 1998-07-23 | 1999-09-01 | 金美华 | Scaffold board |
CN2683755Y (en) * | 2004-02-25 | 2005-03-09 | 肖冰 | Treadle of false work |
CN2911009Y (en) * | 2006-01-23 | 2007-06-13 | 中国海洋石油总公司 | One-leg three-pile simple platform suitable for developing medium-small oil fields in sea |
CN201377087Y (en) * | 2009-02-23 | 2010-01-06 | 何富荣 | Marine hydropower insert plate construction scaffold |
Non-Patent Citations (1)
Title |
---|
钟启华: "立交桥工程中帽梁施工支架的使用分析", 《中国科技信息》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102168418A (en) * | 2011-03-22 | 2011-08-31 | 毕承会 | Construction method of offshore elevated platform |
CN102168418B (en) * | 2011-03-22 | 2012-07-25 | 毕承会 | Construction method of offshore elevated platform |
CN107627079A (en) * | 2017-09-26 | 2018-01-26 | 浙江中南建设集团钢结构有限公司 | Large Diameter Pipeline steel pipe runs through plate processing method |
CN107627079B (en) * | 2017-09-26 | 2019-05-07 | 浙江中南建设集团钢结构有限公司 | Large Diameter Pipeline steel pipe runs through plate processing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201826519U (en) | Building template | |
CN203393848U (en) | Connection node structure of reinforced concrete column and steel I-beam | |
CN201546227U (en) | Steel support beam for supporting foundation pit bracing piling wall and basement structure outer wall | |
CN103452126B (en) | Light combined hanging box with recyclable baseplate steels and construction technology thereof | |
CN101906754A (en) | Rigid connection method for steel beam and concrete pier | |
CN201713827U (en) | Fan base structure of offshore wind power station | |
CN101876174A (en) | Foundation structure of marine wind electric field fan | |
CN205502025U (en) | Stagnant water stake is gone along with sb. to guard him to foundation ditch and shaped steel encloses connection structure between purlin | |
CN101225663A (en) | Steel boxed cofferdam and recovery method thereof | |
CN101812836A (en) | Construction platform of hydraulic plug board on sea | |
CN213682129U (en) | Deep foundation pit unilateral die carrier | |
CN201377087Y (en) | Marine hydropower insert plate construction scaffold | |
CN205839701U (en) | Concrete formwork complexes at a kind of expansion joint | |
CN104594389A (en) | Post-cast strip external wall plugging structure with elastic water stoppers | |
CN201686983U (en) | Double-seam steel sheet pile | |
CN103882840B (en) | A kind of surge shaft Cast-in-place concrete assembling falsework and mounting method thereof | |
CN203238651U (en) | Fixing and leveling structure for installing offshore wind turbine jacket foundation | |
CN202298649U (en) | Buttress structure with longitudinal beams | |
CN211621660U (en) | Anti-pulling base is strengthened in installation of transmission tower | |
CN211037798U (en) | Aluminum-wood combined template system for basement | |
CN208088266U (en) | There is the simple wellhead structure of support | |
CN207405876U (en) | A kind of firm banking for column component | |
CN201137155Y (en) | Underwater temporary support pile joint | |
CN201526048U (en) | Anchor-type metal foundation | |
CN201245926Y (en) | I-shaped beam fastener |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20100825 |