CN101644235A - Pipeline wind driven generation - Google Patents

Pipeline wind driven generation Download PDF

Info

Publication number
CN101644235A
CN101644235A CN200910166052A CN200910166052A CN101644235A CN 101644235 A CN101644235 A CN 101644235A CN 200910166052 A CN200910166052 A CN 200910166052A CN 200910166052 A CN200910166052 A CN 200910166052A CN 101644235 A CN101644235 A CN 101644235A
Authority
CN
China
Prior art keywords
wind
blower
pipeline
wind driven
circular pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910166052A
Other languages
Chinese (zh)
Inventor
周东辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN200910166052A priority Critical patent/CN101644235A/en
Publication of CN101644235A publication Critical patent/CN101644235A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Wind Motors (AREA)

Abstract

The invention relates to permanent power generation realized by sequentially arranging wind driven generators with same radius in an indefinitely long convolution sealing tube under the action of windpower of an air blower. At present, wind driven generators are popular all over the world, but a defect of wind power generation is that wind driven generators can not work if no wind exists. The dream of no-wind power generation can be realized by combining a sealing convolution circular pipeline with an air blower to help the wind driven generator. In addition, structure is simple, and cost isfar lower than needed investment of the existing wind power generation. The sealing convolution circular pipeline is formed by a semicircle cement pipeline and a semicircle metal cover top, wherein, the semicircle cement pipeline is a carrier of the generator combination. The invention has the beneficial effects that the invention can be used without external energy, can work in all seasons, and solves the awkward situation that wind driven generators can not work if no wind exists. The wind driven generator has simple structure and low cost and construction cost and is convenient to replace,which can be finished instantaneously.

Description

Pipeline wind driven generation
Technical field:
The present invention relates to a kind of the identical wind-driven generator of radius is installed in the endless sealing gyrotron successively, under the effect of blower output gas flow, realize generating.
Technical background:
The fashionable now world of wind-power electricity generation is because its environmental protection is subjected to people's favor very much.But wind-power electricity generation a fly in the ointment is calm weather have to be deeply aware of one's own helplessness when faced with a great task, and is at a complete loss as to what to do.
Perpetuum mobile is closed down nearly 200 years but by the machine of modern science and a lot of people's approvals by forefathers.It also is the machine of being unreconciled to abandon in the ideal with going into more.Why be referred to as ideal and be because its be it is believed that can the external energy and create the machine of the unending energy of output.
People have imagined a lot of methods and have attempted to finish perpetuum mobile, still, have all failed.Therefore scientist reaches a conclusion according to law of conservation of energy: perpetuum mobile is the machine that impossible realize, may exist never.Reason is exactly: energy can not produce without foundation, can not eliminate without foundation, and it can only be converted into another kind of form from a kind of form, or transfers to another object from an object, and its total amount remains unchanged in the process that transforms or shift.This conclusion obtains the extensive support of World Science circle and he is write in the textbook, allows children know not time waste in the middle of the illusion of research perpetuum mobile.
, science is improving, and people have had new discovery again by practice: renewable energy sources.Since the energy is renewable, just mean that perpetuum mobile is to make successful machine.
Renewable energy sources comprises " water energy " and " wind energy ".
" water " is not the energy, but the water that flows is " water energy " with regard to produce power, just can be referred to as the energy, and is acknowledged as " renewable energy sources ".
" air " is not the energy, but flow air forms wind with regard to produce power, is " wind energy ", just can be referred to as the energy, and is acknowledged as " renewable energy sources ".
Be that the energy just can produce power.
Be that the energy just can pass through a particular machines output mechanical energy.Mechanical energy just can be done work, for people utilize, for the mankind benefit.
Summary of the invention:
Little experiment:
Get a very long very long plastic straw, put the mouth for one, the other end is hand held and be placed in the palm of the hand.We can feel that one air-flow is impacting the palm of the hand when of pipe blows with mouth when us, and are not free poor.Blow and feel well greatly, palm of the hand sensation wind is big.
We manually build a circular pipe now, also are very long very long, and we install a blower at an end of pipeline and blow in pipeline, and at this moment we can see simultaneously that the other end of pipeline can stir up a cloud of dust.If we put into a lot of light body objects of sheet less than pipe diameter at this end of blower, start blower for a moment, we can see that these objects all fly out from the other end.
Thing is very simple, if our wind-driven generator identical numerous blade radius and that be slightly less than the pipeline radius is fixedly mounted in the pipeline successively in the same way, we can see that each wind-driven generator all can work normally to open blower, without exception.
Thing is desirable even so, and still, the resistance that the wind of blower output should overcome blade also will overcome the resistance of air in nature outside the output terminal, and power must be under some influence.
How to improve the power of blower?
Imagine: two ports of pipeline are linked together realize sealing, what impression can we obtain again so? we can see that all wind-driven generators are all in normal work, without exception.Because there has not been the air port of output terminal, there has not been influence to surrounding environment, also increased the power of blower simultaneously.Reason just is: the front end of blower forms zone of high pressure promotion inner air tube and flows, and the blower rear end forms low pressure area, and inner air tube is played sucking action, and both complement each other, and inner air tube is realized Infinite Cyclic under the effect of blower.So closed conduit is more far better than non-tight pipeline effect theoretically for clump.
We install ammeter, voltmeter and electric consumer to all generators.We can see all generators generate electricity can summation considerably beyond blower institute consuming electric power.At this moment press the required electric weight of blower and can switch part generator electricity wherein and give the blower electricity consumption, cut off the original extraneous power supply of blower.Other generator connects all consumers and they is started working.At this moment the wind-force perpetuum mobile in ideal has been born.
Sealing the circular pipe that circles round cooperates blower to help wind-driven generator to realize the dream of calm generating.And its is simple in structure, and cost, has been cancelled more high-altitude and set up facility though it needs a large-scale ventilation duct well below the required investment of present wind-power electricity generation.In order to increase generating capacity, the generator in the pipe is installed compactness in regular turn, has also saved a large amount of lands used.
Structure:
The wind-force perpetuum mobile is made up of circle round pipeline, wind-driven generator assembly, blower etc. of: closed cylinder.
The wind-driven generator assembly:
Form by blade, booster engine, generator, support, bearing etc.
Support: the rectangular steelframe, card is placed on the semicircle concrete duct.The center of support is the center of circle of circular pipe, is installed with bearing in the center portion of support, and what bearing was firm is sleeved on the generator arbor, guarantee not yaw of blade.
Generator: select corresponding direct current of power or alternator by the energy that blade produced.
Booster engine: be the machinery of guaranteeing the required constant rotational speed of alternator.
It is the machinery that improves the DC generator generating capacity.
Seal the circular pipe that circles round:
By semicircle concrete duct and the combination of semicircle metal caping.
Semicircle concrete duct is the carrier of generator set combination, and its diameter decides by the selected blade radius of blower output wind energy size.The rectangular recess that mounting bracket is arranged in the equidistant design in the diameter position on pipeline both sides.The place that blower is installed will have the sealing machine room.
Maintenance for convenience, pipeline should build up full-open type, and the semicircle caping is made with iron plate or other hard section bar in top, can arbitrarily design opening ways.
Select spacious higher no ponding location, the reinforced concrete pipeline is built in ditching, and ditch soil can be used as outside basis.For the pipeline of saving the area can be designed to two pass or multiple tracks is reciprocating type.
Working principle:
Air when blower is started working in the front-end pipelines of blower is compressed and produces the zone of high pressure, and promotes rapidly that air flows in the shop.And produce low pressure area simultaneously at the other direction of blower, therefore,, make the air in the pipeline form circulation at a high speed for condition has been created in the decompression of zone of high pressure.Though the high-pressure air of blower output is subjected to the resistance layer by layer of blade, low pressure area is that the flow at high speed of inner air tube plays the effect of adding fuel to the flames again, and therefore, how long pipeline has can not weaken the speed that inner air tube flows.
Beneficial effect:
Do not need extra power and the beneficial forever world.
But all weather operations has solved the calm difficult situation of heaving a sigh of wind-power electricity generation.
Simple in structure, cheap, cost is low.
It is convenient to change, and moment gets final product.
Deficiency:
Though maintenance belongs to transient operation, also generating constitutes influence to integral body.
Description of drawings:
Fig. 1, overlook the wind-force perpetuum mobile integrally closed circular pipe schematic representation that circles round.1 circular pipe, 2 blower rooms.
Fig. 2, face the wind-force perpetuum mobile integrally closed circular pipe schematic representation that circles round.1 circular pipe, 2 blower rooms.
Fig. 3, side-looking wind-force perpetuum mobile seal the circular pipe schematic representation that circles round.1 circular pipe, 2 blower rooms.
Fig. 4, overlook the generator support schematic representation.3 supports
Fig. 5, face the generator support schematic representation.4 carriage center bearings.
Fig. 6, side-looking generator support schematic representation.
Circle round circular pipe and generator is installed, the blower scheme of installation of Fig. 7, part wind-force perpetuum mobile sealing.Wherein: 1 circular pipe, 2 blower rooms, 3 supports, 5 generators, 6 rotation blades, 7 blowers.Arrow is represented the air current flow direction.
Embodiment:
The selection of blower 7:
The blower 7 optional chip blowers that get rid of leaves require output power big, and promptly the wind-force of Chan Shenging is strong, and wind speed is fast.Powerful blower can drive more powerful generator for electricity generation.
The installation of blower 7:
On the base that is installed in reinforced concrete that blower 7 will be firm, the exhaust outlet of blower 7 and circular pipe 1 must be tight in conjunction with loosening.Blower 7 will be connected to interim external power circuit and be connected to the permanent circuit that is connected with the automatically controlled version of perpetuum mobile again.
The selection of blade:
The wind speed that is produced by blower 7 and the flow of wind are selected suitable rotation blade 6.For improving the diameter of the restriction circular pipe 1 that wind speed will be suitable, the blade 6 that therefore drives generator 5 rotations will adopt the blade of the property that is fit to pipeline environment.Blade 6 had both required the intact of self, and was sturdy and durable, possessed again to improve rotational speed as far as possible and increase rotating energy, so that adapt to generator 5 required rotating speeds and improve generator 5 output powers.
By the basis, bottom that the requirement design and the building of blade 6 turning radius are sealed the semicircle reinforced concrete ventilation duct 1 of the cylinder that circles round, the rectangular recess of mounting bracket 3 is arranged in the equidistant respectively design in the diameter position of semicircle pipeline circular arc.The top of pipeline is the semicircle buckle closure of metal.It is convenient to require to open, and helps the maintenance and the replacing of equipment.
Article one, circle round pipeline 1 or ventilation duct of sealing is exactly a perpetuum mobile.Therefore, the length of ventilation duct 1 will decide according to the size of plant area, and a blower 7 does not drive 5 generatings of too many generator.Purpose is to consider the convenience of maintenance.Because the fault of every power generating equipment that pipeline is 1 li is got rid of the normal operation that all can influence full machine.
The installation of alternator assembly:
Alternator assembly comprises support 3, generator 5, blade 6.
The two ends of support be rectangle and the concrete duct radius on groove be complementary, reach closely loosening after the installation.So be placed on the intact alternator assembly of assembling in the groove just passable by same direction card.The transmission pressure of generator is connected outside panel and each consumer from the eyelet that designs.
The installation of top cover:
Top cover is the top of circular seal pipeline 1, and its design is very important.
The flexibility of opening is guaranteed in arbitrarily design and installation of top cover, but must guarantee the sealing of pipeline, guarantees the expansivity of opening to guarantee that the dismounting of alternator assembly is easy to maintenance.Certainly, design is handled proper with electric power, can guarantee safety and quick.
The startup of wind-force perpetuum mobile:
Check that each installation is intact, connect the interim power supply of blower 7, the wind-force perpetuum mobile begins proper functioning.Cut off the interim power supply of blower 7 after perpetuum mobile is working properly, and connects the power circuit switch of wind-force perpetuum mobile rapidly, arrive this, an intact wind-force perpetuum mobile has been born.

Claims (4)

1, a kind of wind-force perpetuum mobile, form by circle round circular pipe, wind-driven generator assembly, blower etc. of circular pipe or sealing, it is characterized in that many wind-driven generator assemblies by support in order, equidistantly, card is placed on circular pipe or sealing and circles round in the circular pipe in the same way, under the airflow effect of blower output, realize generating, and can blower continue to finish permanent work with self generating electricity.
2, wind-force perpetuum mobile according to claim 1 is characterized in that circular pipe is an endless, and many wind-driven generator assemblies are installed in order in the pipe, at an end of pipeline high-power blower is installed.
3, wind-force perpetuum mobile according to claim 1 is characterized in that sealing the circular pipe that circles round is endless, and many wind-driven generator assemblies are installed in the pipe in order, and any place in pipeline is equipped with high-power blower.
4, wind-force perpetuum mobile according to claim 1 is characterized in that support is the carrier of wind-driven generator assembly, is that card is placed on the special-purpose member in the circular pipe.
CN200910166052A 2009-08-03 2009-08-03 Pipeline wind driven generation Pending CN101644235A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910166052A CN101644235A (en) 2009-08-03 2009-08-03 Pipeline wind driven generation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910166052A CN101644235A (en) 2009-08-03 2009-08-03 Pipeline wind driven generation

Publications (1)

Publication Number Publication Date
CN101644235A true CN101644235A (en) 2010-02-10

Family

ID=41656249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910166052A Pending CN101644235A (en) 2009-08-03 2009-08-03 Pipeline wind driven generation

Country Status (1)

Country Link
CN (1) CN101644235A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963812A (en) * 2015-06-26 2015-10-07 陈健伟 Wind power generation device
CN105736070A (en) * 2016-04-12 2016-07-06 张洪延 Power generation device based on heat transmission device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963812A (en) * 2015-06-26 2015-10-07 陈健伟 Wind power generation device
CN105736070A (en) * 2016-04-12 2016-07-06 张洪延 Power generation device based on heat transmission device

Similar Documents

Publication Publication Date Title
CN201090372Y (en) Multilevel wind motor
CN206368772U (en) With reference to the wind power generation plant of ventilating fan
CN200993078Y (en) Wind collecting device for wind-force generator
WO2007071120A1 (en) Wind-collecting device for a wind generator
CN101644235A (en) Pipeline wind driven generation
CN201827023U (en) Blind type vertical shaft wind driven generator
CN203560041U (en) Wind power generation unit for exhaust fan
CN201943894U (en) Combination of wind-driven generator and air-condition compressor
CN201358891Y (en) Roof wind-force power-generation device
CN2781026Y (en) Wind-power, hyraulic energy gathering generating set
CN204627860U (en) Honeycomb wind-driven generator
CN104234926A (en) High-efficiency air barrel generation method and system
CN200940913Y (en) Roof sucking ventilator
CN102650264A (en) Parallel matrix integrated wind power generation system
CN208169052U (en) A kind of blast cap power generator
CN203248313U (en) Novel wind driven generator
CN202325986U (en) Multi-section multistage supercharging power generator by utilizing pipe compressed airflow as power
CN201771679U (en) Pneumatic light compensation generating device
CN201045330Y (en) Air energy electric generating apparatus
CN201050445Y (en) Energy-saving device
CN201474856U (en) Direct-pushing type impeller for wind-power and water-power generator
CN103527415A (en) Building distribution combined type wind generating set
CN102312785A (en) Pneumatic light complementary power generation device
CN201318250Y (en) Wind generator
CN201771674U (en) Dual powered blower

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20100210