CN101555686B - Support bar for trial assembling and adjusting of hydropower station tainter valve - Google Patents

Support bar for trial assembling and adjusting of hydropower station tainter valve Download PDF

Info

Publication number
CN101555686B
CN101555686B CN2009100590154A CN200910059015A CN101555686B CN 101555686 B CN101555686 B CN 101555686B CN 2009100590154 A CN2009100590154 A CN 2009100590154A CN 200910059015 A CN200910059015 A CN 200910059015A CN 101555686 B CN101555686 B CN 101555686B
Authority
CN
China
Prior art keywords
steel sleeve
jack
support bar
threaded stud
sleeve pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009100590154A
Other languages
Chinese (zh)
Other versions
CN101555686A (en
Inventor
殷高翔
吴高见
梁涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN2009100590154A priority Critical patent/CN101555686B/en
Publication of CN101555686A publication Critical patent/CN101555686A/en
Application granted granted Critical
Publication of CN101555686B publication Critical patent/CN101555686B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Hinges (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a support bar for trial assembling and adjusting of hydropower station tainter valve which consists of six units, including a jack device, a T-shaped screw thread stud locking mechanism, an outer steel sleeve, an inner steel sleeve, an upper hinge device and a lower hinge device. The support bar provided in the invention has large support force; extent of support force and adjusting length can be adjusted instantly; the supporting length can be longer than 20 metres; the support bar has fine rigidity and excellent stability, thereby locking support length continuously to be applicable to adjustment support of various positions. The support bar is applicable to reuse.

Description

Support bar for trial assembling and adjusting of hydropower station tainter valve
Technical field
The present invention relates to a kind of support bar, particularly relate to the support bar of a kind of power station Segment gate manufacturing examination assembly unit adjustment usefulness.
Background technology
At present, because the Segment gate appearance and size in power station is all bigger, be subjected to the restriction of road transport condition, gate all by the more piece manufacturing, is transported to behind the scene, power station to install in the installation position again and is welded into integral body before dispatching from the factory.In the manufacture process of Segment gate before dispatching from the factory, it makes pre-assembly unit operation is in order to use gate to reach overall performance and the indispensable procedure of designing requirement, and it is smooth respectively to save the gate flap assembly unit when guaranteeing that gate is installed at the scene.The vertical erection method of gate flap is generally adopted in the pre-assembly unit of Segment gate manufacturing, and is highly bigger during vertical assembly unit because the appearance and size of gate is big and divide the more piece manufacturing, has more highly difficult in the high-altitude to every joint gate flap adjustment of forming gate.Conventional employing worker's steel or round steel support to adjust many inconvenience, need weld again fixing during adjustment at every turn, can not adjust immediately, the support bar application of force also inconvenience to bottom support point cutting weld seam, support bar also inconvenience is reused, and adjustment has brought inconvenience to gate flap.
Summary of the invention
The invention discloses a kind of support bar for trial assembling and adjusting of hydropower station tainter valve, comprise the upper hinge device, following hinge means, the outer steel sleeve pipe, interior steel sleeve, jack, upper bracket, lower carriage, T shape threaded stud locking mechanism, wherein, outer steel sleeve pipe and interior steel sleeve pivot bush unit, upper hinge device and following hinge means are separately positioned on the termination, the outside of outer steel sleeve pipe and interior steel sleeve separately, upper bracket and lower carriage then are arranged on outer steel sleeve pipe and the interior steel sleeve sleeve pipe separately, jack is arranged between the lower carriage, and fix by lock stud and lower carriage, upper bracket and outside, jack upper end are provided with block, T shape locking mechanism and lower carriage are fixed, and form by T shape screw nut and upper bracket and can regulate fixingly, jack and T shape locking mechanism are positioned at steel sleeve both sides correspondence position.
T shape threaded stud locking mechanism then is made up of T shape threaded stud and supporting T shape screw nut thereof.
Wherein, the length that is nested of outer steel sleeve pipe and interior steel sleeve is 1500mm, and the fit clearance between outer steel sleeve pipe and the interior steel sleeve is 0.3mm to 0.5mm.
They sup-port power provided by the present invention is big, support force size and to adjust length adjustable immediately, and bearing length can reach more than the 20m, good rigidity, and good stability, lock support length can adapt to the support adjustment of various orientation continuously, can reuse.
Description of drawings
Fig. 1 is a structure chart of the present invention.
The specific embodiment
1, a kind of support bar for trial assembling and adjusting of hydropower station tainter valve, comprise upper hinge device 1, following hinge means 11, outer steel sleeve pipe 2, interior steel sleeve 10, jack 4, upper bracket 3, lower carriage 6, T shape threaded stud locking mechanism, wherein, outer steel sleeve pipe 2 and interior steel sleeve 10 pivot bush units, upper hinge device 1 and following hinge means 11 are separately positioned on the termination, the outside of outer steel sleeve pipe 2 and interior steel sleeve 2 separately.Upper bracket 3 and lower carriage 4 then are arranged on outer steel sleeve pipe 2 and interior steel sleeve 10 sleeve pipes separately, jack 4 is arranged on the lower carriage 6 with T shape threaded stud locking mechanism and is positioned at support bar both sides correspondence position, jack 4 is fixing with lower carriage 6 by lock stud 5, T shape locking mechanism and lower carriage are fixed, and can regulate fixing by T shape screw nut 7,8 and upper bracket 3 formation.Can increase the adjustment stroke according to adjusting the required steel plate that is encased inside suitable thickness between jack 4 and the upper bracket 3, upper bracket 3 is provided with block with outside, jack 4 upper end simultaneously, prevents jack 4 upper ends and the outside slippage of backing plate.
T shape threaded stud locking mechanism is made up of T shape threaded stud 9 and supporting T shape screw nut 7 and 8 thereof.
1.5m about, to guarantee the stability requirement of support bar; Inside and outside steel sleeve fit clearance is got between the 0.3mm to 0.5mm; Support application of force trim lengths and adjust demand according to the lock gate leaf assembly unit and generally be decided to be about 200mm, when the positioning supports bar, but guarantee the be nested length of activity surplus and application of force fine setting of inside and outside steel sleeve; Jack is installed between the support of inside and outside steel sleeve, adjusts support bar length by the support application of force that acts on inside and outside steel sleeve during jack work.Do not adopt T shape threaded stud and supporting T-nut thereof to come stressed adjustment to be herein because: rotate T shape screw nut during its stressed adjustments and make support bar be subjected to torsion, support bar upper and lower side fixed point may be become flexible or change, and very little with the fine setting of the jack operation application of force to the stability influence of support bar.
11 moveable hinge base plate and the welding of lower support face are fixing, after reserving the adjustment amount of jack 4, upper hinge device 1 is fixing with the lock gate leaf proper site welding that needs to adjust, flexible convenient when guaranteeing that support bar is installed in this process, need earlier T shape screw nut 7 to be threaded to the position of threaded stud 9 by the top, T shape screw nut 8 is threaded to the position of threaded stud 9 by the bottom.It is flexible when support bar is adjusted gate flap by jack 4 work controls, when adjusting to the right place, because the functional performance of jack requires can not long-term stressed support, at this moment make threaded stud 9 and upper bracket 3 lockings by adjusting T shape screw nut 7 and 8, with not flexible of lock support, this section of jack 4 off-load back support rods is born support force by T shape threaded stud 9.As also adjusting, unclamp T shape screw nut 7 to correct position, jack 4 work are adjusted, adjust T shape screw nut 8 in case of necessity again and reserve the adjustment surplus.
Very little with the fine setting of the jack operation application of force to the stability influence of support bar, the accuracy in having guaranteed to adjust.The support bar upper and lower side is provided with articulated link mechanism, because the used support bar of Segment gate manufacturing examination assembly unit adopts the bearing diagonal mode, and the internal force influence that the variation of its angle brought the upper and lower side fixed point when articulated link mechanism had then solved the support bar length adjustment.

Claims (1)

1. support bar for trial assembling and adjusting of hydropower station tainter valve, it is characterized in that: comprise the upper hinge device, following hinge means, the outer steel sleeve pipe, interior steel sleeve, jack, upper bracket, lower carriage, T shape threaded stud locking mechanism, wherein, outer steel sleeve pipe and interior steel sleeve pivot bush unit, the length that is nested of outer steel sleeve pipe and interior steel sleeve is 1500mm, fit clearance between outer steel sleeve pipe and the interior steel sleeve is 0.3mm to 0.5mm, upper hinge device and following hinge means are separately positioned on the termination, the outside of outer steel sleeve pipe and interior steel sleeve separately, upper bracket and lower carriage then are arranged on the sleeve pipe of outer steel sleeve pipe and interior steel sleeve separately, jack is arranged between the lower carriage, and fix by lock stud and lower carriage, upper bracket and outside, jack upper end are provided with block, T shape threaded stud locking mechanism is made up of T shape threaded stud and supporting T shape screw nut thereof, T shape threaded stud locking mechanism and lower carriage are fixed, and can regulate fixing by T shape screw nut and upper bracket formation, jack and T shape threaded stud locking mechanism are positioned at steel sleeve both sides correspondence position, it is flexible when support bar is adjusted gate flap by jack work control, when adjusting to the right place, make T shape threaded stud and upper bracket locking by adjusting T shape screw nut, with not flexible of lock support, this section of jack off-load back support rod is born support force by T shape threaded stud.
CN2009100590154A 2009-04-22 2009-04-22 Support bar for trial assembling and adjusting of hydropower station tainter valve Active CN101555686B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100590154A CN101555686B (en) 2009-04-22 2009-04-22 Support bar for trial assembling and adjusting of hydropower station tainter valve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100590154A CN101555686B (en) 2009-04-22 2009-04-22 Support bar for trial assembling and adjusting of hydropower station tainter valve

Publications (2)

Publication Number Publication Date
CN101555686A CN101555686A (en) 2009-10-14
CN101555686B true CN101555686B (en) 2011-06-15

Family

ID=41173949

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100590154A Active CN101555686B (en) 2009-04-22 2009-04-22 Support bar for trial assembling and adjusting of hydropower station tainter valve

Country Status (1)

Country Link
CN (1) CN101555686B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103770199B (en) * 2012-10-26 2016-02-10 葛洲坝机械工业有限公司 A kind of height-adjustable gates of segmental shape fetal membrane steel-support
CN104005386B (en) * 2014-05-29 2015-08-05 芜湖市银鸿液压件有限公司 Hydraulic pressure arc hoists dam
CN107268542B (en) * 2017-08-04 2020-10-16 芜湖市银鸿液压件有限公司 Hydraulic pressure dam coverage structure
CN107299622B (en) * 2017-08-04 2020-10-20 芜湖市银鸿液压件有限公司 Covering type hydraulic dam

Also Published As

Publication number Publication date
CN101555686A (en) 2009-10-14

Similar Documents

Publication Publication Date Title
CN108000047B (en) Thin-wall three-way pipe clamping device
CN101555686B (en) Support bar for trial assembling and adjusting of hydropower station tainter valve
CN207160349U (en) A kind of dot point rotatably plug-in PC wallboard connecting mechanisms and device
CN108127319B (en) Clamping device of thin-wall variable-section three-way pipe
CN104148863A (en) Clamp preventing welding deformation
CN205363123U (en) Bed -jig is assembled to steel construction
CN114541782A (en) Positioning and adjusting device for steel structure installation and construction method thereof
CN201428195Y (en) Drop ceiling node component
CN202028915U (en) Positioning device for assembling rod body of steel pipe rod and connecting flange
CN210231121U (en) Machining mechanism for automobile elbow
CN109678066B (en) Tower crane remote attachment system with length and direction adjustable function
CN220506014U (en) Pipeline fixing hanging bracket
CN203804959U (en) Workpiece position adjusting device
CN209288014U (en) It is a kind of can be to the steel pipe bender that multiple caliber is bent
CN209856503U (en) Height-adjustable's metal support frame
CN208587709U (en) Angle adjustable support arm structure
CN219175660U (en) Connecting bracket device for adjusting size of reinforcement cage
CN215660994U (en) Prestressed pipeline regulator
CN111255249A (en) Building beam building structure and construction method
CN201649627U (en) Building construction template support frame
CN221221709U (en) Novel adjustable movable support
CN215145585U (en) Guide support convenient to adjust for automatic submerged arc welding machine
CN220850348U (en) Valve feedback connecting rod with adjustable length
CN209754403U (en) Pipeline assembly tool
CN204487055U (en) The detent mechanism of a kind of steering box bearing nut arc-welding

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model