CN101556300A - 地电流入侵差动模拟通道导致其误动的检测方法 - Google Patents

地电流入侵差动模拟通道导致其误动的检测方法 Download PDF

Info

Publication number
CN101556300A
CN101556300A CNA200910014885XA CN200910014885A CN101556300A CN 101556300 A CN101556300 A CN 101556300A CN A200910014885X A CNA200910014885X A CN A200910014885XA CN 200910014885 A CN200910014885 A CN 200910014885A CN 101556300 A CN101556300 A CN 101556300A
Authority
CN
China
Prior art keywords
differential
analog channel
transformer
point
detection method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA200910014885XA
Other languages
English (en)
Other versions
CN101556300B (zh
Inventor
苏文博
王大鹏
张国辉
王昕�
牟旭涛
刘延华
井雨刚
高广玲
王涛
周大洲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority to CN200910014885XA priority Critical patent/CN101556300B/zh
Publication of CN101556300A publication Critical patent/CN101556300A/zh
Application granted granted Critical
Publication of CN101556300B publication Critical patent/CN101556300B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

本发明公开了一种地电流入侵差动模拟通道导致其误动的检测方法。若CT二次回路存在第二接地点,且该第二接地点位于变压器中性点附近,并存在上述系统接地故障,以及两个二次绕组电流的幅值差>10%、相位差>5°,则确认为地电流入侵差动模拟通道导致其误动。本发明能够找到并确认这种导致差动模拟通道误动跳闸的原因是地电流入侵差动保护模拟量通道所造成的,利于后续工作的展开。

Description

地电流入侵差动模拟通道导致其误动的检测方法
(一)技术领域
本发明涉及一种地电流入侵差动模拟通道导致其误动的检测方法,属于电力系统变电站保护技术领域。
(二)背景技术
变压器差动保护的目的是在变压器内部出现故障时,无延时跳开变压器各侧断路器,保护变压器本体、各侧引线和套管,并躲开励磁涌流、区外故障引起的穿越陛电流的影响。但近几年来电力系统出现的地电流入侵差动保护模拟量通道并导致其误动作等问题,造成了多次变电站与发电机组的大面积停电事故,给电网的稳定运行带来了严重威胁。
例如,发电厂出现了地电流入侵保护模拟量通道母线差动保护的误动跳闸,严重影响了机组的正常运行。2004年7月24日13时42分,莱芜电厂110KV六南线0.95km处A相遭雷击,六南线3911开关保护零序I段与过流I段出口动作,六南线开关跳闸。同时,110kV II母线母差保护动作,连接于110kV II母线的设备包括#1主变3901开关、#3主变110kV侧3903开关、高压备用厂变3900开关、六银线3912开关、六谷线3916开关、六莱线3917开关全部跳闸,电厂内外系统一片混乱。
再如,500kV滨州等变电站,出现了地电流入侵保护模拟量通道导致变压器差动保护误动跳闸的问题,影响了电网的安全运行。2004年6月10日12时56分,220kV华双线发生C相单相接地故障,500kV滨州站#3主变压器B屏差动保护在区外线路发生单项接地故障时误动跳闸,经检查发现该变压器35kV侧C相CT二次侧C4401对地的绝缘损坏,如此导致CT二次C4401,N4401两点接地。当线路上发生接地故障时由于地电流的作用引起变电站地电位的变化,在差动保护电流输入端C4401、N4401之间外加了一个电压Δu,该电压产生一个附加的电流ΔI,其数值达到了保护的整定值,造成了保护的误动作。
地电流入侵差动保护模拟量通道导致其误动作的问题由来已久,之前的资料中虽有相关报道,但其故障的类型、解决与分析的问题思路相差甚远。类似于上述实例所讲的运行变电站内出现的,电力系统故障的地电流入侵差动保护模拟量通道并导致其误动作的问题,长期以来一直没有合适的方法判断并确认这一故障的原因。
(三)发明内容
因此,针对目前无法判断并确认地电流入侵差动保护模拟量通道导致其误动作的问题,本发明的任务在于提供一种地电流入侵差动模拟通道导致其误动的检测方法,能够找到并确认这种导致差动模拟通道误动跳闸的原因是地电流入侵差动保护模拟量通道所造成的,利于后续工作的展开。
为了实现本发明的发明目的,本发明采用以下技术方案:
该发明地电流入侵差动模拟通道导致其误动的检测方法,在变电站差动保护动作后,并在确认差动保护装置动作信号正常的条件下进行包含如下步骤的检测工作:
1)检测CT二次回路是否存在除设计接地点之外的第二接地点;
2)确认所说的第二接地点位于变压器的中性点附近;
3)根据变电站故障录波资料数据,确定变电站的出线和/或相邻系统在上述变电站差动保护动作前瞬间发生了系统接地故障;并且
4)检测与两个接地点相关的一组CT,对其两个二次绕组电流进行比较,判断是否两者幅值差>10%、相位差>5°;
若存在上述第二接地点,且该第二接地点位于变压器中性点附近,并存在上述系统接地故障,以及两个二次绕组电流的幅值差>10%、相位差>5°,则确认为地电流入侵差动模拟通道导致其误动。
根据本发明的技术方案可知,本发明通过检测第二接地点,以及根据系统故障记录资料和对两个CT二次绕组进行电流测试来确认是否是地电流入侵差动模拟通道导致其误动,检测方法简便,可以在短时间内完成检测。另一方面,如果存在第二接地点,且该第二接地点位于变压器中性点附近,也就是CT二次两个接地点形成后,接地故障电流可以在两个接地点之间形成较大的电位差,导致系统接地故障电流直接分流到变压器差动保护的模拟量输入通道,参与正常的采样、计算等程序,到达设定值后产生保护动作,采用检测所述第二接地点的方式具有准确性高的特点;而本方案步骤3)和4)则用于进一步确认模拟量输入通道误动的原因是地电流入侵造成的,从而可以准确的确认这一原因,为后续的故障处理提供依据,并据此有针对性地提供相应的防范措施。
上述地电流入侵差动模拟通道导致其误动的检测方法,所说的两个二次绕组为差动保护电路和故障录波系统。
所述第二接地点的检测方法是首先断开设定接地点,其后通过对地绝缘电阻法检测CT二次回路除该设定接地点外是否还存在对地绝缘电阻为0MΩ的点。
所说中性点附近指与中性点间的绝缘电阻为0MΩ的区域。。
(四)附图说明
下面结合说明书附图来具体说明一下本发明的技术方案,使本领域的技术人员更好的理解本发明,其中:
图1为220kV华双故障时的系统结构示意图。
图2为500kV滨州变电站一次系统图。
图3为主变差动保护原理接线图。
图4为主变差动保护展开接线图。
图5为CT二次电流已进入保护的动作区。
图6为零序电流在二次回路中被抵消。
图7为当系统单相接地故障时地电流进入保护。
图8为雷电对地放电回路。
(五)具体实施方式
本实施例通过具体分析滨州站的变压器差动保护在区外线路发生单项接地故障时误动跳闸,展示了在寻找故障的检测方法、在确定地电流入侵保护模拟量通道导致其误动作的原因。
参见说明书附图1,途中粗线为500kV线路,细线为220kV线路。500kV滨州站#3主变压器B屏差动保护在区外线路发生单项接地故障时误动跳闸,经检查发现该变压器35kV侧C相CT二次侧C4401对地的绝缘损坏,如此导致CT二次C4401,N4401两点接地。当线路上发生接地故障时由于地电流的作用引起变电站地电位的变化,在差动保护电流输入端C4401、N4401之间外加了一个电压Δu,该电压产生一个附加的电流ΔI,其数值达到了保护的整定值,造成了保护的误动作。
其故障现象如下:2004年6月10日12时56分,220kV华双线发生C相单相接地故障,故障时的系统结构见图1。同时滨州站#3主变保护B屏差动保护动作;#3主变5012、5013、203开关跳闸;#3所用变低压侧401开关跳闸;#3主变压器停电。滨州站的系统情况见图2。
故障时滨州站天气晴好,站内无任何操作。#3主变压器带有功负荷126.9MW、无功负荷53.9Mvar。高压侧电流150A、中压侧电流350A、低压侧只带#3所用变压器运行,电流接近0A。
保护室内3号主变保护B屏上“II跳闸动作”、“保护2动作”、“跳闸位置”、“保护动作”指示灯亮,液晶显示屏显示“差动动作”,保护打印报告为C相故障。
保护打印报告所提供的故障瞬间B屏差动保护低压侧电流与A屏比较,差别较大,A屏为0.01A,B屏为5.3A,所以重点对#3主变室外的二次回路绝缘以及B屏差动保护装置的采样回路进行了检查,结果如下。
#3主变保护B屏差动保护装置采样试验结果正确。
#3主变C相本体低压侧套管CT二次接线端子至主变本体端子箱的电缆中T1c-2S1线芯对地绝缘为零,电流互感器二次线圈绝缘均异常。
#3主变C相本体低压侧套管CT二次回路通电情况。在甩开上述接地线芯的条件下,对CT二次回路通电时B屏差动保护装置显示采样值与所加电流一致;CT二次回路带上述接地线芯后,在CT二次侧通入14.0A电流时,保护装置显示采样值为5.4A,说明接地线芯有明显分流。更换备用芯后绝缘正常,在CT二次侧通入10.0A电流时,保护装置所显示的采样值为10.0A。
检查结果表明:3号主变B屏差动保护存在误动现象。
在此需要看一下主变差动保护的接线与原理,主变差动保护为比例制动原理的微机保护,其原理接线见图3、展开接线见图4。
1、正常及区外接地故障时
系统正常及区外接地故障时,变压器三侧零序电流处于平衡状态:
500kV侧:三相差电流-3i01=0;
220kV侧:三相差电流-3i02=0;
35kV侧:靠接线虑掉了零序电流;
因此,系统正常及区外接地故障时保护不会动作。
2、区内接地故障时
当变压器发生差动保护的区内接地故障时,三相差电流≠0,数值达到定值时保护动作跳闸,其动作特性见图5。
下面是对差动保护误动的原因分析:
1、主变35kV侧输入B屏的电流进入了保护的动作区
主变35kV侧CT二次输入B屏的5.3A电流已进入保护的动作区,因此保护装置动作是毫无疑问的,关键是弄清楚5.3A的电流时怎样产生的。从原理上讲35kV侧为负荷侧,当220kV系统发生故障时,该侧不可能提供短路电流;再者35kV侧CT二次不反映零序电流,因为220kV单相接地故障时35kV侧三角形中形成的环流正好使两者在二次线中抵消,零序电流被抵消的电路见图6。
2、35kV侧的二次电流是CT两点接地造成的
35kV侧CT二次的电流是CT两点接地引起的,并非是由一次电流感应到二次的结果。假如是一次电流感应到二次的话,两个保护屏得到的数据基本是对一致的,但现在只有B屏有电流而A屏没有。
当220kV系统发生单相接地故障时,两点接地的保护输入CT回路从地电流中得到分流,此分得的电流值正是起动保护并使之动作的电流。单相接地故障时的电流分布电路见图6。
3、二次回路的第二接地点是二次绝缘击穿所致
当雷电对地放电或220kV系统发生单相接地故障时,变电站地网中有电流流过,见图7。此时变压器侧二次电缆外层对CT固有接地点(位于保护室)的电位不再是零,变压器中性点处电位升高最大,在绝缘薄弱的环节被击穿,造成了CT二次回路的第二个接地点,这是导致保护误动作的根源所在。
4、结论
综上所述,可以得到如下结论:
是一次系统接地故障使地电位提高导致了C4401的电缆线绝缘的损坏。
是一次系统接地的短路电流直接输入差动保护并使其动作,造成了#3主变跳闸。

Claims (4)

1.一种地电流入侵差动模拟通道导致其误动的检测方法,其特征在于在变电站差动保护动作后,并在确认差动保护装置动作信号正常的条件下进行包含如下步骤的检测工作:
1)检测CT二次回路是否存在除设计接地点之外的第二接地点;
2)确认所说的第二接地点位于变压器的中性点附近;
3)根据变电站故障录波资料数据,确定变电站的出线和/或相邻系统在上述变电站差动保护动作前瞬间发生了系统接地故障;并且
4)检测与两个接地点相关的一组CT,对其两个二次绕组电流进行比较,判断是否两者幅值差>10%、相位差>5°;
若存在上述第二接地点,且该第二接地点位于变压器中性点附近,并存在上述系统接地故障,以及两个二次绕组电流的幅值差>10%、相位差>5°,则确认为地电流入侵差动模拟通道导致其误动。
2.根据权利要求1所述的地电流入侵差动模拟通道导致其误动的检测方法,其特征在于:所说的两个二次绕组为差动保护电路和故障录波系统。
3.根据权利要求1所述的地电流入侵差动模拟通道导致其误动的检测方法,其特征在于:所述第二接地点的检测方法是首先断开设定接地点,其后通过对地绝缘电阻法检测CT二次回路除该设定接地点外是否还存在对地绝缘电阻为0MΩ的点。
4.根据权利要求1所述的地电流入侵差动模拟通道导致其误动的检测方法,其特征在于:所说中性点附近指与中性点间的绝缘电阻为0MΩ的区域。
CN200910014885XA 2009-05-11 2009-05-11 地电流入侵差动模拟通道导致其误动的检测方法 Active CN101556300B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910014885XA CN101556300B (zh) 2009-05-11 2009-05-11 地电流入侵差动模拟通道导致其误动的检测方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910014885XA CN101556300B (zh) 2009-05-11 2009-05-11 地电流入侵差动模拟通道导致其误动的检测方法

Publications (2)

Publication Number Publication Date
CN101556300A true CN101556300A (zh) 2009-10-14
CN101556300B CN101556300B (zh) 2010-09-08

Family

ID=41174494

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910014885XA Active CN101556300B (zh) 2009-05-11 2009-05-11 地电流入侵差动模拟通道导致其误动的检测方法

Country Status (1)

Country Link
CN (1) CN101556300B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102914722A (zh) * 2012-11-19 2013-02-06 山东电力集团公司电力科学研究院 寻找变压器差动保护功率转移时误动跳闸原因的检测方法
CN103001181A (zh) * 2012-11-19 2013-03-27 山东电力集团公司电力科学研究院 解决变压器差动保护在功率转移时误动作的方法
CN105375438A (zh) * 2015-12-16 2016-03-02 国网山东省电力公司青岛供电公司 用于中性点经小电阻接地系统的零序电流检测装置及方法
CN110221165A (zh) * 2019-06-11 2019-09-10 安徽马钢设备检修有限公司 一种电机差动保护试验新方法

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1149402C (zh) * 2001-04-30 2004-05-12 宝山钢铁股份有限公司 一种高压电机故障放电在线监测系统
ES2277724B1 (es) * 2005-02-23 2008-06-16 GAMESA INNOVATION & TECHNOLOGY, S.L. Procedimiento y dispositivo para inyectar intensidad reactiva durante un hueco de tension de red.
CN101271152B (zh) * 2008-05-06 2010-06-09 山东电力研究院 电容型设备绝缘在线监测系统校验方法和装置

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102914722A (zh) * 2012-11-19 2013-02-06 山东电力集团公司电力科学研究院 寻找变压器差动保护功率转移时误动跳闸原因的检测方法
CN103001181A (zh) * 2012-11-19 2013-03-27 山东电力集团公司电力科学研究院 解决变压器差动保护在功率转移时误动作的方法
CN103001181B (zh) * 2012-11-19 2014-12-10 山东电力集团公司电力科学研究院 解决变压器差动保护在功率转移时误动作的方法
CN105375438A (zh) * 2015-12-16 2016-03-02 国网山东省电力公司青岛供电公司 用于中性点经小电阻接地系统的零序电流检测装置及方法
CN105375438B (zh) * 2015-12-16 2018-01-12 国网山东省电力公司青岛供电公司 用于中性点经小电阻接地系统的零序电流检测装置及方法
CN110221165A (zh) * 2019-06-11 2019-09-10 安徽马钢设备检修有限公司 一种电机差动保护试验新方法
CN110221165B (zh) * 2019-06-11 2021-03-26 安徽马钢设备检修有限公司 一种电机差动保护试验新方法

Also Published As

Publication number Publication date
CN101556300B (zh) 2010-09-08

Similar Documents

Publication Publication Date Title
AU2018295936B2 (en) Safe processing method for active voltage reduction of ground fault phase of non-effective ground system
EP2128951B1 (en) Electronic active earthing system for use in high-voltage distribution networks
CN101499649B (zh) 一种基于goose方式网络化母线保护方法
CN102937687B (zh) 中性点经小电阻接地时断线故障与接地故障的区分方法
RU2583452C2 (ru) Направленное детектирование резистивного замыкания на землю и разрыва проводника среднего напряжения
CN109283428A (zh) 一种基于零序分量高阶差分变换的馈线出口处单相接地暂态量保护方法
CN105098748A (zh) 一种浪涌保护器及提升其暂时过电压耐受能力的方法
CN101556300B (zh) 地电流入侵差动模拟通道导致其误动的检测方法
CN103412239A (zh) 地铁交流供电系统中母联闪络故障的检测定位方法
CN202586308U (zh) 微机综合接地保护装置
CN102969695B (zh) 中性点经小电阻接地方式时的接地预告方法
CN100581020C (zh) 利用零序环回功能实现线路高阻快速跳闸的方法
Faxvog et al. HV power transformer neutral blocking device (NBD) operating experience in Wisconsin
CN103683187B (zh) 核电站两段式漏电故障保护方法
Xu et al. Research on current transfer arc-extinguishing technology of distribution network
CN101582583B (zh) 预防地电流入侵差动保护模拟量通道导致其误动的方法
Hou Comparing Fault Resistance Coverage of Different Distribution System Grounding Methods
Kokor et al. Effects of neutral point grounding methods on single-phase short circuit fault characteristics
Fan Analysis of optical fiber differential protection based on relay protection
CN219477255U (zh) 一种接地变及中性点电阻柜的连接方式
CN101764389B (zh) 一种防过电压测控系统及方法
US20230238796A1 (en) System and method for eliminating nuisance fuse operation associated with medium voltage distribution transformers
CN101599636A (zh) 预防干扰信号入侵母差保护导致其误动作的方法
Ni et al. Research on the Application of Smart Substation Area Protection
CN206060185U (zh) 智能电网接地综合保护装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: SHANDONG RESEARCH INST. OF ELECTRIC POWER

Effective date: 20130513

Owner name: SHANDONG RESEARCH INST. OF ELECTRIC POWER

Effective date: 20130513

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 250002 JINAN, SHANDONG PROVINCE TO: 100000 XICHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20130513

Address after: 100000 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee after: State Grid Corporation of China

Patentee after: SHANDONG ELECTRIC POWER Research Institute

Address before: 250002 Shandong Electric Power Research Institute, Middle East, 2nd Ring Road, sixteen Li Town, Ji'nan City, Shandong

Patentee before: SHANDONG ELECTRIC POWER Research Institute

CP03 Change of name, title or address

Address after: 100031 No. 86 West Chang'an Avenue, Beijing, Xicheng District

Patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: Shandong Electric Power Research Institute

Address before: 86 Chang'an Street, Xicheng District, Beijing

Patentee before: State Grid Corporation of China

Patentee before: Shandong Electric Power Research Institute

CP03 Change of name, title or address
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220120

Address after: 100031 No. 86 West Chang'an Avenue, Beijing, Xicheng District

Patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

Address before: 100031 No. 86 West Chang'an Avenue, Beijing, Xicheng District

Patentee before: STATE GRID CORPORATION OF CHINA

Patentee before: Shandong Electric Power Research Institute