CN101324069B CN2008100486512A CN200810048651A CN101324069B CN 101324069 B CN101324069 B CN 101324069B CN 2008100486512 A CN2008100486512 A CN 2008100486512A CN 200810048651 A CN200810048651 A CN 200810048651A CN 101324069 B CN101324069 B CN 101324069B
Authority
CN
China
Prior art keywords
grouting
concrete pouring
pouring
slurry
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008100486512A
Other languages
English (en)
Other versions
CN101324069A (zh
Inventor
陈洪全
潘志军
徐牧明
杨道宽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Original Assignee
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC filed Critical Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority to CN2008100486512A priority Critical patent/CN101324069B/zh
Publication of CN101324069A publication Critical patent/CN101324069A/zh
Application granted granted Critical
Publication of CN101324069B publication Critical patent/CN101324069B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

一种板下注浆新工法,步骤如下:浇筑顶板、钻机成孔、安装注浆管、开始单孔注浆。其优点是:板下注浆工法新颖处主要在于“堵”和“疏”,“堵”是指堵住了浆液流失出口通道,“疏”是指疏导了浆液沿混凝土板下流向;避免浆液流失和浪费,节省工程投资;顶板下注浆,易于控制浆液流向,使加固土体更加均匀,加固土体更加均匀、密实,质量较高,注浆效果更加显著;根据在武钢、宝钢、广西德保市等地的实践证明,可相对节省浆液流失20~50%左右。注浆结束28天后,通过标准贯入试验或轻便触探试验等方法可直接得到灌浆后原位土的强度,与灌浆前原位土的相比其力学性能得到较大提高。

Description

板下注浆新工法
技术领域
本发明涉及工程建筑技术领域,具体的说是一种板下注浆新工法。
背景技术
砂砾层中传统的注浆工艺中的套管护壁法,主要是先钻进成孔,下套管后,再下注浆花管进行分层注浆。注浆时容易沿管壁和土层内冒浆、灌浆质量难以保证、耗费管材较多并且施工工艺比较复杂,生产效率低。
发明内容
本发明的目的是研制一种减少注浆流失、节约原材料、增强原位土的强度、提高力学性能的板下注浆新工法。
本发明板下注浆新工法,步骤如下:
①浇筑顶板:在加固土体顶部(或地面)预先浇筑一层10~30cm厚的素混凝土,形成连续整体面板,面板面积可根据注浆区域大小设定,可比注浆区域略宽2~3m,一般不小于10m×10m。
②钻机成孔:用普通钻机成孔,孔深钻至预定深度后,取出钻具,撤离钻机。
③安装注浆管:将带有注浆孔的注浆花管埋入钻孔中,并与注浆泵连接好,压紧止浆塞。
④开始单孔注浆:开动注浆泵将调制好的浆液按设计压力、流速、流量向孔内自下而上一次灌注浆液。
⑤重复②~④步骤,完成板下注浆施工。
本发明板下注浆新工法的优点是:板下注浆工法新颖处主要在于“堵”和“疏”,“堵”是指堵住了浆液流失出口通道,“疏”是指疏导了浆液沿混凝土板下流向;避免浆液流失和浪费,节省工程投资;顶板下注浆,易于控制浆液流向,使加固土体更加均匀,加固土体更加均匀、密实,质量较高,注浆效果更加显著;根据在武钢、宝钢、广西德保市等地的实践证明,可相对节省浆液流失20~50%左右。注浆结束28天后,通过标准贯入试验或轻便触探试验等方法可直接得到灌浆后原位土的强度,与灌浆前原位土的相比其力学性能得到较大提高。
具体实施方式
一种板下注浆新工法,步骤如下:
①浇筑顶板:在加固土体顶部(或地面)预先浇筑一层10~30cm厚的素混凝土,形成连续整体面板,面板面积可根据注浆区域大小设定,可比注浆区域略宽2~3m,一般不小于10m×10m。
②钻机成孔:用普通钻机成孔,孔深钻至预定深度后,取出钻具,撤离钻机。
③安装注浆管:将带有注浆孔的注浆花管埋入钻孔中,并与注浆泵连接好,压紧止浆塞。
④开始单孔注浆:开动注浆泵将调制好的浆液按设计压力、流速、流量向孔内自下而上一次灌注浆液。
⑤重复②~④步骤,完成板下注浆施工。
该工法相对于常规注浆而言,板下注浆工艺对于一般的小型、民用建筑其效果不是很显著,在砂砾砾石层中浆液水平流向难以准确控制,有可能对周围环境造成危害。但对于防渗要求较高的坝基工程、隧道、矿井等地下工程中则具有得天独厚的优势,尤其是在当前世界提倡节约资源、注重环保的态势下,其应用前景不可估量。

Claims (1)

1.一种板下注浆新工法,其特征在于:步骤如下:
①浇筑顶板:在加固土体顶部或地面预先浇筑一层10~30cm厚的素混凝土,形成连续整体面板,面板面积可根据注浆区域大小设定,可比注浆区域略宽2~3m,不小于10m×10m;
②钻机成孔:用普通钻机成孔,孔深钻至预定深度后,取出钻具,撤离钻机;
③安装注浆管:将带有注浆孔的注浆花管埋入钻孔中,并与注浆泵连接好,压紧止浆塞;
④开始单孔注浆:开动注浆泵将调制好的浆液按设计压力、流速、流量向孔内自下而上一次灌注浆液;
⑤重复②~④步骤,完成板下注浆施工。
CN2008100486512A 2008-07-31 2008-07-31 板下注浆新工法 Active CN101324069B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100486512A CN101324069B (zh) 2008-07-31 2008-07-31 板下注浆新工法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100486512A CN101324069B (zh) 2008-07-31 2008-07-31 板下注浆新工法

Publications (2)

Publication Number Publication Date
CN101324069A CN101324069A (zh) 2008-12-17
CN101324069B true CN101324069B (zh) 2010-07-28

Family

ID=40187759

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100486512A Active CN101324069B (zh) 2008-07-31 2008-07-31 板下注浆新工法

Country Status (1)

Country Link
CN (1) CN101324069B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104533448B (zh) * 2014-11-06 2018-02-27 海南大学 一种岩石地层中盾构隧道端头止水加固的施工方法

Also Published As

Publication number Publication date
CN101324069A (zh) 2008-12-17

Similar Documents

Publication Publication Date Title
CN104846810B (zh) 自循环后注浆钻孔灌注桩施工方法
CN101748741B (zh) 一种混凝土支护结构的施工方法
CN110821503B (zh) 一种超深盾构区间风井先隧后主体施工方法
CN108517877B (zh) 杂填土超深基坑固结注浆结合双排钢管桩支护工法
CN110359467A (zh) 一种基坑工程高压旋喷桩加固的施工方法
CN104612134A (zh) 一种用于浇筑施工的钻孔灌注桩后注浆施工方法
CN101130991A (zh) 基于基床升浆的沉箱围堰及其施工方法
KR20110043017A (ko) 현장타설 콘크리트말뚝과 그라우팅 기둥을 이용한 주열식 토류벽 차수 시공방법
CN104631438B (zh) 长螺旋钻孔压灌混凝土抗拔桩施工方法
CN107725056A (zh) 一种穿越淤泥质地层隧道全环超前快速注浆施工方法
CN114233385B (zh) 一种斜井井筒突泥涌水的治理方法
CN102877470B (zh) 组合土钉支护施工方法
CN105464074A (zh) 一种人工挖孔桩高聚物注浆防护结构及其施工方法
CN111501781A (zh) 一种杂填土超深基坑固结注浆结合双排钢管桩支护方法及结构
CN106065628B (zh) 基于永临结合理念的大直径自来水管安全防护施工方法
CN105569071A (zh) 一种水泥基材料水下注浆或压浆块石基础施工方法
CN110241837A (zh) 一种高承压水地质条件下防止地下室底板开裂的施工方法
CN110685272A (zh) 一种利用斜孔布袋桩治理软基沉降超限的方法
CN112031801B (zh) 一种地铁隧道下穿既有运营线路的沉降控制方法
CN105970955A (zh) 自钻式钉管组合双液注浆土钉施工工艺
CN112227382A (zh) 兼具止水功能的双排桩结构及其施工方法
CN108571330A (zh) 一种处理地铁底板后浇带渗漏水的方法
CN101324069B (zh) 板下注浆新工法
CN106337418A (zh) 一种狭小区域深基坑的支护结构及支护方法
CN103015430A (zh) 长螺旋压灌水泥土型钢桩基坑止水支护方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA METALLURGICAL GROUP WUHAN SURVEY RESEARCH IN

Free format text: FORMER OWNER: CHINA METALLURGICAL GROUP WUHAN SURVEY GEOTECHNICAL FOUNDATION ENGINEERING CO., LTD.

Effective date: 20100419

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20100419

Address after: 430080 Wuhan, Heilongjiang Province, Qingshan District, metallurgical Road, No. 177, No.

Applicant after: Wuhan Surveying-Geotechnical Research Institute of China Metallurgical Science and Industry Group Co

Address before: 430080 Wuhan, Heilongjiang Province, Qingshan District, metallurgical Road, No. 177, No.

Applicant before: China Metallurgy Group Wukan Ground Foundational Engineering Company

C14 Grant of patent or utility model
GR01 Patent grant