CN101329433A - Construction method for paving road slot minitype communication pipe by urban area road - Google Patents
Construction method for paving road slot minitype communication pipe by urban area road Download PDFInfo
- Publication number
- CN101329433A CN101329433A CNA2008101164963A CN200810116496A CN101329433A CN 101329433 A CN101329433 A CN 101329433A CN A2008101164963 A CNA2008101164963 A CN A2008101164963A CN 200810116496 A CN200810116496 A CN 200810116496A CN 101329433 A CN101329433 A CN 101329433A
- Authority
- CN
- China
- Prior art keywords
- pipe
- groove
- micro
- box
- trough
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
- Light Guides In General And Applications Therefor (AREA)
Abstract
The invention relates to a construction method for paving a road trough micro-communication pipeline by utilizing a city road, belonging to the optical fiber cable transmission technology field. A trough line is firstly drawn according to a set planning or a designed router, a road surface is cut along the drawn trough line, and a trough is dug out; a four-way or three-way micro-pipe is embedded at one end of the trough, and a micro-pipe joint box is embedded at the other end of the trough which is close to a manhole or a connection box; a pipe bracket is paved at the bottom part of the trough, a micro-cable sub-pipe is distributed on the pipe bracket, the both ends of the micro-cable sub-pipe are extended into the micro-pipe joint box and a micro-pipe branch box; an upper pipe cover is arranged above the sub-pipe, a cover board is finally covered on the pipe cover; and a super early strength repairing agent is poured into the trough. The construction method has the advantages that: the application range is wide, the construction method can be accessed to the tail end of a metropoliatan area network for communicating the prior communication pipeline and a small-diameter rain (polluted) water pipeline, thereby building the supplement for a micro-pipeline system. The advantage of the network capacity expansion is obvious, when in fault of the optical fiber cable, the rush repair is easy, and the recovery of the communication is fast. The construction is flexible and not limited by an underground pipe network, and the construction risk is very small.
Description
Technical field
The present invention relates to a kind of construction method of utilizing downtown roads to lay the road slot minitype communication pipe, belong to technical field of cable transmission.
Background technology
The construction of conventional cable transmission network, at first broken road ditching on downtown roads or walkway is embedded in communication pipe underground, by the mode of artificial traction, lays ordinary optical cable in pipeline again.
Existing road groove optical cable construction mode is to leave a narrow slit on the downtown roads road surface, buries in the slit and puts an optical cable.Though this form of construction work has short, the advantage flexibly of building time, because road groove system of laying is disposable, installs gradually with the little cable of air-blowing and compare, for later network capacity extension reduction with the obvious advantage, and when breaking down, optical cable is difficult for changing.
The existing micro-control push pipe mode that is used for road groove optical cable laying, owing to be subjected to the influence of complicated subterranean pipe line when constructing in the city, its application is restricted, and there is weak point in the detectivity of micro-control pipe jacking equipment, makes the operation of micro-control push pipe have very big danger.
Road groove microchannel is on downtown roads, across or along road, adopt cast-cutting saw, narrow groove of cutting makes up microchannel in groove on road.
Summary of the invention
The objective of the invention is to propose a kind of construction method of utilizing downtown roads to lay the road slot minitype communication pipe, make the construction of communication pipe in the city convenient more, destruction to original road and urban operating mechanism when communication pipe is laid is reduced to negligible degree, but also not connected people (hand) hole can be interconnected.Provide support for setting up the optical cable Metropolitan Area Network (MAN), the end of Metropolitan Area Network (MAN) is linked in the communication microchannel very easily.
The downtown roads that utilize that the present invention proposes are laid the construction method of road slot minitype communication pipe, may further comprise the steps:
(1) according to setting the planning or the design route picture ditch line of rabbet joint,, digs out groove, and make channel bottom smooth along the ditch line of rabbet joint cutting road surface of finishing;
(2) bury at an end of groove and put four-way or threeway microtubule difference box, the other end of groove buries near manhole or cross-connecting box place puts the microtube joint box;
(3) spread fine sand at described channel bottom, thickness is 5~15 millimeters, and the conduit saddle that tiles on fine sand is placed on little cable pipe cloth on the conduit saddle in the groove, and makes little cable manage two ends to stretch into respectively in microtube joint box and the microtubule difference box;
(4) put shroud above the sub-pipe in groove, shroud and following slit are filled up with fine sand, at last cover plate is covered on shroud;
(5) remove loose material, dust or mud in the groove, in groove, pour instant coagulant and mending agent into, smooth until the groove periphery.
In the said method, the width w of groove is 40~60 millimeters, and the degree of depth h of groove is 200~300 millimeters.
The downtown roads that utilize that the present invention proposes are laid the construction method of road slot minitype communication pipe, and its advantage is:
1, having wide range of applications of the inventive method, the end that can be used for Metropolitan Area Network (MAN) inserts, and links up existing communication pipeline and tubule footpath rain (dirt) waterpipe and makes up replenishing of microchannel system.
2, compare with existing road groove optical cable, owing to adopt the little cable of microtubule, the network capacity extension is with the obvious advantage, and during Cable's Fault, repairing is easy, and recovery communication is fast.
3, compare with existing micro-control push pipe mode, construction is not limited by underground pipe network flexibly, and construction is dangerous minimum.
Description of drawings
Fig. 1 is the construction synoptic diagram that utilizes the inventive method.
Fig. 2 is the A-A cut-open view of Fig. 1.
Fig. 3 is the structural representation of microtubule difference box used in the inventive method.
Fig. 4 is the vertical view of microtubule difference box shown in Figure 3.
Fig. 5 is the B-B cut-open view of microtubule difference box shown in Figure 3.
Fig. 6 is the synoptic diagram of the another kind of structure of microtubule difference box used in the inventive method.
Fig. 7 is the vertical view of microtubule difference box shown in Figure 6.
Fig. 8 is the C-C cut-open view of microtubule difference box shown in Figure 6.
Among Fig. 1 and Fig. 2, the 1st, highway, the 2nd, communication pipe, the 3rd, manhole or cross-connecting box, the 4th, little cable pipe, the 5th, microtube joint box, the 6th, road groove microchannel, the 7th, four-way microtubule difference box, the 8th, threeway microtubule difference box, the 9th, groove, the 10th, filling material, the 11st, cover plate, the 12nd, shroud, the 13rd, microtubule, the 14th, conduit saddle, the 15th, spun yarn.Among Fig. 3~Fig. 5,16 fixing circular holes, the 17th, the outlet of microtubule difference box, the 18th, loam cake, the 19th, microtubule difference box base, among Fig. 6~Fig. 8, the 20th, fixing circular hole, the 21st, microtubule difference box exports, and the 22nd, loam cake, the 23rd, base.Among Fig. 3~Fig. 5, L is the long edge lengths of microtubule difference box, and W is the bond length of microtubule difference box, and h is the thickness of microtubule difference box, R
1Be the outlet diameter of microtubule difference box, L
2Be the length of microtubule difference box outlet.
Embodiment
The present invention proposes to utilize downtown roads to lay the construction method of road slot minitype communication pipe, and its construction synoptic diagram may further comprise the steps as shown in Figure 1:
(1) according to setting planning or design route, on highway 1, draws the ditch line of rabbet joint,, dig out groove 9, and make channel bottom smooth along the ditch line of rabbet joint cutting road surface of finishing;
(2) bury at an end of groove 9 and put four-way microtubule difference box 7 or threeway microtubule difference box 8, the other end of groove buries near manhole 3 or cross-connecting box place puts microtube joint box 5;
(3) spread fine sand 15 in described groove 9 bottoms, as shown in Figure 2, thickness is 5~15 millimeters, tiling conduit saddle 14 on fine sand, optical cable pipe 4 cloth are placed on the conduit saddle 14 in the groove 9, and make little cable manage 4 two ends to stretch into respectively in microtube joint box 5 and the microtubule difference box 7;
(4) put shroud 12 above the little cable pipe in groove, shroud 12 and following slit are filled up with fine sand, fibreglass reinforced plastic cover is covered on rubber shroud 12 at last;
(5) remove loose material, dust or mud in the groove 9, in groove, pour instant coagulant and mending agent into, smooth until the groove periphery.
In the said method, the width w of groove is 40~60 millimeters, and the degree of depth h of groove is 200~300 millimeters.
Used microtubule difference box in the inventive method, two kinds of different structures are arranged, first kind of microtubule difference box is threeway microtubule difference box, its structure such as Fig. 3~shown in Figure 5, form by loam cake 18 and base 19, loam cake 18 and base 19 interlock and closely cooperate, and the relevant position of loam cake 18 and base 19 has fixing with circular hole 16.Microtubule difference box ovalize forms two relative outlets between the loam cake of both sides, the long limit of microtubule difference box and the base, forms the 3rd outlet between the loam cake of a side of microtubule difference box minor face and the base; The long edge lengths L of microtubule difference box is 260~280 millimeters, and bond length W is 150~160 millimeters, and the thickness h of microtubule difference box is 50 millimeters, the diameter R of microtubule difference box outlet
1Be 40~50 millimeters, the length L of microtubule difference box outlet
2It is 20 millimeters.
Second kind of used microtubule difference box is four-way microtubule difference box in the inventive method, its structure such as Fig. 6~shown in Figure 8, form by loam cake 22 and base 23, loam cake 22 and base 23 interlock and closely cooperate, the relevant position of loam cake 22 and base 23 has fixing with circular hole 20, microtubule difference box ovalize forms two relative outlets between the loam cake of both sides, the long limit of microtubule difference box and the base, forms two other relative outlet between the loam cake of the both sides of microtubule difference box minor face and the base.The long edge lengths L of microtubule difference box is 260~280 millimeters, and bond length W is 190~200 millimeters, and the thickness h of microtubule difference box is 50 millimeters, the diameter R of microtubule difference box outlet
1Be 40~50 millimeters, the length L of microtubule difference box outlet
2It is 20 millimeters.
In the inventive method, the material of the little cable pipe that lays in the groove can be high-density polyethylene plastics, and specification is two kinds of ¢ 40/34mm and ¢ 44/34mm.Penetrate 4 ¢ 12/10mm microtubules or 6 ¢ 10/8mm microtubules.Also can be according to the needs of transmission engineering, laying different specification size in empty duct is the microtubule of mixed type, adds 4 ¢ 10/8mm microtubules as 2 ¢ 12/10mm microtubules.
In the construction method of the present invention, different road surfaces to the sub-pipe of high-density polyethylene plastics require as follows:
1, the pipe standard that is applicable to cement concrete pavement is: specification is ¢ 40/34mm, never degenerates in-30-60 ℃ a temperature range, indeformable.Bearing capacity is greater than 3.5KN.
2, the pipe standard that is applicable to bituminous pavement is: never degenerate in-50-80 ℃ a temperature range, indeformable.Bearing capacity:
(1) the Class I highway bearing capacity is greater than 5.0KN, and son pipe specification is ¢ 44/34mm.
(2) the Class II highway bearing capacity is greater than 3.5KN, and son pipe specification is ¢ 40/34mm.
(3) the Class III highway bearing capacity is greater than 3.5KN, and son pipe specification is ¢ 40/34mm.
(4) the Class IV highway bearing capacity is greater than 1.8KN, and son pipe specification is ¢ 40/34mm.
Conduit saddle used in the inventive method is made of foamed material, is used for placing optical cable pipe.Shroud is made of elastomeric material, to release the pressure protection optical cable pipe.Cover plate is made of glass-reinforced plastic material, separates highway pavement and microchannel, the protection microchannel.The microtube joint box is cylinder iron made, and is used for placing microtube joint.Microtubule difference box is cylinder iron made, and is used for the microtubule difference and is convenient to little cable leading in cable cross-connecting box or trunk line with road groove microchannel.
Used instant coagulant and mending agent in the inventive method is composited by aluminium sulfate, aluminate, silicate and efficient surfactant, for Hw series instant coagulant and mending agent, has commercially available.Instant coagulant and mending agent requires to pave evenly, guarantees groove periphery material abundance, but does not disperse the road surface to the groove edge.
Claims (2)
1, a kind of construction method of utilizing downtown roads to lay the road slot minitype communication pipe is characterized in that this method may further comprise the steps:
(1) according to setting the planning or the design route picture ditch line of rabbet joint,, digs out groove, and make channel bottom smooth along the ditch line of rabbet joint cutting road surface of finishing;
(2) bury at an end of groove and put four-way or threeway microtubule difference box, the other end of groove buries near manhole or cross-connecting box place puts the microtube joint box;
(3) spread fine sand at described channel bottom, thickness is 5~15 millimeters, and the conduit saddle that tiles on fine sand is placed on little cable pipe cloth on the conduit saddle in the groove, and son pipe two ends are stretched into respectively in microtube joint box and the microtubule difference box;
(4) put shroud above the sub-pipe in groove, shroud and following slit are filled up with fine sand, at last cover plate is covered on shroud;
(5) remove loose material, dust or mud in the groove, in groove, pour instant coagulant and mending agent into, smooth until the groove periphery.
2, the method for claim 1, the width w that it is characterized in that groove is 40~60 millimeters, the degree of depth h of groove is 200~300 millimeters.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101164963A CN101329433B (en) | 2008-07-11 | 2008-07-11 | Construction method for paving road slot minitype communication pipe by urban area road |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008101164963A CN101329433B (en) | 2008-07-11 | 2008-07-11 | Construction method for paving road slot minitype communication pipe by urban area road |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101329433A true CN101329433A (en) | 2008-12-24 |
CN101329433B CN101329433B (en) | 2010-06-09 |
Family
ID=40205320
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008101164963A Active CN101329433B (en) | 2008-07-11 | 2008-07-11 | Construction method for paving road slot minitype communication pipe by urban area road |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101329433B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103293623A (en) * | 2013-05-11 | 2013-09-11 | 中煤科工集团武汉设计研究院 | Communication system and laying method for optical cable lines for long-distance pipeline coal conveyance |
CN104360450A (en) * | 2014-09-23 | 2015-02-18 | 新疆远建通信技术有限公司 | Micro-trenching method for communication transmission |
CN106968290A (en) * | 2017-04-07 | 2017-07-21 | 安徽建筑大学 | A kind of method of supplying water of Huizhou City Traditional feature Building group based on remote sensing technology |
-
2008
- 2008-07-11 CN CN2008101164963A patent/CN101329433B/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103293623A (en) * | 2013-05-11 | 2013-09-11 | 中煤科工集团武汉设计研究院 | Communication system and laying method for optical cable lines for long-distance pipeline coal conveyance |
CN104360450A (en) * | 2014-09-23 | 2015-02-18 | 新疆远建通信技术有限公司 | Micro-trenching method for communication transmission |
CN106968290A (en) * | 2017-04-07 | 2017-07-21 | 安徽建筑大学 | A kind of method of supplying water of Huizhou City Traditional feature Building group based on remote sensing technology |
Also Published As
Publication number | Publication date |
---|---|
CN101329433B (en) | 2010-06-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9353887B2 (en) | Multi-purpose micro-trench insert | |
US8480332B2 (en) | Laying and protecting cable into existing covering surfaces | |
KR101355399B1 (en) | Flexible jointing structure of road installation and constructing method thereof | |
CN106049530B (en) | City integrated piping lane and construction method | |
CN103874803A (en) | Method for building structures, particularly passages under operating railways or the like. | |
KR101026836B1 (en) | Structure for open cut excavation using light weight composite lining boards, and their construction methods | |
CN101329433B (en) | Construction method for paving road slot minitype communication pipe by urban area road | |
KR20120013182A (en) | Structure for Open Cut Excavation Using Light Weight Composite Lining Boards, and Their Construction Methods | |
CN113529752A (en) | Construction method for ecologically treating tunnel entrance and exit structure by using foam concrete | |
CN201943093U (en) | Settlement joint water-proof structure for basement with drainage channel | |
KR20180025391A (en) | Waterproof Firming Mat Composition and Method of Manufacturing Waterproof Firming Mat using the Composition thereof | |
CN101141054A (en) | Compaction grouting method for preventing land subsidence after non-digging horizontal drilling | |
CN103850162A (en) | Bridge type combined-structure road surface system and construction method thereof | |
KR102543052B1 (en) | Drainage Facilty Without Backfill | |
CN113201989B (en) | Road structure of mating formation and road of mating formation of permeating water | |
CN114855532A (en) | Reconstruction construction method for old road in rural area | |
CN104894942B (en) | The recyclable combination construction sidewalk of drainage type | |
CN107268368A (en) | Latch gap water-permeable brick | |
CN210151784U (en) | Integration template piping lane | |
KR100926539B1 (en) | Temperature and humidity control apparatus of stone block sidewalk by geothermy and rainwater circulation, using the same Eco-friendly stone block sidewalk constructing | |
CN113152512A (en) | Gravity type retaining wall and construction method | |
RU2183230C1 (en) | Method of culvert replacement | |
CN203768752U (en) | Bridge type pavement system in composite structure | |
CN103850163A (en) | Bridge type steel-plate road surface system and construction method thereof | |
CN210946357U (en) | Horizontal double escape canal structure of motor vehicle way |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |