CN101793333A - Construction method for crossing pipeline by single-sided directional drill - Google Patents

Construction method for crossing pipeline by single-sided directional drill Download PDF

Info

Publication number
CN101793333A
CN101793333A CN 201010126547 CN201010126547A CN101793333A CN 101793333 A CN101793333 A CN 101793333A CN 201010126547 CN201010126547 CN 201010126547 CN 201010126547 A CN201010126547 A CN 201010126547A CN 101793333 A CN101793333 A CN 101793333A
Authority
CN
China
Prior art keywords
pipeline
crossing
canyon
sole
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010126547
Other languages
Chinese (zh)
Inventor
张金宝
孟强
王普成
刘立波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Petroleum Exploration Bureau Of China Petrochemical Corp
China Petrochemical Corp
Original Assignee
Jiangsu Petroleum Exploration Bureau Of China Petrochemical Corp
China Petrochemical Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Petroleum Exploration Bureau Of China Petrochemical Corp, China Petrochemical Corp filed Critical Jiangsu Petroleum Exploration Bureau Of China Petrochemical Corp
Priority to CN 201010126547 priority Critical patent/CN101793333A/en
Publication of CN101793333A publication Critical patent/CN101793333A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a construction method for crossing a pipeline by a single-sided directional drill, which comprises the following steps of: firstly drilling a guide hole inclining to the bottom of a canyon from a pipeline embedded point at one side of the canyon through a horizontal directional crossing drill, then carrying out pre-reaming, wherein the aperture is 1.2-1.5 times of the diameter of a crossing pipe, penetrating a prefabricated crossing pipeline into the hole and enabling the pipeline to reach one side at the bottom of the canyon; then drilling a guide hole inclining to the bottom of the canyon from a pipeline unearthed point at the other side of the canyon through the horizontal directional crossing drill, then carrying out pre-reaming, wherein the aperture is also 1.2-1.5 times of the diameter of the crossing pipe, penetrating the prefabricated crossing pipeline into the hole and enabling the pipeline to reach the other side at the bottom of the canyon; and then communicating and fixing the nozzles of the pipelines at both sides of the bottom of the canyon through a connecting pipe. The construction method avoids large-area earthwork evacuation, protects native vegetation and water and soil resources at both sides of the canyon, shortens the construction period and lowers the construction cost and the engineering cost.

Description

Construction method for crossing pipeline by single-sided directional drill
Technical field
The present invention relates to a kind of piping erection method of construction, particularly a kind of construction method for crossing pipeline by single-sided directional drill that is applicable to landform such as coombe, abrupt slope, valley.
Background technique
At present, for the piping erection of passing through the narrow landform of U type such as coombe, valley, abrupt slope, pipeline rout is bent downwardly along a side slope in valley earlier, after passing sole, upwards climb along the valley opposite side is domatic again, pipeline adopts method of construction such as heavy excavation, massif explosion along the line, after piping laying finishes, carries out the earthing backfill again.This method of construction, excavation area is big, will cause the destruction of surface water soil resource and natural vegetation, the infringement ecotope; The amount of earth and stone digging simultaneously is big, and the job execution environment is abominable, the difficulty of construction height, and construction safety hidden danger is many.In addition, the workload of water conservancy project protection and land restoration and difficulty of construction are also very big, and the pipe trench at especially domatic place is difficult to earthing, will cause soil erosion, often will just can finish by means of the method for concrete masonry units, cause fundamentally having destroyed the ecosystem environment.
Summary of the invention
For solving in the existing pipeline construction method for crossing; the earth and stone digging amount is big; the problem of difficulty of construction height and destruction ecotope; the invention provides a kind of construction method for crossing pipeline by single-sided directional drill; not only easy construction, safety, economy, and natural vegetation and the water and soil resources that can protect the valley to locate.
For solving above technical problem, construction method for crossing pipeline by single-sided directional drill provided by the present invention, this method of construction comprises the steps: that (1) pipeline of one side buries and a little passes through rig with horizontal orientation and make a pilot hole that tilts to sole from the valley, carry out pre-reaming then, the aperture is to pass through 1.2~1.5 times of caliber, prior prefabricated crossing pipeline is penetrated in this hole, make pipeline arrive a side of sole; (2) pass through rig from the pipeline unearthed point of valley opposite side with horizontal orientation and make a pilot hole that tilts to sole, carry out pre-reaming then, the aperture is similarly 1.2~1.5 times that pass through caliber, prior prefabricated crossing pipeline is penetrated in this hole, make pipeline arrive the opposite side of sole; (3), the mouth of pipe of both sides pipeline connected by connecting tube connect and fixing at sole.
With respect to prior art; the present invention has obtained following beneficial effect: this method of construction has been avoided two side slope large-area earthwork evacuation along the valley; protect the natural vegetation and the water and soil resources of both sides, valley, shortened the construction period, reduced construction cost and engineering cost.
Connecting tube to sole is buried, and one side is built waterwall by laying bricks or stones in current upstream, the valley of described connecting tube.Waterwall helps the protection to the sole connecting tube, prevents that it is subjected to washing away of valley current for a long time and damages.
Description of drawings
Fig. 1 is the pipe laying route map of existing method of construction.
Fig. 2 is a pipe laying route map of the present invention.
Among the figure: 1 heavy excavation pipeline position, 2 single-sided directional drilling pipe line positions.
Embodiment
At present, for the piping erection of passing through the narrow landform of U type such as coombe, valley, abrupt slope, pipeline rout is bent downwardly along a side slope in valley earlier, after passing sole, upwards climb along the valley opposite side is domatic, pipeline adopts method of construction such as heavy excavation, massif explosion along the line again, and heavy excavation pipeline position 1 as shown in fig. 1, after piping laying finishes, carry out the earthing backfill again.This method of construction, excavation area is big, will cause the destruction of surface water soil resource and natural vegetation, the infringement ecotope; The amount of earth and stone digging simultaneously is big, and the job execution environment is abominable, the difficulty of construction height, and construction safety hidden danger is many.In addition, the workload of water conservancy project protection and land restoration and difficulty of construction are also very big, and the pipe trench at especially domatic place is difficult to earthing, will cause soil erosion, often will just can finish by means of the method for concrete masonry units, cause fundamentally having destroyed the ecosystem environment.
Construction method for crossing pipeline by single-sided directional drill of the present invention comprises the steps: that (1) pipeline of one side buries and a little passes through rig with horizontal orientation and make a pilot hole that tilts to sole from the valley, carry out pre-reaming then, the aperture is to pass through 1.2~1.5 times of caliber, prior prefabricated crossing pipeline is penetrated in this hole, make pipeline arrive a side of sole; (2) pass through rig from the pipeline unearthed point of valley opposite side with horizontal orientation and make a pilot hole that tilts to sole, carry out pre-reaming then, the aperture is similarly 1.2~1.5 times that pass through caliber, prior prefabricated crossing pipeline is penetrated in this hole, make pipeline arrive the opposite side of sole; (3), the mouth of pipe of both sides pipeline connected by connecting tube connect and fixing at sole; (4) connecting tube of sole is buried, one side is built waterwall by laying bricks or stones in current upstream, the valley of described connecting tube.Single-sided directional drilling pipe line position 2 as shown in Figure 2.
In addition to the implementation, the present invention can also have other mode of executions.All employings are equal to the technological scheme of replacement or equivalent transformation formation, all drop in the protection domain of requirement of the present invention.

Claims (2)

1. a construction method for crossing pipeline by single-sided directional drill is characterized in that, this method of construction comprises the steps:
(1) pipeline of one side buries a little and to pass through rig with horizontal orientation and make a pilot hole that tilts to sole from the valley, carry out pre-reaming then, the aperture is to pass through 1.2~1.5 times of caliber, and prefabricated crossing pipeline is in advance penetrated in this hole, makes pipeline arrive a side of sole;
(2) pass through rig from the pipeline unearthed point of valley opposite side with horizontal orientation and make a pilot hole that tilts to sole, carry out pre-reaming then, the aperture is similarly 1.2~1.5 times that pass through caliber, prior prefabricated crossing pipeline is penetrated in this hole, make pipeline arrive the opposite side of sole;
(3), the mouth of pipe of both sides pipeline connected by connecting tube connect and fixing at sole.
2. construction method for crossing pipeline by single-sided directional drill according to claim 1 is characterized in that, the connecting tube of sole is buried, and one side is built waterwall by laying bricks or stones in current upstream, the valley of described connecting tube.
CN 201010126547 2010-03-18 2010-03-18 Construction method for crossing pipeline by single-sided directional drill Pending CN101793333A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010126547 CN101793333A (en) 2010-03-18 2010-03-18 Construction method for crossing pipeline by single-sided directional drill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010126547 CN101793333A (en) 2010-03-18 2010-03-18 Construction method for crossing pipeline by single-sided directional drill

Publications (1)

Publication Number Publication Date
CN101793333A true CN101793333A (en) 2010-08-04

Family

ID=42586183

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010126547 Pending CN101793333A (en) 2010-03-18 2010-03-18 Construction method for crossing pipeline by single-sided directional drill

Country Status (1)

Country Link
CN (1) CN101793333A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106870819A (en) * 2017-03-24 2017-06-20 广州市恒盛建设工程有限公司 A kind of high density polyethylene (HDPE) non-pressure pipe horizontal directional drilling construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5452967A (en) * 1994-03-22 1995-09-26 Fuller; Frank E. Pipe laying system and method
CN1247284A (en) * 1999-08-24 2000-03-15 范中明 Underground construction method for installing pipeline with diameter of more than 0.8 m without excavating earth surface
CN1693668A (en) * 2005-06-17 2005-11-09 上海市隧道工程轨道交通设计研究院 Counter pulling method used in underground pipe culvert linear dark digging
CN101457853A (en) * 2008-11-20 2009-06-17 江苏广宇建设集团有限公司 Non-digging tube-pulling construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5452967A (en) * 1994-03-22 1995-09-26 Fuller; Frank E. Pipe laying system and method
CN1247284A (en) * 1999-08-24 2000-03-15 范中明 Underground construction method for installing pipeline with diameter of more than 0.8 m without excavating earth surface
CN1693668A (en) * 2005-06-17 2005-11-09 上海市隧道工程轨道交通设计研究院 Counter pulling method used in underground pipe culvert linear dark digging
CN101457853A (en) * 2008-11-20 2009-06-17 江苏广宇建设集团有限公司 Non-digging tube-pulling construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《石油工程建设》 20080229 赵文明等 单边定向钻在大型黄土冲沟管道施工中的应用 , 2 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106870819A (en) * 2017-03-24 2017-06-20 广州市恒盛建设工程有限公司 A kind of high density polyethylene (HDPE) non-pressure pipe horizontal directional drilling construction method
CN106870819B (en) * 2017-03-24 2017-12-26 广州市恒盛建设工程有限公司 A kind of high density polyethylene (HDPE) non-pressure pipe horizontal directional drilling construction method

Similar Documents

Publication Publication Date Title
CN101775988B (en) Construction method for inclined shaft to main tunnel of weak surrounding rock
CN105421470B (en) Assembled anchor pole arched framework combined type ecological revetment construction method
CN102155234B (en) Excavation construction method for unsymmetrical small-space tunnel
CN102979103A (en) Step type excavating method for large unloading loose rocky side slope
CN103726495B (en) Coastal waters deep foundation pit supporting structure and construction method thereof
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN104676110A (en) On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit
CN107664035A (en) The construction method of well after shield piping lane elder generation shield
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN107268600A (en) Grouting strengthening method, pipe jacking construction method and application
CN105544603A (en) Construction method for underground pipeline reinforcement
CN110306581A (en) One kind new old pipeline connection well and its construction method in water rich strata
CN104895121B (en) Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction
CN102433883A (en) Space-time conversion construction method of vertical underground pipe of deep foundation pit
CN109594574A (en) Large-scale push pipe open caisson reversed construction method based on the confined space
CN101793333A (en) Construction method for crossing pipeline by single-sided directional drill
CN101141054A (en) Compaction grouting method for preventing land subsidence after non-digging horizontal drilling
CN106149631B (en) High mountain strid arch dam avalanche type Slope Treatment method
CN108978709A (en) City integrated piping lane branch construction method under a kind of space-constrained environments
RU2369797C1 (en) Pipeline dike reinforcement method
KR100701885B1 (en) Non-open cut pipe installation method
CN105113511B (en) Sandstone combines the foundation ditch comprehensive support construction method of soil layer
CN107023012A (en) Multiple tracks annular concrete support Deep Foundation Pit Excavation outward transport construction method
CN105064384A (en) Vacuum tube well precipitation system under special geological conditions
JP2011157692A (en) Open-cutting method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20100804