CN101642637B CN2009101038471A CN200910103847A CN101642637B CN 101642637 B CN101642637 B CN 101642637B CN 2009101038471 A CN2009101038471 A CN 2009101038471A CN 200910103847 A CN200910103847 A CN 200910103847A CN 101642637 B CN101642637 B CN 101642637B
Authority
CN
China
Prior art keywords
urceolus
construction
beveled cone
whirlwind tank
ring beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009101038471A
Other languages
English (en)
Other versions
CN101642637A (zh
Inventor
邓玉孙
蒙瑜
罗福盛
薛尚铃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CISDI Engineering Co Ltd
Original Assignee
CISDI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CISDI Engineering Co Ltd filed Critical CISDI Engineering Co Ltd
Priority to CN2009101038471A priority Critical patent/CN101642637B/zh
Publication of CN101642637A publication Critical patent/CN101642637A/zh
Application granted granted Critical
Publication of CN101642637B publication Critical patent/CN101642637B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明涉及一种旋流池,包括斜锥体(2)和外筒(3),其关键在于所述斜锥体(2)和/或外筒(3)增设有至少一个外挑环梁(1)。本发明同时还涉及这种旋流池的施工方法。本发明的抗浮能力强,投资小,并可发挥斜锥体的拱体传力效应,减小外筒及斜锥体的厚度,整个结构体系布置合理,传力简单、刚度协调;同时,本发明可缩小基坑土方开挖作业面,降低降水难度,并为边坡稳定提供条件。

Description

一种旋流池及施工方法
技术领域
本发明涉及一种旋流池结构体系及旋流池的施工方法,属于主要由混凝土构造的结构工程技术领域。
背景技术
在钢铁企业建设中,旋流池是作为水处理系统的重要组成部分,具有直径大、埋置深、降水难度大、抗浮设计困难、混凝土体量大、造价高、施工周期长的特点。
旋流池结构体系包括外筒、内筒、顶板层、泵房层、支柱、斜锥体、底板。泵房层和顶板层支撑在内外筒之间,前者放置水泵设备,后者封闭旋流池。内筒、泵房层及顶板层的竖向荷载通过支柱传至底板上。这种结构不能有效地发挥斜锥体良好的受力特性。
另一方面,地下水位较高时,为满足抗浮要求,常采用增加旋流池的自重,例如增加斜锥体、外筒、内筒的重量来平衡水浮力。这种做法会导致旋流池混凝土体积增加,施工周期延长,而且不经济。
同时,大开挖法施工旋流池时,基坑开挖至底板底面后,自下至上先后施工底板、斜锥体、外筒、支柱、内筒、泵房层、顶板层。因斜锥体施工作业面深、作业时间长,基坑开挖面积大,不利于基坑降水及大开挖边坡的安全。
发明内容
本发明的目的在于提供一种抗浮能力强的旋流池。
本发明的第二目的在于提供一种基坑开挖面积小的旋流池施工方法。
本发明的第一目的是通过以下技术方案实现的:一种旋流池,包括斜锥体、外筒和底板,其特征是:所述斜锥体和/或外筒增设有至少一个外挑环梁。
在满足性能的前提下,为方便施工,所述斜锥体和外筒上可以仅设置一个外挑环梁。
为发挥斜锥体良好的受力特性,所述外挑环梁设置在所述斜锥体与所述外筒的结合处。
为进一步增强旋流池的抗浮性能,所述斜锥体或/和所述底板的下部设置有锚在岩土里的锚杆群。所述锚杆群可以采用高压注浆工艺施工制得。
本发明的第二目的是通过以下技术方案实现的:一种旋流池的施工方法,其特征是:所述旋流池按以下步骤施工:
(1)开挖基坑至外筒的底部;
(2)施工外挑环梁;
(3)以外挑环梁为外筒施工阶段的基础,施工外筒;
(4)截水并支挡土体,施工斜锥体和底板;
(5)自下至上施工支柱、内筒、泵房层和顶板层。
为缩小基坑土方开挖作业面,所述外筒采用顺做法施工,所述斜锥体采用逆做法施工。
本发明的有益效果是:
(1)本发明利用外挑环梁上部的土体重量,而非旋流池结构重量来提高抗浮能力,节约混凝土,节省投资。
(2)本发明设置的外挑环梁兼做外筒及斜锥体的环向约束,可发挥斜锥体的拱体传力效应,减小外筒及斜锥体的厚度,整个结构体系布置合理,传力简单、刚度协调、受力性能好。
(3)由于斜锥体或/和所述底板的下部设置有锚在岩土里的锚杆群,因此可利用底板与斜锥体区域锚杆群的抗拔力来平衡浮力,从而进一步减小了底板、斜锥体、外筒壁的厚度,节约混凝土量,减少基坑开挖深度,降低降水难度,节省投资。
(4)本发明设置的外挑环梁兼做外筒基础,外筒采用顺作法施工,斜锥体采用逆作法施工,缩小基坑土方开挖作业面,降低降水难度,并为边坡稳定提供条件。
附图说明
图1为本发明实施例1的结构示意图;
图2是图1的受力分析图;
图3是本发明实施例2的结构示意图。
具体实施方式
下面结合具体的实施方式对本发明作进一步说明,但并不因此将本发明限定在以下具体的实施方式之中。
实施例1:如图1所示,一种旋流池,在所述斜锥体2与所述外筒3的结合处设置有外挑环梁1。这种旋流池按以下步骤施工:(1)开挖基坑至外筒3的底部;(2)施工外挑环梁1;(3)以外挑环梁1为外筒3施工阶段的基础,施工外筒3;(4)截水并支挡土体4,施工斜锥体2和底板10;(5)自下至上施工支柱5、内筒6、泵房层7和顶板层8。
如图2所示,本发明工作时,土压力垂直作用于斜锥体2及底板10的下表面,外挑环梁1约束斜锥体2顶部,斜锥体2顶部产生向外推力,外挑环梁1受拉;另一方面,土压力垂直作用于外筒3外表面,外挑环梁1约束外筒3底部,外挑环梁1受压,可部分平衡斜锥体2顶部向外推力。
实施例2:如图3所示,本实施例与实施例1所不同的是,所述斜锥体2和所述底板10的下部设置有锚在岩土里的锚杆群9。所述锚杆群9采用高压注浆工艺施工制得。本实施例的其他结构以及施工方法与实施例1相同。

Claims (2)

1.一种旋流池的施工方法,所述旋流池,包括斜锥体(2)、外筒(3)和底板(10),所述斜锥体(2)和外筒(3)上仅设置一个外挑环梁(1);所述外挑环梁(1)设置在所述斜锥体(2)与所述外筒(3)的结合处,其特征是:所述旋流池按以下步骤施工:
(1)开挖基坑至外筒(3)的底部;
(2)施工外挑环梁(1);
(3)以外挑环梁(1)为外筒(3)施工阶段的基础,施工外筒(3);
(4)截水并支挡土体(4),施工斜锥体(2)和底板(10);
(5)自下至上施工支柱(5)、内筒(6)、泵房层(7)和顶板层(8)。
2.如权利要求1所述的施工方法,其特征是:所述外筒(3)采用顺做法施工,所述斜锥体(2)采用逆做法施工。
CN2009101038471A 2009-05-14 2009-05-14 一种旋流池及施工方法 Active CN101642637B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101038471A CN101642637B (zh) 2009-05-14 2009-05-14 一种旋流池及施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101038471A CN101642637B (zh) 2009-05-14 2009-05-14 一种旋流池及施工方法

Publications (2)

Publication Number Publication Date
CN101642637A CN101642637A (zh) 2010-02-10
CN101642637B true CN101642637B (zh) 2011-12-07

Family

ID=41654792

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101038471A Active CN101642637B (zh) 2009-05-14 2009-05-14 一种旋流池及施工方法

Country Status (1)

Country Link
CN (1) CN101642637B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101949226B (zh) * 2010-09-14 2011-11-23 中国华冶科工集团有限公司 大型池体的交叉施工方法
CN110836030A (zh) * 2019-11-22 2020-02-25 上海宝冶集团有限公司 适应复杂地质条件的顺逆结合的旋流井施工方法
CN111636410B (zh) * 2020-06-08 2021-10-01 淮南东华欧科矿山支护设备有限责任公司 一种注浆自动控制装置

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DD205995A1 (de) * 1982-08-24 1984-01-11 Ulrich Fischer Verfahren und vorrichtung zur integralen vakuum-leckratenmessung
CN201108760Y (zh) * 2007-11-15 2008-09-03 广州市泰克比奥污水处理有限公司 一种高效斜板沉淀池
CN201198666Y (zh) * 2008-05-15 2009-02-25 曾建军 超低温液化天然气地下储气库
CN101372872A (zh) * 2008-10-20 2009-02-25 中冶实久建设有限公司 逆作法施工热轧旋流池结构工程的方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DD205995A1 (de) * 1982-08-24 1984-01-11 Ulrich Fischer Verfahren und vorrichtung zur integralen vakuum-leckratenmessung
CN201108760Y (zh) * 2007-11-15 2008-09-03 广州市泰克比奥污水处理有限公司 一种高效斜板沉淀池
CN201198666Y (zh) * 2008-05-15 2009-02-25 曾建军 超低温液化天然气地下储气库
CN101372872A (zh) * 2008-10-20 2009-02-25 中冶实久建设有限公司 逆作法施工热轧旋流池结构工程的方法

Also Published As

Publication number Publication date
CN101642637A (zh) 2010-02-10

Similar Documents

Publication Publication Date Title
US20220074160A1 (en) Pile-cylinder-truss composite offshore wind turbine foundation and construction process thereof
CN101845820B (zh) 沉井下沉的助沉施工方法
CN1995557A (zh) 桩-桶基础
CN204551518U (zh) 大直径宽浅桶负压桩组合基础
CN202039382U (zh) 加肋式海底吸力锚
CN101761090A (zh) 海上风电机组的空间桁架式多桶基础
CN103015455B (zh) 桥梁桩桶组合基础及其施工方法
CN202117068U (zh) 微型桩板式复合基础
CN102720207A (zh) 一种塔架基础及风力发电机的塔架
CN203701127U (zh) 一种水下重力式基础
CN101642637B (zh) 一种旋流池及施工方法
CN210797617U (zh) 一种桩筒复合桁架式海上风机基础
JPS6149029A (ja) 水中基礎固定装置
CN201713827U (zh) 海上风电场风机基础结构
CN201593193U (zh) 海上风电机组的空间桁架式多桶基础
CN202559371U (zh) 打入式独柱、独桩海上测风塔基础
CN213867902U (zh) 一种海上风电吸力桩基础
CN202830936U (zh) 一种基坑支护结构
CN106555399A (zh) 一种碳酸盐岩地区抗拔锚杆注浆排水装置及其施工方法
CN112302046A (zh) 一种海上风电吸力桩基础附加顶板结构及其安装方法
CN109024578B (zh) 一种钢柱砼根深水基础结构及其施工方法
CN202969405U (zh) 一种杯型混凝土风力发电塔基础
CN202164862U (zh) 一种适用于海洋工程的塔筒式结构物
CN215483071U (zh) 一种多桶多立柱与预制混凝土承台相结合的风机基础
CN210482350U (zh) 一种海上风电机组圆台辅助加强式单桩基础

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant