CN105673934A - 一种电缆缚设排管非开挖方法 - Google Patents

一种电缆缚设排管非开挖方法 Download PDF

Info

Publication number
CN105673934A
CN105673934A CN201510982376.1A CN201510982376A CN105673934A CN 105673934 A CN105673934 A CN 105673934A CN 201510982376 A CN201510982376 A CN 201510982376A CN 105673934 A CN105673934 A CN 105673934A
Authority
CN
China
Prior art keywords
pipe
well
cement
wicresoft
dig technique
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510982376.1A
Other languages
English (en)
Inventor
张思平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Shenjie Environmental Protection Technology Co Ltd
Original Assignee
Shanghai Shenjie Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Shenjie Environmental Protection Technology Co Ltd filed Critical Shanghai Shenjie Environmental Protection Technology Co Ltd
Priority to CN201510982376.1A priority Critical patent/CN105673934A/zh
Publication of CN105673934A publication Critical patent/CN105673934A/zh
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground

Abstract

本发明公开了一种电缆缚设排管非开挖方法,包括下列步骤:步骤一,挖设工作井和接收井;步骤二,将微创非开挖钻孔设备架设于工作井内,利用导向钻头向接收井方向钻孔,至钻头穿入接收井;步骤三,拆下微创非开挖钻孔设备的导向钻头,并在其钻杆上装设预定规格的回拖扩孔器;然后启动微创非开挖钻孔设备回拖,开始回托扩孔,回拖扩孔器扩孔移动到工作井为止;步骤四,(1)拆掉回拖扩孔器,启动微创非开挖钻孔设备,将钻杆穿越至接收井;(2)在接收井中设置顶管机;(3)使将水泥管放入接收井,套穿上钻杆并安装拖管器;(4)启动微创非开挖钻孔设备回拖,利用拖管器拖动水泥管,同时启动顶管机,将水泥管顶入孔内,直至把水泥管拖顶至预定位置。

Description

一种电缆缚设排管非开挖方法
技术领域
本发明涉及一种为电缆缚设排管非开挖方法的施工工艺,尤其是一种适用于雨污分流工程中的支管小管径管道铺设工艺。
背景技术
现在的市政建设,雨污管道工程中使用顶管技术,工艺比较成熟,但是只能来做大管径的管道,解决不了支管小管径的施工。目前小管径如400mm管径的工程只能采用路面开挖埋管技术,但是这种技术破坏路面,引起大量粉尘,破坏了周围环境,并且影响了交通,导致拥挤的大城市更加拥堵。埋完以后,还要路面修复,大大提高了成本,并且影响了民生。
发明内容
为了解决上述技术问题,本发明的目的在于提供一种电缆缚设排管非开挖方法,用于铺设管径较小的管道,对路面破坏小,施工效率高。
本发明的完整技术方案是:一种电缆缚设排管非开挖方法,其特征在于,包括下列步骤:
步骤一,挖设工作井和接收井。于需铺设管道的路段两端分别挖设一工作井和一接收井,挖设好之后,用槽钢对工作井及接收井加固。
步骤二,打导向孔。首先将微创非开挖钻孔设备架设于工作井内,并固定,然后启动微创非开挖钻孔设备,利用导向钻头向接收井方向钻孔,直至钻头穿入接收井。
步骤三,回拖扩孔。首先拆下微创非开挖钻孔设备的导向钻头,并在其钻杆上装设预定规格的回拖扩孔器;然后启动微创非开挖钻孔设备回拖,开始回托扩孔,回拖扩孔器扩孔移动到工作井为止。
步骤四,顶拉水泥管。(1)拆掉回拖扩孔器,启动微创非开挖钻孔设备,将钻杆穿越至接收井;(2)在接收井中设置顶管机;(3)使将水泥管放入接收井,套穿上钻杆并安装拖管器;(4)启动微创非开挖钻孔设备回拖,利用拖管器拖动水泥管,同时启动顶管机,将水泥管顶入孔内,直至把水泥管拖顶至预定位置。
本发明与现有技术相比有如下有益效果:
本发明提供了一种电缆缚设排管非开挖方法,适用于管径较小的雨污分流工程中的支管小管径管道铺设,相较于开挖埋管技术,施工成本大大降低,由于对路面的破坏较小,不至于造成道路拥堵,不会影响居民正常通行和生活。
具体实施方式
下面将结合具体实施例来详细说明本发明,在此本发明的示意性实施例以及说明用来解释本发明,但并不作为对本发明的限定。
本实施例提供一种电缆缚设排管非开挖方法,包括下列步骤:
步骤一,挖设工作井和接收井。于需铺设管道的路段两端分别挖设一工作井和一接收井,挖设好之后,用槽钢对工作井及接收井加固。
步骤二,打导向孔。首先将微创非开挖钻孔设备架设于工作井内,并固定,然后启动微创非开挖钻孔设备,利用导向钻头向接收井方向钻孔,直至钻头穿入接收井。
步骤三,回拖扩孔,首先拆下微创非开挖钻孔设备的导向钻头,并在其钻杆上装设预定规格的回拖扩孔器;然后启动微创非开挖钻孔设备回拖,开始回托扩孔,回拖扩孔器扩孔移动到工作井为止。
步骤四,顶拉水泥管。(1)拆掉回拖扩孔器,启动微创非开挖钻孔设备,将钻杆穿越至接收井;(2)在接收井中设置顶管机;(3)将水泥管放入接收井,套穿上钻杆并安装拖管器;(4)启动微创非开挖钻孔设备回拖,利用拖管器拖动水泥管,同时启动顶管机,将水泥管顶入孔内,直至把水泥管拖顶至预定位置。
以上对本发明实施例所提供的技术方案进行了详细介绍,本文中应用了具体个例对本发明实施例的原理以及实施方式进行了阐述,以上实施例的说明只适用于帮助理解本发明实施例的原理;同时,对于本领域的一般技术人员,依据本发明实施例,在具体实施方式以及应用范围上均会有改变之处,综上所述,本说明书内容不应理解为对本发明的限制。

Claims (1)

1.一种电缆缚设排管非开挖方法,其特征在于,包括下列步骤:
步骤一,挖设工作井和接收井,于需铺设管道的路段两端分别挖设一工作井和一接收井,挖设好之后,用槽钢对工作井及接收井加固;
步骤二,打导向孔,首先将微创非开挖钻孔设备架设于工作井内,并固定,然后启动微创非开挖钻孔设备,利用导向钻头向接收井方向钻孔,直至钻头穿入接收井;
步骤三,回拖扩孔,首先拆下微创非开挖钻孔设备的导向钻头,并在其钻杆上装设预定规格的回拖扩孔器;然后启动微创非开挖钻孔设备回拖,开始回托扩孔,回拖扩孔器扩孔移动到工作井为止;
步骤四,顶拉水泥管,(1)拆掉回拖扩孔器,启动微创非开挖钻孔设备,将钻杆穿越至接收井;(2)在接收井中设置顶管机;(3)使将水泥管放入接收井,套穿上钻杆并安装拖管器;(4)启动微创非开挖钻孔设备回拖,利用拖管器拖动水泥管,同时启动顶管机,将水泥管顶入孔内,直至把水泥管拖顶至预定位置。
CN201510982376.1A 2015-12-24 2015-12-24 一种电缆缚设排管非开挖方法 Pending CN105673934A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510982376.1A CN105673934A (zh) 2015-12-24 2015-12-24 一种电缆缚设排管非开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510982376.1A CN105673934A (zh) 2015-12-24 2015-12-24 一种电缆缚设排管非开挖方法

Publications (1)

Publication Number Publication Date
CN105673934A true CN105673934A (zh) 2016-06-15

Family

ID=56189649

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510982376.1A Pending CN105673934A (zh) 2015-12-24 2015-12-24 一种电缆缚设排管非开挖方法

Country Status (1)

Country Link
CN (1) CN105673934A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107620831A (zh) * 2017-09-20 2018-01-23 中铁八局集团电务工程有限公司 一种穿越既有路基管线的施工方法
CN107940100A (zh) * 2017-11-26 2018-04-20 上海宝冶集团有限公司 四点定向的拖拉管施工方法
CN109798069A (zh) * 2019-01-22 2019-05-24 福建亿钻机械有限公司 深基坑小口径管道修复成套设备及施工方法
CN109881764A (zh) * 2019-01-26 2019-06-14 广州市中港建设工程有限公司 现有道路地下排水管道加装方法
CN110529136A (zh) * 2019-08-23 2019-12-03 广东凯厦建设工程有限公司 市政排污管道顶管施工方法
CN112443274A (zh) * 2019-08-27 2021-03-05 永城煤电控股集团有限公司 一种煤仓电缆孔的施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4176985A (en) * 1975-07-14 1979-12-04 Reading And Bates Construction Co. System and method for installing production casings
CN1247285A (zh) * 1999-08-24 2000-03-15 范中明 不开挖地表的地下管线安装工程施工方法
CN102522723A (zh) * 2011-12-15 2012-06-27 绍兴电力局 一种不开挖地面电力电缆穿越方法
CN103398215A (zh) * 2013-08-20 2013-11-20 江苏沃迪建设工程有限公司 一种微创非开挖顶拉管工艺
CN103791159A (zh) * 2012-11-02 2014-05-14 成张佳宁 小直径管道的顶管施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4176985A (en) * 1975-07-14 1979-12-04 Reading And Bates Construction Co. System and method for installing production casings
CN1247285A (zh) * 1999-08-24 2000-03-15 范中明 不开挖地表的地下管线安装工程施工方法
CN102522723A (zh) * 2011-12-15 2012-06-27 绍兴电力局 一种不开挖地面电力电缆穿越方法
CN103791159A (zh) * 2012-11-02 2014-05-14 成张佳宁 小直径管道的顶管施工方法
CN103398215A (zh) * 2013-08-20 2013-11-20 江苏沃迪建设工程有限公司 一种微创非开挖顶拉管工艺

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107620831A (zh) * 2017-09-20 2018-01-23 中铁八局集团电务工程有限公司 一种穿越既有路基管线的施工方法
CN107940100A (zh) * 2017-11-26 2018-04-20 上海宝冶集团有限公司 四点定向的拖拉管施工方法
CN107940100B (zh) * 2017-11-26 2020-02-28 上海宝冶集团有限公司 四点定向的拖拉管施工方法
CN109798069A (zh) * 2019-01-22 2019-05-24 福建亿钻机械有限公司 深基坑小口径管道修复成套设备及施工方法
CN109881764A (zh) * 2019-01-26 2019-06-14 广州市中港建设工程有限公司 现有道路地下排水管道加装方法
CN109881764B (zh) * 2019-01-26 2020-09-08 广州市中港建设工程有限公司 现有道路地下排水管道加装方法
CN110529136A (zh) * 2019-08-23 2019-12-03 广东凯厦建设工程有限公司 市政排污管道顶管施工方法
CN112443274A (zh) * 2019-08-27 2021-03-05 永城煤电控股集团有限公司 一种煤仓电缆孔的施工方法

Similar Documents

Publication Publication Date Title
CN105673934A (zh) 一种电缆缚设排管非开挖方法
CN103398215A (zh) 一种微创非开挖顶拉管工艺
CN102734556B (zh) 一种电力排管的非开挖施工方法
CN106437798B (zh) 一种穿过盾构掘进断面的锚索群的预处理方法
CN102889427B (zh) 一种非开挖气动裂管修复地下管道的装置、系统和方法
CN101701646B (zh) 地下管道的泥水平衡式拉管施工方法
CN103603342A (zh) 大直径组合套管超长灌注桩施工方法
CN106481881B (zh) 一种原管位非开挖裂管修复地下管道的施工方法
CN103453216B (zh) 一种多管孔高密度聚乙烯管道的非开挖施工方法
CN108590527A (zh) 一种高压燃气管道非开挖水平定向钻穿越施工的方法
CN102733390B (zh) 一种地下废弃锚索/锚杆的拆除方法
CN105544603A (zh) 一种用于地下管线加固的施工方法
CN101055047A (zh) 水平定向钻穿越夯套管隔离卵砾石工艺方法
CN111911712A (zh) 一种拉顶管式非开挖管道施工方法
CN104695478B (zh) 一种超深地下连续墙内置地埋管结构及其施工方法
CN203757176U (zh) 非开挖式管道更换装置
CN101749485A (zh) 非开挖顶进与液氮水平冷冻开挖铺设相结合的管道铺设施工法
CN105544544A (zh) 低净空条件下快速拔桩的方法
Chapman et al. Research needs for on-line pipeline replacement techniques
CN204942755U (zh) 光缆与油管道同孔回拖的组合结构
CN211113744U (zh) 一种用于更换两个检查井之间老旧管道的非开挖施工结构
CN101737057A (zh) 用于软土地层的地铁车站风井的施工方法
CN111064113A (zh) 一种建筑施工预埋管施工方法
Frankson Digging deep to speed up services: pipeline rehabilitation & trenchless technology
CN103441463A (zh) 一种长距离集束pe管道非开挖穿越方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160615