CN101182712A - Method for controlling influence of engineering piling to surrounding environment - Google Patents

Method for controlling influence of engineering piling to surrounding environment Download PDF

Info

Publication number
CN101182712A
CN101182712A CNA2006101183039A CN200610118303A CN101182712A CN 101182712 A CN101182712 A CN 101182712A CN A2006101183039 A CNA2006101183039 A CN A2006101183039A CN 200610118303 A CN200610118303 A CN 200610118303A CN 101182712 A CN101182712 A CN 101182712A
Authority
CN
China
Prior art keywords
piling
control
energy
noise
surrounding environment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2006101183039A
Other languages
Chinese (zh)
Inventor
郑荣平
朱九仪
张永宝
张志玉
倪军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Hand In Third Board Second Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
Original Assignee
CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd filed Critical CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority to CNA2006101183039A priority Critical patent/CN101182712A/en
Publication of CN101182712A publication Critical patent/CN101182712A/en
Pending legal-status Critical Current

Links

Abstract

A method to control the influences of piling to the surrounding environment comprises the noise control, the vibration control, and the displacement control. The method is characterized in that a hydraulic pile hammer is used and a muffler is arranged on the surface of the hammer for the noise control; the piling energy is controlled, the smaller pile hammer energy is set for piling in the shallow stratum and the pile hammer energy is increased as the depth of piling is increased for the vibration control; an underground continuous wall is arranged and the daily piling quantity is controlled for the displacement control. The invention can effectively reduce the influences to the surrounding environment during the construction, and effectively reduce the noise pollution, the vibration pollution and the soil displacement.

Description

A kind of engineering piling is to the control method of surrounding environment influence
Technical field
The present invention relates to technical field of buildings, concrete is the control method of a kind of engineering piling to surrounding environment influence.
Background technology
The city piling construction, the construction infection scope is big, to around the influence of environment mainly comprise noise pollution, vibration pollution, land movement.Noise pollution influences the townsfolk and has a rest; For near the shielded building the engineering, vibration isolation is strict, can not produce vibration pollution; Near the engineering building is subjected to effect of project can produce displacement.
Given this, control piling process, with reduce engineering to the influence of surrounding environment show very necessary.
Summary of the invention
Technical problem to be solved by this invention is to provide the control method of a kind of engineering piling to surrounding environment influence, to reduce the influence of engineering piling to surrounding environment.
Technical scheme to be solved by this invention can be achieved through the following technical solutions:
A kind of engineering piling is to the control method of surrounding environment influence, comprises that noise control, vibration isolation, displacement control three parts, it is characterized in that, adopts hydraulic pile hammer in the noise control, and in the appearance of hydraulic hammer noise damper is installed; Control driving energy in the vibration isolation, shallow-layer piling is provided with less pile monkey energy, increases with driving depth, increases the pile monkey energy; Underground slider is set and controls the quantity of driving piles every day in the displacement control.
The present invention can effectively reduce in the work progress the influence of surrounding environment, has reduced noise pollution, vibration pollution, land movement effectively.
The specific embodiment
Describe the present invention in detail below in conjunction with the specific embodiment:
1 noise control
The noise of hydraulic impact hammer is less relatively, and this engineering is selected SC-150 type hydraulic pile hammer for use.
SC-150 hydraulic hammer hypomere points of articulation appearance is installed noise damper, and the sealing noise source reduces noise pollution from the source.
The piling time is controlled at 7:00 in morning ~ evening 21:00, sooner or later period and period in the late into the night only pile extension do not drive piles.
In the work progress, use noise decibel monitor that the noise that piling produces is carried out tracking and monitoring; Simultaneously, environmental noise is monitored.The reason that the analysis-by-synthesis noise produces is fed back in construction guiding construction.
2 vibration isolations
The control driving energy.During shallow-layer piling, the pile monkey energy settings is less, and the vibration surface wave energy of generation is also little; Stake is buried dark, and the pile monkey energy settings is bigger, and the energy dissipation face is also big, and is less relatively along the entity wave energy of a direction.So along with the increase of driving depth, for the injection and the bearing capacity needs of stake, hammering energy increases gradually, the diffusingsurface increase of energy is faster, helps reducing the vibration effect to the same building thing.
The degree of depth of open caisson has been cut off the surface wave that piling causes, makes the piling vibration energy account for 2/3rds surface wave and is blocked.
The degree of depth of ground-connecting-wall has been cut off the surface wave that piling causes, makes the piling vibration energy account for 2/3rds surface wave and is further stopped.
Deepen with the high-pressure rotary-spray body along the Suzhou River side at ground-connecting-wall, the entity ripple that the vibration of cut-out stake point produces makes compressional wave and shearing wave partly be reflected, partly be absorbed.
Project organization is optimized: pile foundation changes Φ 1000mm bored pile into.Obviously, Bored Pile Construction can not produce vibration to the soil body.
3 displacements control
Before south gate pier and the northern gate pier pile foundation construction, do diaphragm wall in two sides respectively, diaphragm wall is double-deck lattice structure, wall thickness 1000mm.Ground-connecting-wall is set plays the effect that face of land vibration wave transmits that cuts off.
Control the piling quantity of every day, one day pile sinking of southern gate pier Construction of Engineering Pile is controlled within 2, makes the soil body have the long time to discharge underground super interstitial hydraulic pressure, reduces the land movement amount.During the gate pier pile foundation construction, the stake distance of positions is suitably relaxed pile sinking quantity every day more than the 50m of two sides.
In the work progress, sedimentation, the horizontal movement of engineering structure and surrounding building are monitored; Lateral displacement is monitored to soil body deep layer; Underground water level, pore water pressure are monitored; Monitor in inclination and surrounding building crack to surrounding building.Analysis-by-synthesis produces the reason of sedimentation and displacement, feeds back in construction guiding construction.
According to the construction monitoring reflection, piling causes surrounding environment influence degree (maximum value) to be:
Noise: 96.3dB (pier 65m in the distance)
Vibration: 2.843 (apart from 13.8m)
Displacement: 22mm (ground-connecting-wall QW15)
All satisfy the environment control criterion of determining when going into operation.
Although invention has been described for the foregoing description, for the technician of the industry, still can do multiple variation to present embodiment, therefore, every employing similar variation of the present invention all should be listed protection scope of the present invention in.

Claims (1)

1. an engineering piling is to the control method of surrounding environment influence, comprises that noise control, vibration isolation, displacement control three parts, it is characterized in that, adopts hydraulic pile hammer in the noise control, and in the appearance of hydraulic hammer noise damper is installed; Control driving energy in the vibration isolation, shallow-layer piling is provided with less pile monkey energy, increases with driving depth, increases the pile monkey energy; Underground slider is set and controls the quantity of driving piles every day in the displacement control.
CNA2006101183039A 2006-11-13 2006-11-13 Method for controlling influence of engineering piling to surrounding environment Pending CN101182712A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2006101183039A CN101182712A (en) 2006-11-13 2006-11-13 Method for controlling influence of engineering piling to surrounding environment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2006101183039A CN101182712A (en) 2006-11-13 2006-11-13 Method for controlling influence of engineering piling to surrounding environment

Publications (1)

Publication Number Publication Date
CN101182712A true CN101182712A (en) 2008-05-21

Family

ID=39448128

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2006101183039A Pending CN101182712A (en) 2006-11-13 2006-11-13 Method for controlling influence of engineering piling to surrounding environment

Country Status (1)

Country Link
CN (1) CN101182712A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102011401A (en) * 2010-09-09 2011-04-13 平煤建工集团有限公司 High-intensity prestressed concrete tubular pile lead hole hammering construction method for soft soil layer
CN103266611A (en) * 2012-10-17 2013-08-28 广东省长大公路工程有限公司 Efficient damping device for underwater piling
CN103774670A (en) * 2014-01-27 2014-05-07 广东明阳风电产业集团有限公司 Vacuum metal ball noise reduction device for constructing offshore draught fan foundation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102011401A (en) * 2010-09-09 2011-04-13 平煤建工集团有限公司 High-intensity prestressed concrete tubular pile lead hole hammering construction method for soft soil layer
CN103266611A (en) * 2012-10-17 2013-08-28 广东省长大公路工程有限公司 Efficient damping device for underwater piling
CN103774670A (en) * 2014-01-27 2014-05-07 广东明阳风电产业集团有限公司 Vacuum metal ball noise reduction device for constructing offshore draught fan foundation

Similar Documents

Publication Publication Date Title
CN101487274A (en) Slip-casting lifting method for city tunnel passing through existing buildings
CN104805854A (en) Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment
CN111945773A (en) Pile box barrel composite foundation for offshore wind power and construction method thereof
CN101182712A (en) Method for controlling influence of engineering piling to surrounding environment
CN101260664A (en) Soft soil foundation large scale steel float lock head construction method
CN112726684B (en) Method for inhibiting frost heaving deformation of fiber-modified stratum
WO2018166522A1 (en) Construction device for revetment and construction method therefor
CN103195370B (en) A kind of combination type drill bit
CN101709582B (en) Protection method for reducing soil extrusion in construction of prefabricated piles
CN110747861A (en) High-water-level deep foundation pit excavation construction method
CN111155543A (en) Open caisson isolation bottom die wet type bottom sealing structure and construction method thereof
CN103866779B (en) A kind of construction method of sealing space enclosing structure of soft foundation building foundation pit
CN109610522A (en) The light platform structure of frost damage prevention
CN104895130A (en) Underground continuous wall construction method applicable to inclined hard rock section
CN103758133B (en) A kind of method of deep soft soil foundation pit reinforcement
CN209585134U (en) The light platform structure of frost damage prevention
CN203755326U (en) Water stopping building envelope of soft soil foundation building foundation pit
CN207005571U (en) One kind wears dike pipe protection structure
CN104912084B (en) Building dense district deep basal pit external sealing type static press piling construction method
CN216999822U (en) Foundation treatment structure of digestion tank on deep covering layer
CN205742152U (en) The high-pressure rotary jet grouting pile with decompression function reinforces water sealing structure
CN204551160U (en) The formula that the bonds prepressing water discharge consolidation system of blast-filled ground ribbon roadbed
CN201485841U (en) Steel pontoon lock head for soft soil foundation
CN214460730U (en) Dam foundation altered rock mass reinforcing structure
CN204626347U (en) A kind of be applicable to two-way low water head can the reinforced concrete gate of effective sealing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090320

Address after: Postcode of No. 132 Pu circuit, Shanghai, Pudong New Area: 200122

Applicant after: China hand in the Third Board Second Engineering Co., Ltd.

Co-applicant after: China Construction Third Engineering Division Co., Ltd.

Address before: Postcode of No. 132 Pu circuit, Shanghai, Pudong New Area: 200122

Applicant before: China Communications Third Navigational Bureau 2nd Engineering Co., Ltd

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20080521