CN101776735A - 发变组高压侧pt反送电试验方法 - Google Patents

发变组高压侧pt反送电试验方法 Download PDF

Info

Publication number
CN101776735A
CN101776735A CN200910311213A CN200910311213A CN101776735A CN 101776735 A CN101776735 A CN 101776735A CN 200910311213 A CN200910311213 A CN 200910311213A CN 200910311213 A CN200910311213 A CN 200910311213A CN 101776735 A CN101776735 A CN 101776735A
Authority
CN
China
Prior art keywords
generator
pressure side
transformer unit
voltage
change group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910311213A
Other languages
English (en)
Inventor
邵梦桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Electric Power Test and Research Institute
Original Assignee
Guizhou Electric Power Test and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Electric Power Test and Research Institute filed Critical Guizhou Electric Power Test and Research Institute
Priority to CN200910311213A priority Critical patent/CN101776735A/zh
Publication of CN101776735A publication Critical patent/CN101776735A/zh
Pending legal-status Critical Current

Links

Abstract

本发明公开了一种发变组高压侧PT反送电试验方法,在锅炉点火前增加发电机整套启动的试验步骤,它包括以下过程:首先,解开发变组高压侧PT与主变之间的引流线,将发变组高压侧PT接入500kV升压站;然后用系统电源对发变组高压侧PT进行三次充电,充电过程中在发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验同期电压回路的正确性。本发明能够在发电机整套启动前(锅炉未点火时)进行发变组高压侧PT反送电试验,用系统电压检查同期电压回路,发电机零起升压试验时不带母线进行,无需在锅炉点火的情况下进行倒闸操作,因而可以节约大量燃油,减少浪费,并减少了废气排放,有利于环保。

Description

发变组高压侧PT反送电试验方法
技术领域
本发明涉及一种发电机启动的电气试验方法。
背景技术
为检查发电机同期装置的电压回路的正确性,需要在同一个一次电压下对发变组高压侧PT和母线PT的二次电压进行核相。通常的做法是在发电机整套启动试验中用发电机带母线一起进行零起升压试验,升至额定电压时对发变组高压侧PT和母线PT的二次电压进行核相。但这样做试验要在锅炉已点火的情况下进行两次母线倒闸操作,第一次倒闸操作是将母线停电并与发电机连接在一起,零起升压试验完成后要进行第二次倒闸操作,恢复母线的正常运行方式。倒闸操作的时间往往比较长,大约在4-6小时,倒闸操作期间,锅炉又不能熄火,白白烧掉很多燃油,造成浪费,加重环境污染。
发明内容
本发明要解决的技术问题是,提供一种发变组高压侧PT反送电试验方法,该方法节约燃油,以克服现有技术存在的燃油浪费,加重环境污染等不足。
本发明的技术方案为:在锅炉点火前增加发电机整套启动的试验步骤,即用系统电源作为充电电源对发变组高压侧PT进行反充电,充电过程中在发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验同期电压回路的正确性。在锅炉点火后的发电机电气试验中不需要进行母线倒闸操作,以达到节约燃油的目的。
以上技术方案包括以下过程:首先,解开发变组高压侧PT与主变之间的引流线,将发变组高压侧PT接入升压站;然后用系统电源对发变组高压侧PT进行三次充电,充电过程中在发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验同期电压回路的正确性。用系统电源对发变组高压侧PT进行反充电是手段,检验同期电压回路的正确性才是目的。进行过反充电试验检查完同期电压回路后,锅炉点火后进行的发电机电气试验中不需要进行母线倒闸操作,可以节约燃油。
如果不按照以上技术方案进行试验,在锅炉点火后的发电机整套启动电气试验中的发变组零起升压试验中,必需对母线进行倒闸操作,发电机带母线一起进行零起升压试验,在此试验过程中进行同期电压回路正确性的检查,要多烧燃油。
本方案能够在整套启动试验过程中进行零起升压试验时,不需要带母线进行,也不需要在锅炉点火的情况下进行倒闸操作。
本发明的有益效果:本发明能够在发电机整套启动前(锅炉未点火时)进行发变组高压侧PT反送电试验,用系统电压检查同期电压回路,发电机零起升压试验时不带母线进行,无需在锅炉点火的情况下进行倒闸操作,因而可以节约大量燃油,减少浪费,并减少了废气排放,有利于环保。
具体实施方式
本发明的实施例:在锅炉点火前增加发电机整套启动的试验步骤,即在锅炉未点火时用系统电源作为充电电源对发变组高压侧PT进行反充电,充电过程中在发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验同期电压回路的正确性。在锅炉点火后的发电机电气试验中不需要进行母线倒闸操作,以达到节约燃油的目的。
以上技术方案包括以下过程:首先,解开发变组高压侧PT与主变之间的引流线,将发变组高压侧PT接入升压站(所述的升压站为500kV升压站);然后用系统电源对发变组高压侧PT进行三次充电,充电过程中在发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验同期电压回路的正确性。用系统电源对发变组高压侧PT进行反充电是手段,检验同期电压回路的正确性才是目的。进行过反充电试验检查完同期电压回路后,锅炉点火后进行的发电机电气试验中不需要进行母线倒闸操作,可以节约燃油。
利用本发明的技术方案在黔西电厂#3机进行试验。#3机整套启动前,我们编写了《黔西电厂#3发变组高压侧PT反送电试验方案》报送调度,调度批准试验方案后,解开#3发变组高压侧PT与#3主变之间的引流线,将#3发变组高压侧PT接入500kV升压站,用系统电源对#3发变组高压侧PT进行三次充电,充电过程中在#3发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验了同期电压回路的正确性。在#3机整套启动试验过程中进行零起升压试验时没有带母线进行,也就没有在锅炉点火的情况下进行倒闸操作,通过增加PT反送电试验达到节约燃油的目的。

Claims (2)

1.一种发变组高压侧PT反充电试验方法,其特征在于:在锅炉点火前增加发电机整套启动的试验步骤,即用系统电源作为充电电源对发变组高压侧PT进行反充电,充电过程中在发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验同期电压回路的正确性。
2.根据权利要求1所述的发变组高压侧PT反充电试验方法,其特征在于:它包括以下过程:首先,解开发变组高压侧PT与主变之间的引流线,将发变组高压侧PT接入升压站;然后用系统电源对发变组高压侧PT进行三次充电,充电过程中在发电机同期装置上对发变组高压侧PT和母线PT的二次电压进行核相,检验同期电压回路的正确性。
CN200910311213A 2009-12-10 2009-12-10 发变组高压侧pt反送电试验方法 Pending CN101776735A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910311213A CN101776735A (zh) 2009-12-10 2009-12-10 发变组高压侧pt反送电试验方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910311213A CN101776735A (zh) 2009-12-10 2009-12-10 发变组高压侧pt反送电试验方法

Publications (1)

Publication Number Publication Date
CN101776735A true CN101776735A (zh) 2010-07-14

Family

ID=42513244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910311213A Pending CN101776735A (zh) 2009-12-10 2009-12-10 发变组高压侧pt反送电试验方法

Country Status (1)

Country Link
CN (1) CN101776735A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110007229A (zh) * 2019-04-24 2019-07-12 南京泰润电力工程有限公司 一种同步发电机的定相检查方法
CN110504712A (zh) * 2019-08-21 2019-11-26 西安热工研究院有限公司 一种燃气电厂π型同源核相系统及方法
CN111342464A (zh) * 2020-04-21 2020-06-26 西安热工研究院有限公司 一种单母线系统接线方式机组核相的系统及方法
CN112345938A (zh) * 2020-12-01 2021-02-09 中广核工程有限公司 核电厂应急柴油发电机组试验方法
CN113325236A (zh) * 2021-07-02 2021-08-31 山东钢铁股份有限公司 双母线双分段接线gis柜电源送电核相的方法

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110007229A (zh) * 2019-04-24 2019-07-12 南京泰润电力工程有限公司 一种同步发电机的定相检查方法
CN110504712A (zh) * 2019-08-21 2019-11-26 西安热工研究院有限公司 一种燃气电厂π型同源核相系统及方法
CN110504712B (zh) * 2019-08-21 2021-08-31 西安热工研究院有限公司 一种燃气电厂π型同源核相系统及方法
CN111342464A (zh) * 2020-04-21 2020-06-26 西安热工研究院有限公司 一种单母线系统接线方式机组核相的系统及方法
CN112345938A (zh) * 2020-12-01 2021-02-09 中广核工程有限公司 核电厂应急柴油发电机组试验方法
CN112345938B (zh) * 2020-12-01 2022-05-31 中广核工程有限公司 核电厂应急柴油发电机组试验方法
CN113325236A (zh) * 2021-07-02 2021-08-31 山东钢铁股份有限公司 双母线双分段接线gis柜电源送电核相的方法

Similar Documents

Publication Publication Date Title
CN203911578U (zh) 一种应用于二拖一燃机电厂厂用电接线系统
CN101776735A (zh) 发变组高压侧pt反送电试验方法
CN102738831B (zh) 太阳能系统以及通信装置
CN101552462A (zh) 一种黑启动方法
CN105846463A (zh) 一种多源协调的黑启动方法及系统
CN113162215B (zh) 代替海上平台柴油发电机系统的应急电源系统及控制方法
CN104218568A (zh) 一种区域小水电与新能源互补微电网参与电网黑启动方法
CN111628567A (zh) 一种兼顾事故保安和黑启动的柴油发电机系统及启动方法
CN103941720A (zh) 内驱电控点火系统的故障诊断电路及其诊断方法
CN104753087A (zh) 一种含多种储能的风光储微电网的黑启动方法
CN204835555U (zh) 一种人工智能化的发电机并机系统
CN104065111B (zh) 一种用于移动式保电储能的黑启动系统及其启动方法
CN102636753B (zh) 火电机组辅机低电压穿越能力的试验方法
CN203243113U (zh) 汽轮机润滑油系统事故油泵电源
CN203849610U (zh) 内驱电控点火系统的故障诊断电路
CN103259313B (zh) 一种汽车充电连接系统的锁紧结构
CN112290669A (zh) 一种9e和9f燃机联合黑启动的电气系统及其工作方法
CN117353386A (zh) 基于柴油发电机耦合燃机的黑启动系统及方法
CN201786526U (zh) 内燃机启动电机保护器
CN203660578U (zh) 一种用于移动式保电储能的黑启动系统
CN109004678B (zh) 一种多能组合发电厂黑启动配电系统及控制方法
CN208955749U (zh) 一种电池集装箱智能储能系统
CN103647343A (zh) 内桥接线变电站备自投运行方式的改进方法
CN111404259A (zh) 一种发电机组的保安段电源系统及其切换方法
CN102496956A (zh) 用于微网的从并网模式切换到孤岛模式的模式切换方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20100714