CN101532606A - A gas cabinet cabinet-top mounting and positioning apparatus and method thereof - Google Patents

A gas cabinet cabinet-top mounting and positioning apparatus and method thereof Download PDF

Info

Publication number
CN101532606A
CN101532606A CN200910301177A CN200910301177A CN101532606A CN 101532606 A CN101532606 A CN 101532606A CN 200910301177 A CN200910301177 A CN 200910301177A CN 200910301177 A CN200910301177 A CN 200910301177A CN 101532606 A CN101532606 A CN 101532606A
Authority
CN
China
Prior art keywords
cabinet
gas
rod
connecting rod
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910301177A
Other languages
Chinese (zh)
Other versions
CN101532606B (en
Inventor
李轶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Corp
Original Assignee
MCC Shijiu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shijiu Construction Co Ltd filed Critical MCC Shijiu Construction Co Ltd
Priority to CN2009103011774A priority Critical patent/CN101532606B/en
Publication of CN101532606A publication Critical patent/CN101532606A/en
Application granted granted Critical
Publication of CN101532606B publication Critical patent/CN101532606B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a gas cabinet engineering installation apparatus and method, specifically to a large-scale gas cabinet cabinet-top mounting and positioning apparatus and mounting method. The technical problem the invention object to resolve is to provide a safe gas cabinet cabinet-top mounting and positioning apparatus with simple and convenient construction. The gas cabinet cabinet-top mounting and positioning apparatus to solve the technical problem, includes a linkage rod connected to the piston in the cabinet body, wherein, a bird hook is connected to the linkage rod by a bird hook hinge, and the upper part of the linkage rod is connected to the cabinet top through a movable rod. At the same time, the present invention also provides a construction method using the gas cabinet cabinet-top mounting and positioning apparatus, the invention has the following beneficial effects: greatly reduced installation used steel consumption, lowered costs and greatly reduced construction cost, which resolves the potential safety hazard problem of the process, thereby realizing convenient, fast and safe cabinet top high altitude positioning construction.

Description

Gas cabinet cabinet top mounting and positioning device and method thereof
Technical field
The present invention relates to a kind of erecting device and method of gas cabinet, especially be suitable for the mounting and positioning device and the installation method on large-scale gas cabinet top.
Background technique
The general design height of large-scale gas cabinet is all above 90 meters, its installation basic principle, be exactly after cabinet bottom one joint is installed, just earlier the cabinet top is set up immediately, utilize the special-purpose machines and tools connecting rod that the cabinet top is fused with piston temporarily, form little low cabinet earlier, use aerostatic buoyancy, make it to become one " mobile work platform ", movable platform is suspended on the cabinet by the bird hook that is connected with connecting rod, and middle each section of cabinet is installed again, and is high to the top until cabinet, cabinet top and cabinet formally being connected is that cabinet is risen empty location again, finishes the cabinet construction.When cabinet is risen the construction of empty location, should finish the fixing of cabinet top finishes connecting rod and separating that cabinet pushes up again, usually the method that adopts is: under the aerostatic buoyancy effect, earlier cabinet toplap buoyance lift is crossed designed elevation, connecting rod and being connected that cabinet pushes up are removed simultaneously with interim bracket in location, welding cabinet top under the state of suspension of high-altitude, descend in all constructions final vacuum that finishes, finish the cabinet top the location, high-altitude and with the separating of piston.
Conventional cabinet is risen sky and is orientated as and satisfy cabinet toplap buoyance lift apart from having increased a large amount of interim steel using amounts; Need concentrate a large amount of artificial facility to construct and the maintenance of suspension system water, electricity, gas at short notice; Also there is great potential safety hazard in the long-time construction that suspends, in case the elevating movement that air pressure variations all will cause the cabinet top takes place in the suspension work progress, influences the welding of bracket, and serious cabinet top " roof fall " will take place or fall the major accident of damaging bracket after rise.
Conventional construction can't be risen the construction process perfect adaptation of empty location with cabinet with the bird hook, has one-sidedness, nonstandard, lack of standard, and cost reduces not obvious, has great potential safety hazard, can't extensively promote the use of.
Summary of the invention
Technical problem to be solved by this invention provides the gas cabinet cabinet top mounting and positioning device of a kind of easy construction, safety.
The present invention solves the gas cabinet cabinet top mounting and positioning device that its technical problem adopts, and comprises the connecting rod that is connected with piston in the cabinet, and the bird hook is connected with connecting rod by bird hook hinge, and connecting rod top is connected with employing movable rod between cabinet pushes up.
The present invention simultaneously also provides the method for construction that adopts gas cabinet cabinet top mounting and positioning device, may further comprise the steps:
1) adopt connecting rod, movable rod that cabinet top and piston are connected to form whole movable platform;
2) inflation makes the unsteady rising of movable platform in cabinet, and finishes segmentation and install, adjust construction;
3) mounting point according to the cabinet top is provided with bracket at cabinet;
4) bird is hooked on the bracket, adjusts cabinet top and installation in position, finish the fixing of cabinet top;
5) dismounting movable rod is removed being connected between bird hook and the bracket;
6) piston reset is finished installation.
Adopt the mounting and positioning device and the installation method on large-scale gas cabinet of the present invention top, have following beneficial effect: 1, installation used steel consumption greatly reduces, and has reduced raw-material consumption, has reduced cost.2, make and concentrate a large amount of people, machine, things to construct and the system maintenance of water, electricity, gas in the short time that need not hovering when cabinet is risen empty location, operating expenses greatly reduces.3, need not to construct under the buoyance lift floating state, system has solved the security hidden trouble of this technology comprehensively, makes cabinet rise empty location easy construction, quick, safety.
Description of drawings
Fig. 1 is a gas cabinet cabinet of the present invention top mounting structure schematic representation;
Fig. 2 is the schematic side view of gas cabinet cabinet top mounting and positioning device;
Fig. 3 is the schematic representation of another kind of mode of execution.
Reference character among the figure: 1-cabinet top, 2 connecting rods, 3 bird hooks, 4 brackets, 5 cabinets, 6 movable rods, 7-connecting-rod bolts, 8 cabinet top connecting bolts, 10-bird hook hinge.
Embodiment
In the installation process of large-scale gas cabinet, for with cabinet top installation in position, adopt connecting rod 2 that piston in the cabinet and cabinet top 1 are linked together, then to inflation pressurization in the cabinet, also upwards float in the upwards unsteady cabinet top 1 that drives of piston, because it is very high that cabinet pushes up 1 mounting point, the therefore necessary form of construction work that adopts segmentation upwards to float.By bird hook hinge 10 bird hook 3 is installed on the connecting rod 2, bird hook 3 can be avoided the bracket 4 on the cabinet 5 in uphill process, bird hook 3 can hang on the bracket 4 when descending, when a segment distance is floated on cabinet top 1, the coupler body 9 that is connected the bird hook 3 on the connecting rod 2 by bird hook hinge 10 hangs on the protruding bracket 4 that is arranged on the cabinet 5 constructs, and repeats next segmentation on cabinet top 1 after construction is finished again and floats.
Connecting rod of the present invention, bird hook device are as shown in Figure 1, between connecting rod 2 and cabinet top 1, be provided with movable rod 6, adopt the mode of structure that removably connects or adopt reduction movable rod 6 height between movable rod 6 and the connecting rod 2, make between connecting rod 2 and the cabinet top 1 and reserve activity space.Float when being raised to the mounting point on cabinet top on cabinet top 1, the design size that hangs over bird hook 3 satisfies on the bracket 4 of cabinet top installation dimension, like this by cabinet top connecting bolt 8 with cabinet top installation in position, after cabinet pushed up 1 installation, dismounting movable rod 6 made slot milling between connecting rod 1 and the cabinet top 1, and then floating piston and connecting rod 1, remove being connected between bird hook 3 and the bracket 4, make piston drivening rod 2,3 declines of bird hook again, finish whole installation processes.Therefore solved in the existing mounting structure because cabinet top 1 and directly has been connected, be hooked on the problem that to dismantle connecting rod after the installation cabinet pushes up on the bracket bird with connecting rod 2.
As the concrete structure of movable rod 6, can adopt multiple structure, (1) structure as shown in Figure 1, 2 is provided with level between connecting rod 2 and the movable rod 6 and is connected the plane, adopts connecting-rod bolts 7 to link together each other, and being connected of movable rod 6 and cabinet top 1.Behind the installation in position of cabinet top, remove being connected of movable rod 6 and connecting rod 2, cabinet top 1 simultaneously, then movable rod 6 is taken out, make between connecting rod 2 and the cabinet top 1 to form and the highly consistent space of movable rod 6; (2) can also adopt as shown in Figure 3, link together with horizontally disposed connecting-rod bolts 7 in the side of connecting rod 2 and movable rod 6, and being connected of movable rod 6 and cabinet top 1.Remove being connected of movable rod 6 and connecting rod 2, cabinet top 1 simultaneously, movable rod 6 is than easier taking-up of Fig. 2 mode of execution and dismounting; (3) in addition can also be with jack as movable rod 7, jack both had been convenient to cabinet and had been pushed up 1 adjustment when in place like this, be convenient to again dismantle, but its cost was higher.
Installation method as gas cabinet cabinet of the present invention top, adopt following steps:
1) adopt connecting rod 2, movable rod 6 that cabinet top 1 and piston are connected to form whole movable platform;
2) inflation makes the unsteady rising of movable platform in cabinet 5, and adopts bird hook 3 to finish segmentation and install, adjust and construct;
3) push up 1 installation in position position according to the size distance of cabinet top 1 from cabinet, bracket 4 is set in the relevant position of cabinet 5 with bird hook 3;
4) after hanging over bird hook 3 on the bracket 4, adjust cabinet top 1 and installation in position, finish the fixing of cabinet top;
5) dismounting movable rod 6, float rising piston and connecting rod 2 are removed being connected between bird hook 3 and the bracket 4;
6) piston reset is finished installation.
In above-mentioned steps, step 3) can be carried out when arbitrary steps before, and its purpose only is cabinet top 1 when being in the highest mounting point, and bird hook 3 can hang on the bracket 4.

Claims (6)

  1. [claim 1] gas cabinet cabinet top mounting and positioning device, comprise the connecting rod (2) that is connected with piston in the cabinet, bird hook (3) passed through bird hook hinge (10) and is connected with connecting rod (2), it is characterized in that: connecting rod (2) top is pushed up between (1) with cabinet and is adopted movable rod (6) to be connected.
  2. [claim 2] gas cabinet cabinet as claimed in claim 1 top mounting and positioning device is characterized in that: between connecting rod (2) and the movable rod (6) level is set and is connected the plane, and adopt connecting-rod bolts 7 to connect.
  3. [claim 3] gas cabinet cabinet as claimed in claim 1 or 2 top mounting and positioning device is characterized in that: described movable rod (6) is a jack.
  4. [claim 4] gas cabinet cabinet as claimed in claim 1 top mounting and positioning device is characterized in that: the side of connecting rod (2) and movable rod (6) is connected with horizontally disposed connecting-rod bolts (7).
  5. [claim 5] adopts the installation method of gas cabinet cabinet as claimed in claim 1 top mounting and positioning device, may further comprise the steps:
    1) adopt connecting rod (2), movable rod (6) that cabinet top (1) and piston are connected to form whole movable platform;
    2) inflation makes the unsteady rising of movable platform in cabinet (5), and finishes segmentation and install, adjust construction;
    3) mounting point according to cabinet top (1) is provided with bracket (4) at cabinet (5);
    4) bird hook (3) is hung on the bracket (4), adjust cabinet top (1) and installation in position, finish the fixing of cabinet top;
    5) dismounting movable rod (6) is removed being connected between bird hook (3) and the bracket (4);
    6) piston reset is finished installation.
  6. [claim 6] gas cabinet cabinet as claimed in claim 5 top installation method is characterized in that: the mounting point of bracket described in the step 3) (4) is provided with according to the corresponding distance of size between cabinet top (1) and the bird hook (3).
CN2009103011774A 2009-03-27 2009-03-27 A gas cabinet cabinet-top mounting and positioning apparatus and method thereof Active CN101532606B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103011774A CN101532606B (en) 2009-03-27 2009-03-27 A gas cabinet cabinet-top mounting and positioning apparatus and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103011774A CN101532606B (en) 2009-03-27 2009-03-27 A gas cabinet cabinet-top mounting and positioning apparatus and method thereof

Publications (2)

Publication Number Publication Date
CN101532606A true CN101532606A (en) 2009-09-16
CN101532606B CN101532606B (en) 2011-01-05

Family

ID=41103376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103011774A Active CN101532606B (en) 2009-03-27 2009-03-27 A gas cabinet cabinet-top mounting and positioning apparatus and method thereof

Country Status (1)

Country Link
CN (1) CN101532606B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101832465A (en) * 2010-06-18 2010-09-15 江苏环能工程有限公司 Synchronously jacking construction method for side plate and top cover of rubber film sealed gas holder
CN101893162A (en) * 2010-07-23 2010-11-24 武汉一冶钢结构有限责任公司 Construction method for gas holder and connection hooking apparatus for same
CN102494239A (en) * 2011-12-22 2012-06-13 北京首钢建设集团有限公司 Method for installing thin oil sealed dry-type gas tank
CN104325266A (en) * 2014-10-23 2015-02-04 中国三冶集团有限公司 Hanging device and hanging method for integral floating of chamber top of gas chamber

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201401626Y (en) * 2009-04-21 2010-02-10 中冶实久建设有限公司 Gas tank top mounting and positioning device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101832465A (en) * 2010-06-18 2010-09-15 江苏环能工程有限公司 Synchronously jacking construction method for side plate and top cover of rubber film sealed gas holder
CN101832465B (en) * 2010-06-18 2012-08-29 江苏环能工程有限公司 Synchronously jacking construction method for side plate and top cover of rubber film sealed gas holder
CN101893162A (en) * 2010-07-23 2010-11-24 武汉一冶钢结构有限责任公司 Construction method for gas holder and connection hooking apparatus for same
CN101893162B (en) * 2010-07-23 2013-06-19 武汉一冶钢结构有限责任公司 Construction method for gas holder and connection hooking apparatus for same
CN102494239A (en) * 2011-12-22 2012-06-13 北京首钢建设集团有限公司 Method for installing thin oil sealed dry-type gas tank
CN104325266A (en) * 2014-10-23 2015-02-04 中国三冶集团有限公司 Hanging device and hanging method for integral floating of chamber top of gas chamber

Also Published As

Publication number Publication date
CN101532606B (en) 2011-01-05

Similar Documents

Publication Publication Date Title
CN101532606B (en) A gas cabinet cabinet-top mounting and positioning apparatus and method thereof
CN101284628B (en) Hoisting method for framework of large tonnage pressing machine
CN201401626Y (en) Gas tank top mounting and positioning device
CN205637622U (en) Perpendicular unit glass curtain wall hoist and mount system
CN205442393U (en) Posture that falls suspension system
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN101552430B (en) Method for installing and hoisting gas-insulated metal closed power transmission line in shaft and device thereof
CN203959697U (en) The equalizing bar of hoisting platform truss
CN202754704U (en) Hoisting device for heating surface module of heat recovery boiler
CN206774962U (en) Disconnecting switch mounting platform car
CN201062431Y (en) Lifting device for cantilever scaffold
CN215164726U (en) A wholly unload structure that is used for cast-in-place beam steel pipe pile support to demolish fast
CN104325266B (en) A kind of suspension system for the floating liter of top of gas cabinet entirety and hanging method
CN201873407U (en) Lift maintenance protecting device
CN101774516B (en) Lifting device and construction method for replacing rake crane bridge
CN201339309Y (en) Attached self-lifting scaffold
CN209981897U (en) Auxiliary device for ground wire suspension
CN101709344B (en) Method for hoisting terrace for furnace top raw gas pipeline
CN204703485U (en) A kind of lifting material platform
CN214090854U (en) Safety protection operation platform for shaft lining construction
CN204195181U (en) A kind of suspension arrangement for the overall buoyance lift of top of gas cabinet
CN207987785U (en) A kind of upper front beam suspension system of suspended pouring construction hanging basket
CN201056830Y (en) Elevation linkage system of cantilever scaffold
CN219570141U (en) Device convenient to flame proof canopy adds water
CN201546437U (en) Simple high-altitude operating platform capable of being mounted and dismounted quickly

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA 19TH METALLURGICAL CORPORATION

Free format text: FORMER OWNER: MCC SHIJIU CONSTRUCTION CO., LTD.

Effective date: 20110318

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 617000 NO. 350, RENMIN STREET, PANZHIHUA CITY, SICHUAN PROVINCE TO: 617000 NO. 350, RENMIN STREET, EAST DISTRICT, PANZHIHUA CITY, SICHUAN PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110318

Address after: 617000 Panzhihua, Sichuan, East Street, No. 350

Patentee after: China 19th Metallurgical Corporation

Address before: 617000 No. 350 Renmin Street, Sichuan, Panzhihua

Patentee before: MCC Shijiu Construction Co., Ltd.