CN101634145B - Anti-slide pile with vertical prestressed anchor cables - Google Patents

Anti-slide pile with vertical prestressed anchor cables Download PDF

Info

Publication number
CN101634145B
CN101634145B CN2009100601515A CN200910060151A CN101634145B CN 101634145 B CN101634145 B CN 101634145B CN 2009100601515 A CN2009100601515 A CN 2009100601515A CN 200910060151 A CN200910060151 A CN 200910060151A CN 101634145 B CN101634145 B CN 101634145B
Authority
CN
China
Prior art keywords
pile body
pile
anchor
anchor cable
slide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009100601515A
Other languages
Chinese (zh)
Other versions
CN101634145A (en
Inventor
蒋楚生
李庆海
贺钢
梁瑶
李飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN2009100601515A priority Critical patent/CN101634145B/en
Publication of CN101634145A publication Critical patent/CN101634145A/en
Application granted granted Critical
Publication of CN101634145B publication Critical patent/CN101634145B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses an anti-slide pile with vertical prestressed anchor cables, aiming at effectively strengthening the resistance to bending of the anti-slide pile, reducing the steel consumption and increasing the construction efficiency. The technical scheme is as follows: distribution bars (11) are arranged in a pile body (10). The anti-slide pile is characterized in that the pile body (10) comprises a bottom section (10a) and a main section (10b), which are formed through placement of concrete twice; anchor cables (20) are horizontally embedded at intervals inside the tension side of pile body (10); an anchoring section (20a) on the lower part of the anchor cable (20) is connected with the bottom section (10a) of the pile body (10) by anchoring; after vertical prestress is exerted on the pile body (10), the upper end of the anchor cable (20) is connected with the pile body (10) at the top of the pile body (10) by an anchor device. The anti-slide pile is mainly applied to landslide control engineering.

Description

Anti-slide pile with vertical prestressed anchor cables
Technical field
The present invention relates to be applied to the antislide pile of landslide control engineering, particularly a kind of antislide pile that pile body is applied vertical prestressing by anchor cable.
Background technology
Landslide control is that investment is huge, technical sophistication, construction are dangerous and arduous combats a natural disaster engineering.China is a country that landslide disaster is quite serious, for many years, for guaranteeing the safety of people's lives and properties, ensures carrying out smoothly of economic construction, and country has expended great amount of manpower and material resources and financial resources in preventing land slide work.The 1950's, China is many to administer the landslide with retaining wall, and no matter this retaining structure on theoretical and job practices, all is both unreasonable also uneconomical, can only administer very small-scale landslide.The later stage sixties 20th century, bring into use antislide pile to administer the landslide, because antislide pile has advantages such as littler than retaining wall excavation face, that the bricklaying volume is little, speed of application is fast, apply very soon, so far still in extensive use in the whole nation.Antislide pile has timber, steel pipe pile, reinforced concrete pile etc. by pile body material branch, and wherein the utilization of reinforced concrete pile is the most extensive.Reinforced concrete pile is to be arranged circumferentially distribution bar in pile body, along the pile body thickness direction many row's tensile reinforcements is set at interval in tension one side.For guaranteeing the bending resistance of antislide pile, tension master's muscle diameter is big, consumption is many, and steel consumption is big, is unfavorable for reducing the cost of landslide control engineering.In addition, because cloth muscle complexity in the pile body, welding, the colligation workload is big, also has the low deficiency of efficiency of construction.
Summary of the invention
Technical problem to be solved by this invention provides a kind of anti-slide pile with vertical prestressed anchor cables, can strengthen the bending resistance of antislide pile effectively, reduces steel consumption, and improves efficiency of construction.
The technical solution adopted for the present invention to solve the technical problems is: anti-slide pile with vertical prestressed anchor cables of the present invention, be provided with distribution bar in the pile body, it is characterized in that: described pile body is made of end section, the principal piece that twice placing of concrete forms, and the lateral separation is embedded with anchor cable in the pile body tension side; An anchor cable bottom anchoring section and a stake bottom section anchor connection, after pile body is applied vertical prestressing, the anchor cable upper end by anchor device in pile body top and its anchor connection.
The invention has the beneficial effects as follows, replace original tensile reinforcement, pile body is applied vertical prestressing, strengthened the bending resistance of antislide pile effectively by anchor cable with anchor cable; Compare with the conventional steel rib concrete pile, steel consumption reduces significantly, thereby helps reducing the cost of landslide control engineering; Anchor cable is easy for installation, reduces welding, the colligation workload of site operation in a large number, therefore can improve the efficiency of construction and the construction quality of antislide pile effectively.
Description of drawings
This manual comprises following three width of cloth accompanying drawings:
Fig. 1 is the structural representation of anti-slide pile with vertical prestressed anchor cables of the present invention;
Fig. 2 is the sectional view along A-A line among Fig. 1;
Fig. 3 is the sectional view along B-B line among Fig. 1.
Component shown in the figure, toponym and pairing mark: pile body 10, end section 10a, principal piece 10b, distribution bar 11, stirrup 12, spacing horizontal bar 13, connection lengthwise rib 14, anchor cable 20, anchoring section 20a, tensioner ring 21, billet 22, ground tackle 23.
The specific embodiment
The present invention is further described below in conjunction with drawings and Examples.
See figures.1.and.2, anti-slide pile with vertical prestressed anchor cables of the present invention is provided with distribution bar 11 in the pile body 10.Described pile body 10 is made of end section 10a, the principal piece 10b that twice placing of concrete forms, and the lateral separation is embedded with anchor cable 20 in pile body 10 tension sides.Anchor cable 20 bottom anchoring section 20a and the section 10a anchor connection of 10 end of pile body, after pile body 10 is applied vertical prestressing, anchor cable 20 upper ends by anchor device in pile body 10 tops and its anchor connection.Replace original tensile reinforcement with anchor cable 20, pile body 10 is applied vertical prestressing, strengthened the bending resistance of antislide pile effectively, and steel consumption reduces significantly, thereby help reducing the cost of landslide control engineering by anchor cable.Because it is convenient that anchor cable 20 is installed more than the laying of tensile reinforcement, can reduce welding, the colligation workload of site operation in a large number, therefore can improve the efficiency of construction and the construction quality of antislide pile effectively.
See figures.1.and.2, described anchor cable 20 adopts is 4~8 strands steel strand, and anchoring section 20a steel strand are exposed, and vertically are arranged at intervals with tensioner ring 21, and the through hole of laying at interval on the tensioner ring 21 makes each strand steel strand keep a determining deviation.With reference to Fig. 3, except that anchoring section 20a, anchor cable 20 top principal pieces are the free section of non-bending steel cable anchor cable, and it can freely stretch when applying prestressing force.With reference to Fig. 1, described anchor device is made up of ground tackle 23 and billet 22, and billet 22 has the through hole that passes through for anchor cable 20 upper ends.
With reference to Fig. 2, vertical interval is laid with spacing horizontal bar 13 in described pile body 10 end section 10a, fixedly connected with the stirrup 12 that is used for fixing distribution bar 11 in the two ends of spacing horizontal bar 13, before end section 10a pouring with anchoring section 20a positioning and fixing between tension side stirrup 12 and spacing horizontal bar 13.With reference to Fig. 1, be the connection between the end section 10a, the principal piece 10b that strengthen twice placing of concrete formation, be laid with pre-buried connection lengthwise rib 14 at interval on the end section 10a of described pile body 10 and the bonding surface of principal piece 10b, the two ends of connection lengthwise rib 14 extend into respectively in end section 10a, the principal piece 10b.
Job practices below in conjunction with specific embodiment explanation anti-slide pile with vertical prestressed anchor cables of the present invention:
1. elder generation's anchor cable anti-slide pile construction method routinely excavates a stake hole.
2. a spot of distribution bar 11 is in place all around fast by designing requirement, and carries out colligation with stirrup 12 and fix.
3. the anchor cable 20 that will make in advance manually lifts to be filled in the hole, notice that the anchor cable afterbody ties up down putting down gently slowly with rope, after the exposed anchoring section 20a in its underpart is accurately in place, with spacing horizontal bar 13 fixedly colligation be fixed on the stirrup 12, each anchoring section 20a is fixed.
4. water pile body 10 lower bottom section 10a concrete, end section 10a length is 3~4m, adds an amount of early strength admixture in the concrete.Watering to from the connection lengthwise rib 14 that begins during about 3m at the bottom of the stake on cross section every the φ 20mm of the pre-buried long 1m of 50cm, continue to water again the thick concrete of 50cm, keep this concrete surface crude as far as possible, allow connection lengthwise rib 14 expose 50cm, when treating next time pouring principal piece 10b to strengthen twice binding between the concrete.
5. treat after 3 days each anchor cable 20 usefulness stretch-draw jack are stretching, and continuous pouring principal piece 10b C30 concrete incessantly immediately, until following stake top down about 0.2m, the billet 22 that a 280mm * 280mm * 25mm is installed at every anchor cable 20 places and pile concrete pouring are together.
When treating that 6. pile concrete reaches the 7 day length of time, anchor cable 20 applied 50% design pulling force; When treating that pile concrete reaches the 14 day length of time, anchor cable 20 applied 70% design pulling force; During the 28 day length of time, anchor cable 20 is applied 100% design pulling force, and consider the super stretch-draw 5% of loss of prestress.
7. at last with ground tackle 23 outer steel strand excisions, keep the 12cm protruded length, and shut with the C30 concrete of thick 20cm.

Claims (5)

1. anti-slide pile with vertical prestressed anchor cables, be provided with distribution bar (11) in the pile body (10), it is characterized in that: the end section (10a) that described pile body (10) is formed by twice placing of concrete, principal piece (10b) constitute, and the lateral separation is embedded with anchor cable (20) in pile body (10) tension side; Anchor cable (20) bottom anchoring section (20a) and pile body (10) end section (10a) anchor connection, after pile body (10) is applied vertical prestressing, anchor cable (20) upper end by anchor device in pile body (10) top and its anchor connection.
2. anti-slide pile with vertical prestressed anchor cables according to claim 1, it is characterized in that: described anchor cable (20) adopts is 4~8 strands steel strand, anchoring section (20a) steel strand are exposed, and vertically being arranged at intervals with tensioner ring (21), tensioner ring (21) is gone up the through hole of laying at interval makes each strand steel strand keep a determining deviation.
3. as anti-slide pile with vertical prestressed anchor cables as described in the claim 2, it is characterized in that: the vertical spacing horizontal bar (13) that is laid with at interval in described pile body (10) end section (10a), fixedly connected with the stirrup that is used for fixing distribution bar (11) (12) in the two ends of spacing horizontal bar (13), before end section (10a) pouring with anchoring section (20a) positioning and fixing between tension side stirrup (12) and spacing horizontal bar (13).
4. anti-slide pile with vertical prestressed anchor cables according to claim 1, it is characterized in that: described anchor device is made up of ground tackle (23) and billet (22), and billet (22) has the through hole that passes through for anchor cable (20) upper end.
5. anti-slide pile with vertical prestressed anchor cables according to claim 1, it is characterized in that: be laid with pre-buried connection lengthwise rib (14) at interval on the end section (10a) of described pile body (10) and the bonding surface of principal piece (10b), the two ends of connection lengthwise rib (14) extend into respectively in end section (10a), the principal piece (10b).
CN2009100601515A 2009-07-29 2009-07-29 Anti-slide pile with vertical prestressed anchor cables Active CN101634145B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100601515A CN101634145B (en) 2009-07-29 2009-07-29 Anti-slide pile with vertical prestressed anchor cables

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100601515A CN101634145B (en) 2009-07-29 2009-07-29 Anti-slide pile with vertical prestressed anchor cables

Publications (2)

Publication Number Publication Date
CN101634145A CN101634145A (en) 2010-01-27
CN101634145B true CN101634145B (en) 2011-12-28

Family

ID=41593464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100601515A Active CN101634145B (en) 2009-07-29 2009-07-29 Anti-slide pile with vertical prestressed anchor cables

Country Status (1)

Country Link
CN (1) CN101634145B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110805026B (en) * 2019-11-20 2021-02-19 福建省交通规划设计院有限公司 Portal frame type anti-slide pile with vertical prestressed anchor cables arranged in inner pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4070867A (en) * 1974-12-13 1978-01-31 Cassidy Paul G Negative friction pile and isolating casing
EP0574057A1 (en) * 1992-05-14 1993-12-15 Colijn Beheer B.V. Method for the vibration-free construction of a soil displacing foundation pile
JP2000303457A (en) * 1999-04-19 2000-10-31 Sekisui House Ltd Friction pile
CN201016169Y (en) * 2007-02-13 2008-02-06 陕西黄延高速公路有限责任公司 Eccentric prestressed anchor rope friction pile
CN101230577A (en) * 2007-12-28 2008-07-30 中国科学院水利部成都山地灾害与环境研究所 Construction method for vertical prestressed anchor rope friction pile slope-sliding prevention and treatment
CN201459715U (en) * 2009-07-29 2010-05-12 中铁二院工程集团有限责任公司 Anti-slide pile for vertical prestressing anchor rope

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4070867A (en) * 1974-12-13 1978-01-31 Cassidy Paul G Negative friction pile and isolating casing
EP0574057A1 (en) * 1992-05-14 1993-12-15 Colijn Beheer B.V. Method for the vibration-free construction of a soil displacing foundation pile
JP2000303457A (en) * 1999-04-19 2000-10-31 Sekisui House Ltd Friction pile
CN201016169Y (en) * 2007-02-13 2008-02-06 陕西黄延高速公路有限责任公司 Eccentric prestressed anchor rope friction pile
CN101230577A (en) * 2007-12-28 2008-07-30 中国科学院水利部成都山地灾害与环境研究所 Construction method for vertical prestressed anchor rope friction pile slope-sliding prevention and treatment
CN201459715U (en) * 2009-07-29 2010-05-12 中铁二院工程集团有限责任公司 Anti-slide pile for vertical prestressing anchor rope

Also Published As

Publication number Publication date
CN101634145A (en) 2010-01-27

Similar Documents

Publication Publication Date Title
CN101634144A (en) Anti-slide pile with vertical prestressed anchor cables adopting secondary grouting
CN101942833B (en) Frameless unbonded post-tensioned prestressed uplift filling pile and construction method thereof
CN102535456A (en) Back-anchored uplift pile with flexible pile top
CN102345291A (en) Partially prestressed supporting cantilever pile
CN113005926A (en) Construction method of mountain area abrupt slope pier reinforcing device
CN210562163U (en) Prefabricated prestressed anchor rod piece
CN102363957B (en) A kind of post-tensioned prestressing composite uplift pile
CN102808371B (en) The integral precast overlapping Continuous Bridge of a kind of simple-supported thencontinuous and construction method
CN201512786U (en) Secondary grouting type anti-slide pile with vertical prestressed anchor cable
CN201459715U (en) Anti-slide pile for vertical prestressing anchor rope
CN102345292A (en) Composite prestressed uplift pile with expansion heads
CN101634145B (en) Anti-slide pile with vertical prestressed anchor cables
CN102808372B (en) The integral precast overlapping bridge of a kind of freely-supported and construction method
CN202831388U (en) Small beam high pre-stress pre-cast beam
CN202194130U (en) Compound pre-stressed anti-pulling pile with enlarged head
CN202194131U (en) Partially prestressed cantilever soldier pile
CN216713017U (en) Prefabricated stock waist rail
CN102852280A (en) Precast pre-stressed beam with shelving corbel outs
CN102852279A (en) Prestressed reinforced concrete superposed beam having convex-concave superposed surfaces
CN202247914U (en) Fitting-slope foundation structure for rocky slope
CN202830729U (en) First simply supported then continuously supported precast integral-pouring stacking continuous bridge
CN109826186B (en) General prefabricated reinforced concrete guide wall for underground diaphragm wall and implementation method
CN210239717U (en) Strong anchor grouting supporting structure for controlling red shale tunnel
CN202595733U (en) Vertical anti-slide pile with pre-stressed anchor cables
CN103015415B (en) Post-tensioned circular foundation pit support pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant