CN101148985A - Adjusting method for oil field injection and extraction system in ultra-high water-containing period - Google Patents

Adjusting method for oil field injection and extraction system in ultra-high water-containing period Download PDF

Info

Publication number
CN101148985A
CN101148985A CNA2007101444955A CN200710144495A CN101148985A CN 101148985 A CN101148985 A CN 101148985A CN A2007101444955 A CNA2007101444955 A CN A2007101444955A CN 200710144495 A CN200710144495 A CN 200710144495A CN 101148985 A CN101148985 A CN 101148985A
Authority
CN
China
Prior art keywords
injection
well
extraction system
adjustment
oil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2007101444955A
Other languages
Chinese (zh)
Inventor
万新德
方庆
林立
曾雪梅
冷延明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daqing Oilfield Co Ltd
Original Assignee
Daqing Oilfield Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daqing Oilfield Co Ltd filed Critical Daqing Oilfield Co Ltd
Priority to CNA2007101444955A priority Critical patent/CN101148985A/en
Publication of CN101148985A publication Critical patent/CN101148985A/en
Pending legal-status Critical Current

Links

Images

Abstract

The present invention is method of regulating oil field water injecting and oil producing system in very high water containing stage, and aims at solving the problems of too great ratio between oil producing well number and water injecting well number, too high water injecting pressure, and too low stratum pressure and flow pressure in very high water containing stage. The present invention adopts water injecting and oil producing mode with transverse linear water injecting well net, five point area well net, longitudinal linear water injecting well net, and determinant type water injecting well net. The present invention can raise oil output greatly.

Description

The method of adjustment of oil field injection and extraction system in ultra-high water-containing period
Technical field
The present invention relates to a kind of method of adjustment of oil field injection and extraction system.
Background technology
Ultra-high water cut stage is meant that the oil field comprehensive water cut reaches the period more than 90%.Large-scale terrigenous deposit multiple zone heterogeneous body sandstone oil field, the main feature of its oil reservoir are that the number of plies is many, complex shape, serious heterogeneity.After large-scale terrigenous deposit multiple zone heterogeneous body sandstone oil field enters the ultra-high water cut stage mining phase, the injection and extraction system adjustment mainly is to refer to that at the block series of strata (anti-9 method areal well patterns are a kind of flooding patterns to anti-9 method areal well patterns, with 1 mouthful of water injection well is that the center is provided with 8 mouthfuls of oil wells on every side, each flooding unit has 9 mouthfuls of wells, it is 3: 1 that the oil-water well of each flooding unit is counted ratio, promptly 1 mouthful of water injection well provide water filling need for 3 mouthfuls of producing wells) the oil-water well number is than for bigger than normal, water injection capacity does not satisfy the needs of production fluid amount, water injection pressure is higher, strata pressure and flowing pressure are on the low side, and the oil field cover decreases relatively problems such as part wellblock flooding pattern imperfection.Because oil field development is a process that the oil field is constantly adjusted, the Development characteristics difference of different development phases, adjustment practice difference, through once encrypting adjusting stage and superencipher after the adjusting stage, the injection and extraction system adjustment is primarily aimed at the series of strata well pattern of separate, the even perforation independent and perfect of series of strata well pattern, relies on the producing well metaideophone separately, changes the liquid flow path direction, increases the water filling well point, improves injection and extraction system.But ultra-high water cut stage series of strata well pattern is perfect mutually, and well pattern is adjusted one by one and formed local notes in the evolution process to adopt exploitation situation such as imperfection comparatively complicated, has many comparatively outstanding contradiction.It is traditional that only can't solve the ultra-high water cut stage oil field injection and extraction by the method for utilizing old well metaideophone concerns problem.
Summary of the invention
The objective of the invention is for solving existing ultra-high water cut stage mining phase, the injection and extraction system adjustment mainly is to refer to that at the block series of strata anti-9 method areal well pattern oil-water well numbers ratio is for bigger than normal, water injection capacity does not satisfy the needs of production fluid amount, water injection pressure is higher, strata pressure and flowing pressure are on the low side, and oil field cover decreases relatively, and flooding pattern incomplete problem in part wellblock provides a kind of method of adjustment of oil field injection and extraction system in ultra-high water-containing period.The method of adjustment of oil field injection and extraction system in ultra-high water-containing period of the present invention realizes according to the following steps: one, at first injection and extraction system is optimized adjustment, the end hole of the row of adopting forms the injection-production method of horizontal linear injection pattern between annotating between the employing metaideophone, perhaps the metaideophone corner well forms the injection-production method of five-spot areal well pattern, perhaps the end hole of metaideophone oil recovery well array forms the injection-production method of vertical linear injection pattern, perhaps interval metaideophone corner well forms the injection-production method of block water filling unit, perhaps the end hole of metaideophone oil recovery well array forms vertical two row's water injection well folders, three row's producing wells at interval, the injection-production method of the ranks shape injection pattern that middle ware is adopted between annotating; Two, adjust well spacing, it is between 160~190m that well spacing is adjusted to average distance.The situation of present oil field injection and extraction system in ultra-high water-containing period that the present invention has passed through comprehensive systematically assay, complexity in conjunction with the ultra-high water cut stage injection-production relation, at dissimilar oil reservoirs, different geology characteristics, different exploitation situations, different existing well pattern conditions, the injection and extraction system adjustment is reduced five kinds of patterns, taking into full account " five combinations " preferred injection and extraction system method of adjustment simultaneously combines with original well pattern, combine with three encryption adjustment, combine with the complementary off set drilling of well pattern, with improve the single sand body injection-production relation and combine, combine with the improvement of poor efficiency well, optimize supporting technology after the injection and extraction system adjustment, implement the back water drive and respectively overlap the exploitation effect of series of strata and all obtain in various degree improvement, efficiently solve the ultra-high water cut stage multilayer and be the exploitation contradiction under many well patterns condition.Adjust 50.6 tons of back individual well day production fluids, 3.9 tons of day produce oils, comprehensive water cut 92.28%, a day produce oil amplitude improves 34.48%, 1.29 percentage points of water cut decreases.Outstanding effect shows the burden of having alleviated the fractional water flooding well, average water injection pressure drops to 12.11Mpa by 12.42Mpa, 0.31Mpa has descended, the well number of bursting split pressure water filling drops to 40.5% by 69.8%, production capacity is greatly improved, and contrasts 235 mouthfuls of no measure producing well accumulative totals and increases oil 3.4 * 10 4T, 0.42 percentage point of moisture decline, whole district's lapse rate is slowed down 1.27 percentage points.The present invention will make water drive injection and extraction system adjustment technology become better and approaching perfection day by day more, for the injection and extraction system adjustment of large-scale terrigenous deposit multiple zone heterogeneous body sandstone oil field ultra-high water cut stage provides powerful technical support and assurance.
Description of drawings
Fig. 1 is that the end hole of the row of adopting forms the schematic diagram of horizontal linear injection pattern between annotating between metaideophone, Fig. 2 is the schematic diagram that the metaideophone corner well forms the five-spot areal well pattern, Fig. 3 is the schematic diagram that the end hole of metaideophone oil recovery well array forms the vertical linear injection pattern, Fig. 4 is the schematic diagram that interval metaideophone corner well forms block water filling unit, and Fig. 5 is that the end hole of metaideophone oil recovery well array at interval forms the ranks shape injection pattern schematic diagram of adopting between vertical two row's water injection wells folders, three row's producing wells, middle ware notes.The end hole of the row of adopting between annotating between the Reference numeral 1-among the figure, 2-corner well, the end hole of 3-oil recovery well array.
The specific embodiment
The specific embodiment one: (referring to Fig. 1~Fig. 5) method of adjustment of present embodiment oil field injection and extraction system in ultra-high water-containing period realizes according to the following steps: one, at first injection and extraction system is optimized adjustment, the end hole of the row of adopting forms the injection-production method of horizontal linear injection pattern between annotating between the employing metaideophone, perhaps the metaideophone corner well forms the injection-production method of five-spot areal well pattern, perhaps the end hole of metaideophone oil recovery well array forms the injection-production method of vertical linear injection pattern, perhaps interval metaideophone corner well forms the injection-production method of block water filling unit, perhaps the end hole of metaideophone oil recovery well array forms vertical two row's water injection well folders, three row's producing wells at interval, the injection-production method of the ranks shape injection pattern that middle ware is adopted between annotating; Two, adjust well spacing, it is between 160~190m that well spacing (between any two adjacent wells) is adjusted to average distance.
The specific embodiment two: the end hole of the row of adopting formed the injection-production method of horizontal linear injection pattern between (referring to Fig. 1) present embodiment adopted and annotates between metaideophone, and it is 175m that well spacing (between any two adjacent water injection wells and producing well) is adjusted to average distance.Present embodiment water drive control degree is up to 94.4%, and wherein multidirectional connection ratio is 55.8%, and increase rate is 23.4%, and the ultimate recovery value reaches as high as 44.7%, and good with the joining relation of former well pattern.
The specific embodiment three: (referring to Fig. 1~Fig. 5) present embodiment combines with three encryption adjustment, by adjusting well spacing (former well spacing is 250m), to improve thin poor reservoir and to show outer field development degree.1.0 of direction numbers are imitated in three average individual well increases of infill well, encrypt adjustment series of strata benefit at three times and open sandstone thickness 5.9m, effective thickness 1.8m.Adjust and afterwards encrypt to adjust the series of strata thin poor reservoirs three times and show outer field development degree and obviously improve, bring up to present 70.9%, 50.4% respectively by 59.6%, 42.4% before adjusting.
The specific embodiment four: (referring to Fig. 1~Fig. 5) present embodiment combines with the complementary off set drilling of well pattern, improves injection and extraction system.It also is once to encrypt the notes extraction well point of adjusting series of strata that east, the Bei San district basic well pattern grape flower series of strata of Daqing oil field are annotated producing well.After grape flower series of strata oil-water well in Portugal's one group of oil reservoir polymer displacement oil well net all utilizes, cause northern 3-5 row to lack 10 mouthfuls of extraction well points, according to the well pattern present situation at the preferred different method of adjustment of different well arrays, determine to lack 7 mouthfuls of extraction well points northern 3-5, northern 3-6 row, 5 mouthfuls are injected the well point, north 2-1 row lacks 10 mouthfuls of extraction well points, and these wellblock injection-production relations need further perfect.According to the well pattern present situation at the preferred different method of adjustment of different well arrays, determine to mend 21 mouthfuls of the new water injection wells of brill northern 3-5, northern 3-6 row, north 2-1 row makes full use of with superencipher and adjusts series of strata well location complementary relationship, and 8 mouthfuls of superencipher water injection wells are implemented perforations adding in order to improve infilled well pattern one time.58 mouthfuls of producing wells that are communicated with around the new well stake back, the average individual well oily 2.3t that increases day by day, moisture decline 2.25%, strata pressure improves 0.22MPa, and average individual well accumulative total increases oily 298t.The superencipher water injection well is implemented to carry out dispensing behind the perforations adding in good time, and water filling interval number is increased to 5.9 by original 3.8, is communicated with 41 mouthfuls of producing wells around adjusting the back, the average individual well oily 1.1t that increases day by day, and moisture decline 0.67%, strata pressure improves 0.14Mpa.
The specific embodiment five: (referring to Fig. 1~Fig. 5) present embodiment combines with improving the single sand body injection-production relation, implement the corresponding perforations adding of oil-water well, improve the single sand body notes and adopt corresponding rate.To the corresponding perforations adding of other oil-water well in converted production well, relevant producing well, the series of strata.Improve the principle of injection-production relation according to single sand body, the converted production well perforations adding is decided notes to adopt, relevant producing well perforations adding is adopted being doomed, other oil-water well is then taken all factors into consideration according to injection-production relation situation of change after the injection and extraction system adjustment and is carried out perforations adding in the series of strata, emphasis is to be based on the interior single sand body of these series of strata to improve injection-production relation, takes all factors into consideration the joining relation of converted production well and each cover series of strata well pattern, increases multidirectional connection thickness proportion, improve water drive control degree, fully excavate the remaining oil potentiality.The whole district adjusts 25 mouthfuls of wells of the corresponding perforations adding of back oil-water well, and average individual well is mended and opened 4.8 layers, and mend and open sandstone thickness 8.0m, effective thickness 4m, the average individual well liquid 27.2t that increases day by day behind the perforations adding, the oily 3.8t that increases day by day, 3.9 percentage points of moisture declines, the average effective phase is more than 6 months.
The specific embodiment six: (, adjust flexibly and improve regional whole development effect referring to Fig. 1~Fig. 5) present embodiment is administered with the poor efficiency well and combined.The mode of metaideophone end hole is adopted in the northern three-east injection and extraction system adjustment of Daqing oil field on the whole, but the concrete characteristics of calmodulin binding domain CaM are adjusted flexibly when adjusting, and improve the whole development effect.As Bei3-4-064Jing be northern three-east once encrypt adjust annotate between series of strata between a bite producing well of the row of adopting, by once encrypting the series of strata injection and extraction system adjustment mode of adjusting, this well needs metaideophone, but concern from well location, this well location near the 91# tomography, the unidirectional effect, at present full well is penetrated out sandstone 20.6m, effective 9.5m, formation capacity 4.735 μ m 2.m, the back day production fluid 25t that goes into operation, day produce oil 2t, moisture 90.3%, baric flow 1.17MPa does not go up the liquid closing well in February, 2002, belong to a bite poor efficiency well (poor efficiency well produce oil on duty for the day is less than the well of 1t), cumulative oil production has only 5446t before this well closing well, than secondary well average level low 80.2%.For improving regional whole development effect, consider metaideophone corner well north 3-fourth 5-64 well, at present the high moisture closing well of this well.The present day production fluid 18t of Bei3-4-064Jing behind the metaideophone, day produce oil 4t, moisture 77.8%, stream is pressed 2.94MPa, development effectiveness be improved significantly.
To sum up show, the mode of ultra-high water cut stage injection and extraction system adjustment should not be the mode of single dependence OW metaideophone again, must change into based on old well metaideophone, with the mode that multiple measures such as perforations adding, benefit well and the complementary utilization of well pattern combine, integral body is improved injection-production relation.
The water drive exploitation is adjusted, determine that reasonable injection-production ratio is the important assurance that keeps oil reservoir strata pressure, the moisture rising of control and slow down production decline on the one hand, on the other hand, injection-production ratio is adjusted in the reasonable range, can reduce the water injection rate in the higher area of part injection-production ratio, further improve the water drive development benefit.Determine reasonable injection-production ratio according to stage injection-production ratio and pressure reduction relation curve after the three-east injection and extraction system adjustment of north.Strata pressure is a rational state to return near the original formation pressure after the injection and extraction system adjustment, but recover unsuitable too fast, adjusting back pressure rise amplitude is advisable with annual 0.15~0.25MPa, according to the stage pressure reduction of a superencipher well and the relation of injection-production ratio, adjusted injection-production ratio is once encrypted the adjustment series of strata and be should be 1.6~1.7, and the superencipher well is encrypted the adjustment series of strata and be should be 2.1~2.2.
The ultra-high water cut stage oil reservoir carries out the injection and extraction system adjustment and should by doing the reasonable segmentation adjustment of separate water injection well well, improve the adjustment effect of injection and extraction system in the vertical in conjunction with single layer of sand water logging, producing status owing to water logging, producing status complexity.15 mouthfuls of water injection wells are adjusted in whole district's segmentation, the interval number is increased to 103 by 93, and water injection rate of interval drops to 2690 cubic metres by 3685 cubic metres, and wherein major oil reservoir precipitation is 445 cubic metres, 1440 cubic metres of non-major oil reservoir water lifts, be communicated with 29 mouthfuls of wells on every side, day production fluid is increased to present 2079 tons by 1608 tons before adjusting, and a day produce oil is increased to 143 tons by 83 tons, water content drops to 93.18% by 94.84%, increase day by day 16.9 tons of liquid of average individual well, 2.1 tons of the oil of increasing day by day, water content descends 1.66%.
Will make full use of the perfect opportune time of injection-production relation after the injection and extraction system adjustment, by the reasonable transfer of water injection rate between the old and new's water injection well, between high moisture good oil reservoir and low moisture poor oil reservoir, the change of promotion liquid flow path direction further improves flood effectiveness in the plane.According to the converted production well and the oil well sound attitude data on every side of newly drowning oneself in a well, water injection rate between the old and new's well is rationally mated.Converted production well and stepout well day injection allocation 6100m 3/ d, water injection intensity 8.5m 3/ d.m, the corresponding interval water injection intensity of wherein high moisture, good oil reservoir is 7.4m 3/ d.m, low moisture, the corresponding interval water injection intensity of thin poor reservoir is 9.5m 3/ d.m, the old water injection well waterflood project in metaideophone wellblock is reduced in right amount simultaneously, and a day injection allocation is adjusted downward to 5478m 3/ d, water injection intensity is by 9.3m 3/ d.m drops to 7.9m 3/ d.m.
The oil well extract mainly is by amplifying producing pressure differential and the difference oil reservoir being taked in good time modification measures, answer trace analysis after the injection and extraction system adjustment, in time catch the opportune time of being imitated, promote the whole district evenly to take effect with a definite target in view, the whole district implements to transfer ginseng after the adjustment of Daqing oil field Bei San district east system, change pump, pressure break, production fluid rises to 58.4 tons by 45 tons average individual well day after the acidifying measure, day produce oil rises to 4.1 tons by 2.9 tons, moisturely drop to 93.0% by 93.7%, stream is pressed and is dropped to 3.85Mpa by 5.46Mpa, increase day by day 13.4 tons of liquid of average individual well, increase day by day oily 1.2 tons, moisture decline 0.7%.

Claims (3)

1. the method for adjustment of an oil field injection and extraction system in ultra-high water-containing period, the method of adjustment that it is characterized in that oil field injection and extraction system in ultra-high water-containing period realizes according to the following steps: one, at first injection and extraction system is optimized adjustment, the end hole of the row of adopting forms the injection-production method of horizontal linear injection pattern between annotating between the employing metaideophone, perhaps the metaideophone corner well forms the injection-production method of five-spot areal well pattern, perhaps the end hole of metaideophone oil recovery well array forms the injection-production method of vertical linear injection pattern, perhaps interval metaideophone corner well forms the injection-production method of block water filling unit, perhaps the end hole of metaideophone oil recovery well array forms vertical two row's water injection well folders, three row's producing wells at interval, the injection-production method of the ranks shape injection pattern that middle ware is adopted between annotating; Two, adjust well spacing, it is between 160~190m that well spacing is adjusted to average distance.
2. the method for adjustment of oil field injection and extraction system in ultra-high water-containing period according to claim 1 is characterized in that it is 175m that well spacing is adjusted to average distance.
3. the method for adjustment of oil field injection and extraction system in ultra-high water-containing period according to claim 1 is characterized in that encrypting adjustment series of strata benefit at three times opens sandstone thickness 5.9m, effective thickness 1.8m.
CNA2007101444955A 2007-10-26 2007-10-26 Adjusting method for oil field injection and extraction system in ultra-high water-containing period Pending CN101148985A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2007101444955A CN101148985A (en) 2007-10-26 2007-10-26 Adjusting method for oil field injection and extraction system in ultra-high water-containing period

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2007101444955A CN101148985A (en) 2007-10-26 2007-10-26 Adjusting method for oil field injection and extraction system in ultra-high water-containing period

Publications (1)

Publication Number Publication Date
CN101148985A true CN101148985A (en) 2008-03-26

Family

ID=39249668

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2007101444955A Pending CN101148985A (en) 2007-10-26 2007-10-26 Adjusting method for oil field injection and extraction system in ultra-high water-containing period

Country Status (1)

Country Link
CN (1) CN101148985A (en)

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071922A (en) * 2011-01-15 2011-05-25 胜利油田鲁明油气勘探开发有限公司 Low permeable oil deposit virtual horizontal well development method
CN102628353A (en) * 2012-03-21 2012-08-08 中国海洋石油总公司 Well pattern adjustment and well pattern encryption method applied to on-sea hypotonic oil deposit exploitation
CN102839959A (en) * 2012-09-04 2012-12-26 中国石油天然气股份有限公司 Longitudinally superposed developing two-strata oil reservoir well pattern, and arrangement method of two-strata oil reservoir well pattern
CN103046910A (en) * 2013-01-10 2013-04-17 中国石油天然气股份有限公司 Oil deposit water-driving exploiting method of ultra-high water-containing period
CN103422849A (en) * 2013-07-18 2013-12-04 中国石油天然气股份有限公司 Well pattern rebuilding method and device for water-injection development of old oil field
CN103924966A (en) * 2013-01-10 2014-07-16 中国石油化工股份有限公司 Bed set well pattern reconstruction method based on reservoir physical property time varying model
CN104832142A (en) * 2014-02-07 2015-08-12 中国石油化工股份有限公司 Ultra-high water cut stage oil reservoir periodic alternate injection variable flow line displacement method
CN105148819A (en) * 2015-07-20 2015-12-16 中国石油天然气股份有限公司 Ultrasonic oscillation method and device for preparing micron order bubble dispersing system
CN105283631A (en) * 2013-01-23 2016-01-27 于文英 Two important methods for enhancing steam injection effect
CN105625992A (en) * 2014-11-07 2016-06-01 中国石油化工股份有限公司 Reasonable liquid extracting method specific to roof ridge fault block oil reservoir
CN105822271A (en) * 2015-09-09 2016-08-03 中国石油化工股份有限公司 Adjustment method of variable flow line vector of thick-stratum oil deposit
CN106585223A (en) * 2016-12-19 2017-04-26 中国石油天然气股份有限公司 Drawing board used for drawing pattern water flooding development well patterns
CN106779131A (en) * 2015-11-24 2017-05-31 中国石油化工股份有限公司 Grease hole evaluates phase cumulative production Forecasting Methodology
CN107218024A (en) * 2017-05-02 2017-09-29 中国石油天然气股份有限公司 The method of adjustment of multilayer low permeability sandstone reservoir high water-cut stage rhombic inverted nini-spot well pattern
CN107657338A (en) * 2017-09-18 2018-02-02 中国石油化工股份有限公司 The horizontal lower change of production Forecasting Methodology of different liquid measures
CN108386171A (en) * 2018-02-22 2018-08-10 中海石油(中国)有限公司 Water injection intensity optimization method after deep water turbidite sandstone waterflooding reservoir oil well water breakthrough
CN109726946A (en) * 2019-03-11 2019-05-07 东北石油大学 A kind of oilfields in high water cut period residual oil quantitative division methods
CN110454124A (en) * 2019-08-23 2019-11-15 陈建国 A kind of oil production method
CN110485988A (en) * 2019-08-19 2019-11-22 中国石油天然气股份有限公司大港油田分公司 A kind of low permeability reservoir simulation grid refinement method and device
CN110552673A (en) * 2019-08-16 2019-12-10 中国石油天然气股份有限公司 Method for improving extraction degree of low-pressure tight oil reservoir
CN110630237A (en) * 2019-09-27 2019-12-31 大庆油田有限责任公司 Method chart for pre-fracturing well fracturing culture and post-fracturing protection and application method thereof
CN110671082A (en) * 2019-09-19 2020-01-10 大庆油田有限责任公司 Adjustment method for well group after injection of large-dose flooding fluid into water injection well of thin difference oil layer of sandstone reservoir
CN111058811A (en) * 2019-11-18 2020-04-24 中国石油天然气股份有限公司 Five-point-view alternate mining method and device for facing horizontal well pattern
CN111861071A (en) * 2019-04-30 2020-10-30 中国石油天然气股份有限公司 Method and system for determining cumulative oil production of oil well by using initial monthly production
CN112761603A (en) * 2021-03-03 2021-05-07 大庆油田有限责任公司 Novel method for adjusting water injection rate of ultrahigh water-cut period interval of multilayer heterogeneous sandstone reservoir
CN112983388A (en) * 2019-12-18 2021-06-18 中国石油天然气股份有限公司 Dynamic well pattern deployment method and dynamic well pattern

Cited By (42)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071922B (en) * 2011-01-15 2013-07-03 胜利油田鲁明油气勘探开发有限公司 Low permeable oil deposit virtual horizontal well development method
CN102071922A (en) * 2011-01-15 2011-05-25 胜利油田鲁明油气勘探开发有限公司 Low permeable oil deposit virtual horizontal well development method
CN102628353A (en) * 2012-03-21 2012-08-08 中国海洋石油总公司 Well pattern adjustment and well pattern encryption method applied to on-sea hypotonic oil deposit exploitation
CN102628353B (en) * 2012-03-21 2015-08-05 中国海洋石油总公司 A kind of Well pattern edjustment and well pattern thickening method being applied to the exploitation of marine LOW PERMEABILITY RESERVOIR
CN102839959A (en) * 2012-09-04 2012-12-26 中国石油天然气股份有限公司 Longitudinally superposed developing two-strata oil reservoir well pattern, and arrangement method of two-strata oil reservoir well pattern
CN102839959B (en) * 2012-09-04 2015-04-08 中国石油天然气股份有限公司 Arrangement method of longitudinally superposed developing two-strata oil reservoir well pattern
CN103046910B (en) * 2013-01-10 2015-11-25 中国石油天然气股份有限公司 Ultra-high water cut stage reservoir water drive development approach
CN103046910A (en) * 2013-01-10 2013-04-17 中国石油天然气股份有限公司 Oil deposit water-driving exploiting method of ultra-high water-containing period
CN103924966A (en) * 2013-01-10 2014-07-16 中国石油化工股份有限公司 Bed set well pattern reconstruction method based on reservoir physical property time varying model
CN103924966B (en) * 2013-01-10 2017-03-15 中国石油化工股份有限公司 Grouping of Sand Members And Well based on reservoir properties time-varying model construction method again
CN105283631A (en) * 2013-01-23 2016-01-27 于文英 Two important methods for enhancing steam injection effect
CN103422849B (en) * 2013-07-18 2015-10-14 中国石油天然气股份有限公司 Waterflooding extraction old filed well pattern reconstruction method and device
CN103422849A (en) * 2013-07-18 2013-12-04 中国石油天然气股份有限公司 Well pattern rebuilding method and device for water-injection development of old oil field
CN104832142A (en) * 2014-02-07 2015-08-12 中国石油化工股份有限公司 Ultra-high water cut stage oil reservoir periodic alternate injection variable flow line displacement method
CN104832142B (en) * 2014-02-07 2018-05-08 中国石油化工股份有限公司 Ultra-high water cut stage oil reservoir cycle alternate water injection unsteady flow line displacement method
CN105625992A (en) * 2014-11-07 2016-06-01 中国石油化工股份有限公司 Reasonable liquid extracting method specific to roof ridge fault block oil reservoir
CN105148819A (en) * 2015-07-20 2015-12-16 中国石油天然气股份有限公司 Ultrasonic oscillation method and device for preparing micron order bubble dispersing system
CN105822271A (en) * 2015-09-09 2016-08-03 中国石油化工股份有限公司 Adjustment method of variable flow line vector of thick-stratum oil deposit
CN106779131A (en) * 2015-11-24 2017-05-31 中国石油化工股份有限公司 Grease hole evaluates phase cumulative production Forecasting Methodology
CN106585223A (en) * 2016-12-19 2017-04-26 中国石油天然气股份有限公司 Drawing board used for drawing pattern water flooding development well patterns
CN106585223B (en) * 2016-12-19 2018-05-04 中国石油天然气股份有限公司 For drawing the drawing board of pattern water flooding well pattern
CN107218024B (en) * 2017-05-02 2019-06-11 中国石油天然气股份有限公司 The method of adjustment of multilayer low permeability sandstone reservoir high water-cut stage rhombic inverted nini-spot well pattern
CN107218024A (en) * 2017-05-02 2017-09-29 中国石油天然气股份有限公司 The method of adjustment of multilayer low permeability sandstone reservoir high water-cut stage rhombic inverted nini-spot well pattern
CN107657338A (en) * 2017-09-18 2018-02-02 中国石油化工股份有限公司 The horizontal lower change of production Forecasting Methodology of different liquid measures
CN108386171A (en) * 2018-02-22 2018-08-10 中海石油(中国)有限公司 Water injection intensity optimization method after deep water turbidite sandstone waterflooding reservoir oil well water breakthrough
CN108386171B (en) * 2018-02-22 2020-02-14 中海石油(中国)有限公司 Method for optimizing water injection strength of oil well after water breakthrough in deep water turbid sandstone water injection development
CN109726946B (en) * 2019-03-11 2023-05-26 东北石油大学 Quantitative division method for oil field residual oil in high water content period
CN109726946A (en) * 2019-03-11 2019-05-07 东北石油大学 A kind of oilfields in high water cut period residual oil quantitative division methods
CN111861071A (en) * 2019-04-30 2020-10-30 中国石油天然气股份有限公司 Method and system for determining cumulative oil production of oil well by using initial monthly production
CN111861071B (en) * 2019-04-30 2024-03-05 中国石油天然气股份有限公司 Method and system for determining cumulative oil production from an oil well using initial monthly production
CN110552673A (en) * 2019-08-16 2019-12-10 中国石油天然气股份有限公司 Method for improving extraction degree of low-pressure tight oil reservoir
CN110485988A (en) * 2019-08-19 2019-11-22 中国石油天然气股份有限公司大港油田分公司 A kind of low permeability reservoir simulation grid refinement method and device
CN110454124B (en) * 2019-08-23 2021-07-27 陈建国 Oil extraction method
CN110454124A (en) * 2019-08-23 2019-11-15 陈建国 A kind of oil production method
CN110671082A (en) * 2019-09-19 2020-01-10 大庆油田有限责任公司 Adjustment method for well group after injection of large-dose flooding fluid into water injection well of thin difference oil layer of sandstone reservoir
CN110630237B (en) * 2019-09-27 2022-03-22 大庆油田有限责任公司 Method chart for pre-fracturing well fracturing culture and post-fracturing protection and application method thereof
CN110630237A (en) * 2019-09-27 2019-12-31 大庆油田有限责任公司 Method chart for pre-fracturing well fracturing culture and post-fracturing protection and application method thereof
CN111058811A (en) * 2019-11-18 2020-04-24 中国石油天然气股份有限公司 Five-point-view alternate mining method and device for facing horizontal well pattern
CN112983388A (en) * 2019-12-18 2021-06-18 中国石油天然气股份有限公司 Dynamic well pattern deployment method and dynamic well pattern
CN112983388B (en) * 2019-12-18 2023-02-10 中国石油天然气股份有限公司 Dynamic well pattern deployment method and dynamic well pattern
CN112761603A (en) * 2021-03-03 2021-05-07 大庆油田有限责任公司 Novel method for adjusting water injection rate of ultrahigh water-cut period interval of multilayer heterogeneous sandstone reservoir
CN112761603B (en) * 2021-03-03 2022-04-26 大庆油田有限责任公司 Novel method for adjusting water injection rate of ultrahigh water-cut period interval of multilayer heterogeneous sandstone reservoir

Similar Documents

Publication Publication Date Title
CN101148985A (en) Adjusting method for oil field injection and extraction system in ultra-high water-containing period
Schmidt et al. Innovative Unconventional2 EOR-a light EOR an unconventional tertiary recovery approach to an unconventional bakken reservoir in southeast saskatchewan
CN103046910B (en) Ultra-high water cut stage reservoir water drive development approach
CN102733789B (en) Staged fracturing construction yield increment method for waterpower in deep thickened oil deposit thick-bedded sandstone storage layer
CN105239990B (en) A kind of Oil in Super-low Permeability compact oil reservoir intends the lateral displacement horizontal well well-arranging procedure of this well
Rankin et al. Improved production and profitability achieved with superior completions in horizontal wells: A Bakken/Three Forks case history
CN103174403B (en) Thick-layer drives unitized production method containing the gravity every interlayer common heavy oil reservoir with steam
CN102146788A (en) Method for enhancing recovery ratio through three-dimensional streamline regulation of water drive reservoir
CN102322249B (en) Method for improving oil reservoir recovery efficiency of interlayer developed deep-layer heavy oil
CN101818620B (en) Mining method for maximum reservoir contact well
CN206174945U (en) Three branch U type well multiple spot well pattern mining system are adopted altogether to three gas
CN106437642A (en) Fractured reservoir horizontal well injection-production asynchronous exploitation method
CN104033137B (en) Oilfield sewage is utilized to improve fault block oil reservoir recovery ratio method
CN105822284A (en) Well pattern spacing method of triangular horizontal well
CN105822270A (en) Method for governing large pore paths of oil deposit through oil-water well type transformation
CN110118079B (en) Fracturing exploitation method for high-wax-content oil layer
CN105332678B (en) A kind of method of huff and puff
CN207315337U (en) Well pattern structure for the exploitation of stratiform LOW PERMEABILITY RESERVOIR
CN113969770A (en) High-pressure energy storage-body-to-body release type volume water drive development method for water body of edge water reservoir
CN204252974U (en) A kind of horizontal well well structure for the block fractured reservoir exploitation of deep layer
RU2554971C1 (en) Method of oil field development
CN103628848A (en) Multidirectional interlayer water flooding displacement oil extraction method and system
CN106150458A (en) A kind of injection-production method improving the highly aqueous well production of slit formation buried hill oil pool
Arsenty et al. Integrated analysis and optimization of the development system for West Siberia tight oil reservoirs–Vinogradova field example
CN205078258U (en) Hyposmosis oil reservoir is controlled mutually and is combined linear well pattern structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080326