CN101614017A - A kind of job practices of deep water earth-rock cofferdam structure - Google Patents

A kind of job practices of deep water earth-rock cofferdam structure Download PDF

Info

Publication number
CN101614017A
CN101614017A CN 200910100647 CN200910100647A CN101614017A CN 101614017 A CN101614017 A CN 101614017A CN 200910100647 CN200910100647 CN 200910100647 CN 200910100647 A CN200910100647 A CN 200910100647A CN 101614017 A CN101614017 A CN 101614017A
Authority
CN
China
Prior art keywords
sand
ballast body
rock ballast
rock
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200910100647
Other languages
Chinese (zh)
Other versions
CN101614017B (en
Inventor
陈永红
任金明
王凤军
葛益恒
蒋胜祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN2009101006470A priority Critical patent/CN101614017B/en
Publication of CN101614017A publication Critical patent/CN101614017A/en
Application granted granted Critical
Publication of CN101614017B publication Critical patent/CN101614017B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The present invention relates to a kind of job practices of deep water earth-rock cofferdam structure.Technical problem to be solved by this invention provides under a kind of deep water conditions, and the construction period is short, construction intensity is little, the earth-rock cofferdam structure job practices of good stability.The technical scheme that addresses this problem is: a. is the erection construction pontoon bridge when ordinary water level; B. utilize the pontoon bridge location to throw the back-up sand layer of gravel then; C. between sand gravel layer and rock ballast body II and rock ballast body I, utilize pontoon bridge to throw successively to rockfill slag body III and rock ballast body IV; D. after treating that reservoir level is reduced to level of dead water,, utilize bulldozer to advance method and concentrate to push away and fill out the weathering layer of sand from two sides, left and right sides end above the sand gravel layer, between rock ballast body III and the rock ballast body IV; E. the slag body V that rockfills is thrown in follow-up in weathering layer of sand upstream and downstream both sides; F. above weathering layer of sand and rock ballast body V, adopt the subregion layered rolling to fill rock ballast body VI.That the present invention is applicable to is strict to water level, (reservoir, lake) in the strict deep water of construction period built earth rock cofferdam.

Description

A kind of job practices of deep water earth-rock cofferdam structure
Technical field
The present invention relates to a kind of job practices of deep water earth-rock cofferdam structure.Mainly be applicable to strict to water level, (reservoir, lake) in the strict deep water of construction period built earth rock cofferdam.
Background technology
No matter be newly-built key water control project water retaining structure or the key water control project water retaining structure of having built, As time goes on, all inevitably there are problems such as maintenance, reinforcing, in order thoroughly to keep in repair, to reinforce, often need in reservoir, build earth rock cofferdam, so that form the dry work condition at upstream face, because influences such as environmental protection, power station operations, reservoir level is required again very strictness, and for this reason, the construction depth of water is often darker.The earth-rock cofferdam structure design is extremely important under the deep water conditions.Simultaneously, in order to reduce construction infection, construction period is very strict, and job practices seems extremely important for this reason.
Summary of the invention
The technical problem to be solved in the present invention is: material behavior and subaqueous construction characteristic at the problem of above-mentioned existence is filled material in conjunction with the cofferdam, provide under a kind of deep water conditions, and the construction period is short, construction intensity is little, the earth-rock cofferdam structure job practices of good stability.
The technical solution adopted in the present invention is: a kind of job practices of deep water earth-rock cofferdam structure is characterized in that may further comprise the steps:
A, when ordinary water level the erection construction pontoon bridge, utilize pontoon bridge to locate successively to throw and fill out cofferdam rock ballast body I and rock ballast body II, its side slope is not suddenly in 1: 1.5, elevation is the following 47m of ordinary water level;
B, utilize pontoon bridge location to throw the back-up sand layer of gravel then, its side slope is not suddenly in 1: 1.7, and elevation is the following 45m of ordinary water level;
C, utilize pontoon bridge to throw successively to rockfill slag body III and rock ballast body IV between sand gravel layer and rock ballast body II and rock ballast body I, and its outside side slope is suddenly in 1: 1.5, inslope is not suddenly in 1: 1.7, and elevation is the following 32m of ordinary water level;
D, treat that reservoir level is reduced to level of dead water after, above the sand gravel layer, between rock ballast body III and the rock ballast body IV, utilize bulldozer to advance method and concentrate to push away and fill out the weathering layer of sand from two sides, left and right sides end, adopt vibro replacement stone column to shake then and dash, its side slope is not suddenly in 1: 2.0, and elevation is higher than level of dead water 1.5m;
E, throw the slag body V that rockfills in weathering layer of sand upstream and downstream both sides follow-ups, its side slope is not suddenly in 1: 1.5, and elevation and weathering layer of sand top are fair;
F, adopt the subregion layered rolling to fill rock ballast body VI above weathering layer of sand and rock ballast body V, its side slope is not suddenly in 1: 1.5.
Described cofferdam structure is provided with a plastic concrete impervious wall that runs through weathering layer of sand and sand gravel layer.
The invention has the beneficial effects as follows: the present invention reasonably combines material behavior and the subaqueous construction characteristic that material is filled in the cofferdam, construct according to a definite sequence, thereby significantly reduced construction period and construction intensity, guaranteed that also deep water fills reliability of structure simultaneously.
Description of drawings
Fig. 1 is a profile of the present invention.
Fig. 2 is the construction technology schematic diagram of a among the present invention, b, three steps of c.
The specific embodiment
As shown in Figure 1 and Figure 2, present embodiment may further comprise the steps:
A, when ordinary water level 10 the erection construction pontoon bridge, utilize pontoon bridge to locate throwing successively and fill out cofferdam rock ballast body I1 and rock ballast body II2, both side slopes are not all suddenly in 1: 1.5, elevation is ordinary water level 10 following 47m, pontoon bridge is a kind of provisional bridge or the building that swims waterborne, formed by several buoyancy tank unit with good versatility and interchangeability, extensively apply to traffic support, water project construction and special engineering field, owing to adopt modular technology, mobility strong fills material and adopts the transportation of 20t dump truck;
B, utilize pontoon bridge location to throw back-up sand layer of gravel 3 then, its side slope is not suddenly in 1: 1.7, and elevation is ordinary water level 10 following 45m;
C, between sand gravel layer 3 and rock ballast body II2 and rock ballast body I1, utilize pontoon bridge to throw successively to rockfill slag body III4 and rock ballast body IV5, the outside side slope of rock ballast body III4 and rock ballast body IV5 is not suddenly in 1: 1.5, inslope is not suddenly in 1: 1.7, and elevation is ordinary water level 10 following 32m;
D, treat that reservoir level is reduced to level of dead water 11 after, above the sand gravel layer 3, between rock ballast body III4 and the rock ballast body IV5, utilize bulldozer to advance concentrated the pushing away of method and fill out weathering layer of sand 6 from two sides, left and right sides end, adopting vibro replacement stone column to shake then dashes, fill the density of weathering layer of sand 6 with increase, its side slope is not suddenly in 1: 2.0, and elevation is higher than level of dead water 1.5m;
E, throw the slag body V7 that rockfills in weathering layer of sand 6 upstream and downstream both sides follow-ups, its side slope is not suddenly in 1: 1.5, and elevation and weathering layer of sand 6 tops maintain an equal level, and fill material and adopt the 20t dump truck to transport;
F, adopt the subregion layered rolling to fill rock ballast body VI8 above weathering layer of sand 6 and rock ballast body V7, rock ballast body VI8 top width is 10m, and side slope is not suddenly in 1: 1.5.In this example, the difference in height between ordinary water level 10 and the level of dead water 11 is 20m, and therefore, the height of rock ballast body VI8 should promptly when reservoir level returns to ordinary water level 10, should not have the top of rock ballast body VI8 less than 18.5m.
In order to prevent seepage, cofferdam structure is provided with a plastic concrete impervious wall 9 that runs through weathering layer of sand 6 and sand gravel layer 3.

Claims (2)

1, a kind of job practices of deep water earth-rock cofferdam structure is characterized in that may further comprise the steps:
A, when ordinary water level (10) the erection construction pontoon bridge, utilize pontoon bridge to locate successively to throw and fill out cofferdam rock ballast body I (1) and rock ballast body II (2), its side slope is not suddenly in 1: 1.5, elevation is the following 47m of ordinary water level (10);
B, utilize pontoon bridge location to throw back-up sand layer of gravel (3) then, its side slope is not suddenly in 1: 1.7, and elevation is the following 45m of ordinary water level (10);
C, between sand gravel layer (3) and rock ballast body II (2) and rock ballast body I (1), utilize pontoon bridge to throw successively to rockfill slag body III (4) and rock ballast body IV (5), and its outside side slope is not suddenly in 1: 1.5, inslope is not suddenly in 1: 1.7, and elevation is the following 32m of ordinary water level (10);
D, treat that reservoir level is reduced to level of dead water (11) after, between sand gravel layer (3) top, rock ballast body III (4) and rock ballast body IV (5), utilize bulldozer to advance concentrated the pushing away of method and fill out weathering layer of sand (6) from two sides, left and right sides end, adopting vibro replacement stone column to shake then dashes, its side slope is not suddenly in 1: 2.0, and elevation is higher than level of dead water (11) 1.5m;
E, throw the slag body V (7) that rockfills in weathering layer of sand (6) upstream and downstream both sides follow-ups, its side slope is not suddenly in 1: 1.5, and elevation and weathering layer of sand (6) top are fair;
F, adopt the subregion layered rolling to fill rock ballast body VI (8) in weathering layer of sand (6) and rock ballast body V (7) top, its side slope is not suddenly in 1: 1.5.
2, the job practices of a kind of deep water earth-rock cofferdam structure according to claim 1 is characterized in that: described cofferdam structure is provided with a plastic concrete impervious wall (9) that runs through weathering layer of sand (6) and sand gravel layer (3).
CN2009101006470A 2009-07-13 2009-07-13 Construction method of deep water earth-rock cofferdam structure Active CN101614017B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101006470A CN101614017B (en) 2009-07-13 2009-07-13 Construction method of deep water earth-rock cofferdam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101006470A CN101614017B (en) 2009-07-13 2009-07-13 Construction method of deep water earth-rock cofferdam structure

Publications (2)

Publication Number Publication Date
CN101614017A true CN101614017A (en) 2009-12-30
CN101614017B CN101614017B (en) 2011-06-08

Family

ID=41493888

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101006470A Active CN101614017B (en) 2009-07-13 2009-07-13 Construction method of deep water earth-rock cofferdam structure

Country Status (1)

Country Link
CN (1) CN101614017B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839653A (en) * 2016-05-18 2016-08-10 中铁隧道集团二处有限公司 Construction method for reconstructing cofferdam anti-seepage system in immersed tube tunnel
CN109484883A (en) * 2017-09-11 2019-03-19 广东省航运规划设计院有限公司 A kind of mountain stream region multistage unloading process system

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587397A (en) * 2012-03-13 2012-07-18 中建五局土木工程有限公司 Steel bearing plate soil-and-stone combined coffer structure and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839653A (en) * 2016-05-18 2016-08-10 中铁隧道集团二处有限公司 Construction method for reconstructing cofferdam anti-seepage system in immersed tube tunnel
CN105839653B (en) * 2016-05-18 2018-06-08 中铁隧道集团二处有限公司 A kind of immersed tube tunnel rebuilds the construction method of seepage prevention of cofferdam system
CN109484883A (en) * 2017-09-11 2019-03-19 广东省航运规划设计院有限公司 A kind of mountain stream region multistage unloading process system

Also Published As

Publication number Publication date
CN101614017B (en) 2011-06-08

Similar Documents

Publication Publication Date Title
AU2014308405A1 (en) An artificial dam of distributed coal mine underground reservoir and its constructing method
CN109610874A (en) Increase the basement and its construction process built inside existing workshop
CN106593470A (en) High-permeability water-rich sand shield terminal reinforcing system and construction method thereof
CN104033160A (en) Novel support method applicable to shallow-buried subsurface tunnel of soft soil stratum
CN103321244A (en) Construction method for additionally arranged basement in existing building on sand foundation
CN101614017B (en) Construction method of deep water earth-rock cofferdam structure
CN102444128A (en) Grouting method for ultrathin high polymer cutoff wall
CN104005571A (en) Slanting construction trestle combined with internal supporting system
CN207919486U (en) A kind of deep water soft soil foundation quay wall structure
CN206299392U (en) A kind of high osmosis water-rich sand layer shield end reinforcement system
CN203007961U (en) Gabion cofferdam structure
Smith Types of marine concrete structures
CN109487793A (en) Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment
CN107119716B (en) Construction method of highway tunnel in tidal bore area of tidal marsh
CN201459744U (en) Deepwater earth-rock cofferdam structure
CN105735196B (en) A kind of frame bucket dock structure and its manufacturing method
CN106836035A (en) A kind of cofferdam dam filling construction for being applicable existing culvert under spoil embankment
CN212003214U (en) Open-face tunnel lining structure passing through giant karst cave
CN209742904U (en) Solidification structure suitable for rich water collapsible loess tunnel
CN203977385U (en) Be applied to the self adaptation distortion anti-seepage channel of minery
CN207109624U (en) The deep embeded type stake of culvert, compound contignation are set in a kind of karst region
CN209669910U (en) A kind of karst ground treatment crosses over the combination pile slab structure of larger molten chamber
CN106351173A (en) Water-permeable breakwater structure
EP2758300A1 (en) Floating energy-autonomous platforms, and method for the production thereof
CN207159948U (en) Mud-rock flow blocking dam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant