CN101009001B - Method and system for implementing four-dimensional visualization of engineering model - Google Patents

Method and system for implementing four-dimensional visualization of engineering model Download PDF

Info

Publication number
CN101009001B
CN101009001B CN2006101684723A CN200610168472A CN101009001B CN 101009001 B CN101009001 B CN 101009001B CN 2006101684723 A CN2006101684723 A CN 2006101684723A CN 200610168472 A CN200610168472 A CN 200610168472A CN 101009001 B CN101009001 B CN 101009001B
Authority
CN
China
Prior art keywords
construction
subclauses
clauses
plan
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2006101684723A
Other languages
Chinese (zh)
Other versions
CN101009001A (en
Inventor
刘理成
董玉川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Industry 23 Construction Co Ltd
Original Assignee
China Nuclear Industry 23 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Industry 23 Construction Co Ltd filed Critical China Nuclear Industry 23 Construction Co Ltd
Priority to CN2006101684723A priority Critical patent/CN101009001B/en
Publication of CN101009001A publication Critical patent/CN101009001A/en
Application granted granted Critical
Publication of CN101009001B publication Critical patent/CN101009001B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Or Creating Images (AREA)

Abstract

This invention provides one method to establish engine 4 dimensional mode, which uses current three dimensional module and engine execution plan to add one property for each execution unit in the module and sets the property value to relate the engine execution items; then sorting each execution unit according to the property value and displaying the sorted execution unit to form four dimensional engine module.

Description

The four-dimensional visualization method of engineering model and system
Technical field
The present invention relates to a kind of four-dimensional modeling method, relate in particular to four-dimensional model in visible method and system in the heavy construction project.
Technical background
So-called four-dimensional (4D) modeling is on the basis of three-dimensional (3D) spatial model of building, to introduce design and the construction that time shaft assists to accomplish buildings, realizes four-dimensional digital model by computer technology usually.4D model and remarkable is equal to the work progress simulate effect figure that we often see that construction enterprises make with computer virtual reality technology.By contrast; The 4D model need reach more deep technical merit; The element that it requires room and time is by organic combination more; Wherein the building element in space is a three-dimensional model, and time element refers to the construction speed of engineering construction project, and four-dimensional model launches the space element also to confirm the sequence of construction of each work progress of engineering, construction duration and be connected interspersed matching relationship each other to draft reasonable construction scheme on time element.Its effect can improve efficiency of construction, prevents the prolongation of the construction period that inappropriate sequence of construction causes, and building course is carried out real-time and effective control, practices thrift building cost.
It is project over contract pattern that current in the world engineering is undertaken the construction of pattern, and the formulation of construction plan is basic to be begun with design process synchronously, and also completion basically of construction plan when final design is accomplished is so generally just generate the 4D model in the design phase.For example when engineering design, utilize PDS software to set up the 4D model, this method must will be planned synchronously the 4D model at the beginning from engineering design, promptly will consider construction plan simultaneously.Consider that by the project planner thereby construction problem sets up the 4D model; Difficulty is very big, because this just requires not only will consider design problem, also will consider equilibrium of stock; Factors such as the purchasing of raw materials; Possibly accomplished separately by the designer hardly, so accomplish the 4D model by PDS software, complicacy and appropriate litigation fees are expensive.
At home, design process and work progress are relatively independent, and the formulation of construction plan is generally undertaken by unit in charge of construction.Unit in charge of construction is when formulating construction plan; The complete 3D model that is provided by engineering design unit has been arranged; And unit in charge of construction can utilize the software of establishment project progress plan to work out construction plan, for example in the engineering of middle and small scale, uses MicrosoftProject to produce construction plan usually; And in heavy construction, then use PrimaveraProject Planner (P3) to generate the plan clauses and subclauses of construction plan.This is with regard to for the foundation of 4D model provides another thinking, and promptly unit in charge of construction can utilize existing 3D model and construction plan to set up the 4D model.But, because 3D model and construction plan are formulated by designing unit and unit in charge of construction respectively, between 3D model and construction plan, there is not good interface, the two can't realize good association.Particularly in large-scale engineering project; Object in the 3D model is various; The amount of the plan clauses and subclauses of construction plan is also very big; The association that realizes the two is difficulty very, causes effectively utilizing existing 3D model and makes the 4D model easily with construction schedule, and this has become the major obstacle that the 4D modeling develops to broad space more.
Summary of the invention
The present invention utilizes existing engineering 3D model and construction plan clauses and subclauses, creatively realizes the related of 3D model and plan clauses and subclauses, generates the 4D model.This method can be accomplished in the construction stage by unit in charge of construction, lets 4D Model Design problem become simpler, and has reduced cost.
The present invention provides a kind of method of utilizing computing machine to set up four-dimensional engineering model, will have three-dimensional engineering model now and be divided into a plurality of constructions unit, also comprises:
The construction plan step according to the logical relation of construction operation, is set up the construction plan clauses and subclauses, these plan clauses and subclauses corresponding at least temporal information;
Associated steps; In the database of three-dimensional model; Each construction unit to three-dimensional engineering model increases an attribute; And, select the attribute that increased to this construction unit with construction unit corresponding plan clauses and subclauses assignment, thereby realize the related of said construction unit and said plan clauses and subclauses according to the construction logical relation;
Four-dimensional model generates step, shows each construction unit in proper order according to the value time corresponding of the said attribute in construction unit, generates visual four-dimensional engineering model.
Through method provided by the invention, when finding in the four-dimensional animation model that is generating that model object collision or sequence of construction are unreasonable, can adjust the plan clauses and subclauses, to reduce the loss in the practice of construction.
The present invention also provides a kind of system that utilizes computing machine to set up four-dimensional engineering model, will have three-dimensional engineering model now and be divided into a plurality of constructions unit, and this system also comprises:
The construction plan module according to the logical relation of construction operation, is set up the construction plan clauses and subclauses, these plan clauses and subclauses corresponding at least temporal information;
Relating module; In the database of three-dimensional model; Each construction unit to three-dimensional engineering model increases an attribute; And, select the attribute that increased to this construction unit with construction unit corresponding plan clauses and subclauses assignment, thereby realize the related of said construction unit and said plan clauses and subclauses according to the construction logical relation;
Four-dimensional model generation module shows each construction unit in proper order according to the value time corresponding of the said attribute in construction unit, generates visual four-dimensional engineering model.
Description of drawings
Fig. 1 shows the process flow diagram according to the four-dimensional model of foundation of the embodiment of the invention;
It is the process flow diagram that object increases attribute that Fig. 2 shows according to the embodiment of the invention;
The process flow diagram that the property value that Fig. 3 shows to be increased object according to the embodiment of the invention is made amendment.
Embodiment
Be that example describes in detail to the present invention with a certain heavy construction below, its threedimensional model and construction plan all design and formulate based on this project.
Fig. 1 shows the process flow diagram of setting up the method for the four-dimensional model of engineering according to the embodiment of the invention.At first, the three-dimensional engineering model that utilizes design side design to accomplish is divided into the minimum unit of constructing with three-dimensional engineering model, and I is divided into object.The foundation of three-dimensional model can be used existing software PDS/Microstation to wait with the division of minimum construction unit to carry out.The construction unit can be regarded the set of a plurality of objects as; Simultaneously, according to the construction actual conditions of this project civil engineering, installation, the construction plan of establishment engineering; Set up the construction plan clauses and subclauses inventory (i.e. database) of engineering, be reflected in the database these plan clauses and subclauses corresponding information such as time.This construction schedule can be used existing software Primavera Project Planner (P3) to wait and formulate.
Utilization imports the 3D model that has been divided into each minimum construction unit through the three-dimensional browsing software SmartPlant Review (SPR) of applicant's secondary development.SmartPlantReview5.0 software is a visual software that is used for the large complicated three-dimensional model of interactive browse, be widely used in the heavy construction, but it does not possess the modification model, increases the plan associate field, thereby generates the function of 4D engineering model.The applicant has carried out secondary development to it, makes object and construction plan clauses and subclauses that it can related three-dimensional model, is able to set up the 4D engineering model.
Below; With combining Fig. 2 and Fig. 3 to be described in detail in through how object being increased attribute and according to the construction plan clauses and subclauses it carried out assignment among the SPR of secondary development; Thereby realize the related step of construction unit and construction plan; In Fig. 1, this step corresponding " related plan clauses and subclauses with 3D model construct unit ".
It is the process flow diagram that object increases attribute that Fig. 2 shows according to the embodiment of the invention.The new attribute of object increase to the 3D model is to accomplish through the database of 3D model is operated.This database comprises the labels table, label_names table, label_values table and linkage table or the like.Lables table is the summary table that has comprised each entry index of each object of three-dimensional model, and the delegation in this table has comprised these three of linkage_index (index of object names), label_name_index (the attribute-name index of this object) and label_value_index (the property value index of this object) at least; The title that has comprised attribute in the label_names table; The label_values table has comprised the value of attribute, and has comprised the value of indication three-dimensional model construction unit in the linkage table.
At first, in the labels of 3D model database table, select an object, the index label_name_index of this object of inquiry in lables shows, this index of inquiry is worth accordingly in the label_names table then, judges to be somebody's turn to do whether existence value sequence in the table.If do not have value sequence in the label_names table, then in this table, increase sequence, and return the label_name_index of this value sequence.If exist, then directly return the label_name_index of this value sequence.Through top step, added an attribute sequence just for an object of 3D model.Below, judge in the label_values table whether have the Noseq value, if do not have the Noseq value in the label_values table, then increase Noseq therein, and return the label_value_index of this value Noseq.If exist, then directly return the label_value_index of this value Noseq.Through top step, enclosed initial value Noseq just for an attribute sequence that object added of 3D model.Be reflected in the database, with regard to in the labels table being that the object of code name has increased attribute-name index label_name_index and property value index label_value_index with linkage_index.Each object is repeated top interpolation attribute sequence and the step of attaching initial value, up to accomplishing all objects.
Fig. 3 shows the process flow diagram of the value of attribute sequence being made amendment according to the embodiment of the invention.At first will import to through among the SPR of secondary development by the plan clauses and subclauses of construction schedule software P3 establishment; Be about to plan clauses and subclauses and copy among the p3taskname.txt under the SPR, make and when giving the attribute sequence assignment of object, from a drop-down list box, to select to plan clauses and subclauses.The user according to actual needs, the edit selection condition is screened a plurality of objects that needs are revised the value of attribute sequence according to this condition, the editor of this alternative condition can be realized by common alternative condition mode.Select the corresponding plan clauses and subclauses of these objects then, this selection step need be carried out artificial selection and accomplished from the drop-down list box of plan clauses and subclauses.Then, select an object in a plurality of objects that filter out from above and carry out the modification of Sequence value.In the linkage of database table, find the linkage_index of the object that is selected through DMRSLlinkage (value of representing object in the linkage table).According to this index, in the lable_names table, search the corresponding label_name_index of sequence, according to linkage_index and these two index of the label_name_index definite row that will revise in the labels table.In the label_values table, search the pairing index of selected entry values; Be label_value_index; Judge then whether the plan clauses and subclauses of choosing are arranged in this table; If do not have, then in the label_values table, increase the value of these plan clauses and subclauses of choosing, and return this 1abel_value_index.In the labels table, will be revised as the above-mentioned label_value_index that returns thus by the label_value_index of linkage_index and the determined row of label_name_index.To the step of each modification property value above object repetition, up to accomplishing all objects.
Like this; Accomplished to the increase of all objects attribute sequence in the three-dimensional model and according to the construction plan clauses and subclauses and accomplished modification property value; Through these steps; Object in the three-dimensional model and construction plan clauses and subclauses have been accomplished related because the property value that the construction unit uses comes from the plan clauses and subclauses, so can guarantee good association.
Return among Fig. 1; The construction plan clauses and subclauses related with the object of 3D model good after; SPR through secondary development classifies the object in the 3D model according to the value of its attribute sequence; And show successively according to property value time corresponding (according to time scale), to simulate engineering project and construction speed.
System notes the model picture of presentation process with picture format when the 3D model being carried out the progress demonstration.Through animation soft these pictures are organized, generated video file (the for example file of AVI form).
Play this video file, demonstrated the evolution process of the 3D model of this project along with construction speed, promptly visual 4D model has been realized the visualized management of schedule.
Can find out that the method that present embodiment is described has been utilized existing three-dimensional model and construction plan,, the two carried out association well, realize the making of four-dimensional engineering model simply, at low cost through Computer Interface Technology cleverly.
In the association process of schedule and 3D model or after having generated the 4D model; May find the corresponding construction unit of many schedules; By analysis; Find that it is reasonably that the schedule clauses and subclauses are divided, then be the to construct division of unit of its reason is thin inadequately, and reply 3D model is made amendment; Its construction unit is divided again; Meeting the requirement of logical relation of constructing, and then repeat above-mentioned associated steps, generate new 4D model; Also maybe be by analysis, discovery is because the schedule clauses and subclauses are meticulous, then need adjust the plan clauses and subclauses, and then repeat above-mentioned associated steps, generates new 4D model.In this process that schedule clauses and subclauses are readjusted, also be the process that the construction arrangement of reality is adjusted, have the effect of optimizing project construction.
In addition; Other that can also find that construction schedule possibly occur through visual 4D model are unreasonable; After for example generating the 4D model, find that these can come into plain view because unreasonable model object collision or the sequence of construction of causing of the front and back logical relation of schedule is unreasonable in visual 4D model; Can in time adjust as required the logical relation of schedule; To meet the construction technology logical order, avoided the unreasonable heavy losses that cause owing to schedule in the practice of construction stage, this also is another remarkable result of the present invention.
Should be appreciated that embodiment of the present invention is intended to be used for explaining the present invention.To those skilled in the art, do not breaking away within the spirit and scope of the present invention, can carry out on the various forms with details on change, but all fall within the scope of claim that the back proposes and equivalent thereof.

Claims (6)

1. method of setting up four-dimensional engineering model based on three-dimensional engineering model and construction plan clauses and subclauses; Wherein three-dimensional engineering model is divided into a plurality of constructions unit; Said construction plan clauses and subclauses are set up according to the logical relation of construction operation and corresponding at least temporal information, and said method also comprises:
Import step, said construction plan clauses and subclauses are imported in the database of three-dimensional engineering model;
Associated steps; In the database of three-dimensional engineering model; Each construction unit to three-dimensional engineering model increases an attribute; And, select the attribute that increased to this construction unit with construction unit corresponding plan clauses and subclauses assignment, thereby realize the related of said construction unit and said plan clauses and subclauses according to the construction logical relation;
Four-dimensional model generates step, shows each construction unit in proper order according to the value time corresponding of the said attribute in construction unit, generates visual four-dimensional engineering model;
Wherein, said method further comprises the steps
When finding in the four-dimensional engineering model that is generating that model object collision or sequence of construction are unreasonable, the plan clauses and subclauses are adjusted; Perhaps
When finding a construction of a plurality of plan clauses and subclauses correspondences unit, it is reasonable that judgement plan clauses and subclauses are formulated, and then three-dimensional engineering model made amendment; If judge that three-dimensional engineering model is reasonable in design, then the plan clauses and subclauses are adjusted.
2. according to the method for claim 1, said construction unit is made up of a plurality of objects, and each object to the unit of constructing in associated steps increases attribute and gives this attribute assignment according to the corresponding clauses and subclauses of planning, thereby realizes the related of all objects and plan clauses and subclauses.
3. according to the method for claim 1, showing when respectively constructing the unit, with the model picture of picture format record procedure for displaying, and with these picture tissues generation animation files.
4. system that sets up four-dimensional engineering model based on three-dimensional engineering model and construction plan clauses and subclauses; Wherein three-dimensional engineering model is divided into a plurality of constructions unit; Said construction plan clauses and subclauses are set up according to the logical relation of construction operation and corresponding at least temporal information, and this system also comprises:
Import module, be used for said construction plan clauses and subclauses are imported to the database of three-dimensional engineering model;
Relating module; In the database of three-dimensional engineering model; Each construction unit to three-dimensional engineering model increases an attribute; And, select the attribute that increased to this construction unit with construction unit corresponding plan clauses and subclauses assignment, thereby realize the related of said construction unit and said plan clauses and subclauses according to the construction logical relation;
Four-dimensional model generation module shows each construction unit in proper order according to the value time corresponding of the said attribute in construction unit, generates visual four-dimensional engineering model;
Wherein, said system further comprises following module, is used for
When finding in the four-dimensional engineering model that is generating that model object collision or sequence of construction are unreasonable, the plan clauses and subclauses are adjusted; Perhaps
When finding a construction of a plurality of plan clauses and subclauses correspondences unit, it is reasonable that judgement plan clauses and subclauses are formulated, and then three-dimensional engineering model made amendment; If judge that three-dimensional engineering model is reasonable in design, then the plan clauses and subclauses are adjusted.
5. according to the system of claim 4, said construction unit is made up of a plurality of objects, and each object to the unit of constructing in relating module increases attribute and gives this attribute assignment according to the corresponding clauses and subclauses of planning, thereby realizes the related of all objects and plan clauses and subclauses.
6. according to the system of claim 4, in four-dimensional model generation module with the model picture of picture format record procedure for displaying, and with these picture tissues generation animation files.
CN2006101684723A 2006-12-14 2006-12-14 Method and system for implementing four-dimensional visualization of engineering model Active CN101009001B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2006101684723A CN101009001B (en) 2006-12-14 2006-12-14 Method and system for implementing four-dimensional visualization of engineering model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2006101684723A CN101009001B (en) 2006-12-14 2006-12-14 Method and system for implementing four-dimensional visualization of engineering model

Publications (2)

Publication Number Publication Date
CN101009001A CN101009001A (en) 2007-08-01
CN101009001B true CN101009001B (en) 2012-07-18

Family

ID=38697412

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2006101684723A Active CN101009001B (en) 2006-12-14 2006-12-14 Method and system for implementing four-dimensional visualization of engineering model

Country Status (1)

Country Link
CN (1) CN101009001B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243486A (en) * 2015-09-30 2016-01-13 北京恒华伟业科技股份有限公司 Construction scene simulation display method and apparatus
CN105718650A (en) * 2016-01-19 2016-06-29 上海杰图天下网络科技有限公司 Concealed engineering recording and archiving method by utilizing three-dimensional panorama technology
CN107273374B (en) * 2016-04-06 2021-04-16 北京嘀嘀无限科技发展有限公司 Drop-down window display method and device
CN107545402A (en) * 2016-06-28 2018-01-05 上海洋启投资中心 Realize the secondary project mechanism for automatically creating sub-project
CN107545401A (en) * 2016-06-28 2018-01-05 上海洋启投资中心 Project planning mechanism based on time shaft
CN106897448B (en) * 2017-03-03 2020-09-25 广州地铁集团有限公司 Subway engineering rail-running area cross construction intelligent graphical display and collision detection system
CN111143913A (en) * 2018-10-16 2020-05-12 国网天津市电力公司经济技术研究院 Three-dimensional modeling method and system for transformer substation building

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100593716B1 (en) * 2004-03-24 2006-06-28 고호은 4D construction management system and construction management information provision method using the same
CN1849624A (en) * 2003-09-10 2006-10-18 西门子共同研究公司 System and method for spatio-temporal modeling using guidepoints

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1849624A (en) * 2003-09-10 2006-10-18 西门子共同研究公司 System and method for spatio-temporal modeling using guidepoints
KR100593716B1 (en) * 2004-03-24 2006-06-28 고호은 4D construction management system and construction management information provision method using the same

Also Published As

Publication number Publication date
CN101009001A (en) 2007-08-01

Similar Documents

Publication Publication Date Title
CN101009001B (en) Method and system for implementing four-dimensional visualization of engineering model
CN106200983B (en) A kind of system of combination virtual reality and BIM realization virtual reality scenario architectural design
CN100547596C (en) The product edition and the simulation database system that have user interaction graphical tool
Arayici et al. Building information modelling (BIM) for construction lifecycle management
CN107180069A (en) Engineering project information based on IFC data interactions delivers integrated management system
CN107273640A (en) Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model
CN103823949A (en) Intelligent device control and arrangement system and method applied to indoor design
Marir et al. OSCONCAD: A model-based CAD system integrated with computer applications
CN105046432A (en) Building dimensional guide construction method
CN101567030A (en) Method of constructing virtual preservation and restoration system for wooden structure of ancient architecture
CN102609585A (en) Aircraft instrument efficient modeling design method based on components
CN111767335A (en) Data visualization analysis method
CN101359405A (en) Process for constructing three-dimensional emulation system for electrical power system
El Nimr et al. Application of gaming engines in simulation driven visualization of construction operations
CN102646286B (en) Digital graph medium simulation method with three-dimensional space structure
Penn et al. Intelligent architecture
Rosenman et al. Multidisciplinary design in virtual worlds
Faraj et al. A Modularised Integrated Computer Environment for the Construction Industry: SPACE.
Liu et al. Research on application of BIM technology in construction project
Ibrahim et al. CAD smart objects: potentials and limitations
CN102609554A (en) Computer-aided design method and device for large LED (light-emitting diode) screens
Krawczyk-Dembicka et al. The study of co-design in the area of manufacturing
Watson et al. The need for an integrated 2D/3D cad system in structural engineering
Aouad Trends in information visualisation in construction
Weigert et al. Modelling and optimisation of assembly processes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Liu Licheng

Inventor after: Dong Yuchuan

Inventor before: Deng Xiaoliang

Inventor before: Nian Fayang

Inventor before: Hu Jiang

Inventor before: Zhong Xianjun

Inventor before: Xu Fukui

Inventor before: Ding Xianglong

Inventor before: Liu Licheng

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: DENG XIAOLIANG NIAN FAYANG HU JIANG ZHONG XIANJUN XU FUKUI DING XIANGLONG LIU LICHENG TO: LIU LICHENG DONG YUCHUAN

C14 Grant of patent or utility model
GR01 Patent grant