CN101537801A - Device for installing contact net in tunnel in electrified railway engineering - Google Patents

Device for installing contact net in tunnel in electrified railway engineering Download PDF

Info

Publication number
CN101537801A
CN101537801A CN200910031018A CN200910031018A CN101537801A CN 101537801 A CN101537801 A CN 101537801A CN 200910031018 A CN200910031018 A CN 200910031018A CN 200910031018 A CN200910031018 A CN 200910031018A CN 101537801 A CN101537801 A CN 101537801A
Authority
CN
China
Prior art keywords
conduit
tunnel
contact net
anchor pole
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910031018A
Other languages
Chinese (zh)
Other versions
CN101537801B (en
Inventor
李广骅
陈彩云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huawei Line Equipment Group Co Ltd
Original Assignee
Jiangsu Huawei Line Equipment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huawei Line Equipment Group Co Ltd filed Critical Jiangsu Huawei Line Equipment Group Co Ltd
Priority to CN2009100310187A priority Critical patent/CN101537801B/en
Publication of CN101537801A publication Critical patent/CN101537801A/en
Application granted granted Critical
Publication of CN101537801B publication Critical patent/CN101537801B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a device for installing a contact net in a tunnel in electrified railway engineering, which is characterized in that the back of a channel flow and the bottom of an anchor rod are connected in a welding mode, galvanized and fixed by poring concrete; and the head of a T-shaped bolt is put into the channel flow to ensure that the T-shaped bolt can slide freely in use. The processing of the channel flow comprises the following steps: hot-rolling and molding roughcast and remaining machining allowance; and lubricating cold-rolling and molding after acid washing, alkali wash and water wash, wherein the blooming temperature of rolling is 1050 DEG C, and the finish rolling temperature is 75 DEG C. The device effectively overcomes the defects in the prior art and has pre-embedded installation and no need of post-drilling, is level with concrete after embedded into the concrete, does not occupy space, is easy to install and adjust, reduces the installation time of a contact net structure in a tunnel, reduces the construction cost, and the like.

Description

Be used for installing contact net equipment in the electrified railway engineering tunnel
Technical field
What the present invention relates to is a kind of installing contact net equipment in the electrified railway engineering tunnel that is used for, and belongs to tunnel installation accessories technical field.
Background technology
At tunnel internal fixation structure stand, traditional in the past way is planted crab-bolt after being, way is: bolt, filling concrete are planted in the tunnel lining punching; The tunnel lining punching is filled the chemical glue compound and is planted crab-bolt.No matter be which kind of plants the crab-bolt way after, all will punch, all can cause certain destruction tunnel lining in tunnel lining.And weighting material and the firm degree of concrete bonding are much smaller than the monolithic concrete structure.After plant that crab-bolt is stressed to be concentrated, cause the contact structures subsidiary load bigger to the tunnel lining influence, the fire retardancy of chemical anchor bolts is relatively poor, and construction is inconvenient, cost is high.The fastness of planting plain bolt behind the back plant crab-bolt ratio is better, and is more with chemical anchor bolts in the tunnel usually.Since after to plant the crab-bolt defective more, plant the way of crab-bolt abroad after generally adopting pre-buried conduit to replace, cost is higher.
Summary of the invention
The present invention proposes a kind of installing contact net equipment in the tunnel that is applicable in the electrified railway engineering, be intended to overcome the above-mentioned defective of existing in prior technology, has pre-buried installation, need not back boring, imbed in the cement concrete and flush, do not take up room, install, adjust easy with cement concrete, can reduce the required time of contact system structure installation in the tunnel effectively, reduce characteristics such as construction costs effectively.
Technical solution of the present invention: it is zinc-plated to it is characterized in that the conduit back side and anchor pole bottom is connected by welding process, irrigates fixingly with concrete casting, and the head of T type bolt is put into the inside of conduit, and assurance T type bolt can be free to slide in use.
Advantage of the present invention: adopt pre-buried grooved slideway scheme, can in the design of tunnel lining and work progress, finish synchronously.Conduit back anchor pole is built framework of steel reinforcement with tunnel and is connected closely, guarantees the stressed safety of channel system, makes the stressed demand of contact system can receive sufficient consideration and realization; With after plant crab-bolt and compare, hang and stressedly more disperse, contact system structure subsidiary load is littler to the influence of tunnel lining; Pre-buried installation need not back boring, avoids tunnel lining is damaged; Compare with chemical anchor bolts, can improve the safety on contact system basis in the tunnel; Imbed in the cement concrete and flush, do not take up room, not influenced by construction in later period with cement concrete; Conduit has briar tooth, and fitting like a glove with the T type bolt that has teeth forms firm mechanical snap, and effectively opposing is impacted and oscillatory load, prevents loosening slippage; In order to prevent that cement wash from infiltrating in the channel-section steel, the foam-filled thing of the built-in T type of pre-buried conduit, and weighting material extrusion packing thing when exceeding conduit 1.5mm and guaranteeing that template fixedly prevent that better cement wash from mixing in the conduit mouth; Install, adjust easy, can reduce the required time of the contact system structure installation tunnel in effectively; Reduce construction costs effectively.
Description of drawings
Fig. 1 is the conduit section drawing.
Fig. 2 is the anchor structure scheme drawing.
Fig. 3 is conduit and anchor pole and other mating parts connection diagram.
Among the figure 1 is the age of a draught animal of conduit; The 2nd, the conduit side; The 3rd, the conduit back side; The 4th, the anchor pole top; The 5th, the anchor pole bottom; The 6th, the anchor pole mobile jib.
The specific embodiment
Contrast accompanying drawing 1, its structure is that the age of a draught animal 1 of conduit both sides is symmetrical, and the distance between two ages of a draught animal 1 is 22mm, and the height h1 of the age of a draught animal 1 is 11mm, and the height h2 of the age of a draught animal 1 root is 8mm, the circular arc R 1.5 of the age of a draught animal 1 is 1.5mm; The thickness h 3 of conduit side 2 is 4.5mm, and the width h4 of conduit side 2 is 34mm; The thickness h 5 at the conduit back side 3 is 4.5mm, and the width h6 at the conduit back side 3 is 52mm.
Contrast accompanying drawing 2, its structure is that two anchor pole tops 4 are two identical faces, and the distance h 7 on this two sides is 125mm, and width h8 is 30mm, and thickness h 9 is 7mm; The thickness h 10 of anchor pole mobile jib 6 is 5mm, and length is 40mm.The circular arc R 6 of anchor pole bottom (5) is 6mm.
To be the conduit back side 3 be connected by welding process with the bottom of anchor pole 5 for contrast accompanying drawing 3, its structure.
Conduit and anchor pole by welding process be connected zinc-plated after, irrigate fixingly with concrete casting, the head of T type bolt is put into the inside of conduit, guarantees that T type bolt can be free to slide in use.
Processing conduit processing step, first hot-roll forming blank, and leave stock left for machining, lubricated cold rolling moulding after pickling then, alkali cleaning, the washing, wherein the material of conduit is Q235, according to its material characteristic, rolling breaking down temperature is decided to be 1050 ℃, and finishing temperature is 750 ℃.

Claims (3)

1, is used for installing contact net equipment in the electrified railway engineering tunnel, it is characterized in that the conduit back side (3) is connected zinc-plated with anchor pole bottom (5) by welding process, irrigate fixingly with concrete casting, the head of T type bolt is put into the inside of conduit, guarantees that T type bolt can be free to slide in use.
2, according to claim 1ly be used for installing contact net equipment in the electrified railway engineering tunnel, it is characterized in that described conduit, its structure is that the age of a draught animal (1) of conduit both sides is symmetrical, distance (h0) between two ages of a draught animal (1) is 22mm, the height of the age of a draught animal 1 (h1) is 11mm, the height (h2) of the age of a draught animal (1) root is 8mm, and the circular arc of the age of a draught animal (1) is 1.5mm; The thickness (h3) of conduit side (2) is 4.5mm, and the width (h4) of conduit side (2) is 34mm; The thickness (h5) at the conduit back side (3) is 4.5mm, and the width (h6) of the conduit back side (3) is 52mm.
3, according to claim 1ly be used for installing contact net equipment in the electrified railway engineering tunnel, it is characterized in that described anchor pole, its structure is that two anchor pole tops (4) are two identical faces, and the distance on this two sides (h7) is 125mm, width (h8) is 30mm, and thickness (h9) is 7mm; The thickness (h10) of anchor pole mobile jib (6) is 5mm, and length is 40mm, and the circular arc of anchor pole bottom (5) is 6mm.
CN2009100310187A 2009-04-24 2009-04-24 Device for installing contact net in tunnel in electrified railway engineering Active CN101537801B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100310187A CN101537801B (en) 2009-04-24 2009-04-24 Device for installing contact net in tunnel in electrified railway engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100310187A CN101537801B (en) 2009-04-24 2009-04-24 Device for installing contact net in tunnel in electrified railway engineering

Publications (2)

Publication Number Publication Date
CN101537801A true CN101537801A (en) 2009-09-23
CN101537801B CN101537801B (en) 2010-12-29

Family

ID=41121266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100310187A Active CN101537801B (en) 2009-04-24 2009-04-24 Device for installing contact net in tunnel in electrified railway engineering

Country Status (1)

Country Link
CN (1) CN101537801B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821535A (en) * 2014-03-06 2014-05-28 中铁第一勘察设计院集团有限公司 Shield method tunnel lining structure pre-buried groove connecting element and installing method thereof
CN103967521A (en) * 2013-01-29 2014-08-06 江苏华彤新能源科技有限公司 Pre-buried channel assembly for shield tunnel
CN105442395A (en) * 2015-12-24 2016-03-30 中铁第四勘察设计院集团有限公司 Magnetic suspension engineering contact rail pre-buried channel
CN108150820A (en) * 2018-01-25 2018-06-12 山东钢铁股份有限公司 A kind of hot rolling deformed channel steel
CN109915174A (en) * 2019-04-08 2019-06-21 无锡商业职业技术学院 A kind of rail tunnel folding teeth channel steel and its preparation process
CN111890991A (en) * 2020-06-28 2020-11-06 中铁第一勘察设计院集团有限公司 Cantilever installation device and contact net

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106865407A (en) * 2017-03-23 2017-06-20 江苏华威线路设备集团有限公司 One kind is bumped into clamp rail and mating fastener for nuclear power engineering concrete

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201089374Y (en) * 2007-08-21 2008-07-23 江苏华威线路设备有限公司 Conduit for fixing contacting net
CN201089373Y (en) * 2007-08-21 2008-07-23 江苏华威线路设备有限公司 Contacting net fixing apparatus
CN201096132Y (en) * 2007-08-21 2008-08-06 江苏华威线路设备有限公司 T shaped bolt

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967521A (en) * 2013-01-29 2014-08-06 江苏华彤新能源科技有限公司 Pre-buried channel assembly for shield tunnel
CN103821535A (en) * 2014-03-06 2014-05-28 中铁第一勘察设计院集团有限公司 Shield method tunnel lining structure pre-buried groove connecting element and installing method thereof
CN105442395A (en) * 2015-12-24 2016-03-30 中铁第四勘察设计院集团有限公司 Magnetic suspension engineering contact rail pre-buried channel
CN108150820A (en) * 2018-01-25 2018-06-12 山东钢铁股份有限公司 A kind of hot rolling deformed channel steel
CN109915174A (en) * 2019-04-08 2019-06-21 无锡商业职业技术学院 A kind of rail tunnel folding teeth channel steel and its preparation process
CN111890991A (en) * 2020-06-28 2020-11-06 中铁第一勘察设计院集团有限公司 Cantilever installation device and contact net

Also Published As

Publication number Publication date
CN101537801B (en) 2010-12-29

Similar Documents

Publication Publication Date Title
CN101537801B (en) Device for installing contact net in tunnel in electrified railway engineering
CN201446891U (en) Apparatus for mounting contact net in tunnel for electrified railroad engineering
CN101429826B (en) Concrete silo inner lining steel rail and warehouse wall slip form integrated construction method
CN109914587A (en) A kind of cross-connecting structure of prefabricated floor and wallboard
CN204936869U (en) A kind of detachable pre-buried channel flow
CN202611109U (en) Steel strand connector
CN101812871A (en) Method for horizontally connecting precast concrete members
CN205638802U (en) Formula precast concrete pylon structure is made up in segmentation
CN201172680Y (en) Zinc nose in galvanizing bath for cold-rolled steel strip
CN206753622U (en) A kind of bar-mat reinforcement for coal mine roadway bolt-mesh-spurting supporting
CN213061905U (en) Novel hydraulic engineering slope net
CN204370647U (en) The hollowcore slab that a kind of filling box combinationally uses
CN204476179U (en) Auxiliary frame construction and installation fixture
CN209443573U (en) A kind of connecting node of the high ductility round steel concrete column-beams of concrete of assembled
CN203403359U (en) Vertical prestress steel bar threaded anchor used in box girder
CN207828932U (en) A kind of power station outlet anchor point anchor structure
CN208441288U (en) A kind of connector construction for the connection of prefabricated assembled shear wall
CN202047609U (en) Jacking bracket for integrally lifting house
CN206784183U (en) A kind of connection of bridge reinforcement cage longitudinal reinforcement, processing unit (plant)
CN208055895U (en) External prestressing strengthening structure
CN205975235U (en) Electronic installation device of anchor board
CN104047460B (en) A kind of transmission tower
CN201133025Y (en) Internal mold of thin wall case for filling hollow building cover of PCM concrete
CN206000027U (en) A kind of precast concrete connector
CN213837275U (en) Glass curtain wall fixing structure for architectural engineering decoration

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant