CN101565936B - 滩涂海水吹填围堤龙口合拢施工方法 - Google Patents

滩涂海水吹填围堤龙口合拢施工方法 Download PDF

Info

Publication number
CN101565936B
CN101565936B CN2009100276491A CN200910027649A CN101565936B CN 101565936 B CN101565936 B CN 101565936B CN 2009100276491 A CN2009100276491 A CN 2009100276491A CN 200910027649 A CN200910027649 A CN 200910027649A CN 101565936 B CN101565936 B CN 101565936B
Authority
CN
China
Prior art keywords
longkou
sand
sand pocket
closure gap
upstream
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009100276491A
Other languages
English (en)
Other versions
CN101565936A (zh
Inventor
葛加君
张国建
宋秀芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
RUDONG WATER RESOURCES AND POWER CONSTRUCTIONAL ENGINEERING Co Ltd
Original Assignee
RUDONG WATER RESOURCES AND POWER CONSTRUCTIONAL ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by RUDONG WATER RESOURCES AND POWER CONSTRUCTIONAL ENGINEERING Co Ltd filed Critical RUDONG WATER RESOURCES AND POWER CONSTRUCTIONAL ENGINEERING Co Ltd
Priority to CN2009100276491A priority Critical patent/CN101565936B/zh
Publication of CN101565936A publication Critical patent/CN101565936A/zh
Application granted granted Critical
Publication of CN101565936B publication Critical patent/CN101565936B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

本发明公开了一种滩涂海水吹填围堤龙口合拢施工方法,包括龙口选址、龙口防护、龙口收缩、龙口闭拢等步骤。本发明合拢施工方便、效果好、易操作。本发明有效减少龙口冲刷,控制土体流失,主要材料就地取材,成本低,闭拢成功率高达100%。

Description

滩涂海水吹填围堤龙口合拢施工方法
技术领域:
本发明涉及一种滩涂海水吹填围堤龙口合拢施工方法。
背景技术:
随着国际贸易远洋运输事业的发展,港口码头建设量的增加,近海围堤筑坝工程成为基本建设的重点工程,然而在围堤项目工程中龙口合拢成为技术中的难题,困扰着建设者。
发明内容:
本发明的目的在于提供一种合拢施工方便、效果好的滩涂海水吹填围堤龙口合拢施工方法。
本发明的技术解决方案是:
一种滩涂海水吹填围堤龙口合拢施工方法,其特征是:依次包括下列步骤:
(1)龙口选址:选择相对标高0.20~0.50m之间,且底为硬性砂质土地段设置为龙口位置;
(2)龙口防护:采用机织土工布和编织布加工成的Φ300的砂肋进行龙口护底防护,分块实施,沿上下游方向重叠3条砂肋压重,相邻砂肋之间通过绞缝连接,接缝处用砂袋吹厚400mm压搭接,形成导流墩;上下游段防护长度均为新筑坝海堤堤脚宽度的1.2倍;在下游吹沙袋一条形成下游翼墙,上游用泥库作上游翼墙;
(3)龙口收缩:选择在较小潮位时,进行留坡,每层沙袋加留5m的留坡,在2~3天内将收缩施工段施工到龙口合龙施工方案设计标高,收缩段沙袋的经丝为沙袋的周长方向,收缩段沙袋吹冲厚度为600mm;
(4)龙口闭拢:采用充泥沙袋外棱体平堵合拢闭气方式进行,合拢按设计断面分层进行,每层1~2个沙袋,沙袋同时加高,保持沙袋标高一致;在布第二层沙袋的同时打闭气土方和内棱体沙袋;在龙口封闭成功后,在龙口外侧铺设一层机织土工布,土工布上满铺袋装碎石,并用石压实保护。
本发明合拢施工方便、效果好、易操作。本发明有效减少龙口冲刷,控制土体流失,主要材料就地取材,成本低,闭拢成功率高达100%。
下面结合实施例对本发明作进一步说明。
具体实施方式:
一种滩涂海水吹填围堤龙口合拢施工方法,依次包括下列步骤:
(1)龙口选址:选择相对标高0.20~0.50m之间,且底为硬性砂质土地段设置为龙口位置;
(2)龙口防护:采用机织土工布和编织布加工成的Φ300的砂肋进行龙口护底防护,分块实施,沿上下游方向重叠3条砂肋压重,相邻砂肋之间通过绞缝连接,接缝处用砂袋吹厚400mm压搭接,形成导流墩;上下游段防护长度均为新筑坝海堤堤脚宽度的1.2倍;在下游吹沙袋一条形成下游翼墙,上游用泥库作上游翼墙;
(3)龙口收缩:选择在较小潮位时,进行留坡,每层沙袋加留5m的留坡,在2~3天内将收缩施工段施工到龙口合龙施工方案设计标高,收缩段沙袋的经丝为沙袋的周长方向,收缩段沙袋吹冲厚度为600mm;
(4)龙口闭拢:采用充泥沙袋外棱体平堵合拢闭气方式进行,合拢按设计断面分层进行,每层1~2个沙袋,沙袋同时加高,保持沙袋标高一致;在布第二层沙袋的同时打闭气土方和内棱体沙袋;在龙口封闭成功后,在龙口外侧铺设一层机织土工布,土工布上满铺袋装碎石,并用石压实保护。

Claims (1)

1.一种滩涂海水吹填围堤龙口合拢施工方法,其特征是:依次包括下列步骤:
(1)龙口选址:选择相对标高0.20~0.50m之间,且底为硬性砂质土地段设置为龙口位置;
(2)龙口防护:采用机织土工布和编织布加工成的Φ300的砂肋进行龙口护底防护,分块实施,沿上下游方向重叠3条砂肋压重,相邻砂肋之间通过绞缝连接,接缝处用砂袋吹厚400mm压搭接,形成导流墩;上下游段防护长度均为新筑坝海堤堤脚宽度的1.2倍;在下游吹砂袋一条形成下游翼墙,上游用泥库作上游翼墙;
(3)龙口收缩:选择在较小潮位时,进行留坡,每层砂袋加留5m的留坡,在2~3天内将收缩施工段施工到龙口合龙施工方案设计标高,收缩段砂袋的经丝为砂袋的周长方向,收缩段砂袋吹冲厚度为600mm;
(4)龙口闭拢:采用充泥砂袋外棱体平堵合拢闭气方式进行,合拢按设计断面分层进行,每层1~2个砂袋,砂袋同时加高,保持砂袋标高一致;在布第二层砂袋的同时打闭气土方和内棱体砂袋;在龙口封闭成功后,在龙口外侧铺设一层机织土工布,土工布上满铺袋装碎石,并用石压实保护。
CN2009100276491A 2009-05-15 2009-05-15 滩涂海水吹填围堤龙口合拢施工方法 Expired - Fee Related CN101565936B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100276491A CN101565936B (zh) 2009-05-15 2009-05-15 滩涂海水吹填围堤龙口合拢施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100276491A CN101565936B (zh) 2009-05-15 2009-05-15 滩涂海水吹填围堤龙口合拢施工方法

Publications (2)

Publication Number Publication Date
CN101565936A CN101565936A (zh) 2009-10-28
CN101565936B true CN101565936B (zh) 2011-06-15

Family

ID=41282284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100276491A Expired - Fee Related CN101565936B (zh) 2009-05-15 2009-05-15 滩涂海水吹填围堤龙口合拢施工方法

Country Status (1)

Country Link
CN (1) CN101565936B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104711952A (zh) * 2013-12-13 2015-06-17 上海勘测设计研究院 适用于深滩圈围的龙口保护结构及其合龙方法
CN106049350A (zh) * 2016-07-26 2016-10-26 浙江省水利水电勘测设计院 一种具有桩基框架肋板结构的防渗海堤

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1217406A (zh) * 1997-11-11 1999-05-26 杨锡福 一种江河截流大坝合龙时的施工方法
CN2605302Y (zh) * 2003-03-27 2004-03-03 上海航道勘察设计研究院 砂肋软体排

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1217406A (zh) * 1997-11-11 1999-05-26 杨锡福 一种江河截流大坝合龙时的施工方法
CN2605302Y (zh) * 2003-03-27 2004-03-03 上海航道勘察设计研究院 砂肋软体排

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
岳建文等.国华黄骅发电厂围海造陆工程围堤龙口封堵施工技术.《港工技术》.2004,(第4期),第37-38页. *
胡军庆等.上海南汇东滩促淤圈围(四期)工程1#龙口合拢技术的探讨.《皖西学院学报》.2004,第20卷(第5期),第61-65页. *
陈建峰等.浅论上海人工半岛圈围造地工程围堤工程(北围区)5#龙口施工技术.《科技资讯》.2006,(第14期),第42-43页. *

Also Published As

Publication number Publication date
CN101565936A (zh) 2009-10-28

Similar Documents

Publication Publication Date Title
Shin et al. Coastal erosion prevention by geotextile tube technology
CN105714733A (zh) 一种半透水防波堤及其成型方法
CN105178245A (zh) 河湖航道大型充填袋生态堤防和护岸的建造方法
CN109629585A (zh) 软弱覆盖层下新型围堰结构及施工方法
JP4920057B2 (ja) 水域構造物基礎の強化方法
Corbella et al. Geotextile sand filled containers as coastal defence: South African experience
CN101565936B (zh) 滩涂海水吹填围堤龙口合拢施工方法
CN111014226A (zh) 一种可溶性废盐的吨包及填埋场
CN100516367C (zh) 跨河大桥水中墩土工充泥管袋围堰及其制备方法
CN103074867B (zh) 一种防冲护底软体排突变处的搭接方法
CN105604075A (zh) 便于恢复的临时坞口围堰施工方法及围堰结构
CN105839653A (zh) 一种沉管隧道重建围堰防渗体系的施工方法
KR100791264B1 (ko) 방조제, 해안매립 호안공 등의 팩 필터 시공방법
Fowler et al. Dredged material filled geotextile containers
CN207017219U (zh) 一种新型围堤
CN212983755U (zh) 一种适用于油气输送管道定向钻河流穿越的水土保持系统
CN201058995Y (zh) 一种海边土围堰
CN201080616Y (zh) 跨河大桥水中墩土工充泥管袋围堰
CN205557441U (zh) 一种半透水防波堤
CN206438468U (zh) 一种围垦工程中适用于大潮差合龙的堤坝
EP3526410B1 (en) Artificial breakwater reef and related manufacturing method
Lawson Geotextiles in marine engineering
Sitharam Sea dike construction challenges in coastal waters for storage of river flood waters: a sustainable strategy for water resource development using coastal reservoirs
CN207567799U (zh) 一种适用于沿海深水区的土石围堰结构
CN211938369U (zh) 一种可溶性废盐的吨包及填埋场

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110615

Termination date: 20120515