CN101644160A - 高地应力软岩卸压施工方法 - Google Patents

高地应力软岩卸压施工方法 Download PDF

Info

Publication number
CN101644160A
CN101644160A CN200910062525A CN200910062525A CN101644160A CN 101644160 A CN101644160 A CN 101644160A CN 200910062525 A CN200910062525 A CN 200910062525A CN 200910062525 A CN200910062525 A CN 200910062525A CN 101644160 A CN101644160 A CN 101644160A
Authority
CN
China
Prior art keywords
hole
construction
anchor
concrete
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910062525A
Other languages
English (en)
Other versions
CN101644160B (zh
Inventor
陈卫忠
田洪铭
郭小红
乔春江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Institute of Rock and Soil Mechanics of CAS
Original Assignee
Wuhan Institute of Rock and Soil Mechanics of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Institute of Rock and Soil Mechanics of CAS filed Critical Wuhan Institute of Rock and Soil Mechanics of CAS
Priority to CN2009100625257A priority Critical patent/CN101644160B/zh
Publication of CN101644160A publication Critical patent/CN101644160A/zh
Application granted granted Critical
Publication of CN101644160B publication Critical patent/CN101644160B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种高地应力软岩卸压施工方法,其步骤是:A.锚喷支护施工,锚喷支护施工必须紧跟掌子面,清除危岩;B.泡沫板挂设,进行聚苯乙烯泡沫板挂设施工;C.仰拱开挖及U型钢架设,衬砌成环,对钢架间隙进行喷射混凝土复喷;D.仰拱回填,U型钢架设完成后,进行仰拱回填施工,对混凝土进行养护;E.防水隔离层施工,在隧道收敛速率趋于稳定后,进行防水隔离层施工;F.二次衬砌施工,在防水隔离层施工完成后,进行二次衬砌施工;G.预应力锚索施工,通过现场放样,确定锚索孔位以及钻孔方向,对孔位位置进行清理。该施工方法对于控制高地应力下软岩隧道大变形效果明显,该方法简便易行,操作简单,效果明显,成本相对较低。

Description

高地应力软岩卸压施工方法
技术领域
本发明设计涉及公路隧道施工技术领域,更具体涉及一种高地应力软岩卸压施工方法。
背景技术
随着我国西部交通基础设施特别是高等级公路建设的不断发展,穿越高地应力区的软岩隧道也越来越多。高地应力软岩隧道围压不仅变形大,而且力学性质具有高度的非线性。目前,常规的施工工法很难适应软岩隧道大变形的要求,施工过程中很容易出现衬砌的开裂和破坏,需要不断的修复施工,这不仅严重的影响施工进度,增加施工成本,而且给施工造成了安全隐患,隧道的施工质量也难以保证。因此急需发明一种成本相对较低,易于操作和控制,并适用于高地应力软岩隧道的卸压施工工法。
发明内容
本发明的目的是在于提供了一种高地应力软岩卸压施工方法,该方法易行,操作简单,效果明显,成本相对较低。
为了实现上述的目的,本发明采用以下技术方案:
一种高地应力软岩卸压施工方法,其步骤是:
1、锚喷支护施工,锚喷支护施工必须紧跟掌子面。清除危岩,应用空压机产生的高压风将开挖面的粉岩和杂物清理干净,按照设计要求,沿洞周布放样锚杆安装位置,用钻机沿洞径方向钻孔,当钻孔达到预定深度(4.4m到4.6m)后,用高压风将孔吹干净,安装锚杆到预定位置,安装SD-02型隧道推力止浆塞,用注浆机向钻孔内注浆,注浆要一次完成,当注浆完成后立即封口。当锚杆抗拔力达到50KN后,将在洞外预先焊接绑扎成片钢筋网,运至洞内铺设,并与锚杆、钢支撑焊牢,钢筋网与围岩间距3~4cm。按先墙后拱,先下后上的顺序,向开挖面喷浆,在初喷混凝土终凝以后,进行复喷,复喷2~3次。
2、泡沫板挂设,当锚喷支护的强度达到设计强度80%时,进行聚苯乙烯泡沫板挂设施工。为保证施工安全,挂设施作点距爆破面应在150m,距灌筑二次衬砌处20m。施工前,要测量开挖断面,对欠挖部位加以凿除,对喷射混凝土表面凹凸显著部位分层喷射找平,将外露的锚杆头齐根切除,并用水泥砂浆抹平。在加工场地将泡沫板切割成块(2m×3m)。按照设计,在隧道内测量放样确定泡沫板安装位置,泡沫板采用加长膨胀螺丝(6mm×350mm)固定,先固定底部,然后固定顶部,安装从下到上分块依此进行。
3、仰拱开挖及U型钢架设,为尽早使衬砌成环,仰拱的施工要尽早进行。仰拱开挖,采用挖机施工,每次施作12m,紧跟开挖掌子面。仰拱开挖完成后随即进行U型钢架设。按照设计尺寸在平面上放出1∶1大样,并把整榀钢架分成10到12个单元,在加工场将各单元焊接完成,并焊好连接法兰,法兰的焊接要准确周正,孔眼对应。测量确定隧道中垂线,架立钢拱架,复核钢拱架倾斜度小于2°,钢架尽可能与泡沫板贴靠紧密(空隙小于5cm为宜),两侧底脚使用垫块支垫牢固。如基底松软则安装时应设置垫板,为防止支撑受荷载下沉,必要时,先用混凝土加固基底。法兰之间对正,用螺栓连接牢固,钢架与纵向钢筋焊牢,钢架与钢架之间用φ22螺纹钢焊接连成整体,起到整体支护效果。上述操作完成后,对钢架间隙进行喷射混凝土复喷。
4、仰拱回填,U型钢架设完成后,立即近行仰拱回填操作。回填采用模铸混凝土,用运输车将混凝土运送到指定位置,直接用输送泵将混凝土泵送至立好的模板内,然后对混凝土进行适当的养护,待混凝土强度达到要求之后,拆除模板。
5、防水隔离层施工,隧道收敛变化率趋于稳定后,进行防水隔离层施工。防水隔离层采用聚氯乙烯PVC板。施工前,切除外露的膨胀螺丝螺杆,以免膨胀螺丝将防水隔层割破。测量定位PVC板的架设位置,安设定位PVC板所用的铁丝网,将洞外预先焊接完成的PVC板安装到指定位置,并用螺钉将其固定,用焊接塑料板搭接缝,并对焊缝进行补强。
6、二次衬砌施工,在防水隔离层施工完成后,进行二次衬砌施工。通过测量放样,确定模板的架设位置,将台车移动到指定位置。将模板清理干净,根据放样的控制点架设堵头模板。用混凝土搅拌车将混凝土运送到指定浇注地点,进行混凝土浇筑。浇注从下往上进行,浇注的过程中要不断的分层振捣。每环混凝土拱顶预埋φ57×3注浆钢管,当衬砌混凝土强度达到设计强度80%后,用与衬砌同标号的混凝土进行拱顶回填灌浆。当拱顶混凝土强度达到设计强度的75%以上时,拆除堵头模具,拆模时,要注意保护混凝土角隅及表面的保护。
7、预应力锚索施工,根据设计要求,通过现场放样,确定锚索孔位以及钻孔方向,对孔位位置进行清理,采用潜孔冲击式钻机,为预应力锚索打孔,钻孔深度应超出设计值0.5m,钻孔结束后,拔出钻杆钻头,用一根聚乙烯管复核孔深,并用高压风清孔,然后拔出聚乙烯管。再用高压风清孔一次,然后放入锚索,锚索外套上定位片使锚索居中,应防止锚索扭压、弯曲、注浆管应随锚索一同入孔,注浆管头部距孔底5~10cm,锚索定位止浆环到达孔口时,停止推送,再检查一遍,排气管是否畅通。然后锚固段注浆,采用排气注浆,砂浆由下倾孔的孔底注入,空气由锚索孔排出。上倾和水平孔砂浆由孔口注入,空气压向孔底,再进入排气管排出孔外,注浆压力0.4~0.6MPa,中砂过筛,添加HSA高效速凝剂,砂浆搅拌机搅拌均匀,浆液在初凝之前用完,并不得混入杂物,注浆到锚固段注满后即停止。立模现浇锚墩,锚墩中部应按设计钻孔倾角预埋塑料管形成孔道,对现浇锚墩进行必要的养护。锚墩及砂浆达到70%强度后,进行初张拉,待锚墩混凝土达到100%强度后,进行末张拉,为确保预应力部分损失后不低于设计值,应进行超张拉。张拉完成后,通过预留注浆管,管口距原砂浆面30cm,进行封孔注浆,孔中的空气由设在定位止浆环处的排气管排出,要求孔中注满浆液,然后从锚具量起留5cm钢铰线,用錾截子去多余部分,外覆8cm厚的细石混凝土保护层。
本发明与现有技术相比,具有以下优点和效果
1、采用预应力锚索来控制高地应力软岩隧道的底臌,工艺成熟,效果明显。
2、采用聚苯乙烯泡沫板作为预留变形层,工艺简单、操作方便,对操作人员的技术素质要求也不高,不需要专业培训,整个操作程序简单快捷。
3、该方法简便易行,操作简单,效果明显,成本相对较低。
附图说明
图1衬砌横断面图
图2泡沫板安装示意图
其中:1-砂浆锚杆、2-预应力锚索、3-喷射混凝土、4-聚苯乙烯泡沫板、5-防水隔离层、6-U型钢支架、7-连接法兰、8-二次衬砌、9-仰拱、10-膨胀螺丝。
具体实施方式
下面结合附图对本发明作进一步详细描述:
高地应力软岩隧道卸压工法原理为:针对高地应力软岩隧道大变形的特点,利用预应力锚索来控制隧道的仰拱上升,利用泡沫板来吸收隧道较大的流变变形。
一种高地应力软岩卸压施工方法,其具体的施工步骤如下:
1、锚喷支护施工,锚喷支护施工必须紧跟掌子面。清除危岩,应用高压风将开挖面的粉岩和杂物清理干净,按照设计要求,沿洞周布放样锚杆1的安装位置,用钻机沿洞径方向钻孔,当钻孔达到预定深度后,用高压风将孔吹干净,安装锚杆1到预定深度(4.4m到4.6m),安装SD-02型隧道推力止浆塞,用注浆机向钻孔内注浆,注浆要一次完成,当注浆完成后封口。当锚杆1抗拔力达到50KN后,将在洞外预先焊接绑扎成片钢筋网,运至洞内铺设,并与锚杆1焊牢,钢筋网与围岩间距3~4cm。按先墙后拱,先下后上的顺序,向开挖面喷浆,在初喷混凝土3终凝以后,进行复喷,复喷2~3次。
2、泡沫板4挂设,当喷射混凝土3强度达到设计强度80%时,进行聚苯乙烯泡沫板4挂设施工。为保证施工安全,挂设施作点距爆破面应在150m,距灌筑二次衬砌8处20m。施工前,要测量开挖断面,对欠挖部位加以凿除,对喷射混凝土表面凹凸显著部位分层喷射找平,将外露的锚杆1杆头齐根切除,并用水泥砂浆抹平。在加工场地将泡沫板切割成块(2m×3m)。按照设计,在隧道内测量放样确定泡沫板4安装位置,泡沫板采用加长膨胀螺丝10(6mm×350mm)固定,先固定底边,然后固定顶部,安装从下到上分块依此进行。
3、仰拱9开挖及U型钢6架设,为尽早使衬砌成环,仰拱9的施工要适时进行。仰拱9开挖,采用挖机施工,每次施作12m,紧跟开挖掌子面。仰拱开挖完成后随即进行U型钢6架设。按照设计尺寸在平面上放出1∶1大样,并把整榀钢架分成10到12个单元,在加工场将各单元焊接完成,并焊好连接法兰7,法兰的焊接要准确周正,孔眼对应。测量确定隧道中垂线,架立钢拱架6,复核钢拱架6倾斜度小于2°,钢架6尽可能与泡沫板4贴靠紧密(空隙小于5cm为宜),两侧底脚使用垫块支垫牢固。如基底松软则安装时应设置垫板,为防止支撑受荷载下沉,必要时,先用混凝土加固基底。法兰7之间对正,用螺栓连接牢固,钢架与纵向钢筋焊牢,钢架与钢架之间用φ22螺纹钢焊接连成整体,起到整体支护效果。上述操作完成后,对钢架间隙进行喷射混凝土复喷。
4、仰拱9回填,U型钢6架设完成后,立即近行仰拱9回填施工。回填采用模铸混凝土,用运输车将混凝土运送到指定位置,直接用输送泵将混凝土泵送至立好的模板内,然后对混凝土进行适当的养护,待混凝土强度达到要求之后,拆除模板。
5、防水隔离层5施工,隧道收敛速率趋于稳定后,进行防水隔离层5施工。防水隔离层采用聚氯乙烯PVC板。施工前,切除外露的膨胀螺丝10螺杆,以免膨胀螺丝将防水隔层割破。测量定位防水隔离层5的架设位置,安设定位防水隔离层5所用的铁丝网,将洞外预先焊接完成的防水隔离层5安装到指定位置,并用螺钉将其固定,用焊接塑料板搭接缝,并对焊缝进行补强。
6、二次衬砌8施工,在防水隔离层5施工完成后,进行二次衬砌8施工。通过测量放样,确定模板的架设位置,将台车移动到指定位置。将模板清理干净,根据放样的控制点架设堵头模板。用混凝土搅拌车将混凝土运送到指定浇注地点,进行混凝土浇筑。浇注从下往上进行,浇注的过程中要不断的分层振捣。每环混凝土拱顶预埋φ57×3注浆钢管,当衬砌混凝土强度达到设计强度80%后,用与衬砌8同标号的混凝土进行拱顶回填灌浆。当拱顶混凝土强度达到设计强度的75%以上时,拆除堵头模具,拆模时,要注意保护混凝土角隅及表面的保护。
7、预应力锚索2施工,根据设计要求,通过现场放样,确定锚索2孔位以及钻孔方向,对孔位位置进行清理,采用潜孔冲击式钻机,为预应力锚索2打孔,钻孔深度应超出设计值0.5m,钻孔结束后,拔出钻杆钻头,用一根聚乙烯管复核孔深,并用高压风清孔,然后拔出聚乙烯管。再用高压风清孔一次,然后放入锚索2,锚索2外套上定位片使锚索2居中,应防止锚索2扭压、弯曲、注浆管应随锚索2一同入孔,注浆管头部距孔底5~10cm,锚索定位止浆环到达孔口时,停止推送,再检查一遍,排气管是否畅通。然后,锚固段注浆,采用排气注浆,砂浆由下倾孔的孔底注入,空气由锚索孔排出。上倾和水平孔砂浆由孔口注入,空气压向孔底,再进入排气管排出孔外,注浆压力0.4~0.6MPa,中砂过筛,添加HSA高效速凝剂,砂浆搅拌机搅拌均匀,浆液在初凝之前用完,并不得混入杂物,注浆到锚固段注满后即停止。立模现浇锚墩,锚墩中部应按设计钻孔倾角预埋塑料管形成孔道,对现浇锚墩进行必要的养护。锚墩及砂浆达到70%强度后,进行初张拉,待锚墩混凝土达到100%强度后,进行末张拉,为确保预应力部分损失后不低于设计值,应进行超张拉。张拉完成后,通过预留注浆管,管口距原砂浆面30cm,进行封孔注浆,孔中的空气由设在定位止浆环处的排气管排出,要求孔中注满浆液,然后从锚具量起留5cm钢铰线,用錾截子去多余部分,外覆8cm厚的细石混凝土保护层。

Claims (1)

1、一种高地应力软岩卸压施工方法,其步骤是:
A、锚喷支护施工,锚喷支护施工必须紧跟掌子面,清除危岩,用高压风将开挖面的粉岩和杂物清理干净,沿洞周布放样锚杆(1)的安装位置,用钻机沿洞径方向钻孔,钻孔达到预定深度后,用高压风将孔吹干净,安装锚杆(1)到预定深度4.4m到4.6m,安装SD-02型隧道推力止浆塞,用注浆机向钻孔内注浆,注浆一次完成,注浆完成后封口,锚杆(1)抗拔力达到50KN后,将在洞外预先焊接绑扎成片钢筋网,运至洞内铺设,并与锚杆(1)焊牢,钢筋网与围岩间距3~4cm,按先墙后拱,先下后上的顺序,向开挖面喷浆,在初喷混凝土(3)终凝以后,进行复喷,复喷2~3次;
B、泡沫板(4)挂设,喷射混凝土(3)强度达到80%,进行聚苯乙烯泡沫板(4)挂设施工,挂设施作点距爆破面在150m,距灌筑二次衬砌(8)处20m,施工前,测量开挖断面,对欠挖部位加以凿除,对喷射混凝土表面凹凸部位分层喷射找平,将外露的锚杆(1)杆头齐根切除,并用水泥砂浆抹平,在加工场地将泡沫板切割成块2m×3m,在隧道内测量放样确定泡沫板(4)安装位置,泡沫板采用加长膨胀螺丝(10)固定,先固定底边,然后固定顶部,安装从下到上分块依此进行;
C、仰拱(9)开挖及U型钢(6)架设,衬砌成环,仰拱(9)的施工进行,仰拱(9)开挖,采用挖机施工,每次施作12m,紧跟开挖掌子面,仰拱(9)开挖完成后进行U型钢(6)架设,在平面上放出1∶1大样,并把整榀钢架分成10到12个单元,在加工场将各单元焊接完成,并焊好连接法兰(7),法兰的焊接要准确周正,孔眼对应,测量确定隧道中垂线,架立钢拱架(6),复核钢拱架(6)倾斜度,钢架与泡沫板(4)贴靠紧密,两侧底脚使用垫块支垫牢固,基底松软安装时设置垫板,法兰(7)之间对正,用螺栓连接牢固,钢架与纵向锚杆焊牢,钢架与钢架之间用φ22螺纹钢焊接连成整体,对钢架间隙进行喷射混凝土复喷;
D、仰拱(9)回填,U型钢(6)架设完成后,进行仰拱(9)回填施工,回填采用模铸混凝土,用运输车将混凝土运送到指定位置,直接用输送泵将混凝土泵送至立好的模板内,对混凝土进行养护;
E、防水隔离层(5)施工,在隧道收敛速率趋于稳定后,进行防水隔离层(5)施工,防水隔离层(5)采用聚氯乙烯PVC板,施工前,切除外露的膨胀螺丝(10)螺杆,测量定位防水隔离层(5)的架设位置,安设定位防水隔离层(5)所用的铁丝网,将洞外预先焊接完成的防水隔离层(5)安装到指定位置,并用螺钉将其固定,用焊接塑料板搭接缝,并对焊缝进行补强;
F、二次衬砌(8)施工,在防水隔离层(5)施工完成后,进行二次衬砌(8)施工,通过测量放样,确定模板的架设位置,将台车移动到指定位置,将模板清理干净,用混凝土搅拌车将混凝土运送到指定浇注地点,进行混凝土浇筑,浇注从下往上进行,浇注的过程中要不断的分层振捣,每环混凝土拱顶预埋φ57×3注浆钢管,衬砌混凝土强度达到80%后,用与衬砌(8)同标号的混凝土进行拱顶回填灌浆,拱顶混凝土强度达到75%时,拆除堵头模具;
G、预应力锚索(2)施工,通过现场放样,确定锚索(2)孔位以及钻孔方向,对孔位位置进行清理,采用潜孔冲击式钻机,为预应力锚索(2)打孔,钻孔深度超出设计值0.5m,钻孔结束后,拔出钻杆钻头,用一根聚乙烯管复核孔深,用高压风清孔,然后拔出聚乙烯管,再用高压风清孔一次,然后放入锚索(2),锚索(2)外套上定位片使锚索(2)居中,防止锚索(2)扭压、弯曲、注浆管应随锚索(2)一同入孔,注浆管头部距孔底5~10cm,锚索定位止浆环到达孔口时,停止推送,再检查一遍,排气管畅通,锚固段注浆,采用排气注浆,砂浆由下倾孔的孔底注入,空气由锚索孔排出,上倾和水平孔砂浆由孔口注入,空气压向孔底,再进入排气管排出孔外,注浆压力0.4~0.6MPa,中砂过筛,添加HSA高效速凝剂,砂浆搅拌机搅拌均匀,浆液在初凝之前用完,并不得混入杂物,注浆到锚固段注满后停止,立模现浇锚墩,锚墩中部应按设计钻孔倾角预埋塑料管形成孔道,对现浇锚墩进行养护,锚墩及砂浆达到70%后,进行初张拉,锚墩混凝土达到100%后,进行末张拉,张拉完成后,通过预留注浆管,管口距原砂浆面30cm,进行封孔注浆,孔中的空气由设在定位止浆环处的排气管排出,孔中注满浆液,然后从锚具量起留5cm钢铰线,用錾截子去多余部分,外覆8cm厚的细石混凝土保护层。
CN2009100625257A 2009-06-05 2009-06-05 高地应力软岩卸压施工方法 Expired - Fee Related CN101644160B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100625257A CN101644160B (zh) 2009-06-05 2009-06-05 高地应力软岩卸压施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100625257A CN101644160B (zh) 2009-06-05 2009-06-05 高地应力软岩卸压施工方法

Publications (2)

Publication Number Publication Date
CN101644160A true CN101644160A (zh) 2010-02-10
CN101644160B CN101644160B (zh) 2011-07-20

Family

ID=41656199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100625257A Expired - Fee Related CN101644160B (zh) 2009-06-05 2009-06-05 高地应力软岩卸压施工方法

Country Status (1)

Country Link
CN (1) CN101644160B (zh)

Cited By (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101975071A (zh) * 2010-10-16 2011-02-16 山东科技大学 可缩性喷浆护壁装置及其施工方法
CN102011595A (zh) * 2010-10-28 2011-04-13 辽宁工程技术大学 煤岩巷道冲击让位吸能支护装置
CN102080551A (zh) * 2010-12-17 2011-06-01 长安大学 软弱破碎围岩隧道初期支护仰拱三幅施工方法
CN102155239A (zh) * 2011-04-15 2011-08-17 中铁隧道集团有限公司 用于高地应力软岩隧道正台阶法开挖的地应力释放方法
CN102155246A (zh) * 2011-05-16 2011-08-17 安徽省皖北煤电集团有限责任公司百善煤矿 一种临时支护防片网装置
CN102226399A (zh) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 软岩四线大跨隧道三台阶以索代撑开挖施工方法
CN102235171A (zh) * 2011-08-09 2011-11-09 河南理工大学 松软破碎煤岩定向注浆加固方法
CN102444407A (zh) * 2011-12-12 2012-05-09 中铁二局股份有限公司 高地应力软弱围岩隧道下台阶施工变形控制方法
CN102587939A (zh) * 2012-03-22 2012-07-18 山东华联矿业股份有限公司 地下矿淋水防水板隔离复喷治理方法
CN102606169A (zh) * 2012-03-16 2012-07-25 铁道部工程管理中心 隧道支护方法、隧道支护结构及隧道
CN102996148A (zh) * 2012-11-22 2013-03-27 中交第二公路勘察设计研究院有限公司 一种高地应力软岩公路隧道支护方法
CN103046935A (zh) * 2012-12-31 2013-04-17 西南交通大学 一种环向开孔大跨大体积混凝土隧道衬砌结构的建造方法
CN103410524A (zh) * 2013-08-19 2013-11-27 葛洲坝新疆工程局(有限公司) 一种软岩隧道施工方法
CN103899333A (zh) * 2014-04-24 2014-07-02 中国科学院武汉岩土力学研究所 一种急倾斜煤层巷道的支护方法
CN104047613A (zh) * 2014-07-10 2014-09-17 中煤科工集团西安研究院有限公司 煤矿巷道底板用锚固方法
CN104806266A (zh) * 2015-04-01 2015-07-29 山东大学 一种新型壁后复合充填结构及其施工工艺
CN105114098A (zh) * 2015-06-08 2015-12-02 中国电建集团贵阳勘测设计研究院有限公司 引水隧洞不良地质洞段处理方法及大直径引水隧洞结构
CN105401947A (zh) * 2015-10-26 2016-03-16 中铁二十局集团有限公司 高地应力软弱围岩隧道大变形控制施工方法
CN105781587A (zh) * 2016-04-30 2016-07-20 山西省交通科学研究院 一种隧道开挖拱顶紧急支护设备及方法
CN106014446A (zh) * 2016-05-27 2016-10-12 中铁隧道集团有限公司 一种增强高地应力软岩隧道仰拱结构稳定性的加固方法
CN106050266A (zh) * 2016-07-22 2016-10-26 中铁建大桥工程局集团第五工程有限公司 富水砂卵石地层隧道内盾构区间联络通道暗挖的施工方法
CN106401614A (zh) * 2016-10-17 2017-02-15 中铁五局集团第五工程有限责任公司 一种用于大断面软弱围岩隧道施工支护结构及其施工方法
CN106761867A (zh) * 2016-12-23 2017-05-31 四川广旺能源发展(集团)有限责任公司 急倾斜回采巷道围岩稳定支护设施及支护工艺
CN106837384A (zh) * 2017-03-31 2017-06-13 中铁二院昆明勘察设计研究院有限责任公司 隧道衬砌剥离裂损病害整治结构及方法
CN107387114A (zh) * 2017-09-05 2017-11-24 湖南科技大学 一种基于巷旁钻孔的煤矿巷道连续卸压方法
CN107460790A (zh) * 2017-07-22 2017-12-12 中铁二院工程集团有限责任公司 一种无砟轨道铁路膨胀岩石路堑结构及施工方法
CN107630706A (zh) * 2017-10-24 2018-01-26 中交第二航务工程局有限公司 一种消除高地压区隧道仰拱隆起的隧底结构及施工方法
CN108166999A (zh) * 2017-09-18 2018-06-15 招商局重庆交通科研设计院有限公司 一种寒区隧道的防水防冻防火结构
CN108756942A (zh) * 2018-05-28 2018-11-06 中交城市轨道交通设计研究院有限公司 一种设有隔离层结构的双衬砌隧道
CN109339828A (zh) * 2018-11-29 2019-02-15 中南大学 一种隧道预应力仰拱结构及其施工方法
CN109595003A (zh) * 2019-01-24 2019-04-09 三峡大学 一种隧洞大截面超挖衬砌支护及自主卸压装置及施工方法
CN109667622A (zh) * 2018-11-22 2019-04-23 中国电建集团成都勘测设计研究院有限公司 隧道围岩长期变形灾害控制系统及控制方法
CN110985077A (zh) * 2019-11-22 2020-04-10 中铁十二局集团有限公司 一种利用预应力锚索防隧道仰拱隆起的方法
CN111365038A (zh) * 2020-04-27 2020-07-03 中国矿业大学(北京) 扭剪螺栓群连接抗弯系杆钢管混凝土拱联合空间支护装置
CN111663953A (zh) * 2020-06-17 2020-09-15 中建三局基础设施建设投资有限公司 一种用于污水隧道薄壁二衬变形缝的防水构造及施工方法
CN111706366A (zh) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 一种穿越大型全充填溶洞的隧道衬砌结构及施工方法
CN111911188A (zh) * 2020-09-04 2020-11-10 湖南科技大学 一种高压力隧道卸压装置的安装方法
CN111997657A (zh) * 2020-08-04 2020-11-27 天地科技股份有限公司 用于煤矿回采巷道底板的固定底角弧形架及其安装方法
CN114922628A (zh) * 2022-05-30 2022-08-19 山东黄金矿业科技有限公司深井开采实验室分公司 一种深井井壁压裂释能与高压注浆联合施工方法
CN115478703A (zh) * 2022-10-17 2022-12-16 四川大学 一种防止混凝土孔洞冻胀开裂的方法

Cited By (58)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101975071A (zh) * 2010-10-16 2011-02-16 山东科技大学 可缩性喷浆护壁装置及其施工方法
CN102011595A (zh) * 2010-10-28 2011-04-13 辽宁工程技术大学 煤岩巷道冲击让位吸能支护装置
CN102011595B (zh) * 2010-10-28 2013-12-11 辽宁工程技术大学 煤岩巷道冲击让位吸能支护装置
CN102080551B (zh) * 2010-12-17 2013-04-10 长安大学 软弱破碎围岩隧道初期支护仰拱三幅施工方法
CN102080551A (zh) * 2010-12-17 2011-06-01 长安大学 软弱破碎围岩隧道初期支护仰拱三幅施工方法
CN102155239A (zh) * 2011-04-15 2011-08-17 中铁隧道集团有限公司 用于高地应力软岩隧道正台阶法开挖的地应力释放方法
CN102155246A (zh) * 2011-05-16 2011-08-17 安徽省皖北煤电集团有限责任公司百善煤矿 一种临时支护防片网装置
CN102226399A (zh) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 软岩四线大跨隧道三台阶以索代撑开挖施工方法
CN102235171A (zh) * 2011-08-09 2011-11-09 河南理工大学 松软破碎煤岩定向注浆加固方法
CN102444407A (zh) * 2011-12-12 2012-05-09 中铁二局股份有限公司 高地应力软弱围岩隧道下台阶施工变形控制方法
CN102444407B (zh) * 2011-12-12 2015-06-03 中铁二局股份有限公司 高地应力软弱围岩隧道下台阶施工变形控制方法
CN102606169B (zh) * 2012-03-16 2014-06-11 铁道部工程管理中心 隧道支护方法、隧道支护结构及隧道
CN102606169A (zh) * 2012-03-16 2012-07-25 铁道部工程管理中心 隧道支护方法、隧道支护结构及隧道
CN102587939B (zh) * 2012-03-22 2014-10-15 山东华联矿业股份有限公司 地下矿淋水防水板隔离复喷治理方法
CN102587939A (zh) * 2012-03-22 2012-07-18 山东华联矿业股份有限公司 地下矿淋水防水板隔离复喷治理方法
CN102996148A (zh) * 2012-11-22 2013-03-27 中交第二公路勘察设计研究院有限公司 一种高地应力软岩公路隧道支护方法
CN102996148B (zh) * 2012-11-22 2016-05-04 中交第二公路勘察设计研究院有限公司 一种高地应力软岩公路隧道支护方法
CN103046935A (zh) * 2012-12-31 2013-04-17 西南交通大学 一种环向开孔大跨大体积混凝土隧道衬砌结构的建造方法
CN103410524A (zh) * 2013-08-19 2013-11-27 葛洲坝新疆工程局(有限公司) 一种软岩隧道施工方法
CN103410524B (zh) * 2013-08-19 2015-09-16 葛洲坝新疆工程局(有限公司) 一种软岩隧道施工方法
CN103899333B (zh) * 2014-04-24 2016-04-20 中国科学院武汉岩土力学研究所 一种急倾斜煤层巷道的支护方法
CN103899333A (zh) * 2014-04-24 2014-07-02 中国科学院武汉岩土力学研究所 一种急倾斜煤层巷道的支护方法
CN104047613A (zh) * 2014-07-10 2014-09-17 中煤科工集团西安研究院有限公司 煤矿巷道底板用锚固方法
CN104047613B (zh) * 2014-07-10 2016-08-24 中煤科工集团西安研究院有限公司 煤矿巷道底板用锚固方法
CN104806266A (zh) * 2015-04-01 2015-07-29 山东大学 一种新型壁后复合充填结构及其施工工艺
CN105114098A (zh) * 2015-06-08 2015-12-02 中国电建集团贵阳勘测设计研究院有限公司 引水隧洞不良地质洞段处理方法及大直径引水隧洞结构
CN105401947A (zh) * 2015-10-26 2016-03-16 中铁二十局集团有限公司 高地应力软弱围岩隧道大变形控制施工方法
CN105781587A (zh) * 2016-04-30 2016-07-20 山西省交通科学研究院 一种隧道开挖拱顶紧急支护设备及方法
CN105781587B (zh) * 2016-04-30 2017-07-21 山西省交通科学研究院 一种隧道开挖拱顶紧急支护设备及方法
CN106014446A (zh) * 2016-05-27 2016-10-12 中铁隧道集团有限公司 一种增强高地应力软岩隧道仰拱结构稳定性的加固方法
CN106050266A (zh) * 2016-07-22 2016-10-26 中铁建大桥工程局集团第五工程有限公司 富水砂卵石地层隧道内盾构区间联络通道暗挖的施工方法
CN106050266B (zh) * 2016-07-22 2018-01-02 中铁建大桥工程局集团第五工程有限公司 富水砂卵石地层隧道内盾构区间联络通道暗挖的施工方法
CN106401614A (zh) * 2016-10-17 2017-02-15 中铁五局集团第五工程有限责任公司 一种用于大断面软弱围岩隧道施工支护结构及其施工方法
CN106761867A (zh) * 2016-12-23 2017-05-31 四川广旺能源发展(集团)有限责任公司 急倾斜回采巷道围岩稳定支护设施及支护工艺
CN106837384B (zh) * 2017-03-31 2019-09-10 中铁二院昆明勘察设计研究院有限责任公司 隧道衬砌剥离裂损病害整治结构及方法
CN106837384A (zh) * 2017-03-31 2017-06-13 中铁二院昆明勘察设计研究院有限责任公司 隧道衬砌剥离裂损病害整治结构及方法
CN107460790A (zh) * 2017-07-22 2017-12-12 中铁二院工程集团有限责任公司 一种无砟轨道铁路膨胀岩石路堑结构及施工方法
CN107387114A (zh) * 2017-09-05 2017-11-24 湖南科技大学 一种基于巷旁钻孔的煤矿巷道连续卸压方法
CN108166999A (zh) * 2017-09-18 2018-06-15 招商局重庆交通科研设计院有限公司 一种寒区隧道的防水防冻防火结构
CN108166999B (zh) * 2017-09-18 2023-10-27 招商局重庆交通科研设计院有限公司 一种寒区隧道的防水防冻防火结构
CN107630706B (zh) * 2017-10-24 2023-05-26 中交第二航务工程局有限公司 一种消除高地压区隧道仰拱隆起的隧底结构及施工方法
CN107630706A (zh) * 2017-10-24 2018-01-26 中交第二航务工程局有限公司 一种消除高地压区隧道仰拱隆起的隧底结构及施工方法
CN108756942A (zh) * 2018-05-28 2018-11-06 中交城市轨道交通设计研究院有限公司 一种设有隔离层结构的双衬砌隧道
CN109667622A (zh) * 2018-11-22 2019-04-23 中国电建集团成都勘测设计研究院有限公司 隧道围岩长期变形灾害控制系统及控制方法
CN109667622B (zh) * 2018-11-22 2020-05-19 中国电建集团成都勘测设计研究院有限公司 隧道围岩长期变形灾害控制系统及控制方法
CN109339828A (zh) * 2018-11-29 2019-02-15 中南大学 一种隧道预应力仰拱结构及其施工方法
CN109339828B (zh) * 2018-11-29 2024-01-30 中南大学 一种隧道预应力仰拱结构及其施工方法
CN109595003A (zh) * 2019-01-24 2019-04-09 三峡大学 一种隧洞大截面超挖衬砌支护及自主卸压装置及施工方法
CN109595003B (zh) * 2019-01-24 2020-09-01 三峡大学 一种隧洞大截面超挖衬砌支护及自主卸压装置及施工方法
CN110985077A (zh) * 2019-11-22 2020-04-10 中铁十二局集团有限公司 一种利用预应力锚索防隧道仰拱隆起的方法
CN111365038A (zh) * 2020-04-27 2020-07-03 中国矿业大学(北京) 扭剪螺栓群连接抗弯系杆钢管混凝土拱联合空间支护装置
CN111663953A (zh) * 2020-06-17 2020-09-15 中建三局基础设施建设投资有限公司 一种用于污水隧道薄壁二衬变形缝的防水构造及施工方法
CN111706366A (zh) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 一种穿越大型全充填溶洞的隧道衬砌结构及施工方法
CN111997657A (zh) * 2020-08-04 2020-11-27 天地科技股份有限公司 用于煤矿回采巷道底板的固定底角弧形架及其安装方法
CN111911188A (zh) * 2020-09-04 2020-11-10 湖南科技大学 一种高压力隧道卸压装置的安装方法
CN114922628A (zh) * 2022-05-30 2022-08-19 山东黄金矿业科技有限公司深井开采实验室分公司 一种深井井壁压裂释能与高压注浆联合施工方法
CN115478703A (zh) * 2022-10-17 2022-12-16 四川大学 一种防止混凝土孔洞冻胀开裂的方法
CN115478703B (zh) * 2022-10-17 2024-05-10 四川大学 一种防止混凝土孔洞冻胀开裂的方法

Also Published As

Publication number Publication date
CN101644160B (zh) 2011-07-20

Similar Documents

Publication Publication Date Title
CN101644160B (zh) 高地应力软岩卸压施工方法
CN106958256B (zh) 一种分层浇筑、多次下沉的沉井施工工艺
CN101864959B (zh) 一种地下车站主体结构的暗挖施工方法
CN106320377B (zh) 一种富水软土地区深基坑盖挖逆作施工方法
CN110656959B (zh) 一种大断面黄土隧道初期支护侵限换拱施工方法
CN102996148A (zh) 一种高地应力软岩公路隧道支护方法
CN103244128A (zh) 一种大断面岩溶隧道双侧壁导坑预留核心土施工方法
CN102606162A (zh) 隧道软弱围岩浅埋易坍塌区快速施工方法
CN106968139B (zh) 下穿铁路顶进框构桥顶进过程中铁路路基支护的施工方法
CN106917409A (zh) 一种岩石盖重固结灌浆施工方法
CN111577334B (zh) 运营隧道仰拱修复方法
CN110939303B (zh) 一种旋流池半逆作法施工方法
CN112575670B (zh) 一种适用于隧道穿越巨型溶洞的t形刚构桥及其施工技术
CN112609703B (zh) 一种土钉墙支护施工工艺
CN104831734A (zh) 一种深基坑建筑旋喷桩复合土钉墙支护施工方法
CN110905523A (zh) 一种地铁竖井施工方法
CN103088830A (zh) 超深地下室复合外墙结构的施工方法
CN113174958A (zh) 一种劣质地况下临近道路基坑施工方法
CN112145203A (zh) 全断面前进式分段注浆施工方法及重叠隧道施工工法
CN102235007B (zh) 上钉下桩组合的深基支护方法
CN110552371A (zh) 基于逆作法的环形内衬墙消除水平施工缝的施工方法
CN107700490B (zh) 砂卵地层桩间喷射混凝土超前弥补施工结构及其施工方法
CN113216215A (zh) 一种复杂环境下深沟槽支护逆作施工方法
CN110529120B (zh) Ⅵ级围岩浅埋暗挖黄土隧道凿除侵限构筑物施工方法
CN110306989B (zh) 一种非明挖装配式管沟开挖支护加固方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110720

Termination date: 20170605

CF01 Termination of patent right due to non-payment of annual fee