CN101113592A - Underground engineering inner waterproofing process - Google Patents

Underground engineering inner waterproofing process Download PDF

Info

Publication number
CN101113592A
CN101113592A CNA2006100149628A CN200610014962A CN101113592A CN 101113592 A CN101113592 A CN 101113592A CN A2006100149628 A CNA2006100149628 A CN A2006100149628A CN 200610014962 A CN200610014962 A CN 200610014962A CN 101113592 A CN101113592 A CN 101113592A
Authority
CN
China
Prior art keywords
coiled material
reinforced concrete
fixed
dong
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CNA2006100149628A
Other languages
Chinese (zh)
Inventor
张云波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhonghong Tianjin Industry Co Ltd
Original Assignee
Zhonghong Tianjin Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhonghong Tianjin Industry Co Ltd filed Critical Zhonghong Tianjin Industry Co Ltd
Priority to CNA2006100149628A priority Critical patent/CN101113592A/en
Publication of CN101113592A publication Critical patent/CN101113592A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Abstract

The invention relates to a waterproof process for underground engineering. Channels are built for draining. Cement mortar is smeared on the surface and wall of a hole to form a drainage channel, the top and wall of the hole are provided with four leakage points and four drainage channels are built; a leakage proof coiled material layer is arranged to prevent leakage and the leakage proof coiled material is laid from the upper to the lower and fixed to the drainage channel by an expansion bolt; the roiled material needs lapping and the lapping part is adhered by heating method and a wholly closed light reinforced concrete thin shell bushing protection is arranged; when the leakage proof coiled material layer is arranged, a layer of steel wire mesh is hanged below the coiled material and waterproof cement mortar of 2-3cm thick is smeared, thereby forming a light sticking wall thin reinforced concrete protection which is connected and fixed with the hole wall by bolts, after the light reinforced concrete protection sleeve is consolidated, a waterproof coating is coated on the surface thereof. The invention has the advantages of good leakage proof effect and easy construction.

Description

Underground engineering inner waterproofing process
Technical field
The present invention relates to a kind of underground engineering inner waterproofing process.
Background technology
At present, underground chamber inner waterproofing method has stifled and row both at home and abroad, outer stifled all water sources that leak of not stopping; In the stifled normal stifled west, east that occurs leak, interior row often is subjected to again that the restriction in space and existing facility often is difficult to realization in the hole in.
Summary of the invention
The objective of the invention is to overcome above-mentioned defective, a kind of underground engineering inner waterproofing process is provided.
Technical scheme of the present invention is: a kind of underground engineering inner waterproofing process is characterized in that: build leakproof material layer, Yan Dongbi builds the escape canal drainage of catchmenting, and builds light-duty, attached wall steel concrete shell, and the escape canal nation of escape canal is recorded by cement mortar; Shell is made by gauze wire cloth, waterproofing mortar and water-repellent paint on light-duty, the attached wall reinforced concrete; Be connected and fixed by bolting steel reinforced concrete shell and leakproof coiled material layer, Dong Bi.
The present invention has the following advantages: good leak-proof effect, construction easily.
The specific embodiment
Embodiment: a kind of underground engineering inner waterproofing process; build the canal drainage; smear cement mortar at the Dong Miandong wall; form escape canal nation; Dong Ding Dong Bi has four leakage points; build four escape canals; the leakproof coiled material is laid in the Lou coiled material layer leakproof of setting up defences from top to bottom, is fixed in the escape canal nation with expansion bolt; coiled material will overlap; lap-joint is bonding with hot method, establishes the protection of Totally-enclosed-type lightweight section reinforced concrete shell lining, when the leakproof coiled material layer is installed; below coiled material, hang the layer of steel wire net; and smear the waterproof cement mortar of 2-3 cm thick thereon, make it to form one light-duty; adherent thin layer protecting steel reinforced concrete casing is connected and fixed by bolt and Dong Bi; after lightweight section reinforced concrete protective jacket is fixed, be coated with water-repellent paint one on its surface.

Claims (1)

1. underground engineering inner waterproofing process; it is characterized in that: build the canal drainage; smear cement mortar at the Dong Miandong wall; form escape canal nation; Dong Ding Dong Bi has four leakage points; build four escape canals; the leakproof coiled material is laid in the Lou coiled material layer leakproof of setting up defences from top to bottom, is fixed in the escape canal nation with expansion bolt; coiled material will overlap; lap-joint is bonding with hot method, establishes the protection of Totally-enclosed-type lightweight section reinforced concrete shell lining, when the leakproof coiled material layer is installed; below coiled material, hang the layer of steel wire net; and smear the waterproof cement mortar of 2-3 cm thick thereon, make it to form one light-duty; adherent thin layer protecting steel reinforced concrete casing is connected and fixed by bolt and Dong Bi; after lightweight section reinforced concrete protective jacket is fixed, be coated with water-repellent paint one on its surface.
CNA2006100149628A 2006-07-28 2006-07-28 Underground engineering inner waterproofing process Withdrawn CN101113592A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2006100149628A CN101113592A (en) 2006-07-28 2006-07-28 Underground engineering inner waterproofing process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2006100149628A CN101113592A (en) 2006-07-28 2006-07-28 Underground engineering inner waterproofing process

Publications (1)

Publication Number Publication Date
CN101113592A true CN101113592A (en) 2008-01-30

Family

ID=39022108

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2006100149628A Withdrawn CN101113592A (en) 2006-07-28 2006-07-28 Underground engineering inner waterproofing process

Country Status (1)

Country Link
CN (1) CN101113592A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605804A (en) * 2011-01-19 2012-07-25 张继红 Method for directional flow guiding leaking stoppage construction of underground structure
CN109024926A (en) * 2018-08-03 2018-12-18 陕西理工大学 A method of for preventing and treating water leakage in building wall bodies
CN109594585A (en) * 2018-11-30 2019-04-09 中国人民解放军陆军勤务学院 A kind of islands and reefs engineering underground safeguard structure based on seawater aggregate concrete
CN112302045A (en) * 2019-07-26 2021-02-02 中铁十八局集团第五工程有限公司 Construction method of foundation beam side vertical face waterproof structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605804A (en) * 2011-01-19 2012-07-25 张继红 Method for directional flow guiding leaking stoppage construction of underground structure
CN109024926A (en) * 2018-08-03 2018-12-18 陕西理工大学 A method of for preventing and treating water leakage in building wall bodies
CN109594585A (en) * 2018-11-30 2019-04-09 中国人民解放军陆军勤务学院 A kind of islands and reefs engineering underground safeguard structure based on seawater aggregate concrete
CN109594585B (en) * 2018-11-30 2020-09-22 中国人民解放军陆军勤务学院 Island reef engineering underground protective structure based on seawater aggregate concrete
CN112302045A (en) * 2019-07-26 2021-02-02 中铁十八局集团第五工程有限公司 Construction method of foundation beam side vertical face waterproof structure

Similar Documents

Publication Publication Date Title
CN102444265B (en) Vent-thru-roof (VTR) assembly on roof and method for preventing vent stack from water leakage
CN203258206U (en) Through floor pipeline leakage-prevention structure with sleeve
CN206319910U (en) Infiltration disposal system is reinforced in a kind of tunnel-liner
CN206917119U (en) One kind goes out roof pipeline waterproof construction
CN107816138A (en) A kind of construction technology of subsided rest room
CN107605054A (en) A kind of external wall water-proofing anticracking insulation construction
CN101113592A (en) Underground engineering inner waterproofing process
CN110219458A (en) A kind of waterproof integrated equipment room floor construction method of sound insulation and noise reducing
CN111851599B (en) House building basement waterproof structure and construction method
CN101560777A (en) Waterproof construction method for bottom plate of basement with anti-float anchor rod
CN206545364U (en) A kind of accomodation ground waterproof construction
CN106049667B (en) A kind of single side formwork outer wall of basement with flexible waterproof layer external mold
CN1047225C (en) Fully-enlosed cave internal anti-leakage method
CN103628506B (en) Construction method for waterproof positions of foundation platform and pile head
CN211525713U (en) Pre-buried waterproof bushing structure of outer wall through-wall
CN208871172U (en) The Prestressed concrete cylinder pipe of included antiseptic property
CN208804332U (en) A kind of hydrous fluids basement wall pipe waterproof construction
CN206016013U (en) A kind of waterproof floor slab
CN102168500A (en) Antiseptic processing method for capping part of brick lining chimney
CN206015921U (en) Drain pipe waterproof construction
CN211286636U (en) Riser pipe hanger construction structures
CN104831925B (en) Passive house wall bushing waterproof air tightness structure construction method
CN209873864U (en) Waterproof construction of arch steel buckled plate utility tunnel
CN104594390B (en) A kind of aproll construction method at fireproof heat-preserving wall place
CN204826160U (en) Balcony surface drainage mouth structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C04 Withdrawal of patent application after publication (patent law 2001)
WW01 Invention patent application withdrawn after publication