CN101414368A - Single step regulation method for train formation plan of railway technology station - Google Patents

Single step regulation method for train formation plan of railway technology station Download PDF

Info

Publication number
CN101414368A
CN101414368A CNA2008102275323A CN200810227532A CN101414368A CN 101414368 A CN101414368 A CN 101414368A CN A2008102275323 A CNA2008102275323 A CN A2008102275323A CN 200810227532 A CN200810227532 A CN 200810227532A CN 101414368 A CN101414368 A CN 101414368A
Authority
CN
China
Prior art keywords
station
wagon flow
technical
condition
rectilinear direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008102275323A
Other languages
Chinese (zh)
Inventor
林柏梁
王鹏
陈柏谦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiaotong University
Original Assignee
Beijing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiaotong University filed Critical Beijing Jiaotong University
Priority to CNA2008102275323A priority Critical patent/CN101414368A/en
Publication of CN101414368A publication Critical patent/CN101414368A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Train Traffic Observation, Control, And Security (AREA)

Abstract

The invention relates to a railway technical station train formation plan single step regulation method, which is an electric digital processing method and a computer simulation method. The invention is realized in this way: the system uses universal digital computers and technical station formation plan single step regulation procedure which is used for railway transportation and is installed in the computer; the operating steps of the system comprises: choosing modules; forming initial proposals; regulating proposals; and forming final projects. With the use of the invention, computation sheets are not necessary to be drawn by workers, so as to effectively reduce the workload of planning personnel. With the computer simulation, dull tabular calculation method can be vividly simulated by computers, so that the method of the invention is vivid and direct, which is conveniently used and makes the understanding of tabular calculation simple.

Description

Single step regulation method for train formation plan of railway technology station
Technical field
The present invention relates to single step regulation method for train formation plan of railway technology station, is a kind of method of electric digital processing, is a kind of method for computer simulation.
Background technology
At present, utilize just draw calculation form manually of tabular calculation establishment optimisation technique station marshaling plan of train, manually calculate each technical station constraint condition, each step is whole all to need the artificial earlier complicated computation sheet of drawing, calculate adjustment again, very trouble.
Summary of the invention
The objective of the invention is to propose a kind of single step regulation method for train formation plan of railway technology station, described method is to use computing machine that the single group of transportation by railroad technical station establishment marshaling plan of train is utilized human-computer interaction, the method of adjusting is a kind of computer simulation to tabular calculation.
The present invention is achieved in that single step regulation method for train formation plan of railway technology station, and the step of described method is as follows:
A, selection template: select template: four kinds of circuit form templates are: 6 technical stations of rectilinear direction, 5 technical station right-hand members of rectilinear direction band branched line, 5 technical station left ends of rectilinear direction band branched line, 5 technical station two ends of rectilinear direction band branched line.Select a kind of in four kinds of circuit form templates, required wagon flow data of each technical station and parameter are provided with voluntarily by the user in the template of selection, save as the Txt document;
B, formation initial scheme: form a plurality of selectable initial scheme, three conditions that direct train is started by selecting to satisfy the condition of starting direct train:
Necessary condition: N Directly∑ t Joint〉=cm,
Adequate condition:
Figure A200810227532D00031
Absolute condition:
Figure A200810227532D00032
Parameter wherein is:
N DirectlyFor: the vehicle flowrate (unit: car) of through wagon flow;
t JointDo not have the car of reorganization by technical station for: through wagon flow and hour save time (unit: hour)
Cm is: the assembly car that diel consumed when this wagon flow was started direct train hour (unit: car hour)
C, project setting: change the operation situation of wagon flow, satisfy the wagon flow of three kinds of conditions and represent with three kinds of different forms with the wagon flow that does not satisfy any one condition by the relevant art station.
D, formation final plan: adjust the back and form final plan, listed the reorganization scheme of wagon flow and the reorganization operation situation of each technical station automatically,, proceed to adjust if be unsatisfied with.
Beneficial effect of the present invention: need not free-hand draw calculation form, effectively alleviated planning personnel's workload.Simulate with computing machine, uninteresting tabular calculation is come out with the simulation of computing machine image, visual in image, easy to use, be convenient to understand tabular calculation.
Description of drawings
Below in conjunction with drawings and Examples the present invention is done further narration.
The principle of work block diagram of Fig. 1 system of the present invention;
The synoptic diagram of 6 technical station templates of Fig. 2 rectilinear direction;
The synoptic diagram of 5 technical station right-hand members of Fig. 3 rectilinear direction band branched line template;
The synoptic diagram of 5 technical station left ends of Fig. 4 rectilinear direction band branched line template;
The synoptic diagram of 5 technical station two ends of Fig. 5 rectilinear direction band branched line template;
Six technical station line profiles of Fig. 6 rectilinear direction;
Fig. 7 initial calculation form;
The through condition judgment of starting of Fig. 8;
The initial starting scheme of Fig. 9;
Figure 10 project setting;
Figure 11 adjusts the back scheme;
Figure 12 final plan and each station job information.
Embodiment
Embodiment one:
Present embodiment is a single step regulation method for train formation plan of railway technology station.The operating procedure of described method is as shown in Figure 1:
A, selection template: 6 technical stations of rectilinear direction (Fig. 1), 5 technical station right-hand members of rectilinear direction band branched line (Fig. 2), 5 technical station left ends of rectilinear direction band branched line (Fig. 3), 5 technical station two ends of rectilinear direction band branched lines (Fig. 4).In each template, on behalf of technical station, the form of template, letter be the simple description of rail track form, and straight line is represented rail track, and on behalf of rail track, bifurcated the circuit of shunting is arranged at crotch.This method establishes database, has stored required wagon flow data and the parameter of each technical station in the template in this database.These data comprise: the vehicle flowrate on the circuit between each technical station.Parameter comprises: the assembly car hour that is meant each technical station itself consumes, and separates volume ability and through wagon flow and does not have saving time that reorganization passes through.When carrying out the through project setting of technical station, required wagon flow data of each technical station and parameter are provided with voluntarily by the user in the template of selection, save as the Txt document;
B, formation initial scheme: form a plurality of selectable initial scheme, three conditions that direct train is started by selecting to satisfy the condition of starting direct train:
Necessary condition: independent or many long-range wagon flows of any long-range wagon flow merge starts the direct train arrival station, its necessary condition be on the way technical station do not have that reorganization hour saves by the car that obtains must be more than or equal to of the assembly car hour consumption of this direct train arrival station, that is: at the starting station
N Directly∑ t Joint〉=cm;
Wherein: N Directly---the through train flow;
t Joint---through wagon flow does not have the car of reorganization by technical station on the way and hour saves time;
The assembly parameter of c---technical station;
M---train weave into a number.
With six technical stations of rectilinear direction is that example describes, and technical station A starts and arrives the wagon flow of technical station D, if tissue is through, it hour consumes and must not have saving time of station B that reorganization passes through and C halfway less than it at the assembly car at A station so.Suppose that it hour consumes at the assembly car at A station is 600, saving in the nothing reorganization at B station is 360, and saving in the nothing reorganization at C station is 380, and wagon flow AD just meets and starts through necessary condition so.
Adequate condition: the long-range wagon flow of single or many merging, adequate condition to shorter direct train arrival station or short through wagon flow, be that its nothing reorganization in the acquisition of overtaking section is passed through the car hour saving of technical station more than or equal to the car of assembling at the starting station hour consumption, that is:
Figure A200810227532D00051
t Joint is far away---long-range wagon flow does not have reorganization at the section that is out of the line and saves by the time of technical station acquisition on the way.
With six technical stations of rectilinear direction is that example describes, it is through to suppose that wagon flow AE, AF start, assembling car hour consumption all is 600, wagon flow AF does not have the saving of reorganization by E station, and to be 640,640〉600 direct train AF satisfy adequate condition to direct train AE promptly requires wagon flow AF not have car that reorganization passes through at the E station hour to save greater than it and hour consume at the assembly car of technical station A.
Absolute condition: any single Zhi Yuancheng wagon flow is started the absolute condition of direct train separately, and to be it in the nothing reorganization of arbitrary technical station on the way hour save all more than or equal to the assembly car at this direct train arrival station by car hour consumes, promptly;
Figure A200810227532D00061
t Joint is minimum---single Zhi Yuancheng wagon flow does not have reorganization and saves time by the minimum in the technical station on the way.
Example with the explanation necessary condition is analyzed, if wagon flow AD hour saves greater than hour consuming 600 at the assembly car at A station at the car at its technical station B that passes through and C station, then wagon flow AD satisfies the absolute condition of starting direct train.
C, project setting: change the operation situation of wagon flow, satisfy the wagon flow of three kinds of conditions and represent with three kinds of different forms with the wagon flow that does not satisfy any one condition by the relevant art station; Satisfy the wagon flow of absolute condition and represent, satisfy the wagon flow of relative conditon and represent, do not start through wagon flow and represent with black with green with redness.Changing wagon flow is to represent wagon flow to realize in the color of the numeral of the car hour consumption at this station to change in the operation situation of technical station, just can change the operation situation that color digital on the button has also promptly changed this station as long as click the corresponding button in station.
D, formation final plan: adjust the back and form final plan, listed the reorganization scheme of wagon flow and the reorganization operation situation of each technical station automatically,, proceed to adjust if be unsatisfied with;
Present embodiment is that basic system provides four kinds of circuit formal models using always in the teaching with the tabular calculation.
The input of system data is with the form realization of read data files at random, and the random data file can be used as exam pool and uses for teacher or student; 1. the drafting of form forms with the text box arrangement in the system; 2. three conditions that direct train is started in the system:
Necessary condition: N Directly∑ t Joint〉=cm
Adequate condition:
Absolute condition:
Figure A200810227532D00063
Form with check box realizes that the user judges condition by the selection to check box; 3. the wagon flow that satisfies three kinds of conditions is represented (the expression color of adequate condition and necessary condition is the same) with the wagon flow that does not satisfy any one condition with three kinds of different forms, and wagon flow is represented the reorganization situation of wagon flow at this station at the color relation of each technical station correspondence; 4. organize into groups of the form realization of the adjustment form of scheme with button; 5. realize the change of wagon flow by clicking operation in relevant art station reorganization situation to button.6. adjusted scheme system provides automatically, and the parameters such as load of individual technical station are calculated automatically.7. system also provides the automatic scoring function to user's operation, and the automatic scoring function is that scheme and the optimal case made by the user compare realization.
1, select template: at first select template after entering system, Fig. 6 is the rectilinear direction template, and vehicle flowrate is read at random by text between each technical station parameter and station;
2, form initial scheme: enter dialog box shown in Figure 7 behind " determining " button in the dialog box shown in some Fig. 6,, select to satisfy the wagon flow of starting the direct train condition and see Fig. 8 by clicking dialog box the right three buttons such as " necessary conditions ".Determine that the back forms initial scheme as shown in Figure 7.
3, project setting: (numeral that highlights is green in the design of this method among each figure in dialog box shown in Figure 9, below respectively scheme identical), click the corresponding button in the right and carry out project setting, as shown in figure 10, change the operation situation of wagon flow by the color of clicking button change button by the relevant art station, as: want that wagon flow AC is not had reorganization to be changed in the reorganization of B station by technical station B, as long as click the button of first row of wagon flow AC correspondence, word color blackening on the button, just can finish, as shown in figure 11.
4, form final plan: adjust the back and form final plan as shown in figure 12, the reorganization scheme of wagon flow and the reorganization operation situation of each technical station in Figure 12, have been listed automatically, if dissatisfied, can click " getting back to initial form " or " getting back to project setting " and proceed to adjust.

Claims (1)

1. single step regulation method for train formation plan of railway technology station is characterized in that following steps:
A, selection template: four kinds of circuit form templates are: 6 technical stations of rectilinear direction, 5 technical station right-hand members of rectilinear direction band branched line, 5 technical station left ends of rectilinear direction band branched line, 5 technical station two ends of rectilinear direction band branched line.Select a kind of in four kinds of circuit form templates, required wagon flow data of each technical station and parameter are provided with voluntarily by the user in the template of selection, save as the Txt document;
B, formation initial scheme: by selecting the satisfied wagon flow formation initial scheme that direct train is started condition of starting, three conditions that direct train is started:
Necessary condition: N Directly∑ t Joint〉=cm,
Adequate condition:
Absolute condition:
C, project setting: change the operation situation of wagon flow, satisfy the wagon flow of three kinds of conditions and represent with three kinds of different forms with the dissatisfied wagon flow of starting through condition by the relevant art station;
D, formation final plan: adjust the back and form final plan, listed the reorganization scheme of wagon flow and the reorganization operation situation of each technical station,, can get back to the project setting step and continue to adjust if be unsatisfied with.
CNA2008102275323A 2008-11-28 2008-11-28 Single step regulation method for train formation plan of railway technology station Pending CN101414368A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008102275323A CN101414368A (en) 2008-11-28 2008-11-28 Single step regulation method for train formation plan of railway technology station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008102275323A CN101414368A (en) 2008-11-28 2008-11-28 Single step regulation method for train formation plan of railway technology station

Publications (1)

Publication Number Publication Date
CN101414368A true CN101414368A (en) 2009-04-22

Family

ID=40594895

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008102275323A Pending CN101414368A (en) 2008-11-28 2008-11-28 Single step regulation method for train formation plan of railway technology station

Country Status (1)

Country Link
CN (1) CN101414368A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106991495A (en) * 2017-03-24 2017-07-28 北京交通大学 A kind of method and system of china railway unified organizational system freight trains grouping plan
CN111369065A (en) * 2020-03-09 2020-07-03 西南交通大学 Method for determining minimum marshalling number of goods train based on time window constraint

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106991495A (en) * 2017-03-24 2017-07-28 北京交通大学 A kind of method and system of china railway unified organizational system freight trains grouping plan
CN111369065A (en) * 2020-03-09 2020-07-03 西南交通大学 Method for determining minimum marshalling number of goods train based on time window constraint
CN111369065B (en) * 2020-03-09 2022-05-31 西南交通大学 Method for determining minimum marshalling number of goods train based on time window constraint

Similar Documents

Publication Publication Date Title
Merschbrock et al. BIM technology acceptance among reinforcement workers-the case of Oslo airport's terminal 2
von Schönfeld et al. Unpacking social learning in planning: who learns what from whom?
Hess et al. Common core meets education reform: What it all means for politics, policy, and the future of schooling
EP1638028A3 (en) Computer aided generation and change management for user interfaces
Dörfler et al. Learning from a drastic failure: the case of the Airbus A380 program
CN103955173B (en) A kind of On-Line Control Method and system that keeps steel smelting-continuous casting production stability
Hagen et al. “Magic through many minor measures”: How introducing a flowline production mode in six steps enables journalist team autonomy in local news organizations
Harrison et al. Promoting interdisciplinarity in engineering teaching
CN101414368A (en) Single step regulation method for train formation plan of railway technology station
CN102799767A (en) Marking software system
CN108764626A (en) A kind of diagnosis of energy saving method and apparatus
Melnikova et al. Transforming requirements for engineering occupations as affected by technological changes
Maggard et al. Total productive maintenance; TPM that works
Grasso Obstacles to lean accountancy
Restel et al. The Railway Timetable Evaluation Method in Terms of Operational Robustness against Overloads of the Power Supply System
Hollermann et al. BIM-A challenge for communication between parties involved in construction
Zahedi et al. Seamless integration of simulation and analysis in early design phases
Carroll Leadership in lean, empowering manufacturing organizations
DI GIUDA et al. Engineering and management of information modeling requirements
CN105205593A (en) Team information integrated comprehensive display system
Jourdan et al. Sign code development process: Best practices
Li et al. Ranking the efficiency performance within a set of decision making units by data envelopment analysis
CN106980927A (en) A kind of business model evaluation method and system
Bullen Digital manufacturing: the digital tapestry
Basson et al. The use of building information modelling as a tool to improve informed design communication between student and lecturer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20090422