CN101660426A - Method for conveying coal and refilling ash and slag in goafs of slapithead power plant - Google Patents
Method for conveying coal and refilling ash and slag in goafs of slapithead power plant Download PDFInfo
- Publication number
- CN101660426A CN101660426A CN200810013006A CN200810013006A CN101660426A CN 101660426 A CN101660426 A CN 101660426A CN 200810013006 A CN200810013006 A CN 200810013006A CN 200810013006 A CN200810013006 A CN 200810013006A CN 101660426 A CN101660426 A CN 101660426A
- Authority
- CN
- China
- Prior art keywords
- coal
- ash
- mine
- goafs
- slag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Loading Or Unloading Of Vehicles (AREA)
Abstract
The invention provides a method for conveying coal and refilling ash and slag in goafs of a slapithead power plant and solves technical problems that: no ideal mode is available to solve ash and slagfloor occupation and environmental pollution problems of coal fired power plants; goafs are formed in a coal mine after the coal mining, and the phenomenon, still common today, causes serious geological and ecological damages such as surface subsidence; and passive refilling of the goafs increases cost and consumes finite resources of clay, sand stone and the like. The key points of the method include: an upper branch of a tubular belt conveyer conveys coal at a well head or a coal storage yard of a mine to a coal bin of the slapithead power plant; and meanwhile, a lower branch of the tubularbelt conveyer reversely conveys ash and slag generated from coal-fired power generation back to a grout injection station at the well head of the mine to refill the ash and slag in the underground goafs from a grout injection system of the mine. The method has the advantage of solving the problems of surface subsidence, ash and slag floor occupation, environmental and atmosphere pollution and thelike at one time.
Description
Technical field
The present invention relates to the Coal Transport between near coal-mine power plant and the mine and utilize its backhaul cinder of electric power plant loopback grouting pipeline to be filled the activities of underground goaf.
Background technology
For a long time, in the production of state, inside and outside secondary energy sources, consumption structure, coal-burning power plant's proportion is very big, and the annual coal that consumes has tens tons.The extraction of on the one hand a large amount of coals will unavoidably form huge goaf, cause the face of land or underground ecological disruption; On the other hand, the lime-ash that stays behind the coal burning in the power generation process also brings pollution to environment and air quality except that will taking a large amount of soils.
The lime-ash of coal-burning power plant takes up an area of and environmental pollution problem fails to find more satisfactory good processing mode always, the alternative limestone of a small amount of lime-ash is produced cement, instead of clay is manufactured building brick though utilize, but be subjected to the restriction of various objective condition, can't fundamentally realize the comprehensive regulation; And the goaf that mine forms behind coal mining also can be found everywhere at present, causes serious geology ecological disruptions such as surface subsidence for a long time, as passive backfill, increases cost on the one hand, and the person also will consume resources such as limited clay or sandstone in addition.This has arrived instant stage.
Summary of the invention
The object of the present invention is to provide the method for coal conveying of a kind of near coal-mine power plant and lime-ash backfilling goaf, it utilizes the backhaul of transporting coal, cinder of electric power plant loopback grouting pipeline is filled underground goaf, fundamentally solve the problem of man made geologic hazards such as lime-ash occupation of land, contaminated environment and surface subsidence.
The object of the present invention is achieved like this: the top set of pipe conveyer is transported near coal-mine power plant coal bunker with the coal of mine well head or coal yard, the function of its top set is for carrying coal, simultaneously, utilize the condition of inferior division idle running, the lime-ash that produces behind the coal fired power generation is oppositely backhauled to mine well head slip casting station, and the grouting pipeline system of process mine is backfilling into underground goaf.Utilize pipe conveyer adhesive tape under operation condition to have round tubular feature of one's own, coal and lime-ash are in transportation under the closed state all the time, avoiding the coal dust environmental pollution.
The present invention compared with prior art, its advantage is: it is disposable to have solved surface subsidence, lime-ash takes up an area of and environment and air quality are brought problems such as pollution.
Description of drawings
Further specify the present invention below in conjunction with accompanying drawing.
Accompanying drawing is a system drawing of the present invention.
The specific embodiment
Ribbon conveyer 101 is given pipe conveyer 102 with the Coal Transport and the reprinting of mine or well head coal yard, utilize pipe conveyer adhesive tape under operation condition to have round tubular feature of one's own, coal is in transportation under the state of sealing all the time, under the prerequisite of avoiding the coal dust environmental pollution, coal is transported to power plant's coal store 3 with growing distance and stores and generating.Meanwhile, ribbon conveyer 103 and 104 is transported to ribbon conveyer 105 with the lime-ash the like waste material that stores in power plant ash storehouse 2 and the slag storehouse 1 respectively, and by the inferior division of its reprinting to pipe conveyer 102, utilize the backhaul of pipe conveyer to transport lime-ash to mine lime-ash transfer post 5, be transported to the lime-ash filling through common belt conveyor 106 again and prepare storehouse 4, lime-ash mixes with water after water seal drag conveyor 107 enters mine slip casting station 6, is filled in the underground goaf 7 by grouting pipeline again.
Claims (1)
1, the method for coal conveying of a kind of near coal-mine power plant and lime-ash backfilling goaf, it is characterized in that: the top set of pipe conveyer is transported near coal-mine power plant coal bunker with the coal of mine well head or coal yard, simultaneously, the lime-ash that inferior division produces after with coal fired power generation oppositely backhauls to mine well head slip casting station, is backfilling into underground goaf through the grouting pipeline system of mine.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200810013006A CN101660426A (en) | 2008-08-29 | 2008-08-29 | Method for conveying coal and refilling ash and slag in goafs of slapithead power plant |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200810013006A CN101660426A (en) | 2008-08-29 | 2008-08-29 | Method for conveying coal and refilling ash and slag in goafs of slapithead power plant |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101660426A true CN101660426A (en) | 2010-03-03 |
Family
ID=41788666
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200810013006A Pending CN101660426A (en) | 2008-08-29 | 2008-08-29 | Method for conveying coal and refilling ash and slag in goafs of slapithead power plant |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101660426A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2012155531A1 (en) * | 2011-05-17 | 2012-11-22 | 山东新煤机械设备股份有限公司 | Technology and equipment for separating coal and gangue and refilling gangue. |
CN109681267A (en) * | 2018-12-29 | 2019-04-26 | 吕梁学院 | Utilize the device and method of band-chain doubly-fed machine conveying mine paste body filling slurry |
-
2008
- 2008-08-29 CN CN200810013006A patent/CN101660426A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2012155531A1 (en) * | 2011-05-17 | 2012-11-22 | 山东新煤机械设备股份有限公司 | Technology and equipment for separating coal and gangue and refilling gangue. |
CN109681267A (en) * | 2018-12-29 | 2019-04-26 | 吕梁学院 | Utilize the device and method of band-chain doubly-fed machine conveying mine paste body filling slurry |
CN109681267B (en) * | 2018-12-29 | 2020-11-27 | 吕梁学院 | Device and method for conveying mine paste filling slurry by using belt-chain double-conveyer |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102155261B (en) | Paste combined filling method utilizing solid wastes of mine | |
CN102305069B (en) | Technology and equipment for separating coal and gangue and refilling gangue | |
CN102748071B (en) | Underground backfilling and transporting method for ground gangue of coal mine | |
WO2018045633A1 (en) | Consolidated solid strip backfill mining method for coal mine | |
AU2018376026B2 (en) | Microbial modification filling-based coal mining method | |
EA201270083A1 (en) | CREATING THE MINE STEM FOR THE UNDERGROUND MINE | |
CN103133034A (en) | Method and equipment for backfilling underground goaf with waste rock on well | |
CN104033152A (en) | Solid filling mining design method under building | |
CN202266260U (en) | Technical equipment for separating coal from gangue and backfilling gangue | |
Zhang et al. | INDUSTRIAL TESTS OF WASTE ROCK DIRECT BACKFILLING UNDERGROUND IN FULLY MECHANIZED COAL MINING FACE. | |
CN104791006A (en) | Filling technology for carrying out refilling on goaf | |
CN101660426A (en) | Method for conveying coal and refilling ash and slag in goafs of slapithead power plant | |
CN102434163A (en) | Method for mining coal through comprehensive mechanized solid filling | |
CN109519218B (en) | Method for filling goaf by utilizing aeolian sand dry-type filling net cage bearing body | |
CN101660368A (en) | Method for dumping ash and slag from power plants in open-pit dump | |
CN102716901A (en) | Method for disposing and reusing building waste nearby coal mine | |
CN216974901U (en) | Double-transportation single-filling hydraulic support | |
Yanli et al. | Underground backfilling technology for waste dump disposal in coal mining district | |
CN104453998A (en) | Coal mine solid filling coal mining ground material throwing system and technology | |
CN205002133U (en) | Conveniently clear up boiler of coal ash | |
CN202741419U (en) | Treatment and reuse system of construction waste near coal district | |
CN114412530A (en) | Double-transportation single-filling hydraulic support and using method thereof | |
CN206174998U (en) | Material conveying system is thrown to fly ash and waste rock | |
Ma et al. | The application research on backfill mining technology of gangue for coal pillar mining in Xingtai mining village | |
CN102276221A (en) | Dynamic gangue concrete filled beside gob-side entry retaining |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20100303 |