CN101608548B - Method for protecting underground structure of single round shield side face construction in close distance - Google Patents
Method for protecting underground structure of single round shield side face construction in close distance Download PDFInfo
- Publication number
- CN101608548B CN101608548B CN2009100549164A CN200910054916A CN101608548B CN 101608548 B CN101608548 B CN 101608548B CN 2009100549164 A CN2009100549164 A CN 2009100549164A CN 200910054916 A CN200910054916 A CN 200910054916A CN 101608548 B CN101608548 B CN 101608548B
- Authority
- CN
- China
- Prior art keywords
- shield
- construction
- underground structure
- tunnel
- underground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 62
- 238000000034 method Methods 0.000 title claims abstract description 41
- 238000012544 monitoring process Methods 0.000 claims abstract description 35
- 238000004458 analytical method Methods 0.000 claims abstract description 7
- 238000004088 simulation Methods 0.000 claims abstract description 7
- 238000012360 testing method Methods 0.000 claims abstract description 6
- 238000013461 design Methods 0.000 claims abstract description 3
- 239000002689 soil Substances 0.000 claims description 42
- 238000006073 displacement reaction Methods 0.000 claims description 27
- 239000011148 porous material Substances 0.000 claims description 27
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 27
- 230000005641 tunneling Effects 0.000 claims description 16
- 230000035515 penetration Effects 0.000 claims description 10
- 230000001186 cumulative effect Effects 0.000 claims description 9
- 230000002787 reinforcement Effects 0.000 claims description 5
- 230000015572 biosynthetic process Effects 0.000 claims description 4
- 238000010586 diagram Methods 0.000 claims description 4
- 238000005516 engineering process Methods 0.000 claims description 4
- 230000003068 static effect Effects 0.000 claims description 4
- 238000001514 detection method Methods 0.000 claims 1
- 238000005457 optimization Methods 0.000 claims 1
- 238000009412 basement excavation Methods 0.000 abstract description 8
- 229910000831 Steel Inorganic materials 0.000 description 4
- 238000004364 calculation method Methods 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000007596 consolidation process Methods 0.000 description 3
- 230000001681 protective effect Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 229920006395 saturated elastomer Polymers 0.000 description 2
- 230000002159 abnormal effect Effects 0.000 description 1
- 230000001133 acceleration Effects 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 230000010485 coping Effects 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000035945 sensitivity Effects 0.000 description 1
- 238000013517 stratification Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- 230000009974 thixotropic effect Effects 0.000 description 1
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明涉及一种建筑工程技术领域的单圆盾构侧面近距离施工保护地下结构的方法。包括步骤:采用Robertson方法;通过地下结构和隧道的设计图纸确定盾构穿越地下结构参数;采用三维有限元模型进行数值模拟;制定监测方案,在穿越施工前,现场进行测点布置和监测;检测试推的工效,选择施工参数;通过实时监测反馈分析进行施工;对设置的监测点进行跟踪监测,直至各项监测数据稳定在步骤(6)所述优化安全施工参数的范围。本发明确保了地下结构的正常使用和盾构的顺利掘进,所采取的技术措施适用于单圆盾构近距离侧面通过各种地下结构的需要,为其提供了一项重要的技术保证。
The invention relates to a method for protecting an underground structure by short-distance construction on the side of a single-circle shield in the technical field of construction engineering. Included steps: using the Robertson method; determining the parameters of the shield passing through the underground structure through the design drawings of the underground structure and tunnel; using a three-dimensional finite element model for numerical simulation; formulating a monitoring plan, and conducting on-site measuring point layout and monitoring before the crossing construction; testing According to the work efficiency of the trial push, select the construction parameters; carry out the construction through real-time monitoring feedback analysis; track and monitor the set monitoring points until the monitoring data stabilizes within the scope of the optimized safe construction parameters described in step (6). The invention ensures the normal use of the underground structure and the smooth excavation of the shield, and the technical measures adopted are suitable for the requirement that the single-circle shield pass through various underground structures at a short distance side, providing an important technical guarantee for it.
Description
技术领域technical field
本发明涉及一种建筑工程技术领域的方法,具体是一种单圆盾构侧面近距离施工保护地下结构的方法。The invention relates to a method in the technical field of construction engineering, in particular to a method for protecting an underground structure by short-distance construction on the side of a single-circle shield.
背景技术Background technique
伴随着城市建设的加速以及充分利用城市建设空间资源的需要,城市地下空间进一步开发,地下管线、隧道及其它地下建、构筑物的日益密集,国内城市轨道交通建设发展越来越迅速。在轨道交通建设中,盾构工法由于其优越性在国内的应用越来越多。为了使轨道交通尽快形成网络达到预期的规模效应,轨道交通的建设也在加速。但城市规划建设,特别是通常伴随地铁建设的沿线开发的增多,工程建设所面临的是越来越复杂的周边环境,穿越障碍物或近距离通过既有建(构)筑物的情况也越来越多。工程施工时既需要对既有建(构)筑物进行保护,又要确保工程本身的安全性和进展顺利,因此对不同的情况采用相应的应对技术十分必要。如何确保在穿越施工过程中以及穿越后邻近已建建(构)筑物的正常使用,已成为盾构法隧道工程中亟待解决的难题之一。With the acceleration of urban construction and the need to make full use of urban construction space resources, urban underground space is further developed, and underground pipelines, tunnels, and other underground buildings and structures are increasingly dense, and domestic urban rail transit construction is developing more and more rapidly. In the construction of rail transit, the shield tunneling method has been applied more and more in China due to its superiority. In order to form a rail transit network as soon as possible to achieve the expected scale effect, the construction of rail transit is also accelerating. However, urban planning and construction, especially along with the increase of development along the subway construction, the project construction is faced with more and more complex surrounding environment, and the situation of crossing obstacles or passing existing buildings (structures) at close range is becoming more and more difficult. more and more. During the construction of the project, it is necessary to protect the existing buildings (structures) and ensure the safety and smooth progress of the project itself. Therefore, it is necessary to adopt corresponding coping techniques for different situations. How to ensure the normal use of the adjacent built (structure) structures during the crossing construction process and after the crossing has become one of the problems to be solved urgently in shield tunneling engineering.
确定场地土的地质分层和土性参数对保证盾构成功实现近距离穿越至关重要。1992年,Robertson等(Estimating coefficient of consolidation from piezoconetets,Canadian Geotechnical Journal,29(4),551-557;加拿大国家科学委员会主办的《加拿大岩土工程学报》,“用孔隙水压式的静力触探测定土层的固结性状与相关计算公式” )通过应用孔隙水压力的分布规律来确定土层分布及土层的固结性状与相关计算公式(以下简称Robertson方法)。It is very important to determine the geological stratification and soil parameters of the site soil to ensure the successful short-distance crossing of the shield. In 1992, Robertson et al. (Estimating coefficient of consolidation from piezoconetets, Canadian Geotechnical Journal, 29(4), 551-557; Canadian Journal of Geotechnical Engineering sponsored by the Canadian National Science Council, "Using pore water pressure static contact Detecting the consolidation properties of soil layers and related calculation formulas") By applying the distribution law of pore water pressure to determine the distribution of soil layers and the consolidation properties of soil layers and related calculation formulas (hereinafter referred to as the Robertson method).
经对现有的技术文献检索发现,发明人为周文波、顾春华、吴惠明等,申请号为CN200610116618.X,专利申请的名称为“双圆盾构近距离穿越建筑物或构筑物的施工方法”,该技术通过采用穿越建筑物或构筑物的前期准备、对建筑物或构筑物预先采取保护措施、施工监测、设置合理的近距离穿越建筑物或构筑物时的盾构施工参数、双圆盾构穿越后的二次注浆等步骤,但该技术并不适用实现单圆盾构近距离穿越地下结构,同时该技术的施工监测,并未记载其测点布置方法,也未明确实时监测和盾构施工的关系。After searching the existing technical literature, it is found that the inventors are Zhou Wenbo, Gu Chunhua, Wu Huiming, etc., and the application number is CN200610116618.X. The technology adopts the pre-preparation for crossing buildings or structures, taking protective measures for buildings or structures in advance, construction monitoring, setting reasonable shield construction parameters when crossing buildings or structures at short distances, and double-circle shield tunneling after crossing. Grouting and other steps, but this technology is not suitable for the single-round shield to pass through the underground structure at close range. At the same time, the construction monitoring of this technology does not record the method of measuring point layout, nor does it clarify the relationship between real-time monitoring and shield construction. .
发明内容Contents of the invention
本发明针对现有技术中存在的不足和缺陷,提出一种单圆盾构侧面近距离施工保护地下结构的方法。本发明确保了地下结构的正常使用和盾构的顺利掘进,所采取的技术措施适用于单圆盾构近距离侧面通过各种地下结构的需要,为其提供了一项重要的技术保证。Aiming at the deficiencies and defects in the prior art, the invention proposes a method for protecting an underground structure by short-distance construction on the side of a single-circle shield. The invention ensures the normal use of the underground structure and the smooth excavation of the shield, and the technical measures adopted are suitable for the requirement that the single-circle shield pass through various underground structures at a short distance side, providing an important technical guarantee for it.
本发明是通过以下技术方案实现的,包括以下步骤:The present invention is achieved through the following technical solutions, comprising the following steps:
(1)采用Robertson方法利用孔隙水压式的静力触探检测地层的贯入阻力与孔隙水压力随深度的变化曲线(称为贯入阻力曲线与孔隙水压力分布曲线);再以测得的孔隙水压与贯入阻力之比为横轴,以贯入阻力与初始地层应力之比为纵轴,作出关系图,将该图划分若干不同土性特征区,每一种特征代表一种土的类型;将实测的静力触探曲线的数据标于该图以判断场地土层的类型;再根据土的类型对照贯入阻力曲线与孔隙水压力分布曲线,确定土层分布的深度和厚度,包括粘性土层下砂性土的埋深。(1) Using the Robertson method to detect the formation penetration resistance and pore water pressure variation curve with depth (called the penetration resistance curve and pore water pressure distribution curve) by pore water pressure static penetration sounding; The horizontal axis is the ratio of pore water pressure to penetration resistance, and the vertical axis is the ratio of penetration resistance to initial formation stress. A relationship diagram is drawn, and the diagram is divided into several regions with different soil properties. Each characteristic represents a The type of soil; mark the data of the measured static penetrating curve on the map to judge the type of soil layer on the site; then compare the penetration resistance curve and pore water pressure distribution curve according to the type of soil to determine the depth and distribution of the soil layer Thickness, including the burial depth of sandy soil under the cohesive soil layer.
(2)通过地下结构和隧道的设计图纸确定盾构穿越地下结构的总长度Ld米,区间隧道埋深Hmin~Hmax米,地下结构和盾构隧道的相互距离Lmin~Lmax米,隧道的顶部埋深H米,隧道的直径D米。(2) According to the design drawings of the underground structure and the tunnel, determine the total length L d meters of the shield passing through the underground structure, the buried depth of the interval tunnel H min ~ H max meters, and the mutual distance between the underground structure and the shield tunnel L min ~ L max meters , the buried depth of the top of the tunnel is H meters, and the diameter of the tunnel is D meters.
(3)采用三维有限元模型对盾构近距离通过地下结构的整个穿越过程进行数值模拟。三维有限元模型范围:水平方向应大于(2H+3D+Lmin)米,深度方向应大于(2H+2D)米,长度据工程实际确定,隧道置于模型的中间,底面距隧道底应大于2D米。边界条件设定如下:隧道内侧采用自由边界,模型两侧约束水平位移,模型底部同时约束竖向与水平位移。土体的本构关系采用考虑弹塑性应变的修正剑桥模型,隧道结构取为弹性体。(3) The three-dimensional finite element model is used to numerically simulate the entire passing process of the shield passing through the underground structure at close range. Three-dimensional finite element model range: the horizontal direction should be greater than (2H+3D+L min ) meters, the depth direction should be greater than (2H+2D) meters, the length is determined according to the actual project, the tunnel is placed in the middle of the model, and the distance between the bottom surface and the tunnel bottom should be greater than 2D meters. The boundary conditions are set as follows: the inner side of the tunnel adopts a free boundary, the horizontal displacement is constrained on both sides of the model, and the vertical and horizontal displacement are constrained at the bottom of the model at the same time. The constitutive relation of the soil adopts the modified Cambridge model considering elastic-plastic strain, and the tunnel structure is taken as elastic body.
通过步骤(3)所述的数值模拟,获得结果为:By the numerical simulation described in step (3), the obtained result is:
①给出盾构、土体、地下结构在穿越施工过程中的判断盾构顺利穿越的可行性。①Give the feasibility of the smooth crossing of the shield tunneling machine, the soil body and the underground structure during the crossing construction process.
所述的判断盾构顺利穿越的可行性,其条件当满足:地表位移:-30mm~+10mm;地下结构位移:累积值:-15mm~+15mm,单次最大变化值:-5mm~+5mm;地下结构塑性区体积:V=0的条件时,不需要对特定区域土体和地下结构采取任何加固措施。The above conditions for judging the feasibility of shield tunneling smoothly should be met: surface displacement: -30mm~+10mm; underground structure displacement: cumulative value: -15mm~+15mm, single maximum change value: -5mm~+5mm ; Underground structure plastic zone volume: under the condition of V=0, there is no need to take any reinforcement measures for the soil and underground structures in specific areas.
②确定盾构近距离穿越对地下结构产生影响的范围Le米,以及穿越过程中地下结构需要重点保护的区段长度Li米。②Determine the range L e meters in which shield tunneling will affect the underground structure at short distances, and the section length L i meters in which the underground structure needs to be protected during the pass.
(4)针对步骤(3)通过数值模拟确定的重点保护穿越区段Li米,制定详细的监测方案,在穿越施工前,现场进行测点布置和监测,包括:(4) For the key protected crossing section L i meters determined by numerical simulation in step (3), a detailed monitoring plan is formulated. Before the crossing construction, the measuring point layout and monitoring are carried out on site, including:
①隧道和地下结构间土体的位移、孔隙水压力和土压力。① Soil displacement, pore water pressure and earth pressure between tunnel and underground structure.
②临近盾构穿越区段一边地下结构的位移和应力。② Displacement and stress of the underground structure near the shield crossing section.
③隧道横断面方向以及沿着隧道轴线方向的地表沉降和重点穿越区段内的重要建筑物的沉降。③Surface settlement in the direction of the tunnel cross section and along the direction of the tunnel axis and the settlement of important buildings in the key crossing section.
(5)结合步骤(3)有限元分析确定的盾构穿越对地下结构的影响范围Le,将距离重点保护区段Li米前20环作为盾构的试掘进区间。同时在试验段布置若干监测点,观察试推的效果,主要布置平行于隧道轴线和垂直于隧道轴线地表沉降监测点,在地下结构上布置相应水平位移监测点。通过在此区间内的试推进,初步确定后面正式近距离通过地下结构时拟采用的施工参数,主要包括:盾构的推力、推进速度、注浆量、注浆压力。(5) Combined with the influence range L e of the shield tunneling on the underground structure determined by the finite element analysis in step (3), the first 20 rings from the key protection section L i meters are used as the trial excavation interval of the shield tunnel. At the same time, a number of monitoring points are arranged in the test section to observe the effect of the test push, mainly the surface settlement monitoring points parallel to the tunnel axis and perpendicular to the tunnel axis are arranged, and the corresponding horizontal displacement monitoring points are arranged on the underground structure. Through the trial advance in this interval, the construction parameters to be adopted when formally passing through the underground structure at close range are preliminarily determined, mainly including: shield thrust, propulsion speed, grouting amount, and grouting pressure.
(6)在盾构穿越重点保护区Li米段过程中,采用现场监测和施工相紧密结合的方式,通过实时监测反馈分析进行施工。通过对监测结果的及时分析,判别前一步施工工艺和施工参数是否符合预期要求,以确定和优化下一步施工参数,确保工程顺利进行并保护地下结构的安全,安全性判断标准:(6) During the process of the shield passing through the L i meter section of the key protection area, the on-site monitoring and construction are closely combined, and the construction is carried out through real-time monitoring and feedback analysis. Through the timely analysis of the monitoring results, it is judged whether the construction process and construction parameters of the previous step meet the expected requirements, so as to determine and optimize the construction parameters of the next step, to ensure the smooth progress of the project and to protect the safety of the underground structure. Safety judgment standards:
①地表沉降:-30mm~+10mm①Surface subsidence: -30mm~+10mm
②土体水平位移:累积值:-30mm~+30mm,单次最大变化值:-15mm~+15mm②Soil horizontal displacement: cumulative value: -30mm~+30mm, single maximum change value: -15mm~+15mm
③土压力:250kPa③Earth pressure: 250kPa
⑤孔隙水压力:200kPa⑤ Pore water pressure: 200kPa
⑥地下结构应力:-10kN/m2~10kN/m2 ⑥Underground structural stress: -10kN/m 2 ~10kN/m 2
⑦地下结构位移:累积值:-15mm~+15mm,单次最大变化值:-5mm~+5mm⑦Underground structure displacement: cumulative value: -15mm~+15mm, single maximum change value: -5mm~+5mm
(7)盾构顺利完全通过地下结构后,对设置的监测点进行跟踪监测,直至各项监测数据稳定在步骤(6)所述优化安全施工参数的范围。(7) After the shield machine passes through the underground structure smoothly, track and monitor the set monitoring points until the monitoring data stabilizes within the range of the optimized safe construction parameters described in step (6).
本发明综合采取了盾构近距离侧面通过地下结构时的多种保护技术措施,采取科学、合理、可靠的方法确定盾构的施工参数,确保了地下结构的正常使用和盾构的顺利掘进。发明中所采取的技术措施可适用于单圆盾构近距离侧面通过各种地下结构的情形,为单圆盾构侧面近距离顺利通过地下结构提供了一项重要的技术保证。The present invention comprehensively adopts multiple protective technical measures when the shield passes through the underground structure at close range, adopts a scientific, reasonable and reliable method to determine the construction parameters of the shield, and ensures the normal use of the underground structure and the smooth excavation of the shield. The technical measures adopted in the invention can be applied to the situation that the single-circle shield passes through various underground structures at a short distance side, and provides an important technical guarantee for the single-circle shield to pass through the underground structures smoothly at a short distance.
附图说明Description of drawings
图1盾构侧面近距离通过地下连续墙平面图Figure 1 Plane view of the side of the shield passing through the underground diaphragm wall at close range
图2盾构侧面近距离通过地下连续墙剖面图Figure 2 Sectional view of the side of the shield passing through the underground diaphragm wall at close range
图3地表沉降观测点平面布置图Figure 3 Plane layout of observation points for land subsidence
图4钢筋应力计、测斜管、孔隙水压计、土压计平面布置图Figure 4 Plane layout of steel bar stress gauge, inclinometer pipe, pore water pressure gauge and earth pressure gauge
图5测斜管、孔隙水压计、土压计立面布置图Figure 5 Facade Layout of Inclinometer Tube, Pore Pressure Gauge, and Earth Pressure Gauge
图6钢筋应力计立面布置图Figure 6 Facade Layout of Reinforcement Stress Gauge
具体实施方式Detailed ways
下面结合附图对本发明的实施例作详细说明:本实施例在以本发明技术方案为前提下进行实施,给出了详细的实施方式和过程,但本发明的保护范围不限于下述的实施例。The embodiments of the present invention are described in detail below in conjunction with the accompanying drawings: the present embodiment is implemented on the premise of the technical solution of the present invention, and detailed implementation methods and processes are provided, but the protection scope of the present invention is not limited to the following implementations example.
实施例:Example:
某地铁区间隧道旁有一待建地下通道,通道地下连续墙施工已经结束,从区间隧道旁侧面近距离穿过,通道内部主体结构正在施工,完成了部分内衬结构。通道地下连续墙与端头盾构接受井呈L型相连接,如图1、2所示,图中显示了盾构侧面近距离通过地下连续墙平面和盾构侧面近距离通过地下连续墙剖面,盾构每环管片长度为1.2m,厚0.35m。There is an underground passage to be built next to the tunnel of a certain subway section. The construction of the underground diaphragm wall of the passage has been completed. It passes through the side of the section tunnel at a short distance. The main structure inside the passage is under construction, and part of the lining structure has been completed. The underground diaphragm wall of the channel is connected with the receiving shaft of the shield machine at the end in an L shape, as shown in Figures 1 and 2. The figure shows the plane of the shield machine passing through the diaphragm wall at close range on the side of the shield machine and the section of the shield machine passing through the diaphragm wall at a short distance on the side of the shield machine , the length of each segment of shield tunneling is 1.2m, and the thickness is 0.35m.
本实施例具体实施步骤如下:The specific implementation steps of this embodiment are as follows:
(1)经详细地质勘探,确定了穿越区各土层的分布、土体物理力学指标。盾构区间隧道主要通过的土层为:第④1层饱和软粘性土(局部为第⑤1层)。均属高含水量、高压缩性、低强度、低渗透性的饱和粘性土,具有较高的灵敏度,明显的触变特性,在动力作用下极易破坏土体结构,使土体强度骤然降低,易造成开挖面的失稳。(1) After detailed geological exploration, the distribution of soil layers and soil physical and mechanical indicators in the crossing area are determined. The soil layer that the shield section tunnel mainly passes through is: the ④ 1st layer saturated soft cohesive soil (partially the ⑤ 1st layer). All are saturated cohesive soils with high water content, high compressibility, low strength and low permeability. They have high sensitivity and obvious thixotropic characteristics. Under dynamic action, they are very easy to destroy the soil structure and reduce the soil strength suddenly. , easily lead to instability of the excavation face.
(2)盾构总的穿越长度约Ld=200m,区间隧道埋深为Hmin~Hmax=8.5m~9.1m,地下结构与隧道的距离区间为Lmin~Lmax=3.8m~12.4m,隧道顶部埋深H=9m,隧道直径D=6.2m。区间隧道和地下连续墙的竖向坡率都为9%左右,因此在整个侧向穿越过程中,区间隧道与地下连续墙间的竖向相对位置关系变化不大。附图1为盾构侧面近距离通过地下连续墙平面图,附图2为盾构侧面近距离通过地下连续墙剖面图。(2) The total crossing length of the shield is about L d = 200m, the buried depth of the tunnel in the interval is H min ~ H max = 8.5m ~ 9.1m, and the distance between the underground structure and the tunnel is L min ~ L max = 3.8m ~ 12.4 m, buried depth at the top of the tunnel H=9m, tunnel diameter D=6.2m. The vertical slope ratios of the interval tunnel and the underground diaphragm wall are both about 9%, so the vertical relative position relationship between the interval tunnel and the underground diaphragm wall does not change much during the entire lateral crossing process. Attached drawing 1 is a plan view of the side of the shield passing through the underground diaphragm wall at short distance, and Fig. 2 is a cross-sectional view of the side of the shield passing through the underground diaphragm wall at short distance.
(3)①建立三维有限元模型,模型水平方向取60m,深度方向50m,长度取为200m,隧道下底与模型底面距离为15m。对盾构近距离通过地下结构的整个穿越过程进行数值模拟。计算表明,通过设置适当的施工参数,地表位移最大值可控制在-16mm~+6mm;地下结构位移的累积最大值可控制在:-10mm~+10mm,单次最大变化值可控制在:-3mm~+3mm;且塑性区体积很容易控制在V=0,因此对土体或地下结构不需采取额外的加固措施,就可实现顺利穿越。(3) ① Establish a three-dimensional finite element model. The horizontal direction of the model is 60m, the depth direction is 50m, the length is 200m, and the distance between the bottom of the tunnel and the bottom of the model is 15m. Numerical simulation is carried out on the whole passing process of the shield passing through the underground structure at close range. Calculations show that by setting appropriate construction parameters, the maximum surface displacement can be controlled within -16mm ~ +6mm; the cumulative maximum displacement of underground structures can be controlled within: -10mm ~ +10mm, and the single maximum change value can be controlled within: - 3mm~+3mm; and the volume of the plastic zone can be easily controlled at V=0, so the smooth crossing can be realized without taking additional reinforcement measures for the soil or underground structures.
②对有限元计算结果进行多角度的分析,确定近距离穿越过程中盾构对地下连续墙产生影响的范围为Le=60m,需要重点保护的穿越区段为离盾构接受井Li=30m的范围。②Analyze the results of finite element calculations from multiple angles, and determine that the scope of the shield TBM’s impact on the underground diaphragm wall during short-distance crossing is L e = 60m, and the crossing section that needs to be protected is the distance from the shield receiving well L i = 30m range.
(4)对步骤(3)确定的Li=30m重点保护范围,在盾构近距离通过时进行现场监测,观测现场土体、地下连续墙及内衬结构的应力与变形性状。地表位移用全站式经纬仪和水准仪观测,临近地下连续墙位移和土体位移用测斜仪观测,内衬墙的内力变化用钢筋应力计观测,土中压力变化用土压力盒和孔隙水压计观测。附图3为地表沉降观测点平面布置图,附图4为钢筋应力计、测斜管、孔隙水压计、土压计平面布置图,附图5为测斜管、孔隙水压计、土压计立面布置图,附图6为钢筋应力计立面布置图。(4) For the key protection range of L i =30m determined in step (3), on-site monitoring is carried out when the shield passes through at close range, and the stress and deformation properties of the on-site soil, underground diaphragm wall and inner lining structure are observed. The ground surface displacement is observed with a total station theodolite and a level, the displacement of the adjacent underground diaphragm wall and soil mass is observed with an inclinometer, the internal force change of the lining wall is observed with a steel stress gauge, and the pressure change in the soil is observed with an earth pressure cell and a pore water pressure gauge observe. Accompanying drawing 3 is the plane layout of observation points for surface settlement, and accompanying drawing 4 is the plane layout of steel bar stress gauges, inclinometer pipes, pore water pressure gauges, and soil pressure gauges. The facade layout of the pressure gauge, and attached drawing 6 is the facade layout of the steel bar stress gauge.
(5)将重点保护区域的前20环作为穿越管线的试掘进区间。初步确定在盾构侧穿连续墙施工过程中,土仓压力设定在0.16MPa~0.25MPa;注浆压力设定在0.28MPa~0.3MPa;每个行程(1.2m)注浆量为2.0m3~3.3m3;推进速度应控制在15mm/min~30mm/min,匀速掘进,24小时连续作业。(5) The first 20 rings in the key protection area are used as the trial excavation interval for crossing the pipeline. It is preliminarily determined that in the construction process of the shield tunneling through the diaphragm wall, the pressure of the soil bin is set at 0.16MPa-0.25MPa; the grouting pressure is set at 0.28MPa-0.3MPa; the grouting amount for each stroke (1.2m) is 2.0m 3 ~ 3.3m 3 ; the propulsion speed should be controlled at 15mm/min ~ 30mm/min, excavation at a constant speed, and continuous operation for 24 hours.
(6)整个推进过程中的监测信息反映盾构对地下连续墙的影响较稳定,只出现了个别特殊情况。盾构经过第一个孔隙水压计测点位置时发现孔隙水压计的读数出现了急剧的大范围的跳动,同时地表沉降监测显示,此处地表开始出现了隆起,地下连续墙的位移变化达到了4.8mm。孔隙水压计读数异常的情况是由于盾构此时的推进速度过快,孔隙水压在封闭空间内不断积聚,无法立即消散,导致压力急剧上升。基于此现象,施工中采取了暂时停推的应对措施,待积聚的孔隙水压消散后再继续推进。此后的推进过程也改为采用白天推进,晚上停推的措施,使孔隙水压充分消散,保证了后续推进的顺利进行。对现场的监测数据进行了分析总结,给出盾构近距离通过地下连续墙的最终施工参数:土压力设定值:210kPa,正常推进过程中实际土压力控制在200kPa以下;推进速度:20mm/min;出土量:37.88m3;盾构机总推力:12750kN;注浆压力:0.56MPa,注浆量:3.0m3。(6) The monitoring information during the whole propulsion process shows that the impact of shield tunneling on the underground diaphragm wall is relatively stable, and only a few special cases have occurred. When the shield passed the first pore water pressure gauge measurement point, it was found that the readings of the pore water pressure gauge fluctuated sharply and in a large range. At the same time, the monitoring of the surface settlement showed that the surface began to bulge here, and the displacement of the underground diaphragm wall changed. Reached 4.8mm. The abnormal reading of the pore water pressure gauge is due to the fact that the advancing speed of the shield machine is too fast at this time, and the pore water pressure continuously accumulates in the enclosed space and cannot be dissipated immediately, resulting in a sharp rise in pressure. Based on this phenomenon, the countermeasures of temporary suspension of push were taken during construction, and the advance was continued after the accumulated pore water pressure dissipated. Afterwards, the propulsion process was also changed to adopt the measures of advancing during the day and stopping at night to fully dissipate the pore water pressure and ensure the smooth progress of the subsequent propulsion. The on-site monitoring data is analyzed and summarized, and the final construction parameters for the shield passing through the underground diaphragm wall at close range are given: the set value of earth pressure: 210kPa, and the actual earth pressure is controlled below 200kPa during normal advance; advance speed: 20mm/ min; unearthed volume: 37.88m 3 ; total thrust of shield machine: 12750kN; grouting pressure: 0.56MPa, grouting volume: 3.0m 3 .
(7)盾构顺利完全通过地下连续墙进入盾构接受井后,跟踪监测显示,地表沉降、土体位移、土压力、孔隙水压值变化幅度逐渐减小,最后达到稳定,地下连续墙内力和变形均无变化,整个穿越过程顺利完成。(7) After the shield machine successfully passed through the underground diaphragm wall and entered the shield receiving well, tracking and monitoring showed that the range of changes in surface settlement, soil displacement, earth pressure, and pore water pressure gradually decreased, and finally reached stability. The internal force of the underground diaphragm wall There is no change in deformation and deformation, and the entire traversal process is successfully completed.
本实施例在盾构穿越过程中,地表沉降值在-2.9mm~+2.6mm范围内变化;土体水平位移累积值范围-28.9mm~+17.5mm,最大变化值为-10.3mm;最大侧向土压力变化值为208kPa;孔隙水压力最大变化值为159kPa;邻近地下连续墙水平位移最大累积值为+12.8mm,最大变化值为为+4.8mm;内衬墙钢筋内力在-0.07kN/m2~0.89kN/m2范围内变化。由监测结果可看出,通过采取本发明的保护措施,盾构施工对周围环境影响较小,同时也保证了盾构的顺利掘进。另外,临近地下结构的位移和内力均处于较低水平,本实施例对临近地下结构起到了很好的保护作用。In this embodiment, during the shield tunneling process, the surface subsidence value varies in the range of -2.9mm to +2.6mm; the cumulative value of the horizontal displacement of the soil ranges from -28.9mm to +17.5mm, and the maximum change value is -10.3mm; The change value of the earth pressure is 208kPa; the maximum change value of the pore water pressure is 159kPa; the maximum cumulative value of the horizontal displacement of the adjacent underground diaphragm wall is +12.8mm, and the maximum change value is +4.8mm; the internal force of the inner wall reinforcement is -0.07kN/ Change within the range of m 2 ~0.89kN/m 2 . It can be seen from the monitoring results that by adopting the protective measures of the present invention, the shield construction has less impact on the surrounding environment, and at the same time, the smooth excavation of the shield is guaranteed. In addition, the displacement and internal force of the adjacent underground structure are at a relatively low level, and this embodiment plays a very good role in protecting the adjacent underground structure.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100549164A CN101608548B (en) | 2009-07-16 | 2009-07-16 | Method for protecting underground structure of single round shield side face construction in close distance |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100549164A CN101608548B (en) | 2009-07-16 | 2009-07-16 | Method for protecting underground structure of single round shield side face construction in close distance |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101608548A CN101608548A (en) | 2009-12-23 |
CN101608548B true CN101608548B (en) | 2011-04-13 |
Family
ID=41482445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100549164A Expired - Fee Related CN101608548B (en) | 2009-07-16 | 2009-07-16 | Method for protecting underground structure of single round shield side face construction in close distance |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101608548B (en) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102071944B (en) * | 2010-12-17 | 2012-12-05 | 中铁十四局集团有限公司 | Simulation detection system for surface subsidence of shield tunnel construction |
CN102155231B (en) * | 2011-03-18 | 2013-05-08 | 大连海事大学 | Quick feedback analyzing system in tunnel constructing process |
CN102157014B (en) * | 2011-04-13 | 2013-01-16 | 西安理工大学 | Method for three-dimensional visualization of comprehensive pipeline of metro |
CN102493424B (en) * | 2011-11-24 | 2014-07-30 | 广州市地下铁道总公司 | Prediction method for urban rail transit shield project |
CN103471647B (en) * | 2013-08-21 | 2016-08-10 | 国家电网公司 | A remote automatic monitoring method for a shield tunnel |
CN103510960B (en) * | 2013-10-22 | 2016-03-16 | 北京交通大学 | The sectional subsidence control method of a kind of shield structure long distance passing through building group |
CN104462855B (en) * | 2014-12-29 | 2018-11-16 | 中国石油天然气集团公司 | A kind of method and apparatus of underground structure monitoring data processing and analysis |
CN106372292A (en) * | 2016-08-29 | 2017-02-01 | 浙江大学城市学院 | Calculation method for building settlement caused by shield tunnel construction |
CN106777839A (en) * | 2017-02-28 | 2017-05-31 | 青岛理工大学 | Building damage scene construction method at most unfavorable position of tunnel construction |
CN109488312B (en) * | 2018-11-28 | 2021-02-09 | 兖州煤业股份有限公司 | Roadway driving direction correction method |
CN113153335A (en) * | 2019-11-11 | 2021-07-23 | 北京住总集团有限责任公司 | Safety management system for shield downward penetration |
-
2009
- 2009-07-16 CN CN2009100549164A patent/CN101608548B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN101608548A (en) | 2009-12-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101608548B (en) | Method for protecting underground structure of single round shield side face construction in close distance | |
Li et al. | Experimental study of the precursor information of the water inrush in shield tunnels due to the proximity of a water-filled cave | |
Zhu et al. | Challenges and development prospects of ultra-long and ultra-deep mountain tunnels | |
CN102900441B (en) | Based on country rock be badly deformed control China tunnel construction method | |
CN103410516B (en) | Minor diameter tunnel full face tunneling surrouding rock deformation early warning engineering method | |
CN101251498B (en) | A method for testing and evaluating loose circles of surrounding rock based on the principle of electromagnetic radiation | |
CN102426069B (en) | Measurement method for rock mass crustal stress under extremely high stress condition | |
CN103471647B (en) | A remote automatic monitoring method for a shield tunnel | |
CN106593526B (en) | A kind of tunnel geology karst methods of risk assessment based on fuzzy Judgment | |
CN105386474B (en) | Method for determining the impact of water-stop curtain leakage on the surrounding environment above the excavation surface of foundation pit | |
CN107861157A (en) | A kind of underground water seal cave depot runs phase micro seismic monitoring method | |
CN104947649A (en) | Control method for open caisson back soil deformation caused by pipe-jacking construction | |
CN111539052B (en) | Method for formulating settlement control standard of close-distance downward-penetrating pipe-jacking tunnel in subway shield interval | |
Liu et al. | Model test study on spatial deformation law of surrounding rock for super-large section and shallow buried tunnels | |
CN103471648A (en) | Disturbance construction monitoring method of top pipe tunnel | |
CN105257318B (en) | A kind of lining cutting localized seepage causes the method for security protection that tunnel structure is deformed | |
Guo et al. | Distribution of ground stress on Puhe coal mine | |
CN110991009B (en) | Method for determining stress deformation of buried pipeline by soil body loss below pipeline | |
CN204154307U (en) | A kind of geology settlement monitoring device | |
CN103867208B (en) | Control the method for earth's surface in tunnel and underground engineering construction process, pipeline distortion | |
Xu et al. | Investigation on the surface settlement of curved shield construction in sandy stratum with laboratory model test | |
CN102102358A (en) | Method for measuring deep sedimentation deformation of foundation by using wireless conduction water pressure meter | |
Sun et al. | Study on reasonable size of coal and rock pillar in dynamic pressure roadway segment of fully mechanized face in deep shaft | |
CN106772613A (en) | A kind of rock mass scene acoustic emission monitor(ing) sensor pushes localization method and device | |
CN106567719A (en) | Determination method of sand karst stratum shield tunnel grouting safe karst cave distance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110413 Termination date: 20130716 |