CN101644048B - 布袋袖阀管注浆方法 - Google Patents

布袋袖阀管注浆方法 Download PDF

Info

Publication number
CN101644048B
CN101644048B CN2009100399434A CN200910039943A CN101644048B CN 101644048 B CN101644048 B CN 101644048B CN 2009100399434 A CN2009100399434 A CN 2009100399434A CN 200910039943 A CN200910039943 A CN 200910039943A CN 101644048 B CN101644048 B CN 101644048B
Authority
CN
China
Prior art keywords
cloth bag
sleeve valve
valve tube
sleeve
shell material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009100399434A
Other languages
English (en)
Other versions
CN101644048A (zh
Inventor
刘吉福
许发明
王业荣
李翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Original Assignee
GUANGDONG HANGSHENG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG HANGSHENG CONSTRUCTION GROUP CO Ltd filed Critical GUANGDONG HANGSHENG CONSTRUCTION GROUP CO Ltd
Priority to CN2009100399434A priority Critical patent/CN101644048B/zh
Publication of CN101644048A publication Critical patent/CN101644048A/zh
Application granted granted Critical
Publication of CN101644048B publication Critical patent/CN101644048B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及一种布袋袖阀管注浆技术,该技术是在常规袖阀管注浆技术基础上开发的,其特点在于:在袖阀管上套一条与之长度相同的布袋,在布袋外侧沿深度方向固定1~2根塑料排水板,在钻孔中插入带有布袋和塑料排水板的袖阀管后,在布袋内灌注套壳料,其后按照常规袖阀管注浆方法施工;采用该技术可以避免跑浆、串浆现象,利于形成桩体;设置塑料排水板可以快速排出浆液中部分水分、消散注浆在地基中产生的超静孔隙水压力,有效减少挤土效应、增加地基土强度。

Description

布袋袖阀管注浆方法
技术领域
本发明涉及一种软土地基加固方法,特别涉及一种布袋袖阀管注浆方法,是在常规袖阀管注浆技术的基础上改进的一种新技术,属于地基及基础工程施工技术领域。
背景技术
袖阀管注浆技术作为一种成熟、先进的注浆工艺,被广泛地应用于基坑帷幕、地基及坝区加固等工程之中,拥有极为广阔的应用前景;袖阀管注浆是将袖阀式注浆管通过钻孔下入地层,采用分段注浆工艺,使浆液在压力条件下,较均匀地进入地层,以达到浆液在地层中分段可控、均匀扩散的目的,常规袖法管注浆技术施工工艺为:钻孔到设计深度→灌注套壳料→下袖阀管→套壳料达到规定强度后分段注浆。
大量的工程实践表明,常规袖阀管注浆技术,浆液扩散范围难以控制,通常不能形成连续的桩体,且易出现跑浆现象;注浆不但在地基中产生超静孔隙水压力,而且增加了地基含水量,挤土效应大、不利于地基稳定。如某路堤边坡下地基由于袖阀管注浆导致坡脚地表位移8~14cm,最大位移为11~16cm,注浆中后期在边坡上出现数条裂缝。另一路堤边坡下地基袖阀管注浆时导致路堤挡土墙位移18~21cm,坡面急流槽被拉断成3~4段,最大开裂3cm,影响施工质量。
发明内容
本发明的目的是针对现有技术的不足,提供一种可以避免跑浆、串浆现象并利于形成桩体的布袋袖阀管注浆技术,同时由于该技术采用塑料排水板快速排出浆液中部分水分、消散注浆在地基中产生的超静孔隙水压力,可有效减少挤土效应、增加地基土强度。
为了解决上述问题,本发明所采用的技术方案是:
一种布袋袖阀管注浆方法,其工艺流程如下:
制作布袋袖阀管→钻孔至设计深度→将安装了布袋和排水板的袖阀管插入钻孔并对中→在布袋内灌注套壳料→套壳料达到规定强度后分段注浆;
具体施工工艺流程为:
袖阀管外侧套一条与袖阀管长度相同的布袋,布袋体积为注浆体积的0.6~0.9倍。布袋可以采用土工布等制作,布袋抗拉强度和缝合强度宜大于15kN/m。在布袋外侧沿深度方向固定1~2根塑料排水板,2根排水板时对称设置。排水板纵向通水量宜大于25cm3/s;宜利用胶布每0.5m左右将布袋和塑料排水板临时固定在袖阀管上;利用地质钻机等设备钻一个直径不小于10cm的钻孔,将安装了布袋和塑料排水板的袖阀管插入钻孔内,并将布袋口固定在地面 上避免布袋和塑料排水板沉入孔内;在布袋内灌注套壳料,采用自孔底开始向上返浆的方式灌注套壳料,孔口流出纯净套壳料后利用铁丝或塑料扣等封闭布袋口,继续灌注套壳料,使套壳料充满钻孔。套壳料达到规定强度后,利用注浆枪,通过袖阀管从孔底向上分段注浆,注浆可以分多次进行。
本发明与现有技术相比有以下优点:
1、袖阀管外侧套一条布袋,约束了水泥的扩散空间,避免跑浆、串浆现象,利于形成桩体。
2、布袋外侧的塑料排水板可以快速排出浆液中部分水分,消散注浆在地基中产生的超静孔隙水压力,有效减少挤土效应、增加地基土强度。
附图说明
图1是布袋袖阀管立面示意图;
图2是布袋袖阀管横剖面图;
图中:1塑料排水板  2布袋  3袖阀管  4橡皮阀  5钻孔  6地面。
具体实施方式
下面结合附图及实施例对本发明做进一步详细说明,这些实施例仅用来说明本发明,并不限制本发明的范围。
实施例1
如图1所示的袖阀管示意图制作布袋袖阀管,利用地质钻机等设备钻一个直径不小于10cm的钻孔,将安装了布袋和塑料排水板的袖阀管插入钻孔内,布袋可以采用土工布等制作,在布袋外侧沿深度方向固定1~2根塑料排水板,利用胶布每0.5m左右将布袋和塑料排水板临时固定在袖阀管上;并采取措施避免布袋和塑料排水板沉入孔内;在布袋内灌注套壳料,采用自孔底开始向上返浆的方式灌注套壳料,孔口流出纯净套壳料后利用铁丝封闭布袋口,继续灌注套壳料,使套壳料充满钻孔。套壳料达到规定强度后,利用注浆枪,通过袖阀管从孔底向上分段注浆。

Claims (4)

1.一种布袋袖阀管注浆方法,其特征在于:工艺流程如下:
制作布袋袖阀管→钻孔→将布袋袖阀管插入钻孔并对中→在布袋内灌注套壳料→分段注浆;
制作布袋袖阀管是在常规的袖阀管外侧套一条与袖阀管长度相同的布袋,布袋外侧设置塑料排水板;
在布袋内灌注套壳料是采用自孔底开始向上返浆的方式灌注套壳料,孔口流出纯净套壳料后利用铁丝或塑料扣封闭布袋口,继续灌注套壳料,使套壳料充满钻孔;
分段注浆是用注浆枪,通过布袋袖阀管从孔底向上分段注浆。
2.根据权利要求1所述的布袋袖阀管注浆方法,其特征在于:所述的布袋体积为注浆体积的0.6~0.9倍。
3.根据权利要求1所述的布袋袖阀管注浆方法,其特征在于:所述的塑料排水板采用1~2根。
4.根据权利要求1所述的布袋袖阀管注浆方法,其特征在于:布袋采用土工布制作。
CN2009100399434A 2009-06-03 2009-06-03 布袋袖阀管注浆方法 Active CN101644048B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100399434A CN101644048B (zh) 2009-06-03 2009-06-03 布袋袖阀管注浆方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100399434A CN101644048B (zh) 2009-06-03 2009-06-03 布袋袖阀管注浆方法

Publications (2)

Publication Number Publication Date
CN101644048A CN101644048A (zh) 2010-02-10
CN101644048B true CN101644048B (zh) 2011-07-27

Family

ID=41656094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100399434A Active CN101644048B (zh) 2009-06-03 2009-06-03 布袋袖阀管注浆方法

Country Status (1)

Country Link
CN (1) CN101644048B (zh)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444118A (zh) * 2010-10-15 2012-05-09 中铁五局(集团)有限公司 袖阀管注浆加固施工方法
CN102127909B (zh) * 2011-01-11 2012-11-28 河海大学 防止塑料套管混凝土桩弯曲变形的施工方法及其装置
CN102561992B (zh) * 2012-01-29 2013-11-06 山东大学 一种采用变形止水器的注浆封堵工艺
CN103898913B (zh) * 2014-03-20 2015-07-08 河海大学 一种内布袋袖阀管注浆施工方法
CN104294822B (zh) * 2014-10-13 2016-01-06 安徽天筑建设(集团)有限公司 加固厚覆盖层深埋软土刚柔组合桩施工方法
CN104389314B (zh) * 2014-12-10 2016-07-20 山东大学 一种浅层黏土注浆加固装置及方法
CN109750670A (zh) * 2017-11-04 2019-05-14 重庆第二师范学院 一种富水卵石层深基坑坑底加固用袖阀管及施工工艺
CN111519627B (zh) * 2020-04-30 2021-01-12 中国水电基础局有限公司 一种适用于深厚覆盖层永久性帷幕的套阀管灌浆方法
CN114108708B (zh) * 2021-08-31 2023-04-07 中交一公局第八工程有限公司 一种岩溶隧道注浆效果模拟装置

Also Published As

Publication number Publication date
CN101644048A (zh) 2010-02-10

Similar Documents

Publication Publication Date Title
CN101644048B (zh) 布袋袖阀管注浆方法
CN101644049B (zh) 双阀布袋袖阀管注浆方法
CN106320354B (zh) 覆盖层下溶洞发育地层的防渗施工方法
CN201908308U (zh) 注浆袖阀管
CN102444118A (zh) 袖阀管注浆加固施工方法
CN107747312B (zh) 一种砂砾石地层钻孔灌浆施工的方法
CN106761835A (zh) 一种岩溶隧道漏水分段注浆施工方法
CN106703010B (zh) 一种无套壳料层袖阀管注浆快速施工方法
CN107513995A (zh) 一种桥梁灌注桩后压浆施工方法
CN105155517B (zh) 钻孔挤压承压型囊式分支桩施工方法
CN107178077B (zh) 一种岩溶地区溶洞上覆土层注浆加固结构及其设计方法
CN106837340B (zh) 冻结壁保护下的壁间注浆防水及强化井壁结构的施工方法
CN201826315U (zh) 注浆袖阀管
CN105178342B (zh) 一种降水井井管及其用于封堵基坑预留洞的方法
CN107524455A (zh) 多段压密式袖阀管及其注浆方法
CN109750668A (zh) 一种富水卵石层深基坑坑底加固用袖阀管及施工工艺
CN104594369B (zh) 喀斯特地区高压群孔置换灌浆方法及其结构
CN207161107U (zh) 多段压密式袖阀管
CN101644051B (zh) 双阀双布袋袖阀管注浆方法
CN207109745U (zh) 一种坝基输水底涵高水头封堵结构
CN203891785U (zh) 水文水井管内投砾专用接头管总成
CN215804475U (zh) 一种袖阀管注浆构件及用于富水岩溶的封孔组件
CN105926577B (zh) 真空预压渗流固结法
CN105970909B (zh) 井点塑排真空预压渗流固结联合降水预压动力固结法
CN107574792A (zh) 一种坝基输水底涵高水头封堵结构及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160503

Address after: 519070 Guangdong city in Zhuhai Province before the mountain Verde Street No. 189

Patentee after: China iron Jian Ganghangju Group Co.,Ltd

Address before: 118 No. 511442 Guangdong province Guangzhou City Southern towns Panyu District Hungnam Avenue

Patentee before: Guangdong Hangsheng Construction Group Co., Ltd.