CN101800428A - 省地协调母线电压协调约束上下限值获得方法 - Google Patents

省地协调母线电压协调约束上下限值获得方法 Download PDF

Info

Publication number
CN101800428A
CN101800428A CN200910244486A CN200910244486A CN101800428A CN 101800428 A CN101800428 A CN 101800428A CN 200910244486 A CN200910244486 A CN 200910244486A CN 200910244486 A CN200910244486 A CN 200910244486A CN 101800428 A CN101800428 A CN 101800428A
Authority
CN
China
Prior art keywords
constraint
vector
voltage
generator
bus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910244486A
Other languages
English (en)
Other versions
CN101800428B (zh
Inventor
孙宏斌
鲁庭瑞
郭庆来
郭建伟
王彬
李海峰
张伯明
罗建裕
吴文传
刘华伟
陈江澜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsinghua University
State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Tsinghua University
State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsinghua University, State Grid Jiangsu Electric Power Co Ltd filed Critical Tsinghua University
Priority to CN2009102444862A priority Critical patent/CN101800428B/zh
Publication of CN101800428A publication Critical patent/CN101800428A/zh
Application granted granted Critical
Publication of CN101800428B publication Critical patent/CN101800428B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/30Reactive power compensation

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Control Of Eletrric Generators (AREA)

Abstract

本发明涉及省地协调母线电压协调约束上下限值获得方法,属于电力系统自动电压控制技术领域。该方法包括,基于准稳态灵敏度,构造二次规划模型,求解尽可能增加省调发电机无功出力,在满足发电机母线电压约束限值,协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,省地协调母线电压所能达到的上限值;尽可能减少省调发电机无功出力,在满足发电机母线电压约束限值,协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,省地协调母线电压所能达到的下限值。该方法可有效降低网损,提高电网的电压安全水平。

Description

省地协调母线电压协调约束上下限值获得方法
技术领域
本发明属于电力系统自动电压控制技术领域,特别涉省地协调电压控制中省地协调母线电压协调约束上下限值获得方法。
背景技术
自动电压控制(AVC,Automatic Voltage Control)系统是电力系统最重要的自动控制系统之一。中国互联电网规模庞大,其运行由分层分区的多级调度机构来负责管理,网调、省调和地调是其中比较有代表性的三个调度级别。传统的无功优化控制系统针对各级电网独立控制,相互之间缺乏有效协调。而事实上,由于各级电网之间互相影响,传统的独立控制方法存在很大局限性,比如如果各地调不能做好本地的无功补偿,将导致无功从高压到低压层层下送,无论网省调如何控制,网损下降都不会显著。此外,随着自动电压控制系统在各级电网中的普遍推广,由于各自动电压控制系统的控制目标不一致、控制信息不共享、控制操作不同步,从而引发控制系统之间的冲突和过调等问题,最终导致控制频繁动作,并显著降低控制品质。省级电网和地区电网的电压控制需要相互协调以实现协调无功电压优化控制,达到省调主网与地区电网之间合理的无功交换的目的。目前较为有效地研究成果为省地协调电压控制方法。省地协调边界为220kV变电站,选择220kV变电站变压器高压侧无功作为省调对地调的协调变量,选择220kV侧母线作为省地协调母线,其母线电压作为地调对省调的协调变量。省调和地调AVC系统分别向对方提出协调变量的期望约束,同时在控制中考虑对方提出的协调约束,实现双向互动,真正发挥协调控制的优势。但目前尚未发现在线实时计算省地协调母线电压协调约束上下限值并传送给地调的研究成果。
在获得省调的控制能力时,需要采用二次优化模型,模型的建立涉及到准稳态灵敏度的计算。孙宏斌,张伯明,相年德在《准稳态的灵敏度分析方法》(中国电机工程学报,1999年4月V19N4,pp.9-13)中提出了准稳态灵敏度方法,与常规的静态的灵敏度分析方法不同,准稳态灵敏度方法考虑了电力系统准稳态的物理响应,计及系统控制前后新旧稳态间的总变化,有效提高了灵敏度分析的精度。该方法基于电力系统的PQ解耦模型,当发电机安装有自动电压调节器(AVR)时,可认为该发电机节点为PV节点;而当发电机装有自动无功功率调节(AQR)或自动功率因数调节(APFR)时,可认为该发电机节点与普通负荷节点相同均为PQ节点。此外,将负荷电压静特性考虑成节点电压的一次或二次曲线。这样所建立的潮流模型就自然地将这些准稳态的物理响应加以考虑,从而基于潮流模型计算出的灵敏度即为准稳态的灵敏度。在潮流模型下,设PQ节点和PV节点个数分别为NPQ和NPV,状态量x是PQ节点的电压幅值
Figure G2009102444862D00021
控制变量u=[QPQ VPV Tk]T,其中
Figure G2009102444862D00022
是PQ节点的无功注入,
Figure G2009102444862D00023
是PV节点的电压幅值,
Figure G2009102444862D00024
是变压器变比,重要的依从变量h=[Qb QPV]T,其中Qb∈Rb是支路无功潮流,
Figure G2009102444862D00025
是PV节点的无功注入。这时,有无功潮流模型:
QPQ(VPQ,VPV,Tk)=0                (1)
Qb=Qb(VPQ,VPV,Tk)                (2)
QPV=QPV(VPQ,VPV,Tk)              (3)
可得准稳态无功类灵敏度的计算公式见表1。
表1准稳态的无功类灵敏度S(x,h)n的计算公式
Figure G2009102444862D00026
其中 S V PQ Q PQ = - [ ∂ Q PQ ∂ V PQ ] - 1 , 上表中的所有量都可以直接对潮流模型(1)-(3)的雅可比矩阵求逆得到。
发明内容
本发明的目的是为弥补当前省地级电网AVC系统互动性不足的缺点,提出省地协调母线电压协调约束上下限值的获得方法。该方法采用准稳态灵敏度和二次规划模型,通过估算省级电网调度中心(以下简称省调)对省地协调母线电压的调节量,获得省地协调母线电压协调约束上下限值,从而有效降低网损,提高电网的电压安全水平。
本发明提出的一种省地协调母线电压协调约束上下限值获得方法;
该方法定义:省地协调边界220KV变电站220KV母线为省地协调母线;设省调侧包含有发电机s个,发电机母线s个,监视母线p个,省地协调母线有q个,s,p,q均为非负整数;其特征在于,该方法包括以下步骤:
1)在一个控制周期开始时,省调实时采集当前s个发电机母线电压矢量Vg;当前s个发电机无功矢量Qg;p个监视母线电压矢量Vs;当前q个省地协调母线电压矢量Vc
2)省调实时更新s个发电机母线电压约束限值矢量,其中约束下限为矢量V g,约束上限为矢量Vg;实时更新s个发电机无功约束限值矢量,其中约束下限为矢量Q g,约束上限为矢量Qg;实时更新p个监视母线电压约束限值矢量,其中约束下限为矢量V s,约束上限为矢量Vs;实时更新q个省地协调母线电压运行约束限值矢量,其中约束下限为矢量V c,电压约束上限为矢量Vc
3)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地省地协调母线电压协调约束限值平方的最大值,及达到该最大值时,省调发电机无功出力矢量增量ΔQg;二次规划模型如式(1)所示:
max Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs      (1)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对省地协调母线节点电压的准稳态灵敏度矩阵(采用已知方法得到);
将求解二次规划模型得到的发电机无功出力矢量增量ΔQg优化值
Figure G2009102444862D00032
代入
Figure G2009102444862D00033
求解得到省地协调母线电压协调约束上限值矢量Vcmax;Vcmax为q维矢量,它的第i个分量代表了通过省调侧发电机对发出无功的调控,在满足发电机母线电压约束限值,省地协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,第i个协调母线电压所能达到最大值;
4)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地协调母线电压协调约束值平方的最小值,及达到该最小值时,省调发电机无功出力矢量增量ΔQg;二次规划模型如式(2)所示:
min Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs        (2)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对省地协调母线节点电压的准稳态灵敏度矩阵;
5)将求解二次规划模型得到的发电机无功出力矢量增量ΔQg优化值
Figure G2009102444862D00042
代入
Figure G2009102444862D00043
求解得到省地协调母线电压下限值矢量Vcmin;Vcmin为q维矢量,它的第i个分量代表了通过省调侧发电机对发出无功的调控,在满足发电机母线电压约束限值,省地协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,第i个协调母线电压所能达到最小值;
6)在下一次控制周期到来时,返回步骤1)。
本发明的特点和效果
本发明从系统全局控制的角度出发,以省地协调母线电压最大向上(向下)可调量为优化目标,构造二次规划模型,求解出省地协调母线电压协调约束的上限(下限)。此方法为建立省地联合优化模型的一个重要步骤,通过考虑省、地调设备运行约束和通过调控,得到全系统最优(或次优)的运行状态,以此作为省地协调的控制目标,以达到省调主网与地区电网之间合理的无功交换的目的。本发明提出的方法可保证省地协调电压控制正常运行,该方法可集成在现场运行的自动电压控制系统中,将目前孤立在省级电网控制中心和地区电网控制中心的AVC系统协调起来,实现省级电网和地区电网之间的相互支撑,在全局范围内实现最优的无功电压分布,从而有效降低网损,提高电网的电压安全水平。
具体实施方式
本发明提出的省地协调母线电压协调约束上下限值获得方法结合实施例详细说明如下:
本方法中事先确定控制周期,一般省地协调控制的周期为5分钟到15分钟不等,此周期可根据实际情况和需求人工设定。
首先定义:省地协调边界220KV变电站220KV母线为省地协调母线;设省调侧包含有发电机s个,发电机母线s个,监视母线(由人工指定的需要监视电压限值的母线)p个,省地协调母线有q个(s,p,q均为非负整数);
本方法包括以下步骤:
1)在一个控制周期开始时,省调(以下简称省调)实时采集当前s个发电机母线电压矢量Vg(s维矢量),单位(KV);当前s个发电机无功矢量Qg(s维矢量),单位(MVAR);p个监视母线电压矢量Vs(p维矢量),单位(KV);当前q个省地协调母线电压矢量Vc(q维矢量),单位(KV);
2)省调实时更新s个发电机母线电压约束限值矢量(s维矢量),单位(KV),其中约束下限为矢量V g,约束上限为矢量Vg;实时更新s个发电机无功约束限值矢量(s维矢量),单位(MVAR),其中约束下限为矢量Q g,约束上限为矢量Qg;实时更新p个监视母线电压约束限值矢量(p维矢量),单位(KV),其中约束下限为矢量V s,约束上限为矢量Vs;实时更新q个省地协调母线电压运行约束限值矢量(q维矢量),单位(KV),其中约束下限为矢量V c,电压约束上限为矢量Vc;上述约束限值由省调通过电网遥测遥信数据通道实时获取;
3)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地协调母线电压协调约束值平方的最大值,及达到该最大值时,省调发电机无功出力矢量增量ΔQg;二次规划模型如式(1)所示:
max Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs       (1)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对省地协调母线节点电压的准稳态灵敏度矩阵(采用背景技术介绍的已知方法得到);
将求解二次规划模型得到的发电机无功出力矢量增量ΔQg优化值代入
Figure G2009102444862D00062
求解得到省地协调母线电压协调约束上限值矢量Vcmax;Vcmax为q维矢量,它的第i个分量代表了通过省调侧发电机对发出无功的调控,在满足发电机母线电压约束限值,省地协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,第i个协调母线电压所能达到最大值;
4)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地协调母线电压协调约束值平方的最小值,及达到该最小值时,省调发电机无功出力矢量增量ΔQg;二次规划模型如式(2)所示:
min Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs        (2)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对省地协调母线节点电压的准稳态灵敏度矩阵;
5)将求解二次规划模型得到的发电机无功出力矢量增量ΔQg优化值
Figure G2009102444862D00064
代入
Figure G2009102444862D00065
求解得到省地协调母线电压下限值矢量Vcmin;Vcmin为q维矢量,它的第i个分量代表了通过省调侧发电机对发出无功的调控,在满足发电机母线电压约束限值,省地协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,第i个协调母线电压所能达到最小值;
6)在下一次控制周期到来时,返回步骤1)。
以下用一个实施例进一步说明本发明的方法:
本实施例设置控制周期可设定为5分钟;设省调侧包含有发电机s个,发电机母线s个,监视母线有p个,省地协调母线有q个(s,p,q均为非负整数);本实施例具体包括以下步骤:
1)在一个控制周期开始时,实时采集当前s个发电机母线电压矢量Vg(s维矢量),例如
Figure G2009102444862D00071
当前s个发电机无功矢量Qg(s维矢量),例如
Figure G2009102444862D00072
p个厂站母线监视电压矢量Vs(p维矢量),例如
Figure G2009102444862D00073
q个省地协调母线电压矢量Vc(q维矢量),例如
Figure G2009102444862D00074
2)省调实时更新s个发电机母线电压约束限值矢量(s维矢量),其中约束下限为矢量V g,例如
Figure G2009102444862D00075
约束上限为矢量Vg,例如
Figure G2009102444862D00076
实时更新s个发电机无功约束限值矢量(s维矢量),其中约束下限为矢量Q g,例如
Figure G2009102444862D00077
约束上限为矢量Qg,例如实时更新p个监视母线电压约束限值矢量(p维矢量),其中约束下限为矢量V s,例如
Figure G2009102444862D00079
约束上限为矢量Vs,例如
Figure G2009102444862D000710
实时更新q个省地协调母线电压运行约束限值矢量(q维矢量),其中约束下限为矢量V c,例如
Figure G2009102444862D000711
电压约束上限为矢量Vc,例如
Figure G2009102444862D000712
上述约束限值由省调AVC系统通过电网遥测遥信数据通道实时获取。
3)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地协调母线电压协调约束值平方的最大值,及达到该最大值时,省调发电机无功出力矢量增量ΔQg;二次规划模型如式(1)所示:
max Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs     (1)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对需要监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对协调关口节点电压的准稳态灵敏度矩阵。
将求解二次规划模型得到的发电机无功出力矢量增量优化值
Figure G2009102444862D000714
例如
Figure G2009102444862D00081
将其代入
Figure G2009102444862D00082
求解得到省调关口电压运行上限值矢量Vcmax;Vcmax为q维矢量,例如其中第i个协调母线电压上限为230KV,代表经省级电网对发出无功的调控,在满足发电机母线电压约束限值,省地协调母线电压运行约束限值,监视母线电压约束限值,发电机无功出力约束限值情况下,第i个协调母线所能达到的电压最大值为230KV。
4)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地协调母线电压协调约束值平方的最小值,及达到该最小值时,省调发电机无功出力矢量增量
Figure G2009102444862D00084
二次规划模型如式(2)所示:
min Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs        (2)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对需要监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对协调关口节点电压的准稳态灵敏度矩阵;
5)将求解二次规划模型得到的发电机无功出力矢量增量优化值
Figure G2009102444862D00086
Figure G2009102444862D00087
将其代入
Figure G2009102444862D00088
求解得到省调关口电压运行上限值矢量Vcmin;Vcmin为q维矢量,例如
Figure G2009102444862D00089
其中第i个协调母线电压上限为212KV,代表经省级电网对发出无功的调控,在满足发电机母线电压约束限值,协调母线电压运行约束限值,监视母线电压约束限值,发电机无功出力约束限值情况下,第i个协调母线所能达到的电压最大值为212KV;
6)在下一次控制周期到来时,返回步骤1)。

Claims (1)

1.一种省地协调母线电压协调约束上下限值获得方法;
该方法定义:省地协调边界220KV变电站220KV母线为省地协调母线;设省调侧包含有发电机s个,发电机母线s个,监视母线p个,省地协调母线有q个,s,p,q均为非负整数;其特征在于,该方法包括以下步骤:
1)在一个控制周期开始时,省调实时采集当前s个发电机母线电压矢量Vg;当前s个发电机无功矢量Qg;p个监视母线电压矢量Vs;当前q个省地协调母线电压矢量Vc
2)省调实时更新s个发电机母线电压约束限值矢量,其中约束下限为矢量V g,约束上限为矢量Vg;实时更新s个发电机无功约束限值矢量,其中约束下限为矢量Q g,约束上限为矢量Qg;实时更新p个监视母线电压约束限值矢量,其中约束下限为矢量V s,约束上限为矢量Vs;实时更新q个省地协调母线电压运行约束限值矢量,其中约束下限为矢量V c,电压约束上限为矢量Vc
3)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地协调母线电压协调约束值平方的最大值,及达到该最大值时,省调发电机无功出力矢量增量ΔQg;二次规划模型如式(1)所示:
max Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs             (1)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对省地协调母线节点电压的准稳态灵敏度矩阵(采用已知方法得到);
将求解二次规划模型得到的发电机无功出力矢量增量ΔQg优化值代入
Figure F2009102444862C00013
求解得到省地协调母线电压协调约束上限值矢量Vcmax;Vcmax为q维矢量,它的第i个分量代表了通过省调侧发电机对发出无功的调控,在满足发电机母线电压约束限值,省地协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,第i个协调母线电压所能达到最大值;
4)根据步骤2)所有的约束限值,构造二次规划模型,通过二次规划模型计算出省地协调母线电压协调约束值平方的最小值,及达到该最小值时,省调发电机无功出力矢量增量ΔQg;二次规划模型如式(2)所示:
min Δ Q g | | V c + C cg Δ Q g | | 2
s.t.V g≤Vg+CggΔQg≤Vg
V s≤Vs+CsgΔQg≤Vs           (2)
V c≤Vc+CcgΔQg≤Vc
Q g≤Qg+ΔQg≤Qg
其中,Cgg为发电机无功出力对发电机母线节点电压的准稳态灵敏度矩阵,Csg为发电机无功出力对监视母线节点电压的准稳态灵敏度矩阵,Ccg为发电机无功出力对省地协调母线节点电压的准稳态灵敏度矩阵;
5)将求解二次规划模型得到的发电机无功出力矢量增量ΔQg优化值
Figure F2009102444862C00022
代入
Figure F2009102444862C00023
求解得到省地协调母线电压下限值矢量Vcmin;Vcmin为q维矢量,它的第i个分量代表了通过省调侧发电机对发出无功的调控,在满足发电机母线电压约束限值,省地协调母线电压运行约束限值,监视母线电压约束限值,发电机无功约束限值情况下,第i个协调母线电压所能达到最小值;
6)在下一次控制周期到来时,返回步骤1)。
CN2009102444862A 2009-12-31 2009-12-31 省地协调母线电压协调约束上下限值获得方法 Expired - Fee Related CN101800428B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009102444862A CN101800428B (zh) 2009-12-31 2009-12-31 省地协调母线电压协调约束上下限值获得方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009102444862A CN101800428B (zh) 2009-12-31 2009-12-31 省地协调母线电压协调约束上下限值获得方法

Publications (2)

Publication Number Publication Date
CN101800428A true CN101800428A (zh) 2010-08-11
CN101800428B CN101800428B (zh) 2011-12-28

Family

ID=42595976

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009102444862A Expired - Fee Related CN101800428B (zh) 2009-12-31 2009-12-31 省地协调母线电压协调约束上下限值获得方法

Country Status (1)

Country Link
CN (1) CN101800428B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102289223A (zh) * 2011-05-16 2011-12-21 河北省电力研究院 自动电压控制系统全网最优控制参数校验方法
CN102684223A (zh) * 2012-05-23 2012-09-19 甘肃省电力公司电力科学研究院 以降低网损为目标的多约束条件下风电送出功率优化评估方法
CN104734201A (zh) * 2015-04-02 2015-06-24 国家电网公司 一种电力系统中风电配送方案的确定方法及装置
CN104868484A (zh) * 2015-05-26 2015-08-26 华南理工大学 220/110kV变电站上下协调无功控制方法
CN105186503A (zh) * 2015-09-22 2015-12-23 清华大学 一种基于电网运行数据的分布式安全特征选择方法
CN107134783A (zh) * 2016-02-29 2017-09-05 中国电力科学研究院 一种基于灵敏度快速筛选的母线电压优化调整方法
CN112615380A (zh) * 2020-12-09 2021-04-06 国家电网公司西北分部 一种基于母线电压历史数据分析的逆调压控制方法

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102289223B (zh) * 2011-05-16 2014-02-19 河北省电力公司电力科学研究院 自动电压控制系统全网最优控制参数校验方法
CN102289223A (zh) * 2011-05-16 2011-12-21 河北省电力研究院 自动电压控制系统全网最优控制参数校验方法
CN102684223A (zh) * 2012-05-23 2012-09-19 甘肃省电力公司电力科学研究院 以降低网损为目标的多约束条件下风电送出功率优化评估方法
CN102684223B (zh) * 2012-05-23 2014-02-19 甘肃省电力公司电力科学研究院 以降低网损为目标的多约束条件下风电送出功率优化评估方法
CN104734201A (zh) * 2015-04-02 2015-06-24 国家电网公司 一种电力系统中风电配送方案的确定方法及装置
CN104734201B (zh) * 2015-04-02 2017-01-25 国家电网公司 一种电力系统中风电配送方案的确定方法及装置
CN104868484B (zh) * 2015-05-26 2017-06-20 华南理工大学 220/110kV变电站上下协调无功控制方法
CN104868484A (zh) * 2015-05-26 2015-08-26 华南理工大学 220/110kV变电站上下协调无功控制方法
CN105186503A (zh) * 2015-09-22 2015-12-23 清华大学 一种基于电网运行数据的分布式安全特征选择方法
CN105186503B (zh) * 2015-09-22 2017-08-11 清华大学 一种基于电网运行数据的分布式安全特征选择方法
CN107134783A (zh) * 2016-02-29 2017-09-05 中国电力科学研究院 一种基于灵敏度快速筛选的母线电压优化调整方法
CN107134783B (zh) * 2016-02-29 2019-12-13 中国电力科学研究院 一种基于灵敏度快速筛选的母线电压优化调整方法
CN112615380A (zh) * 2020-12-09 2021-04-06 国家电网公司西北分部 一种基于母线电压历史数据分析的逆调压控制方法
CN112615380B (zh) * 2020-12-09 2023-05-23 国家电网公司西北分部 一种基于母线电压历史数据分析的逆调压控制方法

Also Published As

Publication number Publication date
CN101800428B (zh) 2011-12-28

Similar Documents

Publication Publication Date Title
CN101800428B (zh) 省地协调母线电压协调约束上下限值获得方法
Krishan et al. Grid-independent PV system hybridization with fuel cell-battery/supercapacitor: Optimum sizing and comparative techno-economic analysis
CN100461579C (zh) 一种大区电网与省级电网的协调电压控制方法
Varma et al. Optimal 24-hr utilization of a PV solar system as STATCOM (PV-STATCOM) in a distribution network
CN109687510B (zh) 一种计及不确定性的配电网多时间尺度优化运行方法
Varma et al. Novel application of a PV solar plant as STATCOM during night and day in a distribution utility network
CN110034587B (zh) 一种优化调度方法
CN102593839B (zh) 计及电网全运行方式的发电机励磁系统调差系数整定方法
CN101800429B (zh) 省地协调电压控制中实时获得地调侧控制能力指标的方法
CN105226665A (zh) 通过自动厂站协调控制降低母线电压日波动率的方法
CN105262098B (zh) 基于风电场发电功率波动评估的敏捷自动电压控制方法
CN105720585B (zh) 风电场集群的无功功率控制方法及系统
CA2998101C (en) Grid tied, real time adaptive, distributed intermittent power
Satsangi et al. Real time performance of solar photovoltaic microgrid in India focusing on self-consumption in institutional buildings
CN101764404B (zh) 省地协调电压控制中省地协调运行状态的判断方法
CN105337301A (zh) 微电网并网点的选择方法和装置
CN105656027B (zh) 风储联合发电系统有功功率和无功电压的控制方法及装置
CN105281331A (zh) 一种基于分区优化的省地协同电压控制方法
CN115545290A (zh) 一种含光伏发电配电网中的分布式储能经济优化配置方法
CN107294105B (zh) 分布式光伏集群无通信条件下的动态调压控制方法
CN110011298A (zh) 一种构建自治型可重构微网群系统的运行控制策略
Murdan et al. Simulation of a single phase grid-tied PV system under net-metering scheme
CN115588991A (zh) 一种三相不平衡配电网最优潮流模型建立方法
CN106253356B (zh) 基于储能电量价值评估的交直流混合微网实时经济调度法
Kasturi et al. Optimal PV & BES units integration to enhance power distribution network Performance

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111228

Termination date: 20191231