CN101608805B CN2008100500844A CN200810050084A CN101608805B CN 101608805 B CN101608805 B CN 101608805B CN 2008100500844 A CN2008100500844 A CN 2008100500844A CN 200810050084 A CN200810050084 A CN 200810050084A CN 101608805 B CN101608805 B CN 101608805B
Authority
CN
China
Prior art keywords
heating pipeline
radiator
hot water
water pipe
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008100500844A
Other languages
Chinese (zh)
Other versions
CN101608805A (en
Inventor
季三荣
张建成
章德尚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Fifth Construction & Installation Engineering (group) Co Ltd
Original Assignee
Henan Fifth Construction & Installation Engineering (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Fifth Construction & Installation Engineering (group) Co Ltd filed Critical Henan Fifth Construction & Installation Engineering (group) Co Ltd
Priority to CN2008100500844A priority Critical patent/CN101608805B/en
Publication of CN101608805A publication Critical patent/CN101608805A/en
Application granted granted Critical
Publication of CN101608805B publication Critical patent/CN101608805B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Heat-Pump Type And Storage Water Heaters (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a mounting method of a household metering heating pipeline, which adopts two-pipe ring reversed return system. The invention is characterized in that the heating pipelines are composed of a fixed heating pipeline and a standby heating pipeline; the installation of a vertical branched pipe is concealed and a special pre-buried hot water pipe assembly is adopted during the concealed installation, meanwhile a pollution discharge total riser is arranged in tube well, pollution discharge valves are all installed on a supply and return water main pipe of a buried pipe for each household, two rows of pollution valves are communicated by threeway, then are communicated to the pollution discharge total riser in the tube well. By using the mounting method of the invention, the cross frequency and time of heating pipeline mounting and civil engineering construction are reduced, the work efficiency and quality of the heating pipeline mounting and the civil engineering construction are improved. Meanwhile the on-site fusion welding joints are reduced, the washing and pollution discharge of the household metering heating pipeline are facilitated, the cleaning of the household metering heating pipeline is ensured, the work condition of the household metering heat meter is improved, and thus the service life of the heat meter is prolonged by using the mounting method of the invention.

Description

The installation method of household metering heating pipeline and special-purpose pre-buried hot water water pipe sub-assembly
Technical field
The present invention relates to a kind of installation method and special-purpose pre-buried hot water water pipe sub-assembly of household metering heating pipeline.
Background technology
For energy-conservation, in the central heating design of the commercial house, all should adopt household metering at present.But in fact household metering is difficult to promote, and the service life that it is calorimeter that household metering is difficult to promote a major reason technically is short, and the cleannes of water quality be cannot say for sure to demonstrate,prove in the heating system.Existing household metering heating pipeline all melting welding is an one, except that radiator detachably, other pipeline all can not be taken cleaning apart, and the whole system process of washing is difficult to guarantee the cleannes of pipeline, cause the particular pollutant in the pipeline to be difficult for discharging, after these particular pollutants are heated by the hot water in the heating system, the water quality in the long-time contaminated system of meeting, this is one of reason of calorimeter weak point in service life.
In the design of existing goods room household metering radiator heating, common design has three kinds, and they are respectively: 1. single tube tandem indoor system.2. radiate the double hose system.3. annular reversed return system.
Back one group of radiator water inlet of single tube tandem indoor system is from the backwater of last group of radiator, this will cause following problem: but the water emptying in one group of last radiator, water in other radiator all can't emptying, if in the pressure testing in winter, do not perform antifreezely, except that one group of last radiator, other radiator all can be freezing, the bigger dirt of density can't be discharged in the ground pipe laying, and promptly dirt such as the grains of sand and metal welding slag all can't be discharged.
Radiation double hose system need use the metal water knockout drum, all there is the control ball valve on each road of metal water knockout drum, these ball valves damage easily, as long as there is one road ball valve to damage on the water knockout drum, the necessary integral replacing of water knockout drum is because each group radiator all will be installed control valve, the ball valve of water knockout drum is sheerly unnecessary, in case the heating back is damaged, replacing is got up very difficult, so the metal water knockout drum is the big hidden danger of one in the household metering heating pipeline.Existing metal water knockout drum all is installed in indoor, it must above ground levelly be installed, this can't discharge the particular pollutant that enters in the pipeline when installing, also make the pressure testing water in the radiator can't emptying, cause the freezing radiator of pressure testing in winter, metal water knockout drum not only price is expensive, and the used pipeline of this design is many.Cost height not only, and extremely inconvenient when causing the owner to fit up ground.
Two-tube annular reversed return system: in the process of this system's operation, the dirt in the radiator can accumulate in the buried backwater main because of washing away, and the dirt ratio of discharging in the system pipeline is easier to this SR minimum.The weak point of this system is to use ground pipe laying less than one times than the single tube train more, and cost is slightly higher than single tube train, but this system has solved the problem that exists in preceding two kinds of system forms, is the system form of pipe laying heating compatibly.
The installation method of existing plastic water pipe pipeline all is melting welding at the scene, because the dust and sand of erecting bed is more, adds that the skill differential of installer's welding technology is bigger, and fusion welding quality is difficult to guarantee.All joint made by flame weldings place must be behind pressure test leak-detecting could be hidden.During melting welding heat time heating time long, can produce the melting welding shrink-ring in the weld pipe, serious shrink-ring even can blocking pipeline.The melting welding shrink-ring is not cleared up in on-the-spot melting welding, can't check the melting welding shrink-ring yet, and the melting welding shrink-ring can increase SR, also strengthens operation energy consumption; Also shelter evil people and countenance evil practices easily on the melting welding shrink-ring, influence the water quality of heating system.
The installation method of existing household metering heating pipeline all is usually: building in face of the ground, lay along the wall limit earlier and fixedly heating installation for the backwater main, build ground again.For the confession return branch and the pressure test leak-detecting of radiator are installed, when building ground, the ground that leads to radiator arm place wouldn't be built.Installing and fixing of radiator will be carried out after metope just whitewashes, fix radiator after, connect the confession return branch of radiator again, and then pressure testing, treat pressure testing pass through to manage check and accept after, could the teeming radiator for the ground at return branch place.Because repeatedly intersecting, heating pipeline installation and civil engineering carry out, project progress not only interacts, also influencing heating pipeline installs and the civil engineering quality, cause radiator by cement mortar and coating repeated pollution, add the phenomenon of trampling radiator is often arranged when window frame and glass are installed, cause the radiator that has fixed loosening, the heating pipeline that pressure testing is good leaks again, before the heating engineering final acceptance, water power contractor will drop into more artificial cleaning radiator, the also mopping again that has, the trimming pipeline.
After key is handed in the existing goods room, many owners will remove bright dress heating pipeline and radiator, reinstall hidden pipe, and select high-grade radiator handsome in appearance for use, also there are many owners will change the position of radiator, the design and installation method of the existing heating pipeline of this explanation, the requirement of Chinese's pursuing individualityization that incompatible affluence is fast got up, thus caused limited resources and artificial waste.
Summary of the invention
Technical problem to be solved by this invention provides a kind of installation method of household metering heating pipeline.
Second technical problem to be solved by this invention provides the special-purpose pre-buried hot water water pipe sub-assembly in a kind of above-mentioned installation method.
For solving above-mentioned first technical problem, the installation method of household metering heating pipeline of the present invention adopts two-tube annular reversed return system, and heating pipeline is by fixedly heating pipeline and standby heating pipeline are formed; The upright arm of radiator adopts the concealed installation mode and adopt special-purpose pre-buried hot water water pipe sub-assembly when concealed installation, in pipe well, establish simultaneously the blowdown main riser, ground, each family pipe laying for the backwater main blowoff valve is installed all along ground, after two blowoff valves are connected with threeway, again with pipe well in the blowdown main riser connect.
As a kind of improvement of the present invention, the concealed installation mode of the upright arm of radiator is divided into three phases, and the phase I is when laying bricks wall or casting concrete wall, reserves the groove of special-purpose pre-buried hot water water pipe sub-assembly on the wall with template; Second stage is the installation and the pressure testing of hidden pipeline; The step the first that this stage comprises is to build in face of the ground, lays along the wall limit earlier and fixingly builds ground again for the backwater main, and the ground that leads to the groove place of special-purpose pre-buried hot water water pipe sub-assembly wouldn't be built; The secondth, after solidify on the ground of having built, special-purpose pre-buried hot water water pipe sub-assembly and the buried main melting welding reserved in the groove are connected, with behind the pre-buried hot water water pipe of special use sub-assembly outer wire connection mouth in upper end or the internal thread interface correction location, tentatively fix then with cement mortar; The 3rd is with loose joint and interim pressure testing flexible pipe one group of radiator in the each household to be connected for, the upright arm of backwater, other radiator seals with stifle or plug for outer wire connection mouth of the upright arm of backwater or internal thread interface, then hidden pipeline pressure testing is checked and accepted, the ground around special-purpose pre-buried hot water water pipe sub-assembly and the buried main interface is built in last teeming, and the pre-buried hot water water pipe of hidden special use sub-assembly; Phase III is fixedly heating pipeline radiator installation, connection and pressure testing stage, connects hidden pipeline and bright tubulature road and carries out the pressure testing of radiator flow control valve and system with loose joint; This stage wall plaster and window in work progress carries out after basic the end is installed; Standby heating pipeline need not be installed radiator.
For solving above-mentioned second technical problem, the pre-buried hot water water pipe of special use of the present invention sub-assembly includes straight tube, straight tube one end fixedly is communicated with outer silk elbow or internal thread elbow, and the straight tube other end fixedly is communicated with a melting welding elbow, and melting welding elbow and straight tube injection moulding or melting welding are integral.
Adopt installation method of the present invention, reduced the intersection number of times and the time of heating pipeline installation and civil engineering, improved the work efficiency and the quality of heating pipeline installation and civil engineering; Reduce on-the-spot joint made by flame welding, made things convenient for the cleaning and the blowdown of household metering heating pipeline, guaranteed the cleaning of household metering heating pipeline, improved the condition of work of metering of heat supplied on a household basis table, therefore can prolong the service life of calorimeter; The phase III that makes the heating pipeline radiator found arm concealed installation method simultaneously can be transferred to the owner and finish, thereby fully satisfies the requirement of most owner's pursuing individualityizatioies, causes limited resources and artificial waste when avoiding the owner to change heating pipeline.
The pre-buried hot water water pipe of special use of the present invention assembling unit structure is simple, easy to use, is suitable for using when radiator founds the arm concealed installation.
Description of drawings
Fig. 1 is a household metering heating system schematic in the involved pipe well of installation method of the present invention;
Fig. 2 is the horizontal layout schematic diagram at A place among Fig. 1;
Fig. 3 is the special-purpose pre-buried hot water water pipe sub-assembly that has outer silk elbow of the present invention;
Fig. 4 is the special-purpose pre-buried hot water water pipe sub-assembly that has the internal thread elbow of the present invention.
The specific embodiment
The design and installation method of household metering heating pipeline of the present invention adopts two-tube annular reversed return system as shown in Figure 1, be provided with total return pipe 1, total feed pipe 2 and blowdown main riser 3 in pipe well, wherein heating pipeline adopts fixedly that heating pipeline adds standby heating pipeline; When radiator founds the arm concealed installation, adopt special-purpose pre-buried hot water water pipe sub-assembly, in pipe well, establish simultaneously blowdown main riser 3 as depicted in figs. 1 and 2, water main 4, the backwater main 5 of each ground, family pipe laying all are equipped with blowoff valve 10 along ground, after the 10 usefulness threeways 11 of two blowoff valves are connected, again with pipe well in blowdown main riser 3 connect.
The installation of the upright arm of the radiator of household metering heating pipeline is divided into three phases, and the phase I is when laying bricks wall or casting concrete wall, reserves the groove of special-purpose pre-buried hot water water pipe sub-assembly on the wall with template; Second stage is the installation and the pressure testing of hidden pipeline; The step the first that this stage comprises is to build in face of the ground, lays along the wall limit earlier and fixingly builds ground again for backwater main 4,5, and the ground that leads to the groove place of special-purpose pre-buried hot water water pipe sub-assembly wouldn't be built; The secondth, after solidify on the ground of having built, special-purpose pre-buried hot water water pipe sub-assembly and the buried main melting welding reserved in the groove are connected, behind the outer wire connection mouth or internal thread interface correction location with the pre-buried hot water water pipe of special use sub-assembly upper end, tentatively fix then with cement mortar; The 3rd is with loose joint and interim pressure testing flexible pipe one group of radiator in the each household to be connected for, the upright arm of backwater.As shown in Figure 3, Figure 4, other radiator then seals with stifle 24 as adopting outer wire connection mouth for the upright arm of backwater, as adopting the internal thread interface then with plug 23 sealings.Then hidden pipeline pressure testing is checked and accepted, the ground around special-purpose pre-buried hot water water pipe sub-assembly and the buried main interface is built in last teeming, and the pre-buried hot water water pipe of hidden special use sub-assembly;
Phase III is fixedly heating pipeline radiator installation, connection and pressure testing stage, connects hidden pipeline and bright tubulature road and carries out the pressure testing of radiator flow control valve and system with loose joint; This stage wall plaster and window in work progress carries out after basic the end is installed; Standby heating pipeline need not be installed radiator; This stage also can be finished by the owner, only provides the heat dissipation capacity of respectively organizing radiator during design, freely selects radiator by the owner.
If the upright arm of radiator needs bright dress, can be undertaken by following two stages.Phase I is that the ground pipe laying is installed the pressure testing stage, its step the first be lay along the wall limit and fixedly radiator for backwater main 4,5, and then build ground, the ground that leads to the upright arm place of radiator wouldn't be built; The secondth, after solidify on the ground of having built, radiator is installed for the upright arm threeway of backwater, this threeway can be the threeway of outer silk, also can be the internal thread threeway; The 4th is radiator to be proofreaied and correct the back, location for the interface of the upright arm threeway of backwater fix with cement mortar; The 5th is with loose joint and interim pressure testing flexible pipe the interface that one group of radiator in the each household supplies, backwater stands arm outer silk threeway or internal thread threeway to be connected, other radiator of this family supplies the outer silk or the internal thread interface of upright arm outer silk threeway of backwater or internal thread threeway to seal with plug or stifle respectively, divides family or subdivision to buried confession, the pressure testing of backwater main then; The 6th is after pressure testing is qualified, builds the ground of the upright arm interface of radiator of not building in the first step.Second stage is connected ground pipe laying pipeline and radiator pipeline for installing and connecting radiator, radiator flow control valve and system's pressure testing stage with loose joint, carries out system's pressure testing then; This stage carries out after wall plaster and the basic end of window installation; For spare duct, just radiator need not be installed, second stage also can be finished by the owner, only provides the heat dissipation capacity of respectively organizing radiator during design, freely selects radiator by the owner.
The pre-buried hot water water pipe of special use of the present invention sub-assembly includes straight tube 22, and straight tube one end fixedly is communicated with an elbow 20, and the straight tube other end fixedly is communicated with a melting welding elbow 21.As shown in Figure 3 and Figure 4, described elbow 20 can also can be the internal thread elbow for outer silk elbow.Described melting welding elbow 21 is integral with straight tube 22 injection mouldings or melting welding, and requiring during melting welding does not have tangible melting welding shrink-ring in the pipe, and qualified through pressure testing.As shown in Figure 3, when elbow 20 adopts the elbow of internal thread interface, in the internal thread interface, be equiped with plug 23.As shown in Figure 4, outside adopting, elbow 20 during the elbow of wire connection mouth, is stamped stifle 24 on the wire connection mouth outside.As shown in Figure 3, Figure 4, on the interface of melting welding elbow, be provided with vinyl cover 25.

Claims (3)

1. the installation method of a household metering heating pipeline adopts two-tube annular reversed return system, it is characterized in that: heating pipeline is by fixedly heating pipeline and standby heating pipeline are formed; The upright arm of radiator adopts the concealed installation mode and adopt special-purpose pre-buried hot water water pipe sub-assembly when concealed installation, in pipe well, establish simultaneously the blowdown main riser, ground, each family pipe laying for the backwater main blowoff valve is installed all along ground, after two blowoff valves are connected with threeway, again with pipe well in the blowdown main riser connect.
2. the installation method of household metering heating pipeline according to claim 1, it is characterized in that: the concealed installation mode of the upright arm of radiator is divided into three phases, phase I is when laying bricks wall or casting concrete wall, reserves the groove of special-purpose pre-buried hot water water pipe sub-assembly on the wall with template;
Second stage is the installation and the pressure testing of hidden pipeline; The step the first that this stage comprises is to build in face of the ground, lays along the wall limit earlier and fixingly builds ground again for the backwater main, and the ground that leads to the groove place of special-purpose pre-buried hot water water pipe sub-assembly wouldn't be built; The secondth, after solidify on the ground of having built, special-purpose pre-buried hot water water pipe sub-assembly and the buried main melting welding reserved in the groove are connected, with behind the pre-buried hot water water pipe of special use sub-assembly outer wire connection mouth in upper end or the internal thread interface correction location, tentatively fix then with cement mortar; The 3rd is with loose joint and interim pressure testing flexible pipe one group of radiator in the each household to be connected for, the upright arm of backwater, other radiator seals with stifle or plug for outer wire connection mouth of the upright arm of backwater or internal thread interface, then hidden pipeline pressure testing is checked and accepted, the ground around special-purpose pre-buried hot water water pipe sub-assembly and the buried main interface is built in last teeming, and the pre-buried hot water water pipe of hidden special use sub-assembly;
Phase III is fixedly heating pipeline radiator installation, connection and pressure testing stage, connects hidden pipeline and bright tubulature road and carries out the pressure testing of radiator flow control valve and system with loose joint; This stage wall plaster and window in work progress carries out after basic the end is installed; Standby heating pipeline need not be installed radiator.
3. realize the special-purpose pre-buried hot water water pipe sub-assembly described in the installation method of claim 1 or 2, it is characterized in that: include straight tube, straight tube one end fixedly is communicated with outer silk elbow or internal thread elbow, the straight tube other end fixedly is communicated with a melting welding elbow, and melting welding elbow and straight tube injection moulding or melting welding are integral.
CN2008100500844A 2008-06-20 2008-06-20 Mounting method of household metering heating pipeline and pre-buried hot water pipe assembly parts Active CN101608805B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100500844A CN101608805B (en) 2008-06-20 2008-06-20 Mounting method of household metering heating pipeline and pre-buried hot water pipe assembly parts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100500844A CN101608805B (en) 2008-06-20 2008-06-20 Mounting method of household metering heating pipeline and pre-buried hot water pipe assembly parts

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN2008101740879A Division CN101608806B (en) 2008-06-20 2008-06-20 Mounting method of individually-charged heating pipelines

Publications (2)

Publication Number Publication Date
CN101608805A CN101608805A (en) 2009-12-23
CN101608805B true CN101608805B (en) 2011-05-11

Family

ID=41482647

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100500844A Active CN101608805B (en) 2008-06-20 2008-06-20 Mounting method of household metering heating pipeline and pre-buried hot water pipe assembly parts

Country Status (1)

Country Link
CN (1) CN101608805B (en)

Also Published As

Publication number Publication date
CN101608805A (en) 2009-12-23

Similar Documents

Publication Publication Date Title
CN109614723B (en) Comprehensive construction method based on BIM technology
EP3296605B1 (en) Prefabricated bamboo composite pipe gallery
CN103437556B (en) Building water supply and drainage and heating engineering waterproofing and insulation construction method
CN103967078B (en) The pre-buried replaceable pipe-line system of a kind of building water supply
CN108443590A (en) Side-type direct-burried part and its construction method
CN206268618U (en) A kind of pipeline support frame used in pipe gallery and its external member
CN101608805B (en) Mounting method of household metering heating pipeline and pre-buried hot water pipe assembly parts
CN101608806B (en) Mounting method of individually-charged heating pipelines
CN209194649U (en) A kind of H-type pipe being easily installed
CN201284886Y (en) Pre-buried water pipe assembly
CN206800600U (en) A kind of high level uses modular same-layer drainage arrangement
CN216009832U (en) Municipal administration drainage is with prefabricated composite tube structure
CN206034485U (en) Corrugate ring pipe structure utility tunnel
CN212715245U (en) Drainage pipe with anti-reflux function for building water supply and drainage
CN107059998A (en) A kind of flexible tube-in-tube water supply component and its construction usage method
CN204676934U (en) A kind of integrated draining integral bathroom water-proof chassis
CN208074294U (en) Side-type direct-burried part
CN106090495A (en) A kind of built-in type list standpipe eddy flow threeway
CN105908778A (en) Comprehensive pipe rack for corrugated spiral pipe structure
CN206902744U (en) A kind of easy-maintaining multifunctional water-proofing component
CN206034484U (en) Corrugate spiral pipe structure utility tunnel
CN205261040U (en) Direct -burried breaking of contact formula sleeve pipe
CN201972234U (en) Drainage device
CN204081034U (en) A kind of Integral glass fibre reinforced plastic inspection pit
CN216196671U (en) A hang mould construction structures for super narrow hydroelectric well

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant