CN101571045A - Top-pulling type construction method for burying box culvert and pipeline underground - Google Patents

Top-pulling type construction method for burying box culvert and pipeline underground Download PDF

Info

Publication number
CN101571045A
CN101571045A CNA2009100518077A CN200910051807A CN101571045A CN 101571045 A CN101571045 A CN 101571045A CN A2009100518077 A CNA2009100518077 A CN A2009100518077A CN 200910051807 A CN200910051807 A CN 200910051807A CN 101571045 A CN101571045 A CN 101571045A
Authority
CN
China
Prior art keywords
box culvert
drag
tube coupling
head
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2009100518077A
Other languages
Chinese (zh)
Other versions
CN101571045B (en
Inventor
方兆昌
李淑海
顾荣森
张志勇
周海松
项向荣
顾迪鸣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI GUANGLIAN ENVIRONMENTAL & GEOTECHNICAL ENGINEERING CO., LTD.
Original Assignee
SHANGHAI GUANGLIAN BUILDING DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI GUANGLIAN BUILDING DEVELOPMENT Co Ltd filed Critical SHANGHAI GUANGLIAN BUILDING DEVELOPMENT Co Ltd
Priority to CN2009100518077A priority Critical patent/CN101571045B/en
Publication of CN101571045A publication Critical patent/CN101571045A/en
Application granted granted Critical
Publication of CN101571045B publication Critical patent/CN101571045B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a construction method for burying a box culvert and a pipeline underground, which relates to the technical field of underground construction and solves the technical problems of improving the suitability of construction sites, driving guide precision and working efficiency of construction. The method comprises the following steps that: firstly, a starting well and a receiving well are constructed at two ends of a designed axis of a pipe culvert; secondly, a horizontal pull device is arranged in the receiving well; thirdly, a plurality of coaxial inhaul cables are paved between two working wells by adopting horizontal directional drilling hole-forming technology, one end of each inhaul cable is locked by the horizontal pull device of the receiving well, while the other end is correspondingly fixed at the front end of a machine head; and fourthly, during construction, the horizontal pull device in the receiving well is mainly utilized to exert the pull on the group of the inhaul cables synchronously and continuously, and simultaneously, a thrustor is utilized to slightly exert the jacking force at the tail end of the box culvert to make the driving machine head perform driving and move forward under the double actions of the pull and the jacking force, and the box culvert tightly connected with the tail part of the machine head is pulled into a culvert synchronously. The method provided by the invention is applicable to the box culverts and the pipelines with various material structures and section sizes and underground passages with similar section morphology.

Description

The top-pulling type construction method of burying box culvert and pipeline underground
Technical field
The present invention relates to the technology of underground construction, particularly relate to a kind of technology of top-pulling type construction method of burying box culvert and pipeline underground.
Background technology
Construction by pipeline jacking method has the little advantage of ground interference, is therefore generally adopted when present burying box culvert and pipeline underground construction.But this job practices has following defective: 1) owing to the space of the shared Starting Well of thrustor in the construction by pipeline jacking method is bigger, but also to reserve tube coupling lifting position, therefore the intended diameter of active well is all bigger, larger-diameter upper pipe working well often is subjected to the restriction of site condition and peripheral building and is difficult to be provided with, compliance to narrow and small construction plant is relatively poor, can run in the construction plant of city limitation and can not satisfy the demand that active well section and " back is leaned on " are reinforced the space, perhaps need to drop into big measure expense is taked extremity to contiguous construction of structures transformation or safeguard measure; 2) because the head of pipe jacking tunnelling machine is heavier, therefore construction by pipeline jacking method is prone to the phenomenon that head departs from axis of travel in the soft clay area tunneling process, particularly head goes out, it is particularly evident to have a down dip when going into the hole, make in the tunneling process the head correction and go out, the soil stabilization of going into openings position becomes requisite measure and the operation in the work progress, thereby increased the rectify a deviation input of oil cylinder and the workload and the corresponding expense of soil stabilization of setting up, also reduced the propelling work efficiency, and because of the expansion in culvert section space due to the correction and the disturbance of undisturbed soil, easily cause the increase of ground settlement, thereby bring many environmental safety troubles; 3) because construction by pipeline jacking method only is applicable to the jacking reinforced concrete box culvert and than the steel box culvert of light section, and the flexural strength of steel box culvert often reduces with the increase of its section, easily produce distortion under jacking force and the place ahead head drag effect, therefore the suitability to box culvert material-structure and cross dimensions has certain limitation.
Summary of the invention
At the defective that exists in the above-mentioned prior art, technical problem to be solved by this invention provides a kind of top-pulling type construction method of burying box culvert and pipeline underground, this method is strong to the compliance of narrow and small construction plant, need not the axial dipole field that extra satisfactory after correcting gets final product STOCHASTIC CONTROL driving head, thereby energy cost saving, raising driving work efficiency, and can prevent soil disturbance, controlling ground settlement, and can be applicable to the box culvert of various material-structures and cross dimensions.
In order to solve the problems of the technologies described above, the top-pulling type construction method of a kind of burying box culvert and pipeline underground provided by the present invention is characterized in that, concrete steps are as follows:
1) build two active wells at pipe culvert design axis two ends, one of them is a Starting Well, and another is a received well;
2) in the head of the Starting Well position of appearing the head device of appearing is installed, and the device of appearing is carried out antiseep handle; Enter the position, hole at the head of received well and head is installed is advanced the hole device, and carry out antiseep and handle advancing the hole device;
3) the drag-line counter force wall is set in received well, and on the drag-line counter force wall, the horizontal pull device is installed;
4) adopt horizontal orientation to creep into hole creating technology and between two active wells, be drilled with a plurality of horizontal orientations hole along being parallel to the burying box culvert and pipeline axis direction, and in each horizontal orientation hole, lay a drag-line, one end of each drag-line is by the locking of the horizontal pull device in the received well, and the other end drags respectively via the horizontal orientation hole and guides to Starting Well;
5) lean on the soil body after the thrustor operating position backside reinforcement in Starting Well, and reserve the operating position of pushing tow back and thrustor;
6) thrustor is installed in Starting Well, and pushing tow back is set at the thrustor rear side;
7) will tunnel head and hang in the Starting Well, and each drag-line axial symmetry will be fixed in driving head front end setting tie point position;
8) will tunnel head and be advanced to the driving initial bit, and strain whole drag-lines;
9) first segment box culvert tube coupling is hung in the Starting Well, and with this box culvert tube coupling and development machine portion's splicing end to end;
10) utilize the horizontal pull device in the received well that the drag-line group is applied pulling force synchronously continuously, utilize thrustor that the box culvert tube coupling afterbody of not holding is applied jacking force simultaneously, the driving head tunnel under the double action of the jacking force of the pulling force of drag-line group and thrustor move ahead, the box culvert tube coupling of not holding is entered in the culvert that is excavated;
11) back one joint box culvert tube coupling is hung in the Starting Well, and the afterbody of this box culvert tube coupling and last joint box culvert tube coupling is spliced, repeating step 10 then, enter desired location in the received well until the front end of first segment box culvert tube coupling.
Further, described thrustor is the jack group, and described horizontal pull device is combined by a plurality of hollow jack that is installed on the drag-line counter force wall, every corresponding hollow jack of drag-line.
Further, by the slight shift that the pulling force of regulating the part drag-line is in time corrected the driving head, tunnel the precision of axially advancing of head with assurance.
Further, during tunneling,, make the mud of institute's pressure injection form the mud cover, to reduce the running resistance of sidewall at each box culvert tube coupling outer wall to each the box culvert tube coupling outer wall pressure injection mud that enters in the culvert that is excavated.
Further, each the box culvert tube coupling outer wall pressure injection cement grout after driving is finished in the culvert that is excavated forms cement paste and solidifies inclusion enclave.
The top-pulling type construction method of burying box culvert and pipeline underground provided by the invention has following beneficial effect:
1) because the driving head tunnels being applied simultaneously by drag-line group and thrustor with joint efforts of moving ahead, and based on pulling force, therefore the jacking force design load is less, thereby the space that thrustor takies in the Starting Well is also less, make the Starting Well diameter satisfying under the single box culvert tube coupling lifting prerequisite and can suitably dwindling, stronger to the compliance of narrow and small construction plant.
2) because having concurrently, the drag-line group provides pulling force and driving head driving guiding function, therefore need not the axial dipole field that extra satisfactory after correcting gets final product STOCHASTIC CONTROL driving head, thereby energy cost saving, raising driving work efficiency, and there is not an increase problem of the culvert section that causes of correction, therefore can prevent soil disturbance, controlling ground settlement.
3) owing to draw the top combined techniques based on pulling force, jacking force is very little, the box culvert traveling process is in tension state, but not squeezed state, distortion be can not produce for the less big section steel box culvert of axial compression resistance distortion moment of flexure, the box culvert, pipeline of various material-structures and cross dimensions or the underground passage of fracture morphology roughly the same therefore can be applicable to.
Description of drawings
Fig. 1 is the schematic top plan view of top-pulling type construction method before construction of the burying box culvert and pipeline underground of the embodiment of the invention;
Fig. 2 is the vertical cross section schematic diagram of top-pulling type construction method before construction of the burying box culvert and pipeline underground of the embodiment of the invention;
Fig. 3 is the schematic top plan view of top-pulling type construction method in construction of the burying box culvert and pipeline underground of the embodiment of the invention;
Fig. 4 is the vertical cross section schematic diagram of top-pulling type construction method in construction of the burying box culvert and pipeline underground of the embodiment of the invention.
The specific embodiment
Below in conjunction with description of drawings embodiments of the invention are described in further detail, but present embodiment is not limited to the present invention, every employing similarity method of the present invention and similar variation thereof all should be listed protection scope of the present invention in.
As Fig. 1-shown in Figure 4, the top-pulling type construction method of a kind of burying box culvert and pipeline underground that the embodiment of the invention provided is characterized in that, concrete steps are as follows:
1) build two active wells at pipe culvert design axis two ends, one of them is a Starting Well 4, and another is a received well 5;
2) in the head of Starting Well 4 position of appearing the head device of appearing is installed, and the device of appearing is carried out antiseep handle; Enter the position, hole at the head of received well 5 and head is installed is advanced the hole device, and carry out antiseep and handle advancing the hole device;
3) the drag-line counter force wall is set in received well 5, and on the drag-line counter force wall, horizontal pull device 8 is installed;
4) adopt horizontal orientation to creep into hole creating technology and between two active wells, be drilled with a plurality of horizontal orientations hole along being parallel to the burying box culvert and pipeline axis direction, and in each horizontal orientation hole, lay a drag-line 7, one end of each drag-line 7 (bar reinforcement or cable wire) is by 8 lockings of the horizontal pull device in the received well 5, and the other end drags respectively via the horizontal orientation hole and guides to Starting Well 4;
5) lean on the soil body 1 after the thrustor operating position backside reinforcement in Starting Well 4, and reserve the operating position of pushing tow back 2 (acting as a cushion) and thrustor 3;
6) thrustor 3 is installed in Starting Well 4, and pushing tow back 2 (acting as a cushion) is set at thrustor 3 rear sides;
7) will tunnel head 6 and hang in the Starting Well 4, and each drag-line 7 axial symmetry will be fixed in driving head 6 front ends;
8) will tunnel head 6 and be advanced to the driving initial bit, and strain whole drag-lines 7;
9) first segment box culvert tube coupling is hung in the Starting Well 4, and with this box culvert tube coupling and the splicing of driving head 6 afterbodys;
10) utilize the 8 pairs of drag-line groups of horizontal pull device in the received well 5 to apply pulling force synchronously continuously, utilize 3 pairs of box culvert tube coupling afterbodys of not holding of thrustor to apply jacking force simultaneously, make driving head 6 under the double action of the jacking force of the pulling force of drag-line group and thrustor 3, tunnel and move ahead, the box culvert tube coupling of not holding is entered in the culvert that is excavated;
11) back one joint box culvert tube coupling is hung in the Starting Well 4, and the afterbody of this box culvert tube coupling and last joint box culvert tube coupling is spliced, repeating step 10 then, enter desired location in the received well 5 until the front end of first segment box culvert tube coupling.
In the embodiment of the invention, the inwall of each box culvert tube coupling is provided with a plurality of splicing apparatus, on driving head 6, be provided with axisymmetric cable wire, and be connected by each splicing apparatus of cable wire and distal box culvert pipe joint inwall, by evenly straining cable wire synchronously, the suffered tensioning pressure of splicing end face that makes each tube coupling is greater than tube coupling outer wall side resistance (this collateral resistance makes the tube coupling syndeton be in tension state), to guarantee reliable connection the between driving head 6 and the tube coupling, between each tube coupling, prevent tube coupling syndeton generation fail in tension.
In the embodiment of the invention, described thrustor 3 is jack groups, and described horizontal pull device 8 is combined by a plurality of hollow jack that is installed on the drag-line counter force wall, each drag-line 7 corresponding hollow jack.
In the embodiment of the invention, by being unearthed during the Starting Well 4 responsible drivings, and controlling to be unearthed and measure, to guarantee construction safety.
In the embodiment of the invention,, tunnel the precision of axially advancing of head 6 with assurance by the slight shift that the pulling force of regulating part drag-line 7 is in time corrected driving head 6.
In the embodiment of the invention, during tunneling,, make the mud of institute's pressure injection form the mud cover, to reduce the running resistance of sidewall at each box culvert tube coupling outer wall to each the box culvert tube coupling outer wall pressure injection mud that enters in the culvert that is excavated.
In the embodiment of the invention, each the box culvert tube coupling outer wall pressure injection cement grout after driving is finished in the culvert that is excavated forms cement paste and solidifies inclusion enclave.
It is prior art that horizontal orientation described in the embodiment of the invention creeps into hole creating technology.
The top-pulling type construction method of the burying box culvert and pipeline underground of the embodiment of the invention is applicable to the underground buried box culvert, pipeline of the steel concrete of various cross dimensionss or steel structure and the underground passage of fracture morphology roughly the same.

Claims (5)

1, a kind of top-pulling type construction method of burying box culvert and pipeline underground is characterized in that, concrete steps are as follows:
1) build two active wells at pipe culvert design axis two ends, one of them is a Starting Well, and another is a received well;
2) in the head of the Starting Well position of appearing the head device of appearing is installed, and the device of appearing is carried out antiseep handle; Enter the position, hole at the head of received well and head is installed is advanced the hole device, and carry out antiseep and handle advancing the hole device;
3) the drag-line counter force wall is set in received well, and on the drag-line counter force wall, the horizontal pull device is installed;
4) adopt horizontal orientation to creep into hole creating technology and between two active wells, be drilled with a plurality of horizontal orientations hole along being parallel to the burying box culvert and pipeline axis direction, and in each horizontal orientation hole, lay a drag-line, one end of each drag-line is by the locking of the horizontal pull device in the received well, and the other end drags respectively via the horizontal orientation hole and guides to Starting Well;
5) lean on the soil body after the thrustor operating position backside reinforcement in Starting Well, and reserve the operating position of pushing tow back and thrustor;
6) thrustor is installed in Starting Well, and pushing tow back is set at the thrustor rear side;
7) will tunnel head and hang in the Starting Well, and each drag-line axial symmetry will be fixed in driving head front end;
8) will tunnel head and be advanced to the driving initial bit, and strain whole drag-lines;
9) first segment box culvert tube coupling is hung in the Starting Well, and with this box culvert tube coupling and development machine portion's splicing end to end;
10) utilize the horizontal pull device in the received well that the drag-line group is applied pulling force synchronously continuously, utilize thrustor that the box culvert tube coupling afterbody of not holding is applied jacking force simultaneously, the driving head tunnel under the double action of the jacking force of the pulling force of drag-line group and thrustor move ahead, the box culvert tube coupling of not holding is entered in the culvert that is excavated;
11) back one joint box culvert tube coupling is hung in the Starting Well, and the afterbody of this box culvert tube coupling and last joint box culvert tube coupling is spliced, repeating step 10 then, enter desired location in the received well until the front end of first segment box culvert tube coupling.
2, method according to claim 1 is characterized in that: described thrustor is the jack group, and described horizontal pull device is combined by a plurality of hollow jack that is installed on the drag-line counter force wall, every corresponding hollow jack of drag-line.
3, method according to claim 1 is characterized in that: by the slight shift that the pulling force of regulating the part drag-line is in time corrected the driving head, tunnel the precision of axially advancing of head with assurance.
4, method according to claim 1 is characterized in that: to each the box culvert tube coupling outer wall pressure injection mud that enters in the culvert that is excavated, make the mud of institute's pressure injection form the mud cover at each box culvert tube coupling outer wall, to reduce the running resistance of sidewall during tunneling.
5, method according to claim 1 is characterized in that: each the box culvert tube coupling outer wall pressure injection cement grout after driving is finished in the culvert that is excavated forms cement paste and solidifies inclusion enclave.
CN2009100518077A 2009-05-22 2009-05-22 Top-pulling type construction method for burying box culvert and pipeline underground Active CN101571045B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100518077A CN101571045B (en) 2009-05-22 2009-05-22 Top-pulling type construction method for burying box culvert and pipeline underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100518077A CN101571045B (en) 2009-05-22 2009-05-22 Top-pulling type construction method for burying box culvert and pipeline underground

Publications (2)

Publication Number Publication Date
CN101571045A true CN101571045A (en) 2009-11-04
CN101571045B CN101571045B (en) 2011-11-16

Family

ID=41230501

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100518077A Active CN101571045B (en) 2009-05-22 2009-05-22 Top-pulling type construction method for burying box culvert and pipeline underground

Country Status (1)

Country Link
CN (1) CN101571045B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101922297A (en) * 2010-08-23 2010-12-22 上海广联建设发展有限公司 Synchronous towing, pushing and tunneling device of underground box culvert or pipeline construction
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line
CN102979957A (en) * 2012-12-10 2013-03-20 上海市基础工程有限公司 Anti-seepage slurry treatment method for horizontal continuous jacking pipe
CN104695971A (en) * 2015-01-07 2015-06-10 同济大学 Annular pipe-jacking construction method
CN106894350A (en) * 2017-02-13 2017-06-27 中交隧道工程局有限公司 A kind of steel basil is buried jacking box culvert device and construction method
CN107023305A (en) * 2017-05-12 2017-08-08 上海广联环境岩土工程股份有限公司 The blocking construction method of underground interface channel
CN107060776A (en) * 2017-05-12 2017-08-18 上海广联环境岩土工程股份有限公司 The unit development machine combination of underground interface channel draws in construction method
CN110873231A (en) * 2019-12-03 2020-03-10 中建四局贵州投资建设有限公司 A equipment for round pipe culvert pushes away construction
CN111088983A (en) * 2019-12-25 2020-05-01 湖北省电力勘测设计院有限公司 Rectangular jacking pipe construction method adopting horizontal directional drilling to carry out jacking and pulling combination
CN111335919A (en) * 2020-03-20 2020-06-26 重庆渝高科技产业(集团)股份有限公司 Prefabricated pipe joint pushing method
CN111335912A (en) * 2019-12-17 2020-06-26 中建水务环保有限公司 Large-pipe-diameter mechanical pipe jacking construction process for soft soil foundation in collapsible loess area
CN111594208A (en) * 2020-05-29 2020-08-28 中铁工程装备集团有限公司 Heading machine and construction method thereof
CN114087421A (en) * 2021-09-24 2022-02-25 华能南通燃机发电有限公司 Construction method for laying pressure pipeline in box culvert

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4145027B2 (en) * 2001-05-30 2008-09-03 株式会社奥村組 Construction method for underground structures
JP2003064997A (en) * 2001-08-23 2003-03-05 Nishimatsu Constr Co Ltd Pipe jacking method
CN100425802C (en) * 2005-06-17 2008-10-15 上海市隧道工程轨道交通设计研究院 Counter pulling method used in underground pipe culvert linear dark digging
CN100425801C (en) * 2005-06-17 2008-10-15 上海市隧道工程轨道交通设计研究院 Counter pulling device used in underground pipe culvert linear dark digging
JP5215781B2 (en) * 2008-09-03 2013-06-19 大成建設株式会社 Equipment insertion and recovery device

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101922297A (en) * 2010-08-23 2010-12-22 上海广联建设发展有限公司 Synchronous towing, pushing and tunneling device of underground box culvert or pipeline construction
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line
CN102979957A (en) * 2012-12-10 2013-03-20 上海市基础工程有限公司 Anti-seepage slurry treatment method for horizontal continuous jacking pipe
CN104695971A (en) * 2015-01-07 2015-06-10 同济大学 Annular pipe-jacking construction method
CN106894350A (en) * 2017-02-13 2017-06-27 中交隧道工程局有限公司 A kind of steel basil is buried jacking box culvert device and construction method
CN107023305A (en) * 2017-05-12 2017-08-08 上海广联环境岩土工程股份有限公司 The blocking construction method of underground interface channel
CN107060776A (en) * 2017-05-12 2017-08-18 上海广联环境岩土工程股份有限公司 The unit development machine combination of underground interface channel draws in construction method
CN107023305B (en) * 2017-05-12 2019-06-07 上海广联环境岩土工程股份有限公司 The blocking construction method of underground interface channel
CN110873231A (en) * 2019-12-03 2020-03-10 中建四局贵州投资建设有限公司 A equipment for round pipe culvert pushes away construction
CN110873231B (en) * 2019-12-03 2024-04-19 中建四局贵州投资建设有限公司 Equipment for pushing construction of circular pipe culvert
CN111335912A (en) * 2019-12-17 2020-06-26 中建水务环保有限公司 Large-pipe-diameter mechanical pipe jacking construction process for soft soil foundation in collapsible loess area
CN111335912B (en) * 2019-12-17 2022-03-11 中建水务环保有限公司 Large-pipe-diameter mechanical pipe jacking construction process for soft soil foundation in collapsible loess area
CN111088983A (en) * 2019-12-25 2020-05-01 湖北省电力勘测设计院有限公司 Rectangular jacking pipe construction method adopting horizontal directional drilling to carry out jacking and pulling combination
CN111335919A (en) * 2020-03-20 2020-06-26 重庆渝高科技产业(集团)股份有限公司 Prefabricated pipe joint pushing method
CN111594208A (en) * 2020-05-29 2020-08-28 中铁工程装备集团有限公司 Heading machine and construction method thereof
CN114087421A (en) * 2021-09-24 2022-02-25 华能南通燃机发电有限公司 Construction method for laying pressure pipeline in box culvert

Also Published As

Publication number Publication date
CN101571045B (en) 2011-11-16

Similar Documents

Publication Publication Date Title
CN101571045B (en) Top-pulling type construction method for burying box culvert and pipeline underground
CN101701646B (en) Method for slurry-water balance type pipe-pulling construction of underground pipeline
CN101749024B (en) Pipe-pulling construction method of underground buried box culvert
CN103643979B (en) Hydraulic support used for roadway temporary support and erecting and use method of hydraulic support
CN102155234B (en) Excavation construction method for unsymmetrical small-space tunnel
CN205117357U (en) Weak surrounding rock tunnel advance support structure based on self -drilling spiral pipe canopy
CN101922297A (en) Synchronous towing, pushing and tunneling device of underground box culvert or pipeline construction
CN104632227B (en) Subway station excavation technology of single-layer beam arch structure
CN204200254U (en) A kind of coal column is reinforced and is used two-way two-ended cables
CN110821537B (en) Support method for fully-mechanized coal mining face pre-digging single-withdrawing channel
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN103899342A (en) Gob-side entrydriving coal pillar anchor cable through reinforcing method
CN201025038Y (en) Adjustable pre-stress steel arch frame
CN104453948B (en) A kind of construction technology of big cross section bored tunnel vertical prestressing steel pipe support
CN201763350U (en) Pulling jack device for underground concealed box culvert or pipe construction
CN110985004A (en) Pre-reinforcing system for advanced small guide pipe and construction method thereof
KR101303448B1 (en) Leading pipe propulsion device and non-open cut pipe installation method of underground structures using the same
CN203701092U (en) Extrusion lock stress dispersion type high-tonnage anchor cable
CN110486021A (en) Tunnel of large section is to two jacked piles with small section conversion construction methods
CN106968687A (en) The closed annulus yield supporting device of half-edge coal seam stope drift active workings and method for protecting support
CN209115124U (en) Rich water sand tomography tunnel per-fore pouring liquid with small pipe constructing structure
CN107060776A (en) The unit development machine combination of underground interface channel draws in construction method
CN110735650A (en) reinforced construction structure of communication channel between shield tunnels and construction method thereof
CN208472739U (en) A kind of heavy cut ruggedized construction
CN103835731A (en) Supporting device and method for primary supporting of expansible soil layer tunnel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 201700 Shanghai city Qingpu District No. 599 new road, building 1, room 869

Patentee after: SHANGHAI GUANGLIAN ENVIRONMENTAL & GEOTECHNICAL ENGINEERING CO., LTD.

Address before: 201700 Shanghai city Qingpu District No. 599 new road, building 1, room 869

Patentee before: Shanghai Guanglian Building Development Co., Ltd.