CN101055047A - 水平定向钻穿越夯套管隔离卵砾石工艺方法 - Google Patents

水平定向钻穿越夯套管隔离卵砾石工艺方法 Download PDF

Info

Publication number
CN101055047A
CN101055047A CN 200710102766 CN200710102766A CN101055047A CN 101055047 A CN101055047 A CN 101055047A CN 200710102766 CN200710102766 CN 200710102766 CN 200710102766 A CN200710102766 A CN 200710102766A CN 101055047 A CN101055047 A CN 101055047A
Authority
CN
China
Prior art keywords
construction
pipe
ground
tamping
tampering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200710102766
Other languages
English (en)
Inventor
吴益泉
刘艳辉
吕泽斌
李勤学
白澍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum Pipeline Bureau Co Ltd
Original Assignee
CHINA PETROLEUM PIPELINE BUREAU CROSSING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA PETROLEUM PIPELINE BUREAU CROSSING Co filed Critical CHINA PETROLEUM PIPELINE BUREAU CROSSING Co
Priority to CN 200710102766 priority Critical patent/CN101055047A/zh
Publication of CN101055047A publication Critical patent/CN101055047A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明涉及一种管道敷设非开挖施工技术。这种水平定向钻穿越夯套管隔离卵砾石工艺方法,首先要构筑工作坑,其改进之处在于:它还设有以下工序:(1)铺设导轨;(2)夯管锤安装;(3)钢套管夯进;(4)管内出土;(5)安装中心定位管。该工艺成功将夯套管施工工艺与水平定向钻施工工艺结合在一起,解决水平定向钻施工中入、出土点两端地质不稳定造成的不能施工的问题,具有以下特点:(1)适应多种土层、回填层、流砂层和各种含砾石地层铺管。(2)地面不会产生隆起或沉降现象,对地层适应性强,铺管速度快,最快可达25m/h。(3)施工占地少。夯管法施工作业面在定向钻穿越钻机场地内,占地面积小,土方量小,操作简便。

Description

水平定向钻穿越夯套管隔离卵砾石工艺方法
技术领域
本发明涉及一种管道敷设技术,尤其是涉及一种非开挖施工技术。
背景技术
自20世纪70年代美国发明使用了水平定向钻技术用于管道穿越工程以来,该技术在世界各地得到运用和发展。起初,定向钻技术只适用于粘土、粉沙、亚粘土等有造浆能力和易成孔的地质结构,后来发展到对于不易塌方的岩石地段。但是,对于砾石、砾砂、卵石等地质结构,一直认为是定向钻施工工艺技术的禁区。一旦遇到这样的地质结构,一般处理方法是改变设计位置或路线,避免穿越此类地质区域。但实际施工过程中,由于有些砾石或砾砂地段的特殊地理位置,无法进行更改,必须在砾石或砾砂地段进行穿越。
发明内容
本发明的目的就是提供一种隔离卵砾石的水平定向钻穿越工艺方法--水平定向钻穿越夯套管隔离卵砾石工艺方法。它具有可在砾石、砾砂或卵石地段进行水平定向钻穿越的特点。
为达到上述目的,本发明采用如下技术方案:这种水平定向钻穿越夯套管隔离卵砾石工艺方法,首先要构筑工作坑,其改进之处在于:它还设有以下工序:(1)铺设导轨;(2)夯管锤安装;(3)钢套管夯进;(4)管内出土;(5)安装中心定位管。
上述技术方案的进一步改进在于:所述的工序(3)钢套管夯进工序中是采用一种能夯进空心钢管的设备——夯管锤,将待铺设的钢套管沿设计路线直接夯入地层。
上述技术方案的进一步改进在于:所述的工序(2)夯管锤安装工序中夯管锤以压缩空气或液压油为动力。
上述技术方案的进一步改进在于:所述的工序(4)管内出土可采用高压水射流或螺旋钻杆或人工挖土方法。
上述技术方案的进一步改进在于:所述的工序(5)安装中心定位管可采用法兰连接或焊接方式连接。
采用夯套管进行水平定向穿越成功将夯套管施工工艺与水平定向钻施工工艺结合在一起,解决了水平定向钻施工中入、出土点两端地质不稳定造成的不能施工的问题,具有以下特点:(1)适应多种土层、回填层、流砂层和各种含砾石地层铺管。用于给排水、电力、通信、油气等管道穿越公路、铁路、建筑物和小型河流的直线管道铺设,不干扰交通,施工效率高。(2)由于切削下来的土芯进入钢管内,因此即使铺管深度很浅时,地面也不会产生隆起或沉降现象。对地层适应性强,铺管速度快,最快可达25m/h。(3)施工占地少。夯管法施工作业面在定向钻穿越钻机场地内,占地面积小,土方量小,操作简便。
附图说明
图1为本发明水平定向钻夯套管施工工艺流程图;
图2为本发明工艺方法所采用的气动夯管施工原理图;
图3为安装中心定位管示意图。
具体实施方式
下面结合附图对本发明作进一步详细说明。
水平定向钻夯套管施工法是解决水平定向钻穿越无法穿越卵、砾石层难题的一种的方法(工艺),是非开挖技术的一种。图1所示为本发明的施工工艺流程图。夯管锤是一种能夯进空心钢管的设备,其基本原理是以压缩空气或液压油为动力。首先构筑工作坑、铺设导轨,焊接切削环和注浆管,安装夯管锤,然后将待铺设的钢套管,沿设计路线直接夯入地层。随着钢套管的推进,被切割的土(石)进入钢套管内,等钢套管抵达目标位置后,将管中的土芯排除,安装中心定位管,再用水平定向钻钻进。进入钢套管内的土,可采用高压水射流、螺旋钻杆、人工掏土等方法进行清理。
以气动夯管锤进行夯套管施工为例(如图2所示),进入施工现场后,先铺设工作坑,再安装导轨6、托架5及气动夯管锤2。气动夯管锤2是一个低频、大冲击的气动冲击器,它由压缩空气1驱动,在夯进过程中,气动夯管锤2产生很大的冲击力,通过夯管帽3、出土器7作用于钢套管8后端,再通过钢套管8传递到前端的环形切削头4上,切削进入土(石)层9。随着钢套管8的推进,被切削的土芯进入钢套管8内,当钢套管8抵达目标后,土芯采用高压水射流或螺旋钻杆或人工挖土方法排出。
由于钢套管8管径较钻杆10直径大,钻机钻进过程中遇到较硬地层时会发生弯曲变形。为防止这种情况发生,在钢套管8中加入钻杆中心定位管11(如图3所示)。中心定位管11是比钻杆10略粗的钢套管。隔一段距离,在中心定位管11的外壁焊接一组直径略小于钢套管8直径的支架12。中心定位管11的连接采用法兰13连接(也可采用焊接方式连接)。最后,利用钻机,将中心定位管11逐一连接推入钢套管8中。
这样,钻杆就可以通过钻杆中心定位管11钻进了。

Claims (5)

1、一种水平定向钻穿越夯套管隔离卵砾石工艺方法,首先要构筑工作坑,其特征在于:它还设有以下工序:(1)铺设导轨;(2)夯管锤安装;(3)钢套管夯进;(4)管内出土;(5)安装中心定位管。
2、如权利要求1所述的水平定向钻穿越夯套管隔离卵砾石工艺方法,其特征在于:所述的工序(3)钢套管夯进工序中是采用一种能夯进空心钢管的设备——夯管锤,将待铺设的钢套管沿设计路线直接夯入地层。
3、如权利要求1所述的水平定向钻穿越夯套管隔离卵砾石工艺方法,其特征在于:所述的工序(2)夯管锤安装工序中夯管锤以压缩空气或液压油为动力。
4、如权利要求1所述的水平定向钻穿越夯套管隔离卵砾石工艺方法,其特征在于:所述的工序(4)管内出土可采用高压水射流或螺旋钻杆或人工挖土方法。
5、如权利要求1所述的水平定向钻穿越夯套管隔离卵砾石工艺方法,其特征在于:所述的工序(5)安装中心定位管可采用法兰连接或焊接方式连接。
CN 200710102766 2007-04-18 2007-04-18 水平定向钻穿越夯套管隔离卵砾石工艺方法 Pending CN101055047A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200710102766 CN101055047A (zh) 2007-04-18 2007-04-18 水平定向钻穿越夯套管隔离卵砾石工艺方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200710102766 CN101055047A (zh) 2007-04-18 2007-04-18 水平定向钻穿越夯套管隔离卵砾石工艺方法

Publications (1)

Publication Number Publication Date
CN101055047A true CN101055047A (zh) 2007-10-17

Family

ID=38795028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200710102766 Pending CN101055047A (zh) 2007-04-18 2007-04-18 水平定向钻穿越夯套管隔离卵砾石工艺方法

Country Status (1)

Country Link
CN (1) CN101055047A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101302922B (zh) * 2008-07-03 2012-02-22 四川石油天然气建设工程有限责任公司 水平定向钻穿越砂卵砾石地层的施工方法
CN102623931A (zh) * 2011-12-26 2012-08-01 中铁六局集团有限公司 一种过道地下管线敷设方法及其专用设备
CN102677724A (zh) * 2012-05-21 2012-09-19 中国石油天然气集团公司 一种机械式钢套管安装装置及其安装方法
CN105155575A (zh) * 2015-08-10 2015-12-16 同济大学 一种钢管内嵌非开挖悬臂式挡土墙及其施工方法
CN105257908A (zh) * 2015-11-18 2016-01-20 北京隆科兴非开挖工程股份有限公司 一种地下管道的顶推钻进施工设备及方法
CN110486531A (zh) * 2019-07-29 2019-11-22 中国铁建港航局集团有限公司 一种人工顶管与夯管联合的管道施工方法

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101302922B (zh) * 2008-07-03 2012-02-22 四川石油天然气建设工程有限责任公司 水平定向钻穿越砂卵砾石地层的施工方法
CN102623931A (zh) * 2011-12-26 2012-08-01 中铁六局集团有限公司 一种过道地下管线敷设方法及其专用设备
CN102677724A (zh) * 2012-05-21 2012-09-19 中国石油天然气集团公司 一种机械式钢套管安装装置及其安装方法
CN102677724B (zh) * 2012-05-21 2014-06-04 中国石油天然气集团公司 一种机械式钢套管安装装置及其安装方法
CN105155575A (zh) * 2015-08-10 2015-12-16 同济大学 一种钢管内嵌非开挖悬臂式挡土墙及其施工方法
CN105257908A (zh) * 2015-11-18 2016-01-20 北京隆科兴非开挖工程股份有限公司 一种地下管道的顶推钻进施工设备及方法
CN110486531A (zh) * 2019-07-29 2019-11-22 中国铁建港航局集团有限公司 一种人工顶管与夯管联合的管道施工方法
CN110486531B (zh) * 2019-07-29 2021-06-22 中国铁建港航局集团有限公司 一种人工顶管与夯管联合的管道施工方法

Similar Documents

Publication Publication Date Title
Kramer An introduction to trenchless technology
CN104947690B (zh) 地下连续墙入岩成槽施工方法
CN101900223B (zh) 导向、螺旋排泥、管道顶进铺设施工方法
CN108678130A (zh) 一种非开挖拖拉管施工方法
CN101055047A (zh) 水平定向钻穿越夯套管隔离卵砾石工艺方法
CN103398215A (zh) 一种微创非开挖顶拉管工艺
CN112664221B (zh) 一种用于复杂地质层的顶管施工方法
CN104455726A (zh) 一种管道底部注浆加固的顶管施工方法
CN108071341A (zh) 长距离定向穿越施工方法
CN1265062C (zh) 一种成桩的施工方法及工具
CN111911712A (zh) 一种拉顶管式非开挖管道施工方法
CN105673934A (zh) 一种电缆缚设排管非开挖方法
CN110656947A (zh) 海底基岩凸起段的掘进方法
CN109594574A (zh) 基于有限空间的大型顶管沉井逆作施工方法
CN1306201C (zh) 地下顶管二工序施工方法
CN112983258A (zh) 一种用于松散岩层地质的潜孔锤快速成孔施工方法
MXPA05004914A (es) Metodo para instalar una cubierta de tuberia subterranea.
CN110528497A (zh) 一种潜孔钻配合冲击钻地下连续墙成槽的施工方法
CN108915693B (zh) 一种用于倾斜矿体上的阶梯管线井的施工方法
CN101302922B (zh) 水平定向钻穿越砂卵砾石地层的施工方法
Wen A Novel and High-Efficiency Reaming Assembly for Underground Pipelines Pulling Back Laying in Horizontal Directional Drilling
JPH10317883A (ja) 超小口径削孔工法
Hennig et al. Trenchless installation methods of Sea Outfalls
RU2770531C1 (ru) Способ бестраншейной прокладки трубопровода и труба для бестраншейной прокладки трубопровода
CN215673900U (zh) 双向非开挖定向钻进铺管结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA PETROLEUM PIPELINE BUREAU

Free format text: FORMER OWNER: CHINA OIL AND NATURAL GAS PIPELINE BUREAU, CHUANYUE BRANCH CORPORATION

Effective date: 20080411

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20080411

Address after: Hebei city of Langfang province Guangyang Road No. 87 post encoding: 065000

Applicant after: China Petroleum and Natural Gas Pipeline Bureau

Address before: Hebei City, Langfang Province Development Zone Jin Yuan East Road No. 16 post encoding: 065001

Applicant before: China Petroleum Pipeline Bureau Crossing Company

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication