CN101684652A - Solid waste earthwork bag and application method thereof - Google Patents

Solid waste earthwork bag and application method thereof Download PDF

Info

Publication number
CN101684652A
CN101684652A CN200810157044A CN200810157044A CN101684652A CN 101684652 A CN101684652 A CN 101684652A CN 200810157044 A CN200810157044 A CN 200810157044A CN 200810157044 A CN200810157044 A CN 200810157044A CN 101684652 A CN101684652 A CN 101684652A
Authority
CN
China
Prior art keywords
solid waste
bag
earthwork bag
earthwork
waste earthwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200810157044A
Other languages
Chinese (zh)
Other versions
CN101684652B (en
Inventor
刘斯宏
汪易森
胡晓平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN200810157044A priority Critical patent/CN101684652B/en
Publication of CN101684652A publication Critical patent/CN101684652A/en
Application granted granted Critical
Publication of CN101684652B publication Critical patent/CN101684652B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Abstract

The invention relates to a solid waste earthwork bag of engineering construction wastes, industrial wastes, stones, dregs and soils of mine tailings, and the like that have no chemical pollutions as well as an application method thereof in a foundation and a side slope. Available crushed solid wastes are directly put into the earthwork bags which are specified strictly, and the solid waste earthwork bags are then piled on the engineering construction foundation and the side slope according to a certain arrangement way and compacted layer by layer by a compacting device to form a building foundation or be used for reinforcing the side slope. As the solid waste soil body restricted and the vibration energy is consumed by the tensile force generated by the compression deformation of the earthwork bag, the whole strength and the shock absorption performance of the solid waste earthwork bag are improved. The solid waste earthwork bag is applied to foundation engineering, saves the resourcesand the land, reduces the vibration, prevents the disaster and the freeze thawing, is green and environment-friendly and has remarkable benefits.

Description

The method of solid waste earthwork bag and application
One, technical field
The present invention relates to a kind of solid waste product of chemical contamination and method of application of not containing, particularly a kind ofly do not contain the solid waste earthwork bag of chemical contamination and be applied to ground and the method for slope project.
Two, background technology
In recent years, the city-building fast development, the dregs of city-building is arbitrarily toppled over has become serious social effects of pollution.The stone, slag, soil etc. that do not contain a large amount of solid waste such as the city-building discarded object of chemical contamination and industrial waste, mining area tailings mix, its object quality differs widely, granular size is inhomogeneous, discarded object intensity can not satisfy the requirement that engineering is used, simultaneously be difficult to carry out classified use again, often take to topple over the disposal options of landfill.Like this, not only take a large amount of soils, and destroy ecological environment.In addition, the Wenchuan violent earthquake that take place this year causes a large amount of landslides and house collapse, and the landslide soil stone body and the building castoff of flood tide are faced with the problem of dealing carefully with.After the earthquake, the antidetonation of engineering works, shockproof problem have caused people's very big concern, and it is imperative to research and develop effective, inexpensive antidetonation, shake-proof technology.
Three, summary of the invention
The present invention packs above-mentioned solid waste in the Polywoven Bag of regulatory specifications, material behind crushing and screening, form a kind of solid waste earthwork bag that can be used for field grounds such as urban housing construction, road construction, dam construction and slope project, provide this solid waste earthwork bag to be applied to the method for ground and slope project, make the regeneration of solid waste energy, reach environmental protection, save the purpose of toppling over the landfill land occupation.The solid waste earthwork bag of being invented is applied to ground and slope project, and is cheap, and construction is simple, has vibration damping, shockproof effect simultaneously, also has anti-freeze thawing effect at cold district.
The present invention is achieved by the following technical solutions:
(A) solid waste such as engineering construction (particularly city-building) discarded object, industrial waste, mining area tailings that will not contain chemical contamination are crushed to that 5cm is following (to be used for cold district, then therefrom rescreen) except that the fine particle materials below the 0.075mm, solid waste 1 such as the stone after the fragmentation, slag, soil are packed in a series of geotechnique bag 2, and by the good sack of 6,7,8,9 take-up straps, the solid waste earthwork bag 3 of formation is stand-by;
(B) on the ground and side slope soil layer face of engineering construction,, and carry out soil layer by standard and handle with this soil layer of rolling compaction machine compacting;
(C) solid waste earthwork bag 3 of step (A) is transported and winches to engineering foundation and side slope place, place solid waste earthwork bag 3 by crisscross arrangement mode, interconnect between solid waste earthwork bag 3 sacks, to improve its globality, 4 usefulness engineering construction places, space soil between the solid waste earthwork bag 3 or broken solid waste 1 are filled.One deck rolls with rolling compaction machine, until the compactness 1.5-2.0g/cm that is compacted to designing requirement after laying and finishing 3Till;
(D) set by step the mode of (C) is successively constructed, and until top layer, forms structure foundation or side slope protection body, is provided with surface protection 5 on each surface of ground and side slope.
The described geotechnique bag of above-mentioned steps (A) 2 by admixture the black polypropylene material of 0.5-1% aging-proof agent make, uvioresistant, good endurance, planar dimension is 40-100cm * 40-100cm.
The above-mentioned solid waste earthwork bag and the method for application are used in worker China Democratic National Construction Association and vibration damping ground.
The above-mentioned solid waste earthwork bag and the method for application are used in grounds such as harbour, highway, railway, airport and dykes and dams, barricade.
Above-mentioned solid waste filters out coarse granule material (between a particle diameter 5cm-0.075mm) solid waste earthwork bag and the application process that geotechnique bag forms of packing into through fragmentation and uses in the cold district ground.
Beneficial effect of the present invention is:
1. saving soil.The application of solid waste earthwork bag can reduce the engineering construction required fried stone that cuts into a mountain, farmland fetches earth, and omits the landfill land used of solid waste simultaneously, realizes the land resources saving.
2. vibration damping is taken precautions against natural calamities.The application of solid waste earthwork bag improves the damping property of engineering construction, reaches effectiveness in vibration suppression near elastomeric material commonly used with lower cost, under the small strain situation, and its equivalent damping ratio h EqAlso can reach the big value about 0.3, approach the equivalent damping ratio of elastomeric material.
3. prevent freeze thawing.The cold district that is applied as of coarse granule solid waste earthwork bag provides a kind of freezing-thawing method that effectively prevents.
4. protection environment.Blue mountains and green waters has been protected in the application of solid waste earthwork bag, realizes environmental friendliness.
5. remarkable benefit.The application of solid waste earthwork bag not only becomes useless be usefulness, remarkable in economical benefits, and promoting employment, obvious social benefit.
Four, description of drawings
Fig. 1 is a solid waste earthwork bag Analysis on Mechanism concept map:
Fig. 2 is applied to the ground schematic diagram for solid waste earthwork bag;
Fig. 3 is a solid waste earthwork bag take-up strap schematic diagram.
Mark among the figure: 1. solid waste, 2. geotechnique's bag, 3. solid waste earthwork bag is 4. filled the solid waste in the space between the solid waste earthwork bag, 5. surface protection (concrete lining or lawn bank protection), 6.7.8.9 take-up strap.
Five, the specific embodiment
A kind of with solid waste earthwork bag and be applied to the method for construction project ground and side slope, its step is as follows:
(A) solid waste such as engineering construction (particularly city-building) discarded object, industrial waste, mining area tailings that will not contain chemical contamination are crushed to that 5cm is following (to be used for cold district, then therefrom rescreen except that the fine particle materials below the 0.075mm) solid waste 1 such as the stone after the fragmentation, slag, soil are packed in a series of geotechnique bag 2, and by the good sack of 6,7,8,9 take-up straps, the solid waste earthwork bag 3 of formation is stand-by;
(B) on the ground and side slope soil layer face of engineering construction,, and carry out soil layer by standard and handle with this soil layer of rolling compaction machine compacting;
(C) solid waste earthwork bag 3 of step (A) is transported and winches to engineering foundation and side slope place, place solid waste earthwork bag 3 by crisscross arrangement mode, interconnect between solid waste earthwork bag 3 sacks, to improve its globality, 4 usefulness engineering construction places, space soil between the solid waste earthwork bag 3 or broken solid waste 1 are filled.One deck rolls with rolling compaction machine, until the compactness 1.5-2.0g/cm that is compacted to designing requirement after laying and finishing 3Till;
(D) set by step the mode of (C) is successively constructed, and until to top layer, forms structure foundation or side slope protection body, is provided with surface protection 5 on each surface of ground and side slope.
The described geotechnique bag 2 of above-mentioned steps (A) be by admixture the black polypropylene material of 0.5-1% aging-proof agent make, uvioresistant, and can be durable, planar dimension is 40-100cm * 40-100cm.
With the related experiment result, the invention will be further described in conjunction with the accompanying drawings.
The Analysis on Mechanism figure that Fig. 1 increases for solid waste earthwork bag intensity.Solid waste earthwork bag uploading the whole generation of solid waste earthwork bag compressive strain under the pressure effect, causes the sack elongation, thereby produce a tension force T in sack after compacting.Sack tension force T plays an effect of contraction to the solid waste in the earth bag conversely, makes that the contact force N between the interior native stone granulate of bag increases.Because native stone body intensity comes from the frictional strength between native stone granulate in essence, contact force N increases between the soil stone granulate, and the frictional strength increase between promptly native stone granulate (meets law of friction F=μ N, μ: friction factor between native stone granulate), therefore, the integral anti-shearing intensity of solid waste earthwork bag increases.
The vibration damping of solid waste earthwork bag monomer is because under the vibrating load effect, the fricting movement consumed energy between the native stone granulate in the flexible modification of bag and the bag causes; Solid waste earthwork bag assembly vibration damping is that vibration is difficult to by the space between bag and the bag because discontinuous between the bag.
The space is bigger between the particle in the coarse granule solid waste earthwork bag, this geotechnique's bag is used for ground and slope reinforcement, water in the geotechnique bag lower soil or underground water can to rise to geotechnique's bag not inner because of capillarity, thereby can prevent freeze thawing at cold district.
According to indoor friction test, during criss-cross arrangement, the interfacial friction coefficient is greater than 1.0, generally between 1.05-1.2 between described solid waste earthwork bag layer and the layer.Therefore the solid waste earthwork bag stability of piling up can guarantee.
The method of described solid waste earthwork bag and application, be applicable to fields such as (comprising city-building, earthquake reconstruction, cold district) building, traffic, water conservancy, be specially house foundation, highway, railway, airport, harbour ground, dykes and dams, side slope, barricade etc.

Claims (5)

1. stone, slag, the solid waste earthwork bag of soil and the methods of application such as engineering construction (particularly city-building) discarded object that does not contain chemical contamination, industrial waste, mining area tailings is characterized in that:
(A) solid waste such as engineering construction discarded object, industrial waste, mining area tailings that will not contain chemical contamination are crushed to that 5cm is following (to be used for cold district, then therefrom rescreen) except that the fine particle materials below the 0.075mm, solid waste (1) such as the stone after the fragmentation, slag, soil are packed in a series of geotechnique bag (2), and by (6), (7), (8), the good sack of (9) take-up strap, the solid waste earthwork bag of formation (3) is stand-by;
(B) on the ground and side slope soil layer face of engineering construction,, and carry out soil layer by standard and handle with this soil layer of rolling compaction machine compacting;
(C) solid waste earthwork bag of step (A) (3) is transported and winches to engineering foundation and side slope place, place solid waste earthwork bag (3) by crisscross arrangement mode, interconnect between solid waste earthwork bag (3) sack, to improve its globality, fill with engineering construction place soil or broken solid waste (1) in the space (4) between the solid waste earthwork bag (3).One deck rolls with rolling compaction machine, until the compactness 1.5-2.0g/cm that is compacted to designing requirement after laying and finishing 3Till;
(D) set by step the mode of (C) is successively constructed, and until to top layer, forms structure foundation or side slope protection body, is provided with surface protection (5) on the external surface of solid waste earthwork bag.
2. the method for a kind of solid waste earthwork bag according to claim 1 and application, it is characterized in that the described geotechnique bag of step (A) be by admixture the black polypropylene material of 0.5-1% aging-proof agent make, planar dimension is 40-100cm * 40-100cm.
3. the method for a kind of solid waste earthwork bag as claimed in claim 1 and application is used in worker China Democratic National Construction Association and road vibration damping ground.
4. the method for a kind of solid waste earthwork bag as claimed in claim 1 and application is used in grounds such as harbour, highway, railway, airport and dykes and dams, barricade.
5. the method for a kind of coarse granule solid waste earthwork bag as claimed in claim 1 and application is used in the cold district ground.
CN200810157044A 2008-09-22 2008-09-22 Solid waste earthwork bag and application method thereof Active CN101684652B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810157044A CN101684652B (en) 2008-09-22 2008-09-22 Solid waste earthwork bag and application method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810157044A CN101684652B (en) 2008-09-22 2008-09-22 Solid waste earthwork bag and application method thereof

Publications (2)

Publication Number Publication Date
CN101684652A true CN101684652A (en) 2010-03-31
CN101684652B CN101684652B (en) 2012-09-05

Family

ID=42048001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810157044A Active CN101684652B (en) 2008-09-22 2008-09-22 Solid waste earthwork bag and application method thereof

Country Status (1)

Country Link
CN (1) CN101684652B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102465481A (en) * 2010-11-09 2012-05-23 刘斯宏 Soilbag roadbed and method
CN102912785A (en) * 2012-11-08 2013-02-06 沈阳建筑大学 Similarly arch stacked bagged gravel and sandy soil foundation reinforcement treatment method
CN103711104A (en) * 2014-01-15 2014-04-09 水利部交通运输部国家能源局南京水利科学研究院 Homogeneous earth dam revetment and anti-frost method thereof
CN103806465A (en) * 2012-11-05 2014-05-21 李鑫 Technique for applying solid waste in mine area to mine geological environment management engineering construction
CN109469040A (en) * 2018-12-05 2019-03-15 三峡大学 Geotechnological rack and its application
CN111074741A (en) * 2018-10-22 2020-04-28 黄种玉 Foundation protection method
CN113567268A (en) * 2021-06-18 2021-10-29 太原理工大学 Shear-damage-resistant geotextile bag and shear-resistant method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102465481A (en) * 2010-11-09 2012-05-23 刘斯宏 Soilbag roadbed and method
CN103806465A (en) * 2012-11-05 2014-05-21 李鑫 Technique for applying solid waste in mine area to mine geological environment management engineering construction
CN102912785A (en) * 2012-11-08 2013-02-06 沈阳建筑大学 Similarly arch stacked bagged gravel and sandy soil foundation reinforcement treatment method
CN103711104A (en) * 2014-01-15 2014-04-09 水利部交通运输部国家能源局南京水利科学研究院 Homogeneous earth dam revetment and anti-frost method thereof
CN103711104B (en) * 2014-01-15 2015-04-01 水利部交通运输部国家能源局南京水利科学研究院 Homogeneous earth dam revetment and anti-frost method thereof
CN111074741A (en) * 2018-10-22 2020-04-28 黄种玉 Foundation protection method
CN109469040A (en) * 2018-12-05 2019-03-15 三峡大学 Geotechnological rack and its application
CN113567268A (en) * 2021-06-18 2021-10-29 太原理工大学 Shear-damage-resistant geotextile bag and shear-resistant method thereof

Also Published As

Publication number Publication date
CN101684652B (en) 2012-09-05

Similar Documents

Publication Publication Date Title
CN101684652B (en) Solid waste earthwork bag and application method thereof
Liu et al. Evaluation of engineering properties and environmental effect of recycled waste tire-sand/soil in geotechnical engineering: A compressive review
Peddaiah et al. Experimental study on effect of waste plastic bottle strips in soil improvement
Cabalar et al. California bearing ratio of a sub-base material modified with tire buffings and cement addition
Yang et al. Advances in properties of rubber reinforced soil
Tajabadipour et al. Laboratory pullout investigation for evaluate feasibility use of scrap tire as reinforcement element in mechanically stabilized earth walls
Touahamia et al. Shear strength of reinforced-recycled material
Jan et al. Soil stabilization using shredded rubber tyre
Emmanuel et al. A critical reappraisal of residual soils as compacted soil liners
CN108978623A (en) Adulterate the composite reinforced Base with Sand Gravel Cushion and construction method of building waste and waste tire
Abdelrahman et al. New replacement formations on expansive soils using recycled EPS beads
Dandin et al. Effect of isolated footing on fly ash subgrade reinforced with PET bottles: An experimental and analytical study
Chiaro et al. Sustainable recycling of end-of-life tyres in civil (geotechnical) engineering applications: turning issues into opportunities in the New Zealand context
Ying et al. Wetting-drying cycle effect on the compressibility of lime-treated soil accounting for wetting fluid nature and aggregate size
Zabielska-Adamska Fly ash as a barrier material
Zardari Stability of tailings dams: focus on numerical modelling
CN201437591U (en) Geotechnique bag for solid waste
CN103806434B (en) A kind of level joins the method building the slag soil engineering bag front saturated over-wet soil ground of engineering of process brill
Basu et al. General report of TC 307, Sustainability in geotechnical engineering
Huangjing et al. The stabilization of loess by chemical additives for road base
Bano et al. Application of Waste Tyre in Highway Pavement: A Literature Review
Shireen et al. Sustainable Utilization of Lightweight Waste Materials as Structural fill for Geotechnical Applications
Do et al. Railway embankment behaviour due to increased axle loads-A numerical study
Blight et al. Issues in the geotechnics of mining wastes and tailings
Murali Krishna et al. Engineering of Ground for Liquefaction Mitigation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant