CN101790170A - Double-center disaster recovery equipment and resource adjustment method in same - Google Patents

Double-center disaster recovery equipment and resource adjustment method in same Download PDF

Info

Publication number
CN101790170A
CN101790170A CN200910076882A CN200910076882A CN101790170A CN 101790170 A CN101790170 A CN 101790170A CN 200910076882 A CN200910076882 A CN 200910076882A CN 200910076882 A CN200910076882 A CN 200910076882A CN 101790170 A CN101790170 A CN 101790170A
Authority
CN
China
Prior art keywords
resource
subregion
division
unit
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910076882A
Other languages
Chinese (zh)
Inventor
崔可升
赵建福
朱祥磊
曹璐
李世冲
廉红吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Mobile Group Shandong Co Ltd
Original Assignee
China Mobile Group Shandong Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mobile Group Shandong Co Ltd filed Critical China Mobile Group Shandong Co Ltd
Priority to CN200910076882A priority Critical patent/CN101790170A/en
Publication of CN101790170A publication Critical patent/CN101790170A/en
Pending legal-status Critical Current

Links

Images

Abstract

The embodiment of the invention discloses a resource adjustment method in double-center disaster recovery equipment. The method comprises: determining the current operation state of a master end and/or a standby end in the double-center disaster recovery equipment; and adjusting resources allocated to the master end and/or the standby end according to preset resource adjustment rules when determining that the resources need to be adjusted according to the current operation state. The embodiment of the invention discloses the double-center disaster recovery equipment. The method can effectively raise the resource utilization rate of the double-center disaster recovery equipment and reduce waste of resources.

Description

Resource adjusting method in two centers disaster tolerance equipment and this equipment
Technical field
The present invention relates to the communications field, relate in particular to the resource adjusting method in a kind of pair of center disaster tolerance equipment and this equipment.
Background technology
For continual service is provided, when device fails, need carries out disaster tolerance and switch.Realize that disaster tolerance switches, need comprise main disaster tolerance system for service deployment, generally with end and standby end, professional is main with holding the request of being responsible for managing business, and when the master breaks down with end, business is switched to standby end, when the master uses the fault recovery of end, again that professional switchback is main with end.
At present, main deployment way with end and standby end mainly contains following two kinds:
First kind, active and standby pattern.This pattern of employing is based upon the main of business on first physical host with holding, and the standby end of this business is based upon on second physical host.When first physical host breaks down, business is switched to second physical host, should business by the standby pipe nipple on second physical host.
Second kind, two center modes.This pattern of employing, the main of first business is based upon on first physical host with end, the main of second business is based upon on second physical host with end, simultaneously, also be deployed with the standby end of second business on first physical host, also be deployed with the standby end of first business on second physical host, promptly two physical hosts all have the main end of using, and the standby end of peer is arranged simultaneously.When first physical host breaks down, first business is switched to second physical host, by standby pipe nipple first business on second physical host.When second physical host breaks down, second business is switched to first physical host, by standby pipe nipple second business on first physical host.
In realizing process of the present invention, the inventor finds to exist in the prior art following technical problem:
In the prior art, can carry out smoothly in order to make disaster tolerance switch, need reserve enough resources respectively with end and standby end for main, but be that the master can be in idle state with end or standby end reserved resource at part-time, make device resource be not fully utilized, resource utilization is lower, causes wasting of resources situation serious.
Summary of the invention
The embodiment of the invention provides the resource adjusting method in a kind of pair of center disaster tolerance equipment and this equipment, is used to improve the resource utilization of two centers disaster tolerance equipment, reduces the wasting of resources.
The embodiment of the invention provides a kind of pair of resource adjusting method in the disaster tolerance equipment of center, and this method comprises:
Determine the main current running status in the described pair of center disaster tolerance equipment with end and/or standby end;
When determining that according to described current running status needs carry out the resource adjustment,, be adjusted into described main resource of distributing with end and/or standby end according to the resource regulation rule that sets in advance.
The embodiment of the invention provides a kind of pair of center disaster tolerance equipment, and this equipment comprises:
First zoning unit is used to carry the main with end of disaster tolerance business;
Second zoning unit is used to carry the standby end of disaster tolerance business;
Determining unit is used for determining described main current running status with end and/or standby end, determines whether that according to described current running status needs carry out the resource adjustment;
Adjustment unit is used for when described determining unit determines to carry out the resource adjustment, according to the resource regulation rule that sets in advance, is adjusted into described main resource of distributing with end and/or standby end.
Among the present invention, when determining that according to the main current running status in the disaster tolerance equipment of two centers needs carry out the resource adjustment with end and/or standby end, according to the resource regulation rule that sets in advance, to adjust for main resource of distributing with end and/or standby end, by resource is dynamically adjusted, can improve resource utilization, make full use of system resource, thereby effectively reduce the wasting of resources.
Description of drawings
The method flow schematic diagram that Fig. 1 provides for the embodiment of the invention;
Fig. 2 is that the subregion of disaster tolerance equipment in the embodiment of the invention is divided schematic diagram;
Fig. 3 is that another subregion of disaster tolerance equipment is divided schematic diagram in the embodiment of the invention;
The device structure schematic diagram that Fig. 4 provides for the embodiment of the invention.
Embodiment
In order to make the resource of disaster tolerance equipment be fully used, the embodiment of the invention provides a kind of pair of resource adjusting method in the disaster tolerance equipment of center, in this method, main resource with end and/or standby end is dynamically adjusted according to main running status in the disaster tolerance equipment of two centers with end and/or standby end.
Referring to Fig. 1, the resource adjusting method in two centers disaster tolerance equipment that the embodiment of the invention provides specifically may further comprise the steps:
Step 10: determine the main current running status in the disaster tolerance equipment of two centers with end and/or standby end;
Step 11: determine whether that according to main current running status needs carry out the resource adjustment with end and/or standby end;
Step 12: when determining that need carry out resource adjusts,, be adjusted into main resource of distributing with end and/or standby end according to the resource regulation rule that sets in advance.
In the step 10, can in the disaster tolerance equipment of two centers, set up the business interface table in advance, therefore this business interface table real time record master, can determine main current running status with end and/or standby end by inquiry business interface table with the running status of end and/or standby end.Main running status with end or standby end comprises: professional busy, professional spare time, application software efficient, execution disaster tolerance switching (comprising the business that business is cut out and takes over other equipment) etc.
In the step 11, determine whether that the concrete grammar that need carry out the resource adjustment can be: the tabulation of preserving the resource regularization condition that inquiry sets in advance, judge whether main current running status with end and/or standby end belongs to the resource regularization condition of listing in this tabulation, if, then determine to carry out the resource adjustment, otherwise, determine not need to carry out the resource adjustment.For example, the resource regularization condition of preserving in tabulation can comprise: the professional business of hurrying, business being cut out, taking over other equipment; So, be professional busy or carry out professionally when cutting out or taking over other equipment professional in main current running status with end and/or standby end, definitely need carry out the resource adjustment.
In the step 12, the described main mode of adjusting with the resource of end and/or the distribution of standby end will be, one or combination in any in the following mode can be comprised:
The first, will be for main with holding assigned portions or whole resource to adjust or being adjusted into slack resources to standby end; Second, to adjust to standby end with end assigned portions resource for main, and will be adjusted into slack resources for main another part resource of distributing with end, for example, to adjust to standby end for main resource 10% of distributing, and will be adjusted into slack resources with other 10% the resource of holding distribution for main with end; The 3rd, will for standby end assigned portions or all resource adjust to main with holding or be adjusted into slack resources; The 4th, will adjust to the main end of using for standby end assigned portions resource, and will be adjusted into slack resources for another part resource that standby end distributes; The 5th, the part or all of slack resources of two centers disaster tolerance equipment is adjusted to main with end or standby end; The 6th, the part slack resources of two centers disaster tolerance equipment is adjusted to main usefulness end, and another part slack resources of two centers disaster tolerance equipment is adjusted to standby end.
For example, arrive predetermined threshold value main with the pending traffic carrying capacity of end, promptly main using when end is professional to hurry, definite needs carry out the resource adjustment, according to the resource regulation rule, to adjust to the main end of using for the slack resources in standby end and/or the two centers disaster tolerance equipment, and specifically adjust the quantity of which kind of resource and adjustment resource and can determine with the pending traffic carrying capacity of end according to resource regulation rule and current master.
Again for example, when standby end need be carried out service take-over, definite needs carry out the resource adjustment, according to the resource regulation rule, to adjust to standby end with the slack resources in end and/or the two centers disaster tolerance equipment for main, and specifically adjust the quantity of which kind of resource and adjustment resource and can determine according to the resource regulation rule and the professional resource requirement of taking over.
Preferable, in order to make the winner with can shared resource between a plurality of business of end carrying, can also be that the resource of main first traffic assignments with the end carrying be adjusted second business of carrying with end to main.For example, when main traffic carrying capacity growth rate with first business of holding carrying comparatively fast reaches setting threshold, the resource that can be chosen for the second slower traffic assignments of growth rate is also adjusted this resource to first business, specifically adjusts the quantity of which kind of resource and adjustment resource and can determine according to the actual volume growth rate of the resource regulation rule and first business.Can comprise when a plurality of for second business chosen, can from a plurality of business, choose non-key business and be the resource of the lower business of priority and adjust to first business.
In order to utilize device resource more fully, can in the disaster tolerance equipment of two centers, test service be set, when needs utilize this test service that main business with end or standby end is tested, can will adjust to test service for main resource of distributing with end and/or standby end, test service utilizes this resource to carry out test job.
As shown in Figure 2, among the present invention, in the disaster tolerance equipment of two centers, can utilize IT system dynamic resource management technology to realize main subregion setting with end and standby end, be about to two centers disaster tolerance equipment and be divided into a plurality of logical partitions, each subregion all has oneself independently operating system, mobile system resource between subregion automatically, and do not need restarting systems.To lead with the end being deployed in first subregion, standby end will be deployed in second subregion.Can also be placed in the 3rd subregion for main remaining slack resources with unallocated, slack resources be managed by the 3rd subregion with end and standby end.If in the disaster tolerance equipment of two centers, test service is set, test service can also be arranged in the 3rd subregion, by the 3rd fen this test service of area carrier.Accordingly:
To adjust to standby end or the method that is adjusted into slack resources for main resource of distributing and be with end: be chosen for the described first subregion assigned portions or whole resources, and with this resource division to described second subregion or described the 3rd subregion;
To adjust to standby end with end assigned portions resource for main, and the method that will be adjusted into slack resources for main another part resource of distributing with end is: be chosen for the described first subregion assigned portions, give described second subregion with this resource division, be chosen for another part resource that described first subregion distributes, give described the 3rd subregion this resource division;
Will for standby end assigned portions or all resource adjust to main and be with end or the method that is adjusted into slack resources: be chosen for the described second subregion assigned portions or whole resources, and with this resource division to described first subregion and/or described the 3rd subregion;
To adjust to main with end for standby end assigned portions resource, and the method that will be adjusted into slack resources for another part resource that standby end distributes is: be chosen for the described second subregion assigned portions resource, give described first subregion with this resource division, be chosen for another part resource that described second subregion distributes, give described the 3rd subregion this resource division;
The part or all of slack resources of two centers disaster tolerance equipment adjusted to main method with end or standby end is: be chosen for described the 3rd subregion assigned portions or whole resources, and with this resource division to described first subregion and/or second subregion;
The part slack resources of two centers disaster tolerance equipment is adjusted to main with end, and the method that another part slack resources of two centers disaster tolerance equipment is adjusted to standby end is: the part resource of choosing described the 3rd subregion, give described first subregion with this resource division, choose another part resource of described the 3rd subregion, give described second subregion this resource division.
The method that to adjust to test service for main resource of distributing with end and/or standby end is: be chosen for the resource that described first subregion and/or second subregion distribute, and give described the 3rd subregion with this resource division.
At Fig. 2, resource adjustment mode is illustrated below:
Embodiment one:
In the present embodiment, give first subregion with 50% resource allocation of two centers disaster tolerance equipment, give second subregion with 10% resource allocation of two centers disaster tolerance equipment, place the slack resources of residue 40% in the 3rd subregion, and, the main standby end with the end and second subregion of first subregion all carries single business, can improve resource utilization by carrying out following steps:
Step S01: main with the goal programming of end loaded service during the phase in reaching first subregion, promptly main when being the spare time with the running status of holding, the resource of first subregion is adjusted to the 3rd subregion, in order to other business such as test, query statistic.When standby end has been carried out professional switching in second subregion, the resource of the 3rd subregion or the resource of first subregion are adjusted to second subregion, to carry the service switchover of second subregion.
Step S02: main with holding the loaded service goal programming during phase in reaching first subregion, when promptly main running status with end is busy, for example reach and surpass planned capacity during the phase in the peak traffic phase, the resource of the 3rd subregion or second subregion is adjusted to first subregion, to solve the resource anxiety of first subregion, after first subregion is tided over the peak period, again resource is recalled to the 3rd subregion or second subregion.
Present embodiment has been realized sharing of active and standby resource, has improved resource utilization ratio largely, has saved system's investment.
Embodiment two:
In the present embodiment, give first subregion with 50% resource allocation of two centers disaster tolerance equipment, give second subregion with 10% resource allocation of two centers disaster tolerance equipment, place the slack resources of residue 40% in the 3rd subregion, the main standby end with the end and second subregion of first subregion all carries multi-service, can improve resource utilization by carrying out following steps:
Step S11: main with the goal programming of end loaded service during the phase in reaching first subregion, promptly main when being the spare time with the running status of holding, the resource of first subregion is adjusted to the 3rd subregion, in order to other business such as test, query statistic.
Step S22: when certain service take-over in second subregion during other equipment professional, the resource of first subregion or the 3rd subregion is adjusted on the second subregion corresponding business, after the professional switchback of taking over, again resource is recalled to first subregion or the 3rd subregion.
Step S23: main with holding the loaded service goal programming during phase in reaching first subregion, when promptly main running status with end is busy, for example in the peak traffic phase and surpass planned capacity during the phase, the resource of the business that traffic carrying capacity growth rate in first subregion is slower is adjusted in first subregion on the slow fast business of traffic carrying capacity growth rate.
Present embodiment has also been realized sharing of active and standby resource when having realized the sharing of active and standby resource, improved resource utilization ratio greatly, has saved system's investment.
Among the present invention, dynamically the resource of adjusting comprises: processor, internal memory, I/O resource etc.Two centers disaster tolerance equipment refers to carry simultaneously the main equipment such as physical host with end and standby end of disaster tolerance system, can be according to type of service and regional in conjunction with the business of distributing each center, can effectively must save resource overhead, can guarantee the disaster-containing pipe of system under abnormal conditions again, improve resource utilization greatly and reduced system's investment.For example the BOSS system designs according to traffic load sharing, and the traffic assignments at 2 centers is as follows:
One center: business, account, letter control, charging, inquiry (Sector East 9 districts and cities)
Two centers: business, account, letter control, charging, inquiry (Westbound 8 districts and cities)
As shown in Figure 3, the main of carrying one center business is arranged in the physical host with end and the standby end that carries two center business, the main of carrying two center business is arranged in another physical host with the standby end of holding and carry a center business.
Referring to Fig. 4, the embodiment of the invention provides a kind of pair of center disaster tolerance equipment, and this equipment comprises:
First zoning unit 30 is used to carry the main with end of disaster tolerance business;
Second zoning unit 31 is used to carry the standby end of disaster tolerance business;
Determining unit 32 is used for determining described main current running status with end and/or standby end, determines whether that according to described current running status needs carry out the resource adjustment;
Adjustment unit 33 is used for when described determining unit determines to carry out the resource adjustment, according to the resource regulation rule that sets in advance, is adjusted into described main resource of distributing with end and/or standby end.
Described adjustment unit 33 comprises:
First division unit is used for being chosen for the resource that described first zoning unit distributes according to the resource regulation rule that sets in advance, and gives described second zoning unit with this resource division;
Second division unit is used for being chosen for the resource that described second zoning unit distributes according to the resource regulation rule that sets in advance, and gives described first zoning unit with this resource division.
This equipment also comprises: the 3rd zoning unit 34 is used to manage the slack resources of described pair of center disaster tolerance equipment;
Accordingly, described first division unit also is used for: be chosen for the resource that described first zoning unit distributes, and give described the 3rd zoning unit with this resource division;
Described second division unit also is used for: be chosen for the resource that described second zoning unit distributes, and give described the 3rd zoning unit with this resource division;
Described adjustment unit 33 also comprises:
The 3rd division unit is used for choosing the resource of described the 3rd zoning unit according to the resource regulation rule that sets in advance, and gives described first zoning unit and/or second zoning unit with this resource division; Perhaps, choose the part resource of described the 3rd zoning unit, give described first zoning unit, choose another part resource of described the 3rd zoning unit, give described second zoning unit this resource division with this resource division.
Described adjustment unit 33 also comprises:
The 4th division unit is used for and will adjusts to described main second business with end for described main resource with first traffic assignments of holding.
Described determining unit 32 is used for: when described master arrives predetermined threshold value with the pending traffic carrying capacity of end, determine to carry out the resource adjustment;
Accordingly, described adjustment unit 33 is used for: be chosen for the resource of described second zoning unit distribution and/or the slack resources of described pair of center disaster tolerance equipment, and give described first zoning unit with this resource division.
Described determining unit 32 is used for: when described standby end is carried out the disaster tolerance switching, determine to carry out the resource adjustment;
Accordingly, described adjustment unit 33 is used for: be chosen for the slack resources of described first zoning unit and/or described pair of center disaster tolerance equipment, and give described second zoning unit with this resource division.
Described the 3rd zoning unit 34 also is used for: carrying is used for the described main test service of testing with end and/or standby end;
Accordingly, described adjustment unit 33 further comprises:
The 5th division unit, be used for when determining to utilize described test service that described master is tested with end and/or standby end, be chosen for the resource that described first zoning unit and/or second zoning unit distribute, and give described the 3rd zoning unit this resource division.
To sum up, beneficial effect of the present invention comprises:
In the scheme that the embodiment of the invention provides, when determining that according to the main current running status in the disaster tolerance equipment of two centers needs carry out the resource adjustment with end and/or standby end, according to the resource regulation rule that sets in advance, to adjust for main resource of distributing with end and/or standby end, by resource is dynamically adjusted, can improve resource utilization, make full use of system resource, thereby effectively reduce the wasting of resources.
Illustrate, for the BOSS system that adopts two centers disaster tolerance pattern, realize the flexible control of resource, originally the resource of distributing to standby end is taken out 40% as the slack resources that can dynamically adjust, about 5% the resource loss that consideration causes because of the facilities and equipments subregion, therefore two centers disaster tolerance of realizing of the present invention has increased by 35% utilization of resources ability than the allocation plan of routine, has promptly reduced by 35% investment.
Then:
If to BOSS dilatation main frame, storage total investment is 6,000 ten thousand, then a joint total value is 6000/0.65*0.35=3230 ten thousand.
If to BOSS dilatation main frame, storage total investment is 8,000 ten thousand, then a joint total value is 8000/0.65*0.35=4307 ten thousand.
In addition, calculate from each customer investment amount, then each customer investment of BOSS capacity expansion project is 11 yuan, far below the investment amount that adopts traditional double center disaster tolerance pattern, has fully verified the economic benefit that the present invention can bring.
Obviously, those skilled in the art can carry out various changes and modification to the present invention and not break away from the spirit and scope of the present invention.Like this, if of the present invention these are revised and modification belongs within the scope of claim of the present invention and equivalent technologies thereof, then the present invention also is intended to comprise these changes and modification interior.

Claims (14)

1. the resource adjusting method in two centers disaster tolerance equipment is characterized in that this method comprises:
Determine the main current running status in the described pair of center disaster tolerance equipment with end and/or standby end;
When determining that according to described current running status needs carry out the resource adjustment,, be adjusted into described main resource of distributing with end and/or standby end according to the resource regulation rule that sets in advance.
2. the method for claim 1 is characterized in that, describedly is adjusted into described main resource with end and/or the distribution of standby end and comprises one or combination in any in the following mode:
Will be for described main with holding assigned portions or whole resource to adjust or being adjusted into slack resources to described standby end;
To main adjust to described standby end for described, and will mainly be adjusted into slack resources for described with another part resource of holding distribution with end assigned portions resource;
Will for described standby end assigned portions or all resource adjust to described main with holding or be adjusted into slack resources;
To adjust to described main for described standby end assigned portions resource, and will be adjusted into slack resources for another part resource that described standby end distributes with end;
The part or all of slack resources of described pair of center disaster tolerance equipment is adjusted to described main with end or standby end;
The part slack resources of described pair of center disaster tolerance equipment is adjusted to described main with end, and another part slack resources of described pair of center disaster tolerance equipment is adjusted to described standby end.
3. method as claimed in claim 2, it is characterized in that, described master is with holding first subregion that is arranged on described pair of center disaster tolerance equipment, and described standby end is arranged on second subregion of described pair of center disaster tolerance equipment, and described slack resources is arranged on the 3rd subregion of described pair of center disaster tolerance equipment;
Described will comprising: be chosen for the described first subregion assigned portions or whole resource, and give described second subregion or described the 3rd subregion with this resource division for described master adjusts to described standby end or is adjusted into slack resources with end assigned portions or whole resource;
Described will the adjustment to described standby end with end assigned portions resource for described master, and will comprise: be chosen for the described first subregion assigned portions for described main another part resource of distributing with end is adjusted into slack resources, give described second subregion with this resource division, be chosen for another part resource that described first subregion distributes, give described the 3rd subregion this resource division;
Described will for described standby end assigned portions or all resource adjust to described main with end or be adjusted into slack resources and comprise: be chosen for the described second subregion assigned portions or whole resources, and with this resource division to described first subregion or described the 3rd subregion;
Described will the adjustment to described main for described standby end assigned portions resource with end, and will be adjusted into slack resources for another part resource that described standby end distributes and comprise: be chosen for the described second subregion assigned portions resource, give described first subregion with this resource division, be chosen for another part resource that described second subregion distributes, give described the 3rd subregion this resource division;
Described part or all of slack resources with described pair of center disaster tolerance equipment is adjusted to described master and is comprised with end or standby end: choose the part or all of resource of described the 3rd subregion, and give described first subregion or second subregion with this resource division;
Described part slack resources with described pair of center disaster tolerance equipment is adjusted to described main with end, and another part slack resources of described pair of center disaster tolerance equipment adjusted to described standby end comprise: the part resource of choosing described the 3rd subregion, give described first subregion with this resource division, choose another part resource of described the 3rd subregion, give described second subregion this resource division.
4. method as claimed in claim 2 is characterized in that, and is described main with a plurality of business of end carrying, describedly is adjusted into described main resource with the end distribution and also comprises:
To adjust to described main second business of carrying for described main resource with first traffic assignments of holding carrying with end.
5. method as claimed in claim 3 is characterized in that,
Describedly determine that according to described current running status needs carry out the resource adjustment and comprise: when described main traffic carrying capacity with end arrives predetermined threshold value, determine to carry out the resource adjustment;
Describedly be adjusted into described main resource and comprise with end and/or the distribution of standby end:
Be chosen for the resource that described second subregion and/or the 3rd subregion distribute, and give described first subregion this resource division.
6. method as claimed in claim 3 is characterized in that,
Describedly determine that according to described current running status needs carry out the resource adjustment and comprise: when described standby end is carried out disaster tolerance and switched, determine to carry out the resource adjustment;
Describedly be adjusted into described main resource and comprise with end and/or the distribution of standby end:
Be chosen for the resource that described first subregion and/or the 3rd subregion distribute, and give described second subregion this resource division.
7. method as claimed in claim 3 is characterized in that, also is provided with test service in described the 3rd subregion, and this method further comprises:
When determining to utilize described test service that described master is tested with end and/or standby end, be chosen for the resource that described first subregion and/or second subregion distribute, and give described the 3rd subregion this resource division.
8. two centers disaster tolerance equipment is characterized in that this equipment comprises:
First zoning unit is used to carry the main with end of disaster tolerance business;
Second zoning unit is used to carry the standby end of disaster tolerance business;
Determining unit is used for determining described main current running status with end and/or standby end, determines whether that according to described current running status needs carry out the resource adjustment;
Adjustment unit is used for when described determining unit determines to carry out the resource adjustment, according to the resource regulation rule that sets in advance, is adjusted into described main resource of distributing with end and/or standby end.
9. equipment as claimed in claim 8 is characterized in that, described adjustment unit comprises:
First division unit is used for being chosen for the resource that described first zoning unit distributes according to the resource regulation rule that sets in advance, and gives described second zoning unit with this resource division;
Second division unit is used for being chosen for the resource that described second zoning unit distributes according to the resource regulation rule that sets in advance, and gives described first zoning unit with this resource division.
10. equipment as claimed in claim 9 is characterized in that, this equipment also comprises:
The 3rd zoning unit is used to manage the slack resources of described pair of center disaster tolerance equipment;
Described first division unit also is used for: be chosen for the resource that described first zoning unit distributes, and give described the 3rd zoning unit with this resource division;
Described second division unit also is used for: be chosen for the resource that described second zoning unit distributes, and give described the 3rd zoning unit with this resource division;
Described adjustment unit also comprises:
The 3rd division unit is used for choosing the resource of described the 3rd zoning unit according to the resource regulation rule that sets in advance, and gives described first zoning unit or second zoning unit with this resource division; Perhaps, choose the part resource of described the 3rd zoning unit, give described first zoning unit, choose another part resource of described the 3rd zoning unit, give described second zoning unit this resource division with this resource division.
11., it is characterized in that described adjustment unit also comprises as claim 9 or 10 described equipment:
The 4th division unit is used for and will adjusts to described main second business with end for described main resource with first traffic assignments of holding.
12. equipment as claimed in claim 8 is characterized in that, described determining unit is used for:
When described main traffic carrying capacity with end arrives predetermined threshold value, determine to carry out the resource adjustment;
Described adjustment unit is used for:
Be chosen for the resource of described second zoning unit distribution and/or the slack resources of described pair of center disaster tolerance equipment, and give described first zoning unit this resource division.
13. equipment as claimed in claim 8 is characterized in that, described determining unit is used for:
When described standby end is carried out the disaster tolerance switching, determine to carry out the resource adjustment;
Described adjustment unit is used for:
Be chosen for the slack resources of described first zoning unit and/or described pair of center disaster tolerance equipment, and give described second zoning unit this resource division.
14. equipment as claimed in claim 10 is characterized in that, described the 3rd zoning unit also is used for:
Carrying is used for the described main test service of testing with end and/or standby end;
Described adjustment unit further comprises:
The 5th division unit, be used for when determining to utilize described test service that described master is tested with end and/or standby end, be chosen for the resource that described first zoning unit and/or second zoning unit distribute, and give described the 3rd zoning unit this resource division.
CN200910076882A 2009-01-23 2009-01-23 Double-center disaster recovery equipment and resource adjustment method in same Pending CN101790170A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910076882A CN101790170A (en) 2009-01-23 2009-01-23 Double-center disaster recovery equipment and resource adjustment method in same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910076882A CN101790170A (en) 2009-01-23 2009-01-23 Double-center disaster recovery equipment and resource adjustment method in same

Publications (1)

Publication Number Publication Date
CN101790170A true CN101790170A (en) 2010-07-28

Family

ID=42533168

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910076882A Pending CN101790170A (en) 2009-01-23 2009-01-23 Double-center disaster recovery equipment and resource adjustment method in same

Country Status (1)

Country Link
CN (1) CN101790170A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102487332A (en) * 2010-12-03 2012-06-06 中兴通讯股份有限公司 Fault processing method, apparatus thereof and system thereof
CN104184611A (en) * 2014-07-24 2014-12-03 华为技术有限公司 Disaster tolerance site, and service message processing device and method
CN105589826A (en) * 2016-02-01 2016-05-18 国网福建省电力有限公司 Method for information interaction of multilevel buses of power distribution network based on plug-and-play
US9798635B2 (en) 2015-12-11 2017-10-24 International Business Machines Corporation Service level agreement-based resource allocation for failure recovery
CN112311566A (en) * 2019-07-25 2021-02-02 中国移动通信集团有限公司 Business disaster tolerance method, device, equipment and medium
CN113395265A (en) * 2021-05-28 2021-09-14 北京佳讯飞鸿电气股份有限公司 Key business processing method, terminal and system

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102487332A (en) * 2010-12-03 2012-06-06 中兴通讯股份有限公司 Fault processing method, apparatus thereof and system thereof
CN102487332B (en) * 2010-12-03 2015-01-28 中兴通讯股份有限公司 Fault processing method, apparatus thereof and system thereof
CN104184611A (en) * 2014-07-24 2014-12-03 华为技术有限公司 Disaster tolerance site, and service message processing device and method
US9798635B2 (en) 2015-12-11 2017-10-24 International Business Machines Corporation Service level agreement-based resource allocation for failure recovery
CN105589826A (en) * 2016-02-01 2016-05-18 国网福建省电力有限公司 Method for information interaction of multilevel buses of power distribution network based on plug-and-play
CN105589826B (en) * 2016-02-01 2019-08-16 国网福建省电力有限公司 Power distribution network multi-level bus information interacting method based on plug and play
CN112311566A (en) * 2019-07-25 2021-02-02 中国移动通信集团有限公司 Business disaster tolerance method, device, equipment and medium
CN112311566B (en) * 2019-07-25 2023-10-17 中国移动通信集团有限公司 Service disaster recovery method, device, equipment and medium
CN113395265A (en) * 2021-05-28 2021-09-14 北京佳讯飞鸿电气股份有限公司 Key business processing method, terminal and system

Similar Documents

Publication Publication Date Title
CN101790170A (en) Double-center disaster recovery equipment and resource adjustment method in same
CN101110776B (en) Backup method, backup device and backup system for data business
CN101772177B (en) Method, system and device for managing base band resources
CN104935460B (en) A kind of multi-controller energy conservation optimizing method based on data surface volume forecasting
CN102740326B (en) Managing method and device for processing resources in BBU
JP2007134840A (en) Mobile communication system, base station apparatus, power consumption reduction method for use therein and its program
CN101622820A (en) Method and system for managing baseband resource pool of global mobile communication system
CN102117225B (en) Industrial automatic multi-point cluster system and task management method thereof
CN202143061U (en) Main/standby redundancy dual-channel communication system
CN102497288A (en) Dual-server backup method and dual system implementation device
CN101489230A (en) Carrier distribution control method and system
CN107846318A (en) A kind of distributed type assemblies and distributed type assemblies management method
CN102802180B (en) Radio frequency resource dispatch control method and device
US20110244867A1 (en) Method and system for realizing energy saving control of bs
CN101958782B (en) Method for realizing node standby and system
CN103476074A (en) Method and equipment for resource preemption
CN101415179B (en) Method, apparatus and system for automatically switching business
CN101420741A (en) Method for implementing carrier control
CN102437949A (en) Load-sensing-type routing method based on dormancy of optical network unit (ONU)
CN100366110C (en) Method for distributing baseband channel processing resource in mobile communication system base station
CN105474732B (en) Apparatus control method, equipment and system under a kind of centralization baseband pool framework
CN101217710B (en) Wireless network license documents sharing system and the corresponding sharing method
US11218914B2 (en) Integration method, device and system for multiple centralized units
CN101146309B (en) A cell resource failure processing method and device in communication system
CN105224470A (en) A kind of memory allocation method and device based on simplifying configuration

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20100728