CN101651309A - 现场压实测试机械强度的直埋电力电缆保护管埋设方法 - Google Patents

现场压实测试机械强度的直埋电力电缆保护管埋设方法 Download PDF

Info

Publication number
CN101651309A
CN101651309A CN200810041609A CN200810041609A CN101651309A CN 101651309 A CN101651309 A CN 101651309A CN 200810041609 A CN200810041609 A CN 200810041609A CN 200810041609 A CN200810041609 A CN 200810041609A CN 101651309 A CN101651309 A CN 101651309A
Authority
CN
China
Prior art keywords
pipe
power cable
comb
direct
mechanical strength
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200810041609A
Other languages
English (en)
Inventor
肖川
刘克军
孙剑民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Construction Co Ltd
Original Assignee
Shanghai Baoye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Construction Co Ltd filed Critical Shanghai Baoye Construction Co Ltd
Priority to CN200810041609A priority Critical patent/CN101651309A/zh
Publication of CN101651309A publication Critical patent/CN101651309A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

本发明涉及直埋电力电缆保护管施工,尤其一种现场压实测试机械强度的直埋电力电缆保护管埋设方法,它包括:步骤一,根据现场施工排管深度,挖好基础并压实已开挖的基础底部;步骤二,排管排列,管底埋深50cm,固定排管的支架间距不超过2m;步骤三,以就地挖出的土来回填,并压实;步骤四,利用施工现场现有车辆或挖土机车,沿管线布置方向和垂直方向压过数次,并停留数分钟;步骤五,开挖回填土,露出排管,检察排管质量;步骤六,若排管纵向、横向未发现开裂现象,管子的横截面上未发现压扁现象,且管材接头弯曲度小于1%,则回填并结构层的施工;若发现排管受损,则重复步骤二至步骤五。本发明保证施工质量可靠,确保日后运行万无一失。

Description

现场压实测试机械强度的直埋电力电缆保护管埋设方法
技术领域
本发明涉及直埋电力电缆保护管施工,尤其涉及直埋电力电缆保护管机械强度测试方法。
背景技术
重型、多根电力电缆集中埋地敷设,大多设计为地下电缆遂道(电缆沟)、多层电力排管。
电缆沿电缆隧道通过时,对电缆的保护教好,这是因为其为钢筋混凝土结构,但占用地下空间,施工周期长。
多层电力排管一般安排在绿化带、人行道上,但在穿过道路时有较高的机械强度要求,由于道路各类车辆来往,往往在此出现电力电缆保护管压扁.破裂变形,机械损伤电力电缆,造成电力电缆短路、断路现象,产生用电事故,造成巨大损失。
作为商品的电力电缆保护管的机械强度性能是实验室内检测出的,未考虑实际现场安装质量,基础及回填土质等因数,不足以说明实际使用中的安全和可靠性能。目前又有各种材质的电力电缆保护管(如钢材、PVC、水泥加石棉等),尤其在多根,多层电力电缆保护管集中过路时,情况更为复杂,仅仅依靠实验室侧得的强度性能无法确保电力排管安装工程质量可靠、在日后运行中万无一失。
发明内容
本发明旨在解决埋地电力电缆保护管在日后路面重荷下,电力电缆保护管容易产生机械变形的问题,提供一种现场压实测试机械强度的直埋电力电缆保护管埋设方法。本发明是在施工过程中的一种经济的模拟现场测试方法,以保证施工质量可靠,确保日后运行万无一失。
一种现场压实测试机械强度的直埋电力电缆保护管埋设方法,它包括:
步骤一,根据现场施工排管深度,挖好基础并压实已开挖的基础底部;
步骤二,排管排列,管底埋深50cm-100cm,固定排管的支架间距不超过2m。
步骤三,以就地挖出的土来回填,并压实;
步骤四,利用施工现场现有车辆或挖土机车,沿管线布置方向和垂直方向压过数次,并停留数分钟;
步骤五,人工开挖回填土,暴露出排管,检察排管质量;
步骤六,若排管纵向、横向未发现开裂现象,管子的横截面上未发现压扁现象,且管材接头弯曲度小于1%,则回填并结构层的施工;
若发现排管受损,则重复步骤二至步骤五。
所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,其特征在于,所述步骤二的排管为3层*3孔,每孔由三根3m管或6m管利用接头连接而成。
所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,所述步骤三中回填高度为距管顶25-35mm。
所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,所述步骤四中的车辆或挖土机车重量不小于15吨,压实次数为2-4次,停留时间为3-5min。
所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,所述步骤六中的管材接头弯曲度为排管最大位移和管长之比乘以100%。
本发明在现场测直接测试,力求符合实际及经济要求。本发明通过现场检测当前施工的电力排管工程是否满足日后路面重荷下的机械强度。否则,查明原因(如电力保护管材质质量,施工的技术方案,施工方法等)及时整改。从而保证施工质量可靠,确保日后运行万无一失。
具体实施方式
下面,结合具体实施方式进一步说明本发明:一种现场压实测试机械强度的直埋电力电缆保护管埋设方法,是:
在电力排管施工中,根据现场施工排管深度,挖好基础并压实已开挖的基础底部。
排管排列3层*3孔(可根据实际设计的孔数和层数附设)。每孔由三根3m管连接而成(用3m管的管接头较6m管多,测试条件越恶劣,保险系数高)。管底埋深50cm-100cm。固定排管的支架间距不超过2m。
以就地挖出的土来回填,回填高度约为距管顶30cm左右,并压实,俗称土路基。(待压路机在路基上压整后才能进行结构层的施工。土路基时,管材受到的考验保险系数较高)。
利用施工现场现有车辆或挖土机车(15吨以上)沿管线布置方向和垂直方向压过2-4次,并停留3-5分钟。
人工开挖回填土,暴露出排管,检察排管质量。
若排管纵向、横向未发现开裂现象,管子的横截面上未发现压扁现象,且管材接头弯曲度小于1%,则回填并结构层的施工;
接头弯曲度为排管最大位移和管长之比乘以100%;
若发现排管受损,则重复步骤二至步骤五。

Claims (5)

1.一种现场压实测试机械强度的直埋电力电缆保护管埋设方法,其特征在于,它包括:
步骤一,根据现场施工排管深度,挖好基础并压实已开挖的基础底部;
步骤二,排管排列,管底埋深50-150cm,固定排管的支架间距不超过2m;
步骤三,以就地挖出的土来回填,并压实;
步骤四,利用施工现场现有车辆或挖土机车,沿管线布置方向和垂直方向压过数次,并停留数分钟;
步骤五,人工开挖回填土,暴露出排管,检察排管质量;
步骤六,若排管纵向、横向未发现开裂现象,管子的横截面上未发现压扁现象,且管材接头弯曲度小于1%,则回填并结构层的施工;
若发现排管受损,则重复步骤二至步骤五。
2.根据权利要求1所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,其特征在于,所述步骤二的排管为3层*3孔,每孔由三根3m管或6m管利用接头连接而成。
3.根据权利要求1所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,其特征在于,所述步骤三中回填高度为距管顶25-35mm。
4.根据权利要求1所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,其特征在于,所述步骤四中的车辆或挖土机车重量不小于15吨,压实次数为2-4次,停留时间为3-5min。
5.根据权利要求1所述的现场压实测试机械强度的直埋电力电缆保护管埋设方法,其特征在于,所述步骤六中的管材接头弯曲度为排管最大位移和管长之比乘以100%。
CN200810041609A 2008-08-12 2008-08-12 现场压实测试机械强度的直埋电力电缆保护管埋设方法 Pending CN101651309A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810041609A CN101651309A (zh) 2008-08-12 2008-08-12 现场压实测试机械强度的直埋电力电缆保护管埋设方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810041609A CN101651309A (zh) 2008-08-12 2008-08-12 现场压实测试机械强度的直埋电力电缆保护管埋设方法

Publications (1)

Publication Number Publication Date
CN101651309A true CN101651309A (zh) 2010-02-17

Family

ID=41673469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810041609A Pending CN101651309A (zh) 2008-08-12 2008-08-12 现场压实测试机械强度的直埋电力电缆保护管埋设方法

Country Status (1)

Country Link
CN (1) CN101651309A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535315A (zh) * 2012-01-10 2012-07-04 江苏建筑职业技术学院 混凝土路面板悬空的处理方法
CN107482538A (zh) * 2017-08-31 2017-12-15 国网山东省电力公司菏泽市定陶区供电公司 一种电缆直埋辅助装置
CN109149488A (zh) * 2018-09-14 2019-01-04 中铁第四勘察设计院集团有限公司 一种市域铁路管线布置结构和方法
CN112415603A (zh) * 2020-10-16 2021-02-26 山东大学 搭载在tbm刀盘上的激发极化电极探测装置、系统与方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535315A (zh) * 2012-01-10 2012-07-04 江苏建筑职业技术学院 混凝土路面板悬空的处理方法
CN102535315B (zh) * 2012-01-10 2015-01-21 江苏建筑职业技术学院 混凝土路面板悬空的处理方法
CN107482538A (zh) * 2017-08-31 2017-12-15 国网山东省电力公司菏泽市定陶区供电公司 一种电缆直埋辅助装置
CN107482538B (zh) * 2017-08-31 2019-07-26 国网山东省电力公司菏泽市定陶区供电公司 一种电缆直埋辅助装置
CN109149488A (zh) * 2018-09-14 2019-01-04 中铁第四勘察设计院集团有限公司 一种市域铁路管线布置结构和方法
CN112415603A (zh) * 2020-10-16 2021-02-26 山东大学 搭载在tbm刀盘上的激发极化电极探测装置、系统与方法

Similar Documents

Publication Publication Date Title
CN101963061B (zh) 一种铁路既有线地下箱涵的施工方法
KR20210130725A (ko) 보강장치 및 다량 수분 함유 자갈 지층 중 심층 피트 국소 냉동 보강 시공 방법
CN102912354B (zh) 地下管道系统用阴极保护系统
CN102734556B (zh) 一种电力排管的非开挖施工方法
CN110158649B (zh) 一种沉井下沉施工时邻近地下管线的施工方法
CN109798396B (zh) 一种复杂地层的长距离大口径混凝土管人工顶进工艺
CN106641440A (zh) 一种横向穿越铁路线地下管道顶进施工方法
CN103711056B (zh) 钢质工具式临时施工道路及其施工方法
CN107191675A (zh) 铁路站场电化区段管道铺设施工工法
CN111173027A (zh) 一种既有管线加固保护的施工方法
CN101575859B (zh) 地下连续墙防渗接头及其施工方法
CN101651309A (zh) 现场压实测试机械强度的直埋电力电缆保护管埋设方法
CN201538975U (zh) 地下连续墙防渗接头
CN105804048A (zh) 一种软弱地基排水板加固方法
CN1242194C (zh) 铺设大口径管道下沟施工方法
CN113324099A (zh) 道路管线保护系统
CN210163910U (zh) 一种管道顶管接收井基坑支护结构
Moore Large-scale laboratory experiments to advance the design and performance of buried pipe infrastructure
CN209798563U (zh) 一种装配式涵洞抗浮结构
KR101682541B1 (ko) 암거 횡단 관로 매설구조물 및 이를 이용한 관로 매설방법
CN215172756U (zh) 道路管线保护系统
CN106247007B (zh) 远距离大直径工业管道自重变位下置铺设直埋施工方法
KR100767747B1 (ko) 배전분야 특고압 케이블 설치구조물
CN111042841A (zh) 一种隧道防排水施工工艺
CN104179220B (zh) 一种预应力混凝土柔性承插口抗渗漏方涵

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20100217