CN101571389A - Method for precisely assembling space remote sensing camera body structure - Google Patents

Method for precisely assembling space remote sensing camera body structure Download PDF

Info

Publication number
CN101571389A
CN101571389A CNA2009100670727A CN200910067072A CN101571389A CN 101571389 A CN101571389 A CN 101571389A CN A2009100670727 A CNA2009100670727 A CN A2009100670727A CN 200910067072 A CN200910067072 A CN 200910067072A CN 101571389 A CN101571389 A CN 101571389A
Authority
CN
China
Prior art keywords
transition piece
pole
assembly
glue
framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2009100670727A
Other languages
Chinese (zh)
Other versions
CN101571389B (en
Inventor
张凯
何欣
谭进国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changchun Institute of Optics Fine Mechanics and Physics of CAS
Original Assignee
Changchun Institute of Optics Fine Mechanics and Physics of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changchun Institute of Optics Fine Mechanics and Physics of CAS filed Critical Changchun Institute of Optics Fine Mechanics and Physics of CAS
Priority to CN2009100670727A priority Critical patent/CN101571389B/en
Publication of CN101571389A publication Critical patent/CN101571389A/en
Application granted granted Critical
Publication of CN101571389B publication Critical patent/CN101571389B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Connection Of Plates (AREA)

Abstract

The invention provides a method for precisely assembling a space remote sensing camera body structure, belonging to the technical field of assembly connection of body equipment. The method is to use a glue film as the close loop size of body assembly, lead assembly precision and assembly stress to depend on the deflection of the glue film, cancel the pad which may generate larger error, change the assembly mode of a transition component from glue connection first and screwed connection second of mechanical connection method into screwed connection first and glue connection second, use the metal pad to be wound on the transition component to be closely matched with an inner hole of a strut, and better achieve the aims of small assembly stress, high assembly precision and steady and firm structure through a microstress glue connection method. The glue connection method reduces the stress of the body structure on sensitive orientation, namely on axial of the strut, and optimizes the stress status of the body. Meanwhile, the method has simple and convenient operation, short assembly period and low cost, and overcomes the defects of long period and high cost of the prior assembly method by finishing the pad.

Description

A kind of Precise Assembling Method of space remote sensing camera airframe structure
Technical field
The invention belongs to the accurate mounting technology of space optics exact instrument airframe structure field, be specially a kind of method of space remote sensing camera airframe structure assembling.
Background technology
Airframe structure is the critical component of space remote sensing camera.Main effect is the relative position that accurately guarantees each optical element, forms optical imaging system, bears extraneous impact.So airframe structure needs the good rigidity of structure and structural stability, this needs that not only sufficient assurance is arranged in design, and also good implementation method will be arranged in the assembling link.
The assembling effect depends on the height of assembly precision and the size of erection stress.Owing to all have error when measuring, processing and assembling, so will inevitably produce erection stress.If erection stress is bigger, fuselage will produce the distortion of the trace that continues in considerable time after assembling, make the fuselage loses stability, causes precise decreasing.Though erection stress can't be eliminated fully, must adopt suitable assembly method to reduce as far as possible.
For satisfying the big lightweight requirement of the high volume of airframe structure rigidity.The large-sized space camera fuselage of many long-focus adopts the split-type structural design mostly, makes load-carrying construction with light-weight high-strength material and connects a plurality of metal frameworks compositions, to reach the effect that loss of weight does not subtract rigidity.
The mechanical connection assembling method partial sectional view that prior art adopts is as shown in Figure 1:
Part shown in the figure: framework 1, transition piece 2, pole 3, glue-line 4, touch-up pad 5.
Being connected between pole 3 and the metal framework 1 is the main task of assembling, now generally adopts bonding mode to carry out both connections.For improving assembly process process, between pole 3 and framework 1, use titanium alloy transition piece 2, one sides to glued joint opposite side and be threaded with framework 1 with pole 3.
It mainly is the relative position that guarantees between former and later two metal frameworks 1 that assembly precision requires.Main accurate assembling means is by the spacing between accurate gage frame 1 and transition piece 2 both ends of the surface now, and the thickness of touch-up pad 5 and face type are just in time to adapt to the method for this spacing, as shown in Figure 1 then.The characteristics of the method are that the closed loop size that will assemble is arranged on the link of repairing accent pad 5.
But there is certain defective in this method:
1. when measuring 5 types of pad, can only find and the true akin situation of face type, can't accurately record true face type by multimetering.
2. the repeatedly measurement resetting to single-point is relatively more difficult, and also there is identical problem in processing with detecting during touch-up pad 5, so produce bigger measurement and mismachining tolerance.
Pad 5 after the finishing when assembling can't be fully state when measuring be consistent, always have some rotation and skew existence.
4. when screw was fastening, friction force can make and produce relative displacement between the connected piece, directly causes frame deflection.Because the assembling link is numerous, cumulative errors is bigger, produces bigger stress and distortion when causing assembling, and grows up to this height assembly period.This influences for requiring high-precision space camera is bigger, will directly cause camera properties to descend, even can't finish preplanned mission.
Summary of the invention
The present invention has changed traditional mechanical assembly method, has overcome the big shortcoming of its assembly precision low stress.A kind of assembly method of simple and fast is provided, has guaranteed higher assembly precision and lower erection stress simultaneously, and significantly reduced the cost and the cycle of assembling.
For further improving assembly precision, use bonded process at work instead and carry out the fuselage assembling, promptly before adhesive solidification, finish the location between each parts of fuselage, rely on adhesive solidification to finish last connection task.
The feature of microstress bonded process is that assembly precision and erection stress depend on the size of glue-line deflection with the closed loop size of glue-line as the fuselage assembling, as shown in Figure 2, comprising framework, transition piece, pole, glue-line, metallic gasket.Bonded process has been cancelled the pad that can produce than mistake, the transition piece fit is gluedd joint by the elder generation of mechanical connection method be threaded again, and changing into is threaded earlier glueds joint the distortion that has produced when having avoided trip bolt again.
Tackifier was a fluid before solidifying, when the Stress Transfer that produces during assembling arrives the glue-line link, tackifier can produce self-adaptation by flowing and absorb stress and distortion, being released camera body in erection stress reaches stable back glue-line and can be cured under this steady state (SS), solidify the back camera body and still can be among this steady state (SS), thereby meet the requirements of high assembly precision and low assembly stress.
Tackifier because of factors such as volatilization, cooling, crosslinked and crystallizations, cause volumetric contraction to produce bond stress, and the differential contraction stress size is relevant with the tackifier volume when solidifying.Because glue-line is unfettered along the pole axial shrinkage time, so axial shrinkage stress is less.Glue-line is subjected to by the constraint of bond along the pole radial shrinkage time, so the bond stress action direction is mainly along pole radially i.e. bondline thickness direction.The best bondline thickness of the tackifier that uses between 0.1mm~0.2mm, the tackifier shrinkage factor is less than 1%, so amount of contraction is about 0.002mm, is far smaller than the error of touch-up pad, so the bonded process erection stress obviously reduces.
The action direction of mechanical connection method erection stress is the fastening direction of screw, promptly along pole axially.The action direction of bonded process erection stress is the glue-line shrinkage direction, is mainly along pole radially.Bonded process has reduced the stress of airframe structure on sensitive direction (being that pole is axial), has optimized the stress of fuselage.
But still there is a shortcoming in this bonded process, be exactly when transition piece 2 glueds joint with carbon fiber pole 3, the hole of pole 3 cooperates with the axle of transition piece 2 and glueds joint, because existing, gravity factor make the glue-line attenuation below glue-line 4 that is stressed in top be subjected to the pulling force thickening, because bondline thickness can produce stress and produce difference on mechanical property after there are differences curing in the abutting edge, make glue-line easily in the weakness fracture, thereby do not reach designing requirement.Think the homogeneity that guarantees glue-line 4, bonded process is improved.Be wrapped on the transition piece 2 with thin metallic gasket 6 and closely cooperate with pole 3 endoporus, replace the position of original a part of tackifier 4, all the other places are still filled up with tackifier 4.Gravity finally is delivered on the metal framework 1 by metallic gasket 6, and tackifier 4 solidifies under situation about not stressing, thereby has guaranteed the homogeneity of bondline thickness, as shown in Figure 3.
Advantage of the present invention: this microstress bonded process is with the closed loop size of glue-line as the fuselage assembling, assembly precision and erection stress depend on the size of glue-line deflection, cancelled the pad that can produce than mistake, the elder generation splicing of transition piece fit by the mechanical connection method is threaded again, and changing into is threaded earlier glueds joint again.Reached better that erection stress is little, assembly precision is high and the firm firm purpose of structure by bonded process.Bonded process has reduced airframe structure at sensitive direction, i.e. the stress of pole on has axially been optimized the stress of fuselage.This method is simple to operation simultaneously, and assembly period, short cost was low, has overcome and has leaned on the shortcoming that the touch-up pad assembly method cycle is long, cost is high in the past.
Description of drawings
Fig. 1 prior art mechanical connection assembling method partial sectional view:
Part shown in the figure is: framework 1, transition piece 2, carbon fiber pole 3, glue-line 4, touch-up pad 5.
Fig. 2 the present invention glueds joint the assembling method partial sectional view, also is Figure of abstract:
Part shown in the figure is: framework 1, transition piece 2, carbon fiber pole 3, glue-line 4, metallic gasket 6.
Fig. 3 glue-line homogeneity control method cut-open view:
Part shown in the figure is: transition piece 2, carbon fiber pole 3, glue-line 4, metallic gasket 6.
Fig. 4 fuselage assembly relation front elevation:
Part shown in the figure is: transition piece 2, carbon fiber pole 3, glue-line 4, metallic gasket 6.
Embodiment
In conjunction with the accompanying drawings 2,3,4, be that example further specifies concrete grammar of the present invention with the space remote sensing camera:
At first, that the surface planarity grinding that cooperatively interacts of framework 1 and transition piece 2 is smooth with the relative position centering between the metal framework 1; The circularity of the axle of the hole of carbon fiber pole 3 and transition piece 2 is ground, and tolerance clearance will be determined according to the use adhesive performance between the axle of hole.Then thin-wall metal pad 6 width are trimmed to about 4mm~5mm, narrow meeting influence bearing accuracy, and wide can the minimizing gluedd joint area.Metallic gasket 6 is wrapped in transition piece 3 thes tip of the axis, and twining the thickness optimum value is that metallic gasket 6 external diameters are less than hole internal diameter 0.02mm~0.04mm, so that assembling and glue-line absorb erection stress.After working good, pole 3 and transition piece 2 take trial assembly between the framework 1, transition piece (2) one sides are threaded with framework (1), opposite side cooperates with pole (3) hole axle, length by finishing pole 3, the transition piece 2 that reaches pole 3 two ends all can be good fit with framework 1, do not make framework 1 produce distortion and be as the criterion.At last transition piece 2 is taken off, between the axle mating surface of hole, reinstall in the hole of pole behind the gluing, transition piece 2 is connected to framework 1, just finish assembling after waiting bonding agent 4 full solidification, shown in Fig. 4 fuselage assembly relation synoptic diagram.If it is longer to glued joint the face length degree, can be according to actual conditions at the end of transition piece 2 according to above method, twine one section metallic gasket 6 again, so that position better.
With respect to the mechanical connection method, the microstress bonded process can be improved the stress distribution situation of bond, has cancelled the pad that has than mistake, has eliminated the distortion when screw is fastening, thereby has reduced erection stress, has improved the assembly precision and the structural stability of fuselage.With the airframe structure of the space remote sensing camera of the method assembling, maximum deformation quantity can be controlled in the 0.01mm, and adopts traditional mechanical assembly method, and maximum deformation quantity is at 0.03mm~0.05mm even bigger; The method can be controlled in about 10 days assembly period, and traditional assembly method then needs about one month.

Claims (2)

1, a kind of Precise Assembling Method of space remote sensing camera airframe structure, it is characterized in that this Precise Assembling Method relates to framework (1), transition piece (2), pole (3), glue-line (4), metallic gasket (6), this microstress bonded process is with the closed loop size of glue-line (4) as the fuselage assembling, cancelled the pad (5) that can produce than mistake, the elder generation splicing of transition piece (2) fit by the mechanical connection method is threaded again, changing into is threaded earlier glueds joint again, and concrete assembly method is as follows:
1), that the surface planarity grinding that cooperatively interacts of framework (1) and transition piece (2) is smooth at first with the relative position centering between the metal framework (1);
2) with the circularity cutting down of the axle of the hole of pole (3) and transition piece (2); ,
3) metallic gasket (6) is wrapped in transition piece (2) the tip of the axis, transition piece (2) and pole (3) endoporus are closely cooperated;
4) after working good, pole (3) and transition piece (2) take trial assembly between the framework 1, between pole (3) and framework (1), use transition piece (2), transition piece (2) one sides are threaded with framework (1), opposite side cooperates with pole (3) hole axle, by the length of finishing pole (3), the transition piece (2) that reaches pole (3) two ends all can be good fit with framework (1);
5) at last transition piece (2) is taken off, between the axle mating surface of hole, reinstall in the hole of pole (3) behind the gluing, transition piece (2) is connected to framework (1), just finish assembling after waiting bonding agent (4) full solidification.
2, the Precise Assembling Method of a kind of space remote sensing camera airframe structure according to claim 1, it is characterized in that for guaranteeing the homogeneity of glue-line (4), be wrapped in metallic gasket (6) that transition piece (2) is gone up and pole (3) endoporus closely cooperates, the position that replaces original a part of tackifier (4), all the other places are still filled up with tackifier, gravity finally is delivered on the metal framework (1) by metallic gasket (6), and glue-line (4) solidifies under situation about not stressing.
CN2009100670727A 2009-06-05 2009-06-05 Method for precisely assembling space remote sensing camera body structure Expired - Fee Related CN101571389B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100670727A CN101571389B (en) 2009-06-05 2009-06-05 Method for precisely assembling space remote sensing camera body structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100670727A CN101571389B (en) 2009-06-05 2009-06-05 Method for precisely assembling space remote sensing camera body structure

Publications (2)

Publication Number Publication Date
CN101571389A true CN101571389A (en) 2009-11-04
CN101571389B CN101571389B (en) 2011-08-17

Family

ID=41230805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100670727A Expired - Fee Related CN101571389B (en) 2009-06-05 2009-06-05 Method for precisely assembling space remote sensing camera body structure

Country Status (1)

Country Link
CN (1) CN101571389B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102284859A (en) * 2011-05-06 2011-12-21 中国科学院上海技术物理研究所 Digital assembly method of space remote sensing instrument
CN102338919A (en) * 2011-10-18 2012-02-01 北京空间机电研究所 Method for assembling and adjusting all-microcrystalline lens
CN102426615A (en) * 2011-09-01 2012-04-25 北京理工大学 Matching error calculation method for error transfer modeling of precision mechanical system
CN104034315A (en) * 2014-06-30 2014-09-10 中国科学院长春光学精密机械与物理研究所 Assembling method of truss structure of ultra-long focal length remote sensing camera
CN104832511A (en) * 2015-04-21 2015-08-12 中国科学院长春光学精密机械与物理研究所 Method for controlling thickness of optical remote sensor space truss rod adhesive glue layer
CN103795907B (en) * 2014-01-23 2017-04-05 中国科学院长春光学精密机械与物理研究所 The main frame assembling device of space optical camera and assembly method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109752903B (en) * 2018-12-29 2020-10-27 中国科学院长春光学精密机械与物理研究所 Truss structure for remote sensing camera and assembling method thereof

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2536446Y (en) * 2002-02-22 2003-02-19 常州理研精工机械有限公司 Luggage racks on vehicle top
CN2743875Y (en) * 2004-10-28 2005-11-30 中国科学院长春光学精密机械与物理研究所 Strucure of optical remote sensing camera frame
CN201042797Y (en) * 2007-05-25 2008-04-02 山东硅苑新材料科技股份有限公司 Alumina ceramic handle kitchen tool

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102284859A (en) * 2011-05-06 2011-12-21 中国科学院上海技术物理研究所 Digital assembly method of space remote sensing instrument
CN102426615A (en) * 2011-09-01 2012-04-25 北京理工大学 Matching error calculation method for error transfer modeling of precision mechanical system
CN102426615B (en) * 2011-09-01 2013-04-10 北京理工大学 Matching error calculation method for error transfer modeling of precision mechanical system
CN102338919A (en) * 2011-10-18 2012-02-01 北京空间机电研究所 Method for assembling and adjusting all-microcrystalline lens
CN103795907B (en) * 2014-01-23 2017-04-05 中国科学院长春光学精密机械与物理研究所 The main frame assembling device of space optical camera and assembly method
CN104034315A (en) * 2014-06-30 2014-09-10 中国科学院长春光学精密机械与物理研究所 Assembling method of truss structure of ultra-long focal length remote sensing camera
CN104034315B (en) * 2014-06-30 2016-01-13 中国科学院长春光学精密机械与物理研究所 The assembly method of overlength focal length remote sensing camera truss-frame structure
CN104832511A (en) * 2015-04-21 2015-08-12 中国科学院长春光学精密机械与物理研究所 Method for controlling thickness of optical remote sensor space truss rod adhesive glue layer

Also Published As

Publication number Publication date
CN101571389B (en) 2011-08-17

Similar Documents

Publication Publication Date Title
CN101571389B (en) Method for precisely assembling space remote sensing camera body structure
CN103969788B (en) A kind of side flexible support structure of space optical remote sensor circular reflector
CN201344989Y (en) An optical lens and lens group
CN102200623B (en) Micro-stress assembly flexible supporting method of small-calibre micro-crystal glass material reflector
CN109263057B (en) A kind of bonding and assembly method of precision carbon fiber truss
CN105388585A (en) Bonding method for supporting pad of large-aperture reflector and application of bonding method
CN103795907A (en) Main frame assembling device and assembling method for space optical camera
CN103826831B (en) Live spindle tool support
CN106405785B (en) A kind of programmable large caliber reflecting mirror component load-carrying construction of heat distortion amount
CN102145752B (en) Method for realizing light-weight high-accuracy composite material frame
CN102539123A (en) Method for determining optical axis of large-caliber aspheric reflector based on centering processing
CN112269237B (en) Large objective lens centering structure for airborne sighting device
CN107144938B (en) Device for centering infrared lens group at low temperature
CN104832511A (en) Method for controlling thickness of optical remote sensor space truss rod adhesive glue layer
CN101338857A (en) Integral carbon fibre member bar preparation method
CN214669794U (en) Gluing centering device for spherical products
CN212229285U (en) High-stability frame embedded structural part and high-stability supporting frame
Reutlinger et al. Glue test results for high-precision large cryogenic lens holder
CN201212511Y (en) High precision set screw
CN107825193A (en) Suitable for high-precision ring-type thin-walled parts without clamping stress processing method
US11327208B2 (en) Method of manufacture for a lightweight, high-precision silicon carbide mirror assembly
CN103560330A (en) Carbon fiber antenna radiation beam and manufacturing method thereof
CN102139765A (en) Adjustable composite material framework
CN107656367B (en) Scanning mirror assembly for satellite-borne scanning mechanism
CN103791880B (en) Device for accurate measurement space composite rod member micro-strain amount

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110817

Termination date: 20130605